PRICE SCHEDULE 02.docx
DOCX document 17 KB Posted
- Solicitation number
- 36C24724R0083
About this file
This document is a Price Schedule for a federal contract opportunity. The intent of the contract is to provide completed porches to the East North and West entrances of Building 10, as well as to provide complete working EV Charging stations, in accordance with the prescribed performance requirements, drawings, statement of work (SOW) and specifications. The contract has a base period of performance, with a deductive alternate option of 30 days if the VA chooses to use a screen wall. The Price Schedule includes two line items: 0001 for the base scope of work, and 0002 for the deductive alternate. Pricing details are not provided, as unit prices and total amounts are left blank. The related federal contract opportunity is Solicitation Number 36C24724R0083, titled "Z1DA--PROJECT 544-21-119 INSTALL B10 PORCHES & CHARGING STATIONS", issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24724R0083 0003.docx | DOCX document | |
| 36C24724R0083 0002.docx | DOCX document | |
| Answers to RFIs as of - 25 July 2024.docx | DOCX document | |
| 36C24724R0083 0001.docx | DOCX document | |
| Attachment 7 - Two Story Porch Assembly Spec.pdf | ||
| Attachment 1 - STATEMENT OF WORK - SOW.docx | DOCX document | |
| Attachment 2 - DRAWINGS - Combined.pdf | ||
| Attachment 6 - Wage Determination .pdf | ||
| Attachment 3 - SPECIFICATIONS - 544-21-119.pdf | ||
| Attachment 5 - Environmental Record Evaluation .docx | DOCX document | |
| 36C24724R0083_1.docx | DOCX document | |
| Attachment 4 - Performance Relevancy Questions.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
The contractor shall provide all materials, equipment, labor, logistics, and supervision to meet the intent, end result, and performance requirements described within. The intent of this contract is to provide completed porches to the East North and West entrances of Buildings 10 as well as to provide complete working EV Charging stations in accordance with the prescribed performance requirements, drawings, statement of work (SOW) and specifications.
Contract Period: Base POP Begin:
POP End:
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deductive Alternate (Screen Wall- See Drawings and Specs for location and details). Deductive Alternate is 30 days, If VA chooses to use deductive alternate then period of performance will be 335 days.
Contract Period: Base POP Begin:
POP End:
| GRAND TOTAL |
| __________________ |
File details come from the government source that posted it. Updated .