This is a transmittal package for HVAC insulation submittals for the Carl Vinson VA Medical Center in Dublin, Georgia, containing an ENG Form 4025-R submittal form and detailed insulation specifications. The package was submitted by Greenland Enterprises (contractor) and Covan's Insulation Company (supplier) for contract W912HP-16-C-0018.

The submittal includes comprehensive insulation charts and thickness schedules for various pipe services and ductwork. Key specifications include: fiberglass insulation for heating hot water and condensate drain pipes, polyisocyanurate for chilled water pipes, calcium silicate for steam pipes, Armaflex for domestic cold water, and 2-inch fiberglass for general ductwork. The package details specific thickness requirements based on pipe diameters, ranging from 1 inch to 3 inches, and includes finishing requirements such as aluminum jacketing, ASJ jackets with PVC fitting covers, and location-specific requirements for areas above and below 7 feet. Accessories specifications include aluminum bands, seals, tapes, fasteners, adhesives, and mastics required for proper installation.

View the file

Other files

File Type Posted
Additional clarification questions.docx DOCX document
23 07 11-3 Transmittal Package_ Pipe Insulation.pdf PDF
36C24725Q0203 0003.docx DOCX document
36C24725Q0203 0002.docx DOCX document
Cogen Plant Spec Combined 051616_COR Approval with boiler tests.pdf PDF
23 64 00-1 transmittal Package water cooled chillers.pdf PDF
Chiller Plant Design.pdf PDF
Site Visit December16th.pdf PDF
36C24725Q0203 0001.docx DOCX document
36C24725Q0203.docx DOCX document
36C24725Q0203_1.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

DATE TRANSMITTAL NO.

TO: FROM: CONTRACT NO. CHECK ONE:

THIS IS A NEW TRANSMITTAL

THIS IS A RESUBMITTAL OF

TRANSMITTAL ___________

SPECIFICATION SEC. NO. (Cover only one section with each transmittal) PROJECT TITLE AND LOCATION 01-Main Register THIS TRANSMITTAL IS FOR: (Check one)

FIO GA DA CR DA/CR DA/GA

ITEM

NO.

(See

Note 3) a.

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.)

b.

SUBMITTAL

TYPE CODE

(See Note 8) c.

NO.

OF

COPIES

d.

CONTRACT REFERENCE

DOCUMENT

SPEC.

PARA. NO.

e.

DRAWING

SHEET NO.

f.

CONTRACTOR

REVIEW

CODE

g.

VARIATION

Enter "Y" if requesting a variation

(See Note 6) h.

USACE

ACTION

CODE

(Note 9) i.

REMARKS I certify that the above submitted items have been reviewed in detail and are correct and in the strict conformance with the contract drawings and specifications except as otherwise stated.

NAME AND SIGNATURE OF CONTRACTOR

SECTION II - APPROVAL ACTION

ENCLOSURES RETURNED (List by item No.) NAME, TITLE AND SIGNATURE OF APPROVING AUTHORITY DATE

ENG FORM 4025-R, MAR 2012 REPLACES EDITION OF MAR 95, WHICH IS OBSOLETE.

04/17/2017 23 07 11-2

23 07 11

W912HP-16-C-0018 NA

SFO - VA Geographic District ROs 69A Hagood Avenue Charleston, SC 29403-5107

GREENLAND ENTERPRISES, INC.

2713 MAGRUDER BLVD STE A

HAMPTON, VA 23666-1572

FY16 VAMC Dublin GA Boiler Plant Rebuild Dublin, GA

X

X

23 Insulation Chart SD-03 0 1.4 A

24 Insulation Thickness Schedule SD-03 0 1.4 A

Nestor Morales

ITEM:

SUBMITTALS NO.: DATE:

SECTION:

Architect:

General Contractor

Mechanical Contractor:

Supplier(s):

Manufacturer(s):

Submitted by: Jose C Colon

Notes:

Carl Vinson VA Medical Center

Dublin, Georgia 31021

Product Data / Shop Drawings (Catalog Cut) Submittal Form

HVAC, Plumbing, and Ductwork Insulation

March 24, 2017230711-01-00

220711 and 230711

SUBMITTAL NOTES:

SWWB Design

The Corporate Center, Suite 621-A

233 12th Street

Columbus, GA 31901

Greenland Enterprises

2000 Aerial Center Parkway, Suite 104

Morrisville, NC 27560

Ivey Mechanical Company, LLC

4554 Stonegate Industrial Blvd, Suite C

Stone Mountain. GA 30083

Covan's Insulation Co., Inc.

