36C24519B0006-002.pdf
PDF 2 MB Posted
- Solicitation number
- 36C24519B0006
About this file
36C24519B0006 PDF Spec.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24519B0006-0004001.pdf | ||
| 36C24519B0006-0004000.docx | DOCX document | |
| 36C24519B0006-0003000.docx | DOCX document | |
| 36C24519B0006-0002001.pdf | ||
| 36C24519B0006-0002002.pdf | ||
| 36C24519B0006-0002003.pdf | ||
| 36C24519B0006-0002000.docx | DOCX document | |
| 36C24519B0006-0002004.pdf | ||
| 36C24519B0006-0001000.docx | DOCX document | |
| 36C24519B0006-0001001.pdf | ||
| 36C24519B0006-005.pdf | ||
| 36C24519B0006-004.docx | DOCX document | |
| 36C24519B0006-003.pdf | ||
| 36C24519B0006-001.docx | DOCX document | |
| 36C24519B0006-006.docx | DOCX document | |
| 36C24519B0006-000.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
03-01-19
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 32 16.13 Network Analysis Schedule – Major Projects 09-15
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 03-19
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 13.13 Glovebag Asbestos Abatement 09-15
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 02-16
04 05 13 Masonry Mortaring 10-17
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 02-16
DIVISION 08 - OPENINGS
08 90 00 Louvers and Vents 05-15
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 06-18
09 23 00 Gypsum Plastering 10-15
09 24 00 Portland Cement Plastering 10-15
09 29 00 Gypsum Board 06-18
09 65 13 Resilient Base and Accessories 02-16
09 91 00 Painting 01-16
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17
03-01-19
00 01 10-2
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 22 13 Steam and Condensate Heating Piping 08-17
31 20 11 Earthwork (Short Form) 10-12
07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
G0.01 COVER SHEET
S1.01 TUNNEL – BASEMENT PLAN
S1.02 LOWER STEEL – FIRST FLOOR INTERSTITIAL KEY PLAN
S1.03 UPPER STEEL – FIRST FLOOR INTERSTITIAL KEY PLAN
S2.00 STRUCTURAL DETAILS
M0.01 MECHANICAL LEGENDS, ABBREVIATIONS AND NOTES
M2.01 MECHANICAL PIPING – BASEMENT INTERSTITIAL KEY PLAN
M2.01a MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-a
M2.01b MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-b
M2.01c MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-c
M2.01d MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-d
M2.01e MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-e
M2.01h MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-h
M2.01m MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-m
M2.01t MECHANICAL PIPING – BASEMENT INTERSTITIAL PLAN-t
M2.02 MECHANICAL PIPING – FIRST FLOOR KEY PLAN
M2.02a MECHANICAL PIPING – FIRST FLOOR PLAN-a
M2.02c MECHANICAL PIPING – FIRST FLOOR PLAN-c
M2.02e MECHANICAL PIPING – FIRST FLOOR PLAN-e
M2.03 MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL KEY PLAN
M2.03a MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL PLAN-a
M2.03b MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL PLAN-b
M2.03c MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL PLAN-c
M2.03d MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL PLAN-d
M2.03e MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL PLAN-e
M2.03g MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL PLAN-g
M2.03h MECHANICAL PIPING – FIRST FLOOR INTERSTITIAL PLAN-h
M3.01 MECHANICAL PIPING – BASEMENT INTERSTITIAL DEMOLITION KEY PLAN
M3.01a MECHANICAL PIPING – BASEMENT INTERSTITIAL DEMOLITION PLAN-a
M3.01b MECHANICAL PIPING – BASEMENT INTERSTITIAL DEMOLITION PLAN-b
M3.01c MECHANICAL PIPING – BASEMENT INTERSTITIAL DEMOLITION PLAN-c
M3.01d MECHANICAL PIPING – BASEMENT INTERSTITIAL DEMOLITION PLAN-d
07-01-15
00 01 15 - 2
M3.01e MECHANICAL PIPING – BASEMENT INTERSTITIAL DEMOLITION PLAN-e
M3.01t MECHANICAL PIPING – BASEMENT INTERSTITIAL DEMOLITION PLAN-t
M4.01 PIPE RISERS
M5.01 MECHANICAL DETAILS
M5.02 MECHANICAL DETAILS
- - - END - - -
10-01-17 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 USE OF ROADWAYS
1.16 RESIDENT ENGINEER'S FIELD OFFICE
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.18 TEMPORARY USE OF EXISTING ELEVATORS
1.19 TEMPORARY USE OF NEW ELEVATORS
1.20 TEMPORARY TOILETS
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
1.22 NEW TELEPHONE EQUIPMENT
1.23 TESTS
1.24 INSTRUCTIONS
1.25 GOVERNMENT-FURNISHED PROPERTY
ii
