This document contains questions submitted and responses provided relating to solicitation number 36C24622B0008 for an HVAC upgrade project at a Department of Veterans Affairs facility. Key details include that the project involves replacing damaged HVAC equipment and heads as necessary, with flow tests and hydraulic calculations only required if additional equipment is added. Normal working hours are 7:00 am to 4:30 pm Monday through Friday, with off-hours work possible for crane lifts and noisy activities. The general contractor will be responsible for commissioning and testing services, and a limited number of parking permits will be provided onsite.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24622B0008 0004.docx | DOCX document | |
| S06 OF 1419 Certified Bid Abstract - HVAC Phase V.pdf | ||
| 36C24622B0008 0003.docx | DOCX document | |
| S06 Attachment I - Initial Drawing Package Reformatted.pdf | ||
| 36C24622B0008 0002.docx | DOCX document | |
| 36C24622B0008 0001.docx | DOCX document | |
| S06 637-19-102 HVAC Ph 5 31 Mar 2022 Site Visit Attendees Sign In Sheet.pdf | ||
| S02 Attachment I - Specification Package.pdf | ||
| S02 Attachment III - Wage Det NC20220043 25 Feb 2022.pdf | ||
| S02 Attachment II - Drawing Package.pdf | ||
| 36C24622B0008.docx | DOCX document | |
| S02 Attachment IV - Bid Item Cost Breakdown WS.xlsx | XLSX spreadsheet | |
| S02 Attachment VI Statement of Requirements 25 Mar 2022.pdf | ||
| S02 Attachment V - Campus Map.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Solicitation 36C24622B0008 - Upgrade HVAC Phase 5 -Questions Submitted and Gov't Responses | |||
| Questions from Industry | Response | Description of any addional Action Taken (e.g. updated Drawing or Spec. provided) | |
| 1 | (1A) Can the Site Superintendent also complete the duties of the CQC manager position, so long as they are adequately qualified and can fulfill the duties of both positions as outlined in the project documents? | Spec Section 014500 - Under 3.4B. – “The CQC System Manger is assigned as CQC System Manager but has duties as project superintendent in addition to quality control. | |
| (2A) Please confirm if the Project Superintendent can also serve as the full time Site Safety and Health Officer. The Quality Control specification already states that the CQC system manager also serves as the Project Superintendent so they would essentially be able to fulfill all 3 duties. Please confirm this is acceptable | Spec Section 014500 - In paragraph 3.4A., “The Safety and Health Manager shall satisfy the requirements of Specification 01 35 26 Safety Requirements and reports directly to a senior project (or corporate) official independent from the CQC System Manager.” The Safety and Health Manager is a separate individual from the CQC System Manager/Project Superintendent. | ||
| (1C) Specification 01 35 26: Can the site superintendent be “duel hatted” as the SSHO? | No. |
Spec Section 013526 - The site superintendent and safety and health manager shall be separate individuals (1D) 2. Can the required SSHO positions be fulfilled by the qualified superintendent? No.
Spec Section 013526 - From 1.7A. - The Prime Contractor shall designate a minimum of one SSHO at each project site that will be identified as the SSHO to administer the Contractor's safety program and government-accepted Accident Prevention Plan. The training requirements for the SSHO are different than those for a superintendent.
| 2 | (2A) Drawing Sheet AE106, Key Note 1, states that the defined area should be re-roofed/repaired to maintain existing factory warranty. Please confirm, does this area currently have an active warranty? | (2A) Yes |
| (2B) If so, who is the manufacturer and installer who holds the existing warranty? | (2B) Carlisle Syntec Systems | |
| 3 | Will all work operations (other than those creating excessive noise/vibration and required outages) be allowed to be completed during normal business hours? | Spec Section 010000 - Under 1.6F. Reads Normal hours of work are 7:00 a.m. until 3:30 p.m. However the referenced Spec contained a typo and for Clarification purposes normal working hours are actually 7:00AM-4:30PM Monday - Firday. Off-hour work including evenings or weekends will be required for crane lifts, and work which transmits noise or vibrations through the building structure. |
| 4 | There is a conflict between the bid schedules in the project documents. The Solicitation document (page 5) shows just a base bid and the Project Specifications, Section 01 00 00 (Pages 1-2), state there is an Alternate No. 1 for Removing AHU-ENDO and all associated work. Please confirm, which of these should be followed for this bid submission? | Typo Corrected, there is only one Bid Alternate for this project. |
| 5 | Where will contractor laydown / storage areas be permitted? | Spec Section 010000 - Under 1.6D. Working space and space available for storing materials shall be as determined by the COR. Onsite storage will be available, but the amount of available space is limited, bed down site for project will be identified prior to the issuance of the Construction NTP. |
| 6 | (6A) Where can the contractor stage cranes / lifts for rooftop work? | Spec Section 010000 - Refer to article 1.19 Cranes in the specification. |
| (6B) Crane locations : Where can crane sets be located? | ||
| 7 | Will there be temporary power available for the contractor’s trailer and operations (that the contractor will be responsible for paying for all connections/disconnects)? | Spec. Section 010000 - Per Article 1.22 - AVAILABILITY AND USE OF UTILITY SERVICES: |
Paragraph A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
Paragraph B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
