36C24519B0006-0003000.docx

DOCX document 18 KB Posted

Attached to
Repair-Upgrade Central Campus Steam Distribution System Project #613-15-301
Solicitation number
36C24519B0006
Issued by

About this file

36C24519B0006 0003 36C24519B0006 0003.docx

View the file

Other files

File Type Posted
36C24519B0006-0004001.pdf PDF
36C24519B0006-0004000.docx DOCX document
36C24519B0006-0002001.pdf PDF
36C24519B0006-0002002.pdf PDF
36C24519B0006-0002003.pdf PDF
36C24519B0006-0002000.docx DOCX document
36C24519B0006-0002004.pdf PDF
36C24519B0006-0001000.docx DOCX document
36C24519B0006-0001001.pdf PDF
36C24519B0006-005.pdf PDF
36C24519B0006-004.docx DOCX document
36C24519B0006-003.pdf PDF
36C24519B0006-002.pdf PDF
36C24519B0006-001.docx DOCX document
36C24519B0006-006.docx DOCX document
36C24519B0006-000.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 613-15-301 Department of Veterans Affairs

VAMC (613)

VISN 5 Contract Satellite Office 510 Butler Avenue, Building 306A Martinsburg

WV

25405 Department of Veterans Affairs

VAMC (613)

VISN 5 Contract Satellite Office 510 Butler Avenue, Building 308B Martinsburg

WV

25405 To all Offerors/Bidders

36C24519B0006

X X

X Subject Solicitation Shall be Amended as Follows:

1. Provide questions and answers received.

2. All other terms and conditions remain unchanged.

Kathryn C. Leatherman Contracting Officer 304-263-0811 ext. 2083 Q1) Construction note 2 on drawing M2.01a says to route the new 2.5” pumped condensate down to existing 1.5” pipe but drawings show the new piping to be 1.5”.

What is the proper size?

A1) New pumped condensate is 1.5” Q2) Spec section 23 05 11, 1.5, E,3 talks about coordination drawings.

Are coordination drawings required for this project?

A2) Yes coordination drawings are required, see paragraph 23 05 11, 1.4, H Q3) In the description of work, under the base bid mechanical work, it says “Two valves must be present in each branch for safety”.

Please explain what this means. Where in the branch are the valves to be located? Are the valves to be installed back to back or is there a certain distance needed between them? Is this to be done every time there is a tee in the line?

A3) Putting a drain valve between (2) shut-off valves allows a point to drain the condensate, and to provide extra safety

Q4) In the description of work, under bid item 2, it says “Delete demolition of old pipe, its insulation and associated material. Remove the abandoned laundry and trash duct systems”.

Is the section stating to remove the laundry and trash duct systems telling us to remove this portion of the work from the bid, or is it restating that this system is to be removed from the building?

A4) If the alternate is taken, the removal of the existing laundry and trash duct is still required to make room for the new steam and condensate piping to be installed. The alternate describes not removing old piping, but ductwork is to be removed.