1.26 RELOCATED // EQUIPMENT // ITEMS //
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.28 CONSTRUCTION SIGN
1.29 SAFETY SIGN
1.30 PHOTOGRAPHIC DOCUMENTATION
1.31 FINAL ELEVATION Digital Images
1.32 HISTORIC PRESERVATION
1.33 VA TRIRIGA CPMS
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Central Campus high-pressure steam and pumped condensate main replacement in Bldg. 500, interface with existing branch piping and the routing to the end of both Building
501 and 502 tunnels, near their respective elevators and interface existing branches there. as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of Valley Engineering, Mount Crawford, VA, as
Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 -2
1.3 STATEMENT OF BID ITEMS
A. Bid Item No.1 (Base Bid):
General Construction: Work includes general construction, alterations, wall openings and replacement for installation and removal of material and certain other items. An allowance of pipe insulation joint mastic removal, believed to be asbestos, shall include 300 joints.
Electrical Work: Work includes all labor, material, and supervision to perform the required electrical construction work on this project including, re-routing of equipment for placement and removal of steam and condensate piping. Rerouting of existing conduits and conductors required to locate the new steam and condensate piping, as shown. An allowance of up to 500 ft. of 1 ½” conduit/conductors and below relocation shall be included. Also include the removal and replacement of (25) lay-in light fixtures.
Mechanical Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including, material storage, rigging, space ventilation for welding and cutting processes, fire watches, protection of existing equipment and utilities.
The primary purpose of this contract is to install new high-pressure steam and pumped condensate mains, full-size from the Bldg. 500 Loading
Dock to the underground tunnel “wye”, with reduced size branches down both Bldg. 501 & 502 tunnels to the respective end-tunnel elevators.
Existing high-pressure steam and pumped condensate piping will be used while this new piping is being installed.
New branch tees, isolation valves and blind flanges shall be installed in the new mains for future interface with existing branches, as shown on the drawings, after the new piping is brought “on-line”. These branch interfaces will be scheduled separately by the Owner and performed by this Contractor. Two valves must be present in each branch for safety. An existing branch isolation valve in the area being served will satisfy the requirement of the second valve. If there is no valve in the area being served, a new isolation valve shall be added.
Additionally, there shall be a vent and drain valve in a convenient location for maintenance, between the two isolation valves.
01 00 00 -3
All pipe support material, insulation, steam traps and accessories, expansion loops and anchors shall be sized and located according to these specifications and drawings. All necessary labor to install these systems shall be provided, including pressure testing.
After all new piping is installed, tested and operated as the primary steam and condensate source, the existing steam and pumped condensate mains, their supports, braces and expansion equipment shall be separated from the new system, with blind flange terminations provided, and removed from the building. The existing 22” Laundry and Trash ducts are abandoned and adjacent to the existing steam and condensate mains.
This whole system shall be removed as well, to provide necessary room for the demolition and removal of the piping from the Basement
Interstitial Space. Temporary building wall openings will be allowed for this material removal and new work staging. The specifics shall be coordinated with the Owner, prior to any cutting.
B. Bid Item No. 2 (Alternate No. 1): All work included in Bid Item No. 1
(Base Bid), except DELETE demolition of old pipe, it’s insulation and associated material. Remove the abandoned Laundry and Trash Duct systems.
C. Bid Item No. 3 (Alternate No. 2): All work included in Bid Item No. 2
(Alternate No.1), except DELETE the new steam and condensate mains from the underground Tunnel “wye” to Area 502. Terminate these pipes with gate valves and blind flanges at the “wye”.