| 8 | Notes on the Fire Protection Drawings refer to the need for both flow tests and hydraulic calcs and new shop drawings being provided. This seems unnecessary if the scope of work is limited to replacing heads that are damaged during new work as laid out in the Sheet Keynotes. Please confirm, is the intent solely to replace damaged heads and nothing further? If so, can the flow test and hydraulic calcs / shop drawings requirement be removed? | The Contractor's Fire Protection Personnel shall determine based on the actual layout of the sprinkler piping system and heads necessary to provide required coverage conclude additional heads are required as a result of new work, then flow tests and hydraulic calculations are required. In the event no additional heads are required based on the sprinkler subcontractors analysis and only existing heads are repositioned and/or damaged heads are replaced, then the flow tests and hydraulic calculations are not required. |
| 9 | Spec 01 00 00 - 1.19 indicates that the Contractor cannot use existing elevators and that an outside type hoist shall be used for transporting materials and equipment. Please confirm this is correct. Please verify if the contractor can use the elevator for personnel or if a man lift will also need to be provided in additional to a material and equipment hoist. | Unfortunately the elevators do not possess capabilities for roof top access. Contractor will need to develop viable safe means in which to gain access to the roof top. |
| 10 | Bid bonds: Are electronic copies of bid bonds acceptable or must hard copies be mailed or included in bid package? | Electronically submitted bids will be required at time of offer submission to be deemed responsive. If the winning bid so happenes to be received electronically, the Contracting Officer shall then coordinate the winner to submit the physical copy to the Contracting Officer's physical location shortly after bid opening. |
| 11 | Attachment statement of requirements section 2.3 asbestos: Is asbestos abatement within the scope of work? | The asbestos abatement specifications will be used if asbestos is discovered during construction and will be handled via change order. There is no known asbestos in the planned construction area. |
| 12 | Reference previous question: if abatement is within the scope of work. Can the Government please provide specs., location , type and amounts? | The asbestos abatement specifications will be used if asbestos is discovered during construction and will be handled via change order. There is no known asbestos in the planned construction area. |
| 13 | Attachment statement of requirements section 2.6 testing: What tests are required? | Refer to specifications to include but not limited to: Commissioning; Shock Hazard and Arc Flash Hazard analyses; 230511 article 3.12 Operating and performance tests; Test & Balance Report for HVAC; Duct Leakage Testing; electrical testing |
| 14 | Reference previous question: Can the Government please provide specifications for any required testing? | The technical sections of the specifications contain the requirements for testing. |
| 15 | Attachment statement of requirements section 2.9 permits: what permits are required? | The contractor is responsible for obtaining permits if they are required due to a work plan developed by the contractor. VA does not know of any local permits that will be required based on this design. |
| 16 | Attachment statement of requirements section 2.10 COMMISSIONING: Can the Government please provide specifications and typical matrix showing responsible parties and scope? | Spec Section 019100 - Refer to Part 3; 3.1 Commissioning Process Roles and Responsibilities. The VA’s commissioning agent if a third party shall address any additional requirements. |
| 17 | Working hours: Is this a normal working hour project? | Spec Section 010000 - Under paragraph 1.6F. Normal hours of work are 7:00 a.m. until 4:30 p.m. Off-hour work including evenings or weekends will be required for crane lifts, and work which transmits noise or vibrations through the building structure. |
| 18 | Ceilings: Can the Government please identify any areas of work that have hard ceilings? | Architectural drawings indicate all ceilings in scope of work are acoustical ceiling tile and grid. |
| 19 | Drawings MH001 general note 3 and 4. Drawing MD101 general note g. appear to imply that latent and unforeseen conditions do not apply to this contract. We can only give responsible pricing based on the documentation provided by the government. Is the intent of these and other notes to remove the FAR and VAR clauses that reference latent and unforeseen conditions? | None of the notes in these documents relieve the contractor of the requirements of the FAR and VAR clauses. However, should any unforeseen sight conditions materialize during performance of the contract, the Contractor shall be responsible for bringing them to the immediate attention of the Contracting Officer and COR. |
| Reference previous question: Can the Government provide an amount for an allowance to include in everyone’s quote to address unforeseen and latent conditions so we are all bidding “ apples to apples”? | Contractors are to provide their bid based on all documentation within the solication, amendments and any attachments as this is the baseline established for the "apples to apples" for all parties. Should something present during the performance of the project, that differes from the documentation provided, the Contractor shall be required to identify, document and engage the CO & COR on the issue for a determination of the next step on a case-by-case basis. It is the intent of the Government to strive for win-win outcomes and not to displace the unknowns onto the sole responsibility of the Contractor. | ||
