This document is an amendment to a solicitation for an HVAC upgrade project at a Veterans Affairs medical facility. The amendment provides responses to industry questions, updates the drawings package, and extends the bid opening date. Key details include upgrading HVAC systems for Phase V at the Veterans Integrated Service Network 6 facility located in Hampton, Virginia. A laydown area will be provided onsite for contractor use. Crane and lift plans must be approved by VA. Existing sprinkler systems need only be repaired if damaged during construction. Reformatted drawings are attached to provide a more accurate basis for contractor takeoffs and bidding. The revised bid opening date is June 2, 2022 at 10:30 AM.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 637-19-102 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 To all Offerors/Bidders

36C24622B0008 03-25-2022

X X X 02 Jun 2022 10:30AM

1. The purpose of this Amendment is to answer the questions submitted by industry in response to this Invitation for Bid (IFB) Amendment A0002. This Amendment also provides an updated format to the initially posted Drawings Set.

Finally, as detailed in this in Block 11 above the Bid Opening Date has been extended to afford interest parties adequate tie in which to completely prepare their bids for submission as a result of this Amendment.

CONTINUATION PAGE

The purpose of this Amendment is to answer the questions submitted by industry in response to this Invitation for Bid (IFB) Amendment A0002. This Amendment also provides an updated format to the initially posted Drawings Set. Finally, as detailed in this in Block 11 above the Bid Opening Date has been extended to afford interest parties adequate tie in which to completely prepare their bids for submission as a result of this Amendment.

Block 14 Continued Below are the responses to the follow-up questions submitted to the Q&A posted in Amendment A0002. Question #’s identified below are from the initial Q&A posted in Amendment A0002.

Question 5 – The location of the Contractor’s lay down area is needed prior to the bid as this will affect the total price for the work. Even if the location will be changed, we need something so that all bidders are bidding the same info.

· Gov’t Response - Lay down area will be located on property. Contractor will not have to acquire off property lay down area. Space is limited and specific space at the time of construction will be assigned based on availability.

Question 6 – the location of where the Contractor is allowed to set a crane and/or man lift is needed prior to the bid as this will affect price- especially since the elevators cannot be used for transporting people or materials to the roof per RFI responses provided. The spec section that is referenced in the response does not provide this info. No information in the DIV 1 spec provides the requested info.

· Gov’t Response - Space for crane location will be made available as close to the construction site as possible. Contractor will be responsible for developing a lift plan with review and approval by the VA.

Question 8 – the response indicates that the Contractors fire protection personnel is to determine if the current existing layout of each area provides the required sprinkler coverage that is needed and if additional heads are required then new calcs, etc… are to be submitted for approval. We must assume that the existing system meets all applicable codes and meets the required coveragea since there is no existing head layout provided with the bid documents. This would need to be priced as a change if needed.

· Gov’t Response - Fire sprinkler requirement and specifications are needed only for any existing sprinkler that is damaged by the contractor. No new sprinklers are anticipated in the building space.

Also, the drawings provided are not to scale. Can updated drawings be provided so that a more accurate takeoff can be completed. This is actually needed on both projects that are bidding next week. Several Subcontractors have asked for this info in order to bid the jobs and will not bid the job unless the scaled drawings can be provided. This was also requested on the Water Loop project but no updated drawings were provided and the response provided with amendment #003 on the water loop project did not address the issue.

· Gov’t Response – Reformatted drawings are made available as Attachment I of this Solicitation Amendment.

(End of Section)

See attached document: S06 Attachment I - Initial Drawing Package Reformatted.