RFIS Responses.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Y1FD--Project: 508-22-102, Renovate Nutrition and Food Service and Freezers
Solicitation number
36C24725R0015
Issued by

About this file

This is a Questions and Answers document containing 88 RFI responses related to a VA renovation project for Nutrition and Food Service and Freezers. The document primarily addresses technical clarifications and logistical requirements for contractors.

Key details include: Siemens is confirmed as the fire alarm and fire suppression company; McKinney's is the preferred HVAC vendor; TrimCo is the preferred roofing vendor. The Superintendent can serve multiple roles including Quality Control Manager (QCM) and Site Safety & Health Officer (SSHO). Work hours for utility shutdowns are 4pm-7am. Contractors must undergo badging/security requirements and TB testing for prime contractors. The VA will provide water and power access but contractors must supply their own mobile office. Materials storage is allowed but VA will only pay for installed materials and those in use for up to 3 weeks. Regarding flooring, epoxy products can be installed over existing tile, with specification section 096723.60 RES 6A replacing section 09 67 23 20. Testing, Adjusting and Balancing (TAB) must be completed at each phase end and project completion.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

RFI #RFI TextCompany NameResponse
1Will the VA confirm the deck height?VENERGY GROUP, LLCRequesting clarification of this question. Need to specify more in order to answer accurately
2Will the VA confirm all activities required for off-hours work?VENERGY GROUP, LLCAny Utility Shutdown
3Will the VA confirm that new resinous flooring can be installed on existing tile (reference AD101 Note O)?VENERGY GROUP, LLCYes, epoxy products can be applied over tile floors. Replace section 09 67 23 20 with new attached section 096723.60 RES 6A
4Will the VA annotate toilet accessory locations on finish plans, or confirm that only soap and paper towel dispensers are required at sink locations and all other toilet accessories are not applicable?VENERGY GROUP, LLCOnly soap and paper towel dispensers are required at new sink locations.
5Will the VA confirm that no FRP is required for this project (finishes)?VENERGY GROUP, LLCConfirmed per Finish Schedule
6Will the VA provide specifications for wall tile (finishes)?VENERGY GROUP, LLCSee 09 30 13 - CeramicPorcelain Tiling for specifications, finish to match adjacent surfaces.
7Will the VA provide specifications for wall covering (finishes)?VENERGY GROUP, LLCWall Coverings are identified in Spec 10 26 00 - Wall and Door Protection
8Will the VA confirm the base building fire alarm company?VENERGY GROUP, LLCSiemens
9Will the VA confirm the base building fire suppression company?VENERGY GROUP, LLCSiemens
10Will the VA confirm base building HVAC controls?VENERGY GROUP, LLCVaries, depends on where work is being performed. There are multiple HVAC controls
11Will the VA confirm the preferred HVAC vendor?VENERGY GROUP, LLCMckinney's
12Will the VA confirm the preferred lightning protection vendor?VENERGY GROUP, LLCThere is no preffered lighting vendor.
13Will the VA confirm the preferred roofing vendor?VENERGY GROUP, LLCTrimCo
14Can we receive a file transfer for the CAD files?Brown and Phillips Architectural DesignCAD files have been submitted to the VA
15Is this a tax-exempt project?B2 Constructors, LLCNo
16If tax-exempt, will the government provide the prime contractor with a tax-exempt certificate for use by subcontractors and vendors?B2 Constructors, LLCNo. Not tax exempt
17Can the Superintendent be shared across multiple projects, or should they only be dedicated full-time to this project?B2 Constructors, LLCYes
18Can the Superintendent fulfill the Quality Control Manager (QCM) role?B2 Constructors, LLCYes
19If the Super cannot fulfill this role, the average ADDITIONAL cost for a dedicated QCM is approximately $26,500 per month (salary, labor burden, per diem, housing, company vehicle, monthly return trips home, company phone, etc). We expect this project to be 12 months long, and the bid is expected to increase by $318,000.00. Please confirm a dedicated QCM is still required.B2 Constructors, LLCN/A, Super can fullfill
20Is the QCM required to be onsite full-time, or can they make site visits as required for inspections?B2 Constructors, LLCIf they also serve as superintendent then must be onsite full-time
21If the QCM is required to be onsite, should they be assigned to this project only, or can they be assigned to another project as well?B2 Constructors, LLCNo, the QCM can be assigned to multpile projects unless the QCM is also the superintendent, in which case they must be assigned to one project.