D. Bid Item No. 4 (Alternate No. 3): All work included in Bid Item No. 3
(Alternate No.2), except DELETE the new steam and condensate mains from the underground Tunnel “wye” to Area 501. Terminate these pipes with gate valves and blind flanges at the “wye”.
01 00 00 -4
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
01 00 00 -5
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
01 00 00 -6
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
01 00 00 -7
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workmen are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. // Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Buildings will be occupied during performance of work.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans
Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
01 00 00 -8
H. When a construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
I. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time
01 00 00 -9 approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
K. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall
01 00 00 -10 conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
For hauling, use only established public roads and roads on Medical Center property. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
01 00 00 -11
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
A. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
B. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
C. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
01 00 00 -12
1.18 TEMPORARY USE OF EXISTING ELEVATORS
A. Contractor will not be allowed the use of existing elevators. Outside type hoist shall be used by Contractor for transporting materials and equipment.
1. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractor’s expense.
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, 01 00 00 -13 electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
1.23 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
1.24 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint.
Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
01 00 00 -14
D. Detail Drawing of construction sign showing required legend and other characteristics of sign is shown on the drawings.
1.25 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR.
D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety sign showing required legend and other characteristics of sign is shown on the drawings.
E. Post the number of accident free days on a daily basis.
- - - E N D - - -
09-01-15
01 32 16.13 - 1
SECTION 01 32 16.13
NETWORK ANALYSIS SCHEDULES - MAJOR PROJECTS
PART 1- GENERAL:
1.1 DESCRIPTION:
A. The Contractor shall develop a fully Resource loaded (cost and manpower) Network Analysis System (NAS) plan and computer generated schedule demonstrating fulfillment of the entire contract requirements, shall keep the plan and computer generated schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating, mitigating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). The Contractor’s initial NAS Diagram submission will be the basis for their initial project schedule and will be designated as a Day 1 submission. After review and approval by
VA, this schedule will be designated as the approved Baseline Schedule.
B. Conventional Critical Path Method (CPM) Precedence Diagramming Method
(PDM) technique shall be utilized to satisfy both time and cost applications. All schedule data and reports required under this specification section shall be based upon total float, not relative or free float schedules. The approved baseline NAS diagram and the schedule becomes the official project schedule of record governing schedule management, oversight and actions on the corresponding contract.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate a representative on the site who will be responsible for the preparation, timeliness, quality and the accuracy of the network diagram, review and report progress of the project with and to the Contracting Officer's representative.
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section and such authority shall not be interrupted throughout the duration of the project.
1.3 CONTRACTOR'S CONSULTANT:
A. To fulfill all of the requirements of this specification section, the
Contractor shall engage an independent CPM consultant who is skilled in the time and cost application of scheduling using (PDM) network techniques for similar sized construction projects. The cost of which
01 32 16.13 - 2 is included in the Contractor's bid proposal price. This consultant shall not have any financial ties, business ties, affiliation with or a subsidiary company of the Contractor. The consultant is expected to provide unbiased professional services to the contractor and to VA’s representatives in developing and maintaining the project schedule.
B. Prior to engaging a consultant, and within 10 calendar days after award of the contract, the Contractor shall submit to the Contracting
Officer:
1. The name and address of the proposed consultant and Company.
2. Sufficient information to show that the proposed consultant has the qualifications to meet the requirements specified in this specification section.
3. A list of prior construction projects, along with selected PDM network diagram samples on current projects which the proposed consultant has performed complete project scheduling services. These network diagram samples must show complete project planning for a project of similar size and scope as covered under this contract.
C. The Contracting Officer has the right to approve or disapprove employment of the proposed consultant, and will notify the Contractor of the VA decision within seven calendar days from receipt of information. In case of disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration.
The contractor must have their CPM Consultant approved prior to i) submitting the Day 1 diagram and schedule, ii) Notice to Proceed, iii)
Pre-construction Conference.
