About this file

36C24518R0046 A00006 Eastern_Central West Virginia Specific Questions and answers MATOC II.pdf

View the file

Other files

File Type Posted
36C24518R0046-A00007000.docx DOCX document
36C24518R0046-A00007001.pdf PDF
36C24518R0046-A00006002.pdf PDF
36C24518R0046-A00006003.pdf PDF
36C24518R0046-A00006000.docx DOCX document
36C24518R0046-A00005010.pdf PDF
36C24518R0046-A00005007.pdf PDF
36C24518R0046-A00005000.docx DOCX document
36C24518R0046-A00005005.pdf PDF
36C24518R0046-A00005009.pdf PDF
36C24518R0046-A00005003.pdf PDF
36C24518R0046-A00005004.pdf PDF
36C24518R0046-A00005006.pdf PDF
36C24518R0046-A00005002.pdf PDF
36C24518R0046-A00005011.pdf PDF
36C24518R0046-A00005001.pdf PDF
36C24518R0046-A00005008.pdf PDF
36C24518R0046-A00004000.docx DOCX document
36C24518R0046-A00003001.pdf PDF
36C24518R0046-A00003005.pdf PDF
36C24518R0046-A00003004.pdf PDF
36C24518R0046-A00003003.pdf PDF
36C24518R0046-A00003002.pdf PDF
36C24518R0046-A00003008.pdf PDF
36C24518R0046-A00003007.pdf PDF
36C24518R0046-A00003006.pdf PDF
36C24518R0046-A00003000.docx DOCX document
36C24518R0046-A00002000.docx DOCX document
36C24518R0046-00001000.docx DOCX document
36C24518R0046-027.pdf PDF
36C24518R0046-021.pdf PDF
36C24518R0046-028.xlsx XLSX spreadsheet
36C24518R0046-010.pdf PDF
36C24518R0046-033.pdf PDF
36C24518R0046-023.pdf PDF
36C24518R0046-024.pdf PDF
36C24518R0046-004.pdf PDF
36C24518R0046-020.pdf PDF
36C24518R0046-019.pdf PDF
36C24518R0046-017.pdf PDF
36C24518R0046-003.docx DOCX document
36C24518R0046-008.pdf PDF
36C24518R0046-034.pdf PDF
36C24518R0046-022.pdf PDF
36C24518R0046-006.pdf PDF
36C24518R0046-012.pdf PDF
36C24518R0046-015.pdf PDF
36C24518R0046-009.pdf PDF
36C24518R0046-014.docx DOCX document
36C24518R0046-018.pdf PDF
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Martinsburg Question/Answers:

RFI’s

VISN 5 Construction MATOC - seed projects Martinsburg Building 500 Continuous

Water Monitoring System

22. Question: The following spec sections are listed in the Table of Contents for the Martinsburg project, but are not included with the specifications. Please advise if these sections will be provided.

00 10 15 - List of Drawing Sheets, 01 91 00 - General Commissioning Requirements, 02 82 11 -

Traditional Asbestos Abatement, 09 06 00 - Schedule for Finishes, 09 91 00 - Painting, 22 05 19 - Meters and Gages for Plumbing Piping, 27 53 19 - Distributed Radio Antenna (Within Building) Equipment and

System.

Answer: 00 10 15 - List of Drawing Sheets, Spec 00 01 15 provided

01 91 00 - General Commissioning Requirements, not required – see revised 00 01 10

02 82 11 - Traditional Asbestos Abatement, not required – use provided specification 02

82 13.13 Glovebag Asbestos Abatement

09 06 00 - Schedule for Finishes, not required – see revised 00 01 10

09 91 00 – Painting, not required – see revised 00 01 10

22 05 19 - Meters and Gages for Plumbing Piping, not required – see revised 00 01 10

27 53 19 - Distributed Radio Antenna (Within Building) Equipment and System, not required – see revised 00 01 10

23. Question: Please provide the duration for the Martinsburg Seed project.

Answer: 120 calendar days (4 months)