This document is a Scope of Work for Project No. 658-22-104 at the Veterans Affairs Medical Center in Salem, Virginia. The project involves renovating shell space in Building 143, Rooms 1C-129 and 1C-129A, to create sixteen new cubicle workstations for employees displaced by ongoing construction or renovation activities. The contractor will be responsible for providing labor, materials, equipment, and supervision to complete the work, which includes modifications to fire alarm, sprinkler, electrical, telecommunication, and HVAC systems, as well as installing new interior finishes.
The construction period is set at 120 calendar days from the Notice to Proceed (NTP), with no deductive alternatives allowed. The scope requires comprehensive system upgrades and renovation to transform the existing shell space into functional workstations, ensuring minimal disruption to medical center operations while providing temporary workspace solutions for displaced employees.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
PROJECT NO. 658-22-104
Renovate Shell Space
VETERANS AFFAIRS MEDICAL CENTER
SALEM, VA 24153
The contractor shall provide all necessary labor, materials, equipment, and qualified supervision to complete the work outlined in the drawings and specifications for Project 658-22-104, aimed at renovating the shell space at VAMC Salem, Virginia. This renovation will create temporary workstations for employees displaced due to ongoing construction, renovation, or repair activities.
The objective of this project is to transform existing shell space in Building 143, Rooms 1C-129 and 1C-129A, into sixteen (16) new cubicle workstations. The scope of work includes modification and renovation to the fire alarm, sprinkler, electrical, telecommunication, and HVAC systems as well as installation of new interior finishes within the space.
The allocated construction period for completing the specified work is one hundred and twenty (120) calendar days from the receipt of the Notice to Proceed (NTP). There is no deductive alternative for this project.