Futera Fusion 750 Interactive Submittal Data Sheet SFTF 750 7_1.pdf
PDF 209 KB Posted
- Solicitation number
- 36C24724Q0633
About this file
This document is a combined synopsis/solicitation for commercial services related to Heating, Ventilation, Air Conditioning (HVAC) & heating hot water heaters, compressed air, and medical air/vacuum systems preventative maintenance and repair at the Department of Veterans Affairs (VA) Birmingham Medical Center.
The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a NAICS code of 238220. The service contract will consist of a base period and four one-year option periods. Responses are due by May 28, 2024 at 5:00 PM EST. The government will evaluate quotes based on technical capability, past performance, and price. A site visit is scheduled for May 14, 2024 and questions are due by May 17, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 41-M0.1- Gas Boiler.pdf | ||
| Mechanical-Heart Station.pdf | ||
| lattner instruction manual space saver july 2020.pdf | ||
| Mechanical-ORs.pdf | ||
| Mechanical- Dental.pdf | ||
| Mechanical-Ambulatory Clinic.pdf | ||
| Mechanical- Sterile Processing.pdf | ||
| AC6B-Heart Station AHU.pdf | ||
| 36C24724Q0633_3.docx | DOCX document | |
| 49-M4.1-Gas boiler.pdf | ||
| Mechanical- Pharmacy.pdf | ||
| Updated Attachment A _ Revised May 27 2024.pdf | ||
| 36C24724Q0633_2.docx | DOCX document | |
| STATEMENT OF WORK.pdf | ||
| SCHEDULE.docx | DOCX document | |
| Site Visit Map.pdf | ||
| Wage Determination No 2015-4591 Rev 25.pdf | ||
| 36C24724Q0633_1.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REP FIRM
SUBMITTED BY
JOB NAME
ARCHITECT
ENGINEER
CONTRACTOR
DATE
FUTERA FUSION 750
Category II or IV Appliance
(see Installation and Operation Manual for venting information)
A Division of Mestek, Inc.
Westfield, MA 01085
(413) 568-9571
SFTF-750-7
SIDE VIEW
TOP VIEW
BACK VIEW
CENTER OF
GRAVITY
CENTER OF
GRAVITY
Ø8 AIR INTAKE
2 NPT
WATER INLET
CIRCULATOR
PUMP
DIVERTER
VALVE 1 NPT
NG GAS INLET
Ø7 CAT. II/IV
FLUE OUTLET
CONDENSATE DRAIN 1/2 NPT
CONDENSATE DRAIN
OUTLET
2 NPT
WATER OUTLET
12 1/2 [318]
25 1/8 [638]
26 15/16 [684]
51 1/8 [1299]
[1499]
25 13/16 [656]
54 15/16 [1396]
29 3/8 [745]
45 11/16 [1160]
26 1/8 [664]
7 1/8 [181]
33 7/16 [849]
46 13/16 [1188]
7 1/8 [181]
15 13/16 [402]
16 7/8 [429]
9 1/2 [241]
16 3/8 [415]
4 5/8 [117]
12 9/16 [319]
18 5/8 [473]
4X � .4375 [11]
4X3/4 [19]
[508]
[281]
[281]
2 1/2 [64]
BOTTOM VIEW
NOTES:
1.) SYMBOL INDICATES CENTER OF GRAVITY
2.) DIMENSIONS ARE NOMINAL AND SUBJECT TO
MANUFACTURING VARIATION AND SHOULD NOT
BE USED FOR "ROUGH IN".
3.) ALL DIMENSIONS ARE INCHES[MM].
BOILER CERTIFIED RATINGS & CAPACITIES
Fuel Type Natural/Propane Gas Total FLA 9.2*
Input BTU/hr. 750,000 / 220 kW Min. Gas Pressure Required 2" W.C.**
Output BTU/hr. 713,250 / 209 kW Max. Gas Pressure Allowed 14" W.C.