1.4 PRIOR TO BASELINE SCHEDULE ACCEPTANCE
A. At the time of the Pre-Construction Conference, prior to the issuance of the project Notice to Proceed, the Contractor and the Contractor’s
Scheduling Consultant shall arrange a separate meeting with the
Contracting Officer and/or his representative to discuss the requirements of this specification.
B. With exception of bonds, insurance, and limited mobilization cost associated with preparatory work such as site trailers, staging areas, haul roads etc., the approval of the baseline NAS schedule is a condition precedent to:
1. Processing of contractor’s pay request(s) for any construction activities/items of work.
2. Review of any schedule updates.
01 32 16.13 - 3
C. Government review comments on the contractor’s schedule shall not relieve the contractor from compliance with requirements of this specification section and the remaining contract documents.
PART 2 - SCHEDULE CRITERIA / DATA REQUIREMENTS:
2.1 COMPUTER PRODUCED SCHEDULE DEVELOPMENT CRITERIA
A. The computer produced schedule shall be prepared and maintained using
Primavera P6 software.
B. Work activity/event relationships shall be restricted to Finish-to-
Start (FS) and Start-to-Start (SS) only without lead or lag constraints. Note: Some exception may be allowed for lag in SS relationship, but must be approved by the VA’s contracting officer on case by case basis prior to inclusion in the schedule.
C. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting
Officer. The contractor shall make a separate written detailed request to the Contracting Officer identifying these date constraints and secure the Contracting Officer’s written approval before incorporating them into the network diagram. The Contracting Officer’s separate approval of the network diagram shall not excuse the contractor of this requirement.
D. Logic events (non-work) will be permitted where necessary to reflect proper logic among work events, but must have zero duration. The complete computer schedule shall reflect the Contractor's approach to pursuing the entire project.
E. Intermediate Phasing milestones contained in the contract documents shall be clearly shown in the schedule.
F. The Contractor’s initial Day 1 submission, prior to VA review and approval, in its original form shall reflect the original contract scope of work.
G. Early Project Completion or “Short Schedule” – VA will not approve any baseline schedule which shows completion date prior to the contract completion date. Also, there should not be any “filler or
“contingency” type of activities to fill the entire contract duration.
VA has no obligation to accelerate activities to support a proposed early contract completion. However, if the subsequent updates show that early handover is feasible due to “ahead of schedule” situation, 01 32 16.13 - 4
VA may accept the facility earlier at no additional cost to the government.
H. The Baseline Schedule Critical Path of the project shall be limited to:
1. No more than 20% of the activities shall be on the critical and near-critical path(s). Critical path is defined as activities with zero (0) day total float. Near-Critical path(s) is defined as activities with one (1) to twenty (20) days of total float.
2. Multiple Critical paths will not be allowed.
I. The Contractor shall show activities/events for:
1. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre-construction work.
2. Contracting Officer's and Architect-Engineer's review and approval of shop drawings, equipment schedules samples, template, or similar items with time duration of no less than 20 workdays.
3. Shutdowns or Interruption of VA Medical Center utilities, delivery of Government furnished equipment (GFE), and rough-in drawings, project phasing and any other specification requirements.
4. VC/VV Equipment - All significant VC (VA furnished and Contractor installed) and VV (VA furnished and VA installed) equipment shall be clearly shown in the schedule. Any smaller VC and VV Equipment shall also be logically grouped together and shown in the schedule.
5. Test, balance and adjust various systems and pieces of equipment, maintenance and operation manuals, instructions and preventive maintenance tasks.