22Can a subcontractor (e.g., Terracon or a similar testing firm) fulfill the QCM role?B2 Constructors, LLCYes
23Can the Superintendent fulfill the Site Safety & Health Officer (SSHO) role?B2 Constructors, LLCYes, as the onsite “Competent Person” if they are designated they will be able to declare an emergency work stoppage if necessary.
24If the Super cannot fulfill this role, the average ADDITIONAL cost for a dedicated SSHO is approximately $26,500 per month (salary, labor burden, per diem, housing, company vehicle, monthly return trips home, company phone, etc). We expect this project to be 12 months long, and the bid is expected to increase by $318,000.00. Please confirm a dedicated SSHO is still required.B2 Constructors, LLCN/A
25Is the SSHO required to be on-site full-time, or can they be a home office employee (e.g., Safety Director) on the prime contractor's staff?B2 Constructors, LLCOn site full-time
26If the SSHO is required to be onsite, should they be assigned to this project only, or can they be assigned to another project as well?B2 Constructors, LLCNo, the SSHO can be assigned to multpile projects unless the SSHO is also the superintendent, in which case they must be assigned to one project.
27Can a subcontractor fulfill the SSHO role with periodic visits?B2 Constructors, LLCNo
28Does the VA require any scope of work in this project to be performed outside of regular work hours?B2 Constructors, LLCRefer to scope of work/contract, Must adhere to Gov Holidays. Also any utility shutdowns
29What trades or scopes will be required to perform off-hours work for work scopes that must be performed?B2 Constructors, LLCAny shutdown
30What will the work hours and days be for scopes that require off-hours work?B2 Constructors, LLCwork hours outside of normal business 4pm- 7am
31In the event of contract modifications, should contractors apply bond premiums to the individual modification or wait until the end of the job where the VA issues a final modification to reimburse contractors for bond overruns for all mods.B2 Constructors, LLCAny bond adjustments should be included per individual modification.
32Where is the designated contractors' and subcontractors' parking area?B2 Constructors, LLCVaries, will be determined at time of award based on hospital needs
33Will the VA allow 2-3 parking spaces for the prime contractor and each subcontractor?B2 Constructors, LLCVaries, will be determined at time of award based on hospital needs
34Where shall these people park if the VA cannot make 2-3 spaces available for the prime contractor and each of the subs?B2 Constructors, LLCVaries, will be determined at time of award based on hospital needs
35Is badging required for the project?B2 Constructors, LLCbadging/security required
36Are background checks and fingerprinting required?B2 Constructors, LLCPrime, yes.
37How long is the turnaround time for background check results?B2 Constructors, LLCVaries depending on the individuals background
38How many hours should the prime contractor and subcontractors budget for on-site badging, safety training, orientation, etc.?B2 Constructors, LLC4 hours
39Is tuberculosis testing required before contractors can commence work onsite?B2 Constructors, LLCPrime, yes.
40In lieu of the provided cost estimate breakdown, will the government accept a printout report from our COTS estimating software that provides the same level of breakdown specified in the government-provided breakdown spreadsheet?B2 Constructors, LLCNo, but it can be submitted as supporting document.
41Will the VA allow a Temp Wall System (i.e., Starc Wall, Edge Guard, etc) instead of a rigid wall ICRA system? This usually provides substantial cost savings to the VA.B2 Constructors, LLC“Starc Walls” may be acceptable considering the multi phasing process being used to complete this project. Duration of construction per phase and reconfiguration of temp wall location approved with separate ICRA.
42If fire-rated walls are required, can we use one-hour-rated temp walls, which are ASTM-certified?B2 Constructors, LLCStarc Walls or equal may be acceptable considering the multi phasing process being used to complete this project. Duration of construction per phase and reconfiguration of temp wall location approved with separate ICRA.