| 20 | Specifications: Can the Government please provide specification’s for all required work? I.E. fire alarm etc. | The attached Spec. Section 000110 – Table of Contents contains a complete list of all sections that were issued in the specification manual dated 09/08/2021. | |
| 21 | Is this project sales tax exempt? | (2A) No, not tax exempt see FAR Clause 52.229-2 North Carolina State and local Sales and Use Tax as required by FAR 29.401-2. For any furhter information on this topic, the Government would urge each interested party consult their tax advisor. | |
| If the project is sales tax exempt can the government provide a sales tax exemption certificate? | (2B) No, not tax exempt see FAR Clause 52.229-2 North Carolina State and local Sales and Use Tax as required by FAR 29.401-2. For any furhter information on this topic, the Government would urge each interested party consult their tax advisor. | ||
| 22 | Will the Owner or GC be responsible for commissioning? | Spec Section 019100 - Per paragraph 1.1A, the general contractor shall contract with the Commissioning Agent for this project. | |
| 23 | Will the Owner or GC be responsible for purchasing testing and lab services? | Spec Section 010000 - Per paragraph 1.2D, the general contractor shall retain the testing laboratory. | |
| 24 | Where will the designated parking area be for workers accessing the construction site? | Spec. Section 010000 - Paragraph 1.5E.2. states – A limited number of (2-5) permits shall be issued for the general contractor and its employees for parking in designated areas only. | |
| 25 | (25A) Who is the current provider for Direct Digital Control Systems within the stated area of work? | (25A) Computrols | |
| (25B) Can the Owner provide a POC to this provider for us to tie-in to existing system? | (25B) Automation System Integrators, Seymour, TN (see Computrols’ website) | ||
| 26 | (26A) Who are the current Low Volt Systems providers within the stated area of work? | ||
| a. | Johnson Controls Inc. – 905 Riverside Dr. Asheville, NC | ||
| b. | Johnson Controls Inc. – 905 Riverside Dr. Asheville, NC | ||
| c. | In House (VA) | ||
| (26B) Can the Owner provide a POC to this provider for us to tie-in to existing system? | |||
| a. | Access control | ||
| b. | CCTV | ||
| c. | Paging Systems | ||
| 27 | As a result of the effect of COVID-19 throughout the U.S., and the resulting Federal, State and local governments’ responses / requirements of safe distancing and potential advocations of working remotely and/or complete organization closures, please advise how the Government intends to address delays resulting there as it pertains to the current solicitation schedule for this and all future projects. | The Contracting Officer is aware and monitoring market conditions as they arise to ensure that a measured response is provided that affords win-win outcomes to the maximum extent practicable. During the preformance of any resultant contract, Real World conditions that threaten the success of this project beyond the control of the parties must be identified and handled on a case by case basis as situations arise. | |
| 28 | Due to the current economic inflation, Will the government reduce the amount of time that contractors must hold their numbers to 60 days? By reducing the inflation risk, the government will avoid escalations costs that general contractors and subcontractors must account for. | In an effort to reduce risk to interested parties, the Contracting Officer has included FAR Clause 52.216-4 Economic Price Adjustment - Labor and Material as identified in FAR Provision 52.216-1 within the section titled "Instrcutions, Conditions, and Other Statements to Bidders/Offerors. | |
| 29 | Please confirm that we are required to submit our bids a day prior to the bid due date. Additionally, does the government anticipate any amendments to this solicitation? | Three forms of Bid/Offer submission has been authorized. |
The first authorized means of bid submission, hand deliver your bid which is expressly articulated in Block 13a of the SF 1442 “Sealed offers in original and __1__copies to perform the work required are due at the place specified in Item 8 by __13:30 EDT__ (hour) local time __05-12-2022_ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.”
However, due to unforeseen circumstances the Bid Opening date has changed, please ensure you refer to the summary of changes.
The second authorized means of bid submission is expressly identified within the instruction in Block 10 of the SF 1442 “Please mail all bids to the POC & address identified in Block 8 of this form”.
The Contracting Officer afforded a special authorization in an effort to promote competition to the maximum extent practicable and further afforded bidders the opportunity not to travel by electing to include of FAR Provision 52.214-31 in which specific instructions were drafted IAW FAR 14.202-8 Electronic Bids and also ensure Offerors were afforded the maximum amount of time as defined by FAR 14.304(b)(1). These instructions are contained within INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS para. (a)(3) in the "General Instructions." If submitting an electronic bid the offeror must conform to this requirement or the Bid will be deemed nonresponsive. In accordance with (IAW) FAR 14.304(b)(1) this is the latest point in time in which an electronic bid could be submitted, modified, or withdrawal their bid from consideration without appearing in person.
If the Offeror elects to not submit an electronic bid, the other two options remain available.