6. Commissioning (Cx)Activities – Based upon the project specific
Commissioning plan and project specification section 01 91 00, the contractor shall include in the Day 1 NAS Diagram all the systems commissioning activities (see systems covered in Division 7, 8, 21, 22, 23, 26, 28, 31 and others as specified) such as start up, Pre-functional check list, Pre–test, individual component and system level Functional test, Operator’s training, O.& M. Manuals etc.(including any deficiency correction and re-testing). The majority of commissioning activities should be completed as part of the normal construction schedule and finalized prior to the construction contract completion date. To this end, it is imperative that the Commissioning Agent and the Contractor collaborate to integrate commissioning activities into the
Contractor’s overall construction schedule. All commissioning
01 32 16.13 - 5 activities shall be cost loaded as required in the earlier paragraphs. The Commissioning Plan will identify critical commissioning activities and associated construction/start up tasks that must precede these activities to allow for successful execution of the commissioning activities. In order to coordinate these activities with the construction schedule, a Commissioning Duration
Schedule should be provided by the Commissioning Agent to the VA SRE and the Contractor to provide a rational basis for integration of commissioning into the Day 1 NAS diagram and the construction schedule. The Commissioning Duration Schedule should include the following information:
I. Description of Commissioning Activity
II. Prerequisite Construction Tasks Required to Execute the Cx Activity
III. Elapsed Time Duration of Each Activity
IV. Documentation Associated with Each Task/Document
Responsibility
7. Once the duration schedule is delivered to the Contractor, the
Contractor will collaborate with the Commissioning Agent to integrate all commissioning activities into the fixed duration construction schedule in accordance with VA NAS requirements for scheduling the project. The Baseline Schedule, as approved by the VA at the beginning, may not have all necessary Cx details, but the contractor is required to subsequently update the commissioning activities as more detailed Commissioning Duration Schedule is being developed.
J. VA inspection and acceptance activity/event with a minimum duration of five work days at the end of each phase and immediately preceding any
VA move activity/event required by the contract phasing for that phase.
Schedule these activities/events so that only one phase is scheduled for completion within the same 30 consecutive calendar day period
(except for those phases immediately preceding the final acceptance).
Maintain this scheduling condition throughout the length of the contract unless waived by the Contracting Officer’s representative in writing.
K. Work activities/events for the asbestos abatement bid item shall have a trade code of ASB.
01 32 16.13 - 6
L. Bid items other than the Base Bid (ITEM 1) and Asbestos Abatement item shall have trade codes corresponding to the appropriate bid item number
(e.g., ITM 3, ITM 4 and other items).
1. Show not only the activities/events for actual construction work for each trade category of the project, but also trade relationships to indicate the movement of trades from one area, floor, or building, to another area, floor, or building, for at least five trades who are performing major work under this contract.
2. Break up the work into activities/events shall have:
a. Duration no longer than 20 work days each, except as to non-construction activities/events (i.e., procurement of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the Contracting Officer may approve the showing of a longer duration.
b. The duration for VA approval of any required submittal, shop drawing, or other submittals shall not be less than 20 work days.
Refer to drawing CPM-1 for VA approval activities/events which will require minimum duration longer than 20 workdays. The construction time as determined by the CPM schedule from early start to late finish for any sub-phase, phase or the entire project shall not exceed the contract time(s) specified or shown.
c. An activity/event shall only reflect the work of one entity
(subcontract or craft).
d. The activity/event once began can continue unimpeded until the activity/event is complete.
3. Describe work activities/events clearly, so the work is readily identifiable with clear scope for assessment of completion.
Activities/events labeled "start," "continue," or "completion," are not specific and will not be allowed. Lead and lag time activities will not be acceptable (Refer to item 2.1 B above for some exceptions).
4. Uniquely number each activity/event ID with ALPHA-NUMERIC value in ascending order. The network diagram should be generally numbered in such a way to reflect trade discipline, phase or location of the work.
2.2 WORK ACTIVITY/EVENT COST AND TRADE RESOURCE DATA
A. Cost Loading - The Contractor shall cost load all work activities/events except procurement activities. The cost loading shall
01 32 16.13 - 7 reflect the appropriate level of effort of the work activities/events.
The cumulative amount of all cost loaded work activities/events
(including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish. These cash flow curves will be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading. In the event of disapproval, the
Contractor shall revise and resubmit in accordance with Article, THE
INITIAL DAY ONE SCHEDULE SUBMITTAL (Item 3.1B below). Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in the FAR 52.232 – 5 (PAYMENTS UNDER FIXED-PRICE
CONSTRUCTION), Article, and VAAR 852.236 - 83(PAYMENTS UNDER
FIXED-PRICE CONSTRUCTION).
C. The Contractor shall cost load work activities/events for ASBESTOS
ABATEMENT. The sum of asbestos abatement work activity/event costs shall equal the value of the asbestos bid item in the Contractors' bid.
