This document contains technical questions and answers related to solicitation number 36C24622Q1163 for document shredding services. The solicitation is for the Central Virginia Veterans Health Care System and involves shredding services at seven locations, with quantities ranging from two to 388 consoles and bins picked up weekly or every two weeks. Pricing will be evaluated for on-site document destruction services, with potential additional line items for media destruction and purges conducted as needed or biannually. The period of performance is extended to begin February 1, 2023. Key details include questions regarding container types and locations, training requirements, compliance with VA directives on destruction timeframes and transportation, and configuration of locking systems. Location lists and current contract information is provided in attached appendices.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24622Q1163 0007.docx | DOCX document | |
| 36C24622Q1163 0006.docx | DOCX document | |
| 36C24622Q1163 0005.docx | DOCX document | |
| VAMC Richmond Bin Location.pdf | ||
| 36C24622Q1163 0003.docx | DOCX document | |
| 36C24622Q1163 0002.docx | DOCX document | |
| 36C24622Q1163 0001.docx | DOCX document | |
| 36C24622Q1163_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 652-23-1-638-0002 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton
VA
23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton
VA
23667 To all Offerors/Bidders
36C24622Q1163 10-11-2022
X X X
November 7, 2022, at 4:30 p.m.
See CONTINUATION Page x The purpose of this amendment is to submit answers to additional technical questions submitted for the Central Virginia Veterans Health Care System's Document Shredding requirement.
1. Answers to technical questions are hereby submitted and begin with Question #5.
2. Q&A begins on Page 2.
3. See attached PDF document for Location and number of CVVHCS consoles and bins.
Natasha Jacobson Contracting Officer
FY23 CVVHCS DOCUMENT SHREDDING
Central Virginia VA Health Care System FY23 Document Shredding
Technical Questions and Answers
| 1. | Could you please provide the quantity of containers, size of containers and frequency of service for each location? |
| Line Item | |
| Location | |
| Bins/Consoles | |
| Frequency |
| 0001 |
| Main CVVHCS Campus Richmond, VA |
| 388 |
| Weekly |
| 0002 |
| Southpoint CBOC |
Fredericksburg, VA
| 6 |
| Every Two Weeks |
| 0003 |
| Mary Washington CBOC Fredericksburg, VA |
| 2 |
| Every Two Weeks |
| 0004 |
| Massaponax CBOC |
Fredericksburg, VA
| 6 |
| Every Two Weeks |
| 0005 |
| Emporia CBOC |
Emporia, VA
| 2 |
| Every Two Weeks |
| 0006 |
| Charlottesville CBOC Charlottesville, VA |
| 3 |
| Every Two Weeks |
| 0007 |
| Henrico CBOC |
Richmond, VA
| 4 |
| Every Two Weeks |
· Currently, there are a total of two bins/consoles, sizes 36 inches and 24 inches
· In addition, there are 5/6 96-gallon portable bins
*Please note, vendor shall supply all bins/consoles*
2. Are all items in the table consoles or are some 96-gallon bins? Would it be possible to separate the two amounts?
· *Update-Breakdown of console and bin locations are attached via a PDF* The 96-gallon portable bins are in the main hospital only and are kept in reserve for overflow usage, so consoles aren’t clogged. Example: A person retiring and cleaning out their office would use a portable bin to shred their old documents
· One person offices do not get a console, as consoles are available for all staff in office suites or wards. Positions that warrant a console in their office will have the smaller, 26in console. *Note: Private consoles are an exception, not the rule.
3. What is an estimate of how many pounds of paper or other items there will be for the locations requiring service?
· Pounds estimate is between 13 tons to 18 tons, (26,000-36,000 pounds) per month, for the main campus and CBOCs combined.
4. Would it be possible to extend the solicitation by a week?
· Response date is hereby extended to Monday, November 7, 2022, by 4:30 p.m.
*The main campus is 111 acres with several buildings, over 1,000,000 square feet* New Technical Questions Begin Below
5. Are any Bridge Contracts in place that extend the current contract?
· The FAR 52.217-8 clause, Option to Extend Services, gives the opportunity to extend a service up to 6 months from the original end date.
6. Will the agency consider extending the offer due date for a questions period and review of answers?
· Yes, the offer due date is extended to Monday, November 7, 2022, by 4:30 p.m.
7. *Page 3* Besides the basic Privacy Act training, are there any specific training requirements?