43Will the VA provide the point of contact information for the BMS integration contractor?B2 Constructors, LLCRicky Smith
44Will the VA provide the point of contact information for the Fire Alarm integration contractor?B2 Constructors, LLCMike Boyle
45Will the VA allow contractors to use water from VA sources?B2 Constructors, LLCYes
46Is temp power available for contractors to connect to?B2 Constructors, LLCYes
47If no temp power is available, a generator will be required, which usually adds significant cost to rent and fuel. Please confirm this is necessary if no temp power is available.B2 Constructors, LLCN/A
48What are the locations for temp power?B2 Constructors, LLCFacility, There are 1400 panels
49Are contractors required to set a pole and meter electric usage?B2 Constructors, LLCNo
50Will the VA provide a space for the Prime Contractor’s Superintendent to set up, or should we add costs to our bid for a mobile office?B2 Constructors, LLCVA will not have space, must include mobile office into bid or find an alternate location.
51Is space available for a 10’ x 40’ temporary ground-level office near the temporary power source?B2 Constructors, LLCNeed to clarify where site will be
52Will the VA provide space for a 20-yard dumpster?B2 Constructors, LLCYes
53Where shall contractor dumpsters be located?B2 Constructors, LLCVaries, will be determined at time of award based on hospital needs
54Can the VA accommodate a dumpster near the job site?B2 Constructors, LLCVaries, will be determined at time of award based on hospital needs
55Will the VA allow contractors to use VA indoor restrooms?B2 Constructors, LLCYes
56Can Porta Johns be placed within a 100’ radius of the job site if required?B2 Constructors, LLCYes
57Can contractors perform crane lifts during regular hours?B2 Constructors, LLCThis is circumstantial.
58Can utility tie-ins be performed during regular hours?B2 Constructors, LLCNo
59Can system commissioning activities be performed during regular hours?B2 Constructors, LLCPotentially, depending if it affects patient care
60Will the VA allow for stored material so that we can procure and lay down long lead items and/or critical path material/equipment?B2 Constructors, LLCVA can allow for space to store material but contractor responsible for maintaining stored material
61Will the VA fully pay for this material/equipment if stored onsite?B2 Constructors, LLCVA will only pay for installed materials and materials in use for up to 3 weeks
62Is there moisture in the substrate?B2 Constructors, LLCUnable to determine without destructive testing.
63Has a test been done to determine if there is moisture in the substrate?B2 Constructors, LLCRequesting clarification of this question. Need to specify more in order to answer accurately
64Please confirm that Stonehard is the sole source of RES-1 resinous flooring. Can another material equal to or better be approved?B2 Constructors, LLCStonhard is the Basis of Design, provide an epoxy flooring that meets the performance criteria of the new attached section 096723.60 RES 6A
65Please provide drawings showing where the existing floor tiles will be removed and replaced with new resinous flooring.B2 Constructors, LLCper AD101 Floor and wall tile to remain throughout
66Please provide drawings showing where tile will need to be replaced or repaired either on walls or floors.B2 Constructors, LLCThe amount of affected wall area will vary based upon the demolition techniques of the demolition Contractor. Contractors Means and Methods will drive Quantities.
67Will the tile be required to be removed for new resinous flooring? If not,B2 Constructors, LLCper AD101 Floor and wall tile to remain throughout
68Is the tile bed thick set or thin set?B2 Constructors, LLCUnable to determine without destructive testing.
69Is resinous flooring intended to be installed over the existing tile?B2 Constructors, LLCYes, epoxy products can be applied over tile floors.
70If the resinous flooring as specified is to be installed over the existing tile, it may void warranty, please confirm if this installation is approved even though it may void warranty.B2 Constructors, LLCReplace section 09 67 23 20 with new attached section 096723.60 RES 6A
71Please provide a “Schedule for Finishes” per specification 09 06 00?B2 Constructors, LLCFile is uploaded to the Sharepoint Site provided in attachment 7 of the soliciation.
72Since the existing walls and barriers have tiles on them. Please provide the existing tile manufacturer, tile sizes, tile color, etc to match the existing for patching or repairs.B2 Constructors, LLCNo existing records of tile are on file. Contractor to provde a match in the field.