Electrical Requirements (L1, NEU, GND) Operating Weight 793 lbs. / 360 kg.
120 VAC / 1 ph / 60 hz
BOILER / WATER HEATER TRIM & CONTROLS
Main Gas Valve Dungs MBC-SE Air Switch Cleveland NS2
Firing Valve 1” Blower Motor Fasco 1/2 hp
Ignition Control Honeywell RM7895C Relief Valve - CW 3/4" x 3/4" set @ 125 psi
Operating Control HeatNet® Relief Valve - CB 3/4" x 3/4" set @ 50 psi
High Limit Jumo Flow Switch TACO
Main Ball Valve 1" Pilot Regulator White-Rodgers 25m
Economizer RBI-1000 Circulator B&G PL-130 - FLA - 5
Mixing Valve 2" By-Pass Piping 2"
A.S.M.E.
ASME Sect IV Htg Surface 97.79 Sq. Ft. / 9.08 Sq. M. Design Data Max. 125 psig & 250°F
Water Volume 3.7 gal. / 14.01 Liters
Water Volume Secondary HX 4.5 gal. / 17.03 Liters
BOILER TEMPERATURE RISE / PRESSURE DROP
20°F / 11.1°C 25°F / 13.9°C
Flow Rate*** Total Loss**** Flow Rate*** Total Loss****
GPM L/s Ft kPa GPM L/s Ft kPa
65.3 4.1 10.5 31.4 52.2 3.3 7.7 23.0
WATER HEATER HOURLY RECOVERY CAPACITY (GPH & LPH)
40°F 22°C 60°F 33°C 80°F 44°C 100°F 56°C 120°F 67°C 140°F 78°C
2,168 8,194 1,445 5,462 1,084 4,097 867 3,277 723 2,731 619 2,341
Notes:
1. Dimensions are approximate and should not be used to "rough-in" equipment.
2. Dimensions are subject to change without notice.
* Includes pump ** For incoming gas pressures lower than 2" W.C. natural or propane, consult factory.
RSUB-97 REV H
*** Primary heat exchanger.
**** Includes primary, secondary, mixing valve and piping.
CODE OPTIONS
CSD-1 Manual Reset LWCO
INDOOR UNIT
FUTERA FUSION 750
OUTDOOR UNIT
CENTER OF
GRAVITY
56 1/2 [1435]
13 1/16 [332]
26 3/16 [664]
30 7/8 [784]
CENTER OF
GRAVITY
2 3/16 [56]
[1499]
[25]
61 7/16 [1560]
57 3/16 [1452]
39 15/16 [1015]
28 1/16 [713]
69 11/16 [1771]
2 NPT
WATER OUTLET
Ø7 [179]
VENT ASSEMBLY
1 NPT
NG GAS INLET
2 NPT
WATER INLET
16 3/8 [415]
12 9/16 [319]
9 1/2 [241]
4 5/8 [117]
33 7/16 [849]
21 1/16 [535]
7 3/8 [187]
45 11/16 [1160]
77 5/16 [1964]
25 5/8 [651]
60 3/16 [1528]
FRONT VIEW
SIDE VIEW
REAR VIEW
TOP VIEW
BOTTOM VIEW
[279]
[279]
4X 3/4 [19]
4X � .4375 [11]
2 1/2 [64]
[508]
NOTES:
1.) SYMBOL INDICATES CENTER OF GRAVITY
2.) DIMENSIONS ARE NOMINAL AND SUBJECT TO
MANUFACTURING VARIATION AND SHOULD NOT
BE USED FOR "ROUGH IN".
3.) ALL DIMENSIONS ARE INCHES[MM].
RSUB-123 REV D
Notes:
1. Dimensions are approximate and should not be used to "rough-in" equipment.
2. Dimensions are subject to change without notice.
| Text8: |
| Text9: |
| Text10: |
| Text11: |
| Text12: |
| Text13: |
| Text14: |
File details come from the government source that posted it. Updated .