· NO
| 8. | *Page 4 of PWS (Scope)* The non-paper media (floppy disks, tapes, DVDs, x-rays, etc.) need to be separated from the paper. It cannot shred together. |
| a. Can it be separated into a different container? |
· THE FACILITY NO LONGER USES COMPUTERS WITH FLOPPY DISKS, TAPES, OR CD ROMS. WE DO NOT NECESSARILY NEED A SEPARATE CONTAINER FOR THIS TYPE OF MEDIA, BUT FACILITY CAN REQUEST A SPECIAL PURGE DATE FOR DESTRUTION OF THIS TYPE OF MEDIA.
· THE FACILITY NO LONGER USES X-RAY FILM; ALL X-RAYS ARE DIGITAL, BUT A SPECIAL PURGE DATE CAN BE REQUESTED FOR DESTRUCTION FOR X-RAYS.
b. Can a separate line item be added for media?
· THE FACILITY WOULD LIKE TO HAVE A PURGE LIST NTE LINE ITEM, MEDIA CAN BE ADDED TO THIS LINE ITEM.
· SEE ABOVE. Yes, a separate line item can be added for media and x-rays.
9. *Page 4 of PWS (Scope)* Can Off-Site Destruction be an option for non-Paper Media as a contingency plan?
· No. For privacy concerns, all documents to include media and x-rays, must be destroyed on facility.
| 10. | *Page 4 of PWS (Specific Requirements) * Due to the VA directive 6371, the timeframe for further destruction has been extended as Interim Destruction on-site “reduces the risk…during transport and short-term storage (i.e., less than 30 days) …as defined in this Directive.” |
| a. Can the 48 hours’ time frame for further destruction be modified in accordance with the 6371 if a Final Destruction is met? |
· YES, LESS THAN 30 DAYS.
| 11. | *Page 5 of PWS (Specific Requirements) * With “…shall supply the COR with extra keys upon request…” ability, the possibility of a breach increases with the number of keys released to the COR. |
| a. What situations would classify extra keys upon request? |
· LOST KEYS OR IF SENIOR MANAGEMENT OF ENVIRONMENTAL MANAGEMENT SERVICE (EMS) REQUESTS A COPY FOR THEIR USE.
12. Can the NIST guideline be removed, and the VA Directive 6371 be the authority over this contract? These two guidelines contradict each other and create a conflict.
· NO, THE NIST IS REFERENCED IN VA DIRECTIVE 6371.
13. Will the Period of Performance start date be extended?
· Yes, the Period of Performance start date is extended to Wednesday, February 1, 2023.
14. *Page 5, Scope and 3.1* This mentions non-paper media needing destruction.
a. Some non-paper media must be destroyed separately from paper and/or off-site (e.g. tapes, x-rays). Will the non-paper media be collected in separate containers?
· Yes
b. What is the anticipated frequency?
· Expected frequency will be as needed or bi-annually
c. Is appropriate off-site destruction allowed for those items that require it?
· Destruction of all documents and media must be done on facility due to content sensitivity
15. *Page 6, 3* This mentions that loads must be “sealed”. Per regulations, the shred truck is securely locked when starting the route and cannot be unlocked until reaching its off-load destination.
a. Could the requirement to “seal” the truck please be removed?
· NO, THE SEAL PROVIDES A EXTRA LAYER OF SECURITY.
16. *Page 6, 7* Stationary consoles and rolling bins have different locking systems.
a. Is it acceptable that all consoles and rolling bins be keyed alike? YES
17. *Page 9, a* Can the day of the week be collaboratively agreed to post-award since the contractor must incorporate the VA work into already existing routes?
18. Will each facility provide an initial list of container placement since a new contractor will not be familiar with building and room numbers?
· Yes. List of console and bin locations are attached via a PDF
19. Amendment 0001, Purges*
a. Please define what LT means.
· LT refers to Lot
b. There is no CLIN in the Price Schedule for purges. Is 0008 listed for informational purposes or, is the agency requesting we provide pricing for these? If so, where should that be entered and please give a more detailed description of what the purge parameters are
· Pricing for line item 0008 purges will be provided by the agency and will be done as needed or bi-annually
20. Amendment 0001
a. Is it possible to expand just a little on how many 24” consoles there are and where they are located? Even something as simple as all are at the VAMC and they won’t exceed 15% of the total containers at that location.
· Please see PDF attachment for console locations and sizes
21. Please confirm that at the CBOCs, there are no steps to negotiate with our rolling collection bins.
· THERE ARE NO STEPS.
22. Could you please provide the contract number for the current contract and when the contract is ending?
· VA246-17-P-6149; January 31, 2023
23. Is the level of effort being performed under the current contract fundamentally the same as what will be required under the new contract?
· Yes
See attached document: VAMC Richmond Bin Location.
File details come from the government source that posted it. Updated .