73Drawing AE100, Plan Note 7 refers to Rigid Vinyl Wallcovering, please provide specifications for Rigid Vinyl Wallcovering.B2 Constructors, LLCWall Coverings are identified in Spec 10 26 00 - Wall and Door Protection
74Please provide a Wall Type Detail on drawing AE002, for Wall Type S6A.1FI.B2 Constructors, LLCRevised Sheet AE002 to be provided with detail
75All notes in the demolition drawings specify that existing wall protection and corner guards will be removed. Will any wall protection and corner guards be reused/saved or should they be disposed of?B2 Constructors, LLCCorner guards and wall protection should be removed and replaced with new. (JC)
76Please provide drawings showing where new or existing wall protection or corner guards will be installed / re-installed.B2 Constructors, LLCModify Note N on AD101 to maintain existing wall protection throughout area of work. File is uploaded to the Sharepoint Site provided in attachment 7 of the soliciation.
77The specifications and the Finish Schedules show two different products. Neither of these two products are suitable for a kitchen environment. The suitable product for a kitchen environment in the VA master spec is 0967 23.60, Res - 6A. Which product will be required for the installation?B2 Constructors, LLCReplace section 09 67 23 20 with new attached section 096723.60 RES 6A
78Is there any equipment furnished by VA?Kotuku, Inc.No
79The order of installed heights for each item (HVAC, Plumbing, Fire Suppression, Electrical Cable/Cable Tray) on ceiling .Kotuku, Inc.The coordination of trade installation sequencing, including the order of installed heights for HVAC, plumbing, fire suppression, and electrical systems, is the contractor’s responsibility. The contractor must ensure proper coordination with other trades to maintain required clearances and comply with project specifications. Additionally, installation should be planned to minimize disruption to the day-to-day operations of the medical facility.
80Should we do T.A.B (Testing, Adjusting, and Balancing) ?
TAB Specialist must be a member of AABC or an experienced technician of the firm certified by the NEBB.Kotuku, Inc.Yes, TAB must be completed at the end of each phase and again at project completion, following the requirements outlined in Specification 230593. Additional details about the TAB Agency requirements can be found in Section 1.5 of the same specification.
81Special Inspector of Record (SIOR) – SIOR must be an independent third party hired directly by the Prime Contractor on this project?Kotuku, Inc.Yes, the SIOR must be an independent 3rd party hired by the GC.
82Designer of Record (DOR) – A registered design professional is contracted by the Government as an A/E responsible for the overall design and review of submittal documents prepared by others.
Should we hire this person (DOR)?Kotuku, Inc.No. DOR is under VA contract.
83VAV Terminal don’t have HWS/HWR piping connection. (51-2-9C, 51-2-10C, 51-2-11C)

Is this right?

Kotuku, Inc.Correct. These are cooling on terminal units.
84We would like to confirm the owner furnished materials (especially, kitchen appliances).Kotuku, Inc.Please see attached equipment list
85Will a site visit sign in sheet be provided in the future?Kotuku, Inc.This was provided in amendment 0001
86After reviewing the bid documents, are there any security or access control items that are part of the project scope? Other than general Div.28 specifications references, there are no security devices noted on the drawings or specific manufacturers or equipment listed”. Please clarifyHarbor Services Inc.There is a security camera in the corridor between Storage GC111J and Cooler GC116 that shall be relocated as a part of this project. See sheet EP110-1.
87There is a discrepancy in spec section (#09672320) for our scope. Section 2.1 states system thickness 2-3mm. However, section 3.5E mentions a trowelled mortar base which is much thicker. Please advise how to bidHarbor Services Inc.Replace section 09 67 23 20 with new attached section 096723.60 RES 6A
88Does firm need contractor license in the State of Georgia to bid on solicitation?Kotuku, Inc.Offerors are required to be registered in SAM to bid on projects. Any proof of licenses would be required when firms register in SAM. We are not requesting proof of license. Under FAR clause 52.236-7 Permits and Responsibilities: This clause stipulates that the Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.