D. The Contractor shall cost load work activities/events for all BID
ITEMS. The sum of the cost loading for each bid item work activities/events shall equal the value of the item in the Contractors' bid.
E. Work activities/events for Contractor bond shall have a trade code and area code of BOND.
F. Manpower loading - In accordance with Article PERFORMANCE OF WORK BY
THE CONTRACTOR in FAR 52.236 – 1 and VAAR 852.236 - 72, the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this Section, a responsibility code for all activities/events of the project for which the
Contractor's forces will perform the work. This shall be the basis for the “Resource loading” of the schedule and the contractor shall provide
“Manpower loading” reports by trades and the overall Trade manpower requirements, when requested by the contracting officer or his/her representatives.
01 32 16.13 - 8
2.3 NETWORK DIAGRAM (NAS) DATA REQUIREMENTS:
A. The Day 1 NAS diagram is the logical plan and forms the basis for contractor’s baseline schedule. Participation and input of key construction personnel from the general contractor and the major subcontractors is a mandatory requirement in the baseline schedule development. The Day 1 NAS diagram in its original form shall reflect the original contract scope of work and contain no contract changes or delays which may have been incurred during the final NAS diagram and baseline schedule development period and shall reflect the entire contract duration as defined in the bid documents. Show on the NAS diagram the sequence and interdependence of work activities/events required for complete performance of all items of work. In preparing the NAS diagram, the Contractor shall:
1. Exercise sufficient care to produce a clear, legible and accurate network diagram, refer to the construction document (CD) drawing, CPM-1 (Sample CPM Network. Computer plotted network diagrams shall legibly display and plot all information required by the VA CPM activity/event legend, otherwise the computer plotted network diagram will not be accepted. If the computer plotted network diagram is not found acceptable by the contracting officer’s representative, then the network diagram will need to be hand drafted and meet legibility requirements. Provide a key plan on each network diagram sheet showing the project area associated with the work activities/events shown on that sheet.
2. Show the following on each work activity/event:
a. Activity/Event ID number.
b. Concise description of the work represented by the location and activity/event.
c. Activity coding – Provide activity coding (five alpha characters or less) for Trades (GEN, MECH, ELEC, CARP, PLAST, or other acceptable abbreviations), Area, Phasing etc. Provide a dictionary of all coding in the front page of the NAS Diagram.
d. Duration (in work days.)
e. Cost (in accordance with Article, ACTIVITY/EVENT COST DATA of this section and less than $9,999,999 per activity).
f. Manpower required (average number of workers per day). Load manpower for each and every activity with proper trade codes in the “resource” field of P6 for ease of generating individual
01 32 16.13 - 9
Trade and overall manpower profile required to plan and complete the project.
g. No open-ended activities with exception of Notice to Proceed and the Final Completion node.
h. The SYMBOL LEGEND format shown below and on the drawing, CPM-1
(Sample CPM Network) is mandatory and shall be followed in preparing final network diagrams.
Pull PowerWiring 1-FL
East
Relationship from Event Elsewhere in the Network
Trade Bump
Relationship Out
Relationship from
Material Event
Relationship to Event Elsewhere in the NetworkTrade Bump
Relationship in
ELE 1FL-
E5 2 120
Event
Identification
Relationship from
Preceeding Event Relationship to
Suceeding Events
S F
Activity
Duration
Manpower
Total Labor &
Material Cost
Area Code
Trade Code
SYMBOL LEGEND
Event Description
Show Network Diagram page number location(s) for all incoming/outgoing node connector(s).
B. To the extent that the network diagram or any revised network diagram shows anything not jointly agreed upon, it shall not be deemed to have been approved by the Contracting Officer. Failure to include any element of work required for the performance of this contract shall not excuse the Contractor from completing all work required within any applicable completion date of each phase regardless of the Contracting
Officer's approval of the network diagram.
C. Compact Disk Requirements and CPM Activity/Event Record Specifications:
Submit to the VA (Senior Resident Engineer and CPM Schedule Analyst) an electronic file(s) containing one file of the data required to produce
01 32 16.13 - 10 a Primavera (P6), (PDM) produced…