534 Corbin Rd

Honea Path, SC 29654

Blake Malone (864) 980-8396

HiTherm,Owens Corning, Industrial Insulation

Group, LLC, Armacell, Speedline Corp, ITW

Insulation Systems, GTA, Specialty

Construction Brands, This package was submitted under submittal/section 2307110100 HVAC, Plumbing, and Ductwork Insulation

Covan’s Insulation Company, Inc.

PO Box 169

534 Corbin Rd

Honea Path, SC 29654

Phone: (864) 369-7100 Fax: (864) 369-7111

Email: covan@covansinsulation.com

Website: www.covansinsulation.com

Pipe & Duct Insulation

Submittal

Project: Co-Gen Project Carl Vinson VA

Medical Center

Finish Below 7ft Finish Above 7ft

Boiler Room Steam Calcium Silicate N/A

All Domestic Cold Water Armaflex No Finish No Finish 0.25

All Domestic Hot Water Fiberglass ASJ w/ PVC fittings ASJ w/ PVC fittings 0.23

Outdoor Cooling Water Fiberglass 0.23

Accessories Type

1/2" Aluminum Bands Mechanical Fastener

1/2" Aluminum Seals Mechanical Fastener

3" ASJ Tape Facing & Jacket

3" FSK Tape Facing & Jacket Seals longitudinal seams on FSK duct finish for complete vapor barrier

Midwest Fasteners Spindles Mechanical Fastener

Midwest Fasteners 12ga Washers Mechanical Fastener

Midwest Fastener Hanger Adhesive Adhesive

Childers CP-85 Adhesive Adhesive

Childers CP-30 Mastic Mastic

Armaflex 520 Adhesive Adhesive

Insulation Chart for Carl Vinson VA Medical Center

Insulation TypeDuct Service Finish

2-1/2" long galvinized pin adhered to duct for securing of fiberglass board

12ga washer fits on to spindle to secure fiberglass board

Class B, Adhere gavanized spindle to duct

Class B, Adhere Fiberglass insulation to duct

MIL-C-19565, Vapor Barrier Compound for indoor use

Class 1, Adhesive for Armaflex installation

All other Heating Hot Water and

Condensate Drain

Factory applied ASJ jacket with PVC fitting covers

Notes:

1/2" Wide Aluminum, 0.020" Thick

1/2" Wide Aluminum, 0.020" Thick

Seals longitudinal seams on ASJ pipe finish for complete vapor barrier

Accessories

K Value @ 75F

Supply Duct in Chiller Room Fiberglass Board Exposed duct will be finished with a 0.024 aluminum jacket

0.23

All Aluminum Jacket

Location

K Value @ 75FInsulation TypePipe Service

0.23

All Aluminum Jacket

Factory applied ASJ jacket with

PVC fitting covers

0.165 aged 180 days

Factory applied ASJ jacket with

PVC fitting covers Aluminum Jacket 0.23

Boiler Room Chilled Water Polyisocyanurate Aluminum Jacket

Boiler Room Heating Hot Water and

Condensate Drain Fiberglass

Fiberglass

Service Pipe ᴓ Thickness Type

Ductwork 2" Fiberglass

(excludes lined duct and general exhaust)

Chilled Water ≤1-1/4" 1-1/2" Polyisocyanurate

Chilled Water ≥1-1/2" 2" Polyisocyanurate

Heating Hot Water ≤1-1/4" 1-1/2" Fiberglass

Heating Hot Water ≥1-1/2" 2" Fiberglass

Condensate Drain ≤1-1/4" 1-1/2" Fiberglass

Condensate Drain ≥1-1/2" 2" Fiberglass

Domestic Cold All 1" Armaflex

Domestic Hot ≤1-1/4" 1-1/2" Fiberglass

Domestic Hot ≥1-1/2" 2" Fiberglass

Steam ≤1-1/4" 2-1/2" Mineral Fiber

Steam ≥1-1/2" 3" Mineral Fiber

Cooling Water (Exterior) All 1" Fiberglass

Drain (Exterior Cooling Tower) All 1" Fiberglass

Insulation Thickness Schedule

23 07 11-2 (183) HVAC Insulation
4410 Procurement Log
Insulation Schedule_REV01

23 07 11-2 Transmittal HVAC Insulation