- VISN 5 CONSTRUCTION MULTIPLE AWARD TASK ORDER CONTRACT $2, 000 - $1, 000, 000 AKA: MATOC TWO
- Solicitation number
- 36C24518R0046
About this file
36C24518R0046 A00006 Eastern_Central West Virginia Specific Questions and answers MATOC II.pdf
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Martinsburg Question/Answers:
RFI’s
VISN 5 Construction MATOC - seed projects Martinsburg Building 500 Continuous
Water Monitoring System
22. Question: The following spec sections are listed in the Table of Contents for the Martinsburg project, but are not included with the specifications. Please advise if these sections will be provided.
00 10 15 - List of Drawing Sheets, 01 91 00 - General Commissioning Requirements, 02 82 11 -
Traditional Asbestos Abatement, 09 06 00 - Schedule for Finishes, 09 91 00 - Painting, 22 05 19 - Meters and Gages for Plumbing Piping, 27 53 19 - Distributed Radio Antenna (Within Building) Equipment and
System.
Answer: 00 10 15 - List of Drawing Sheets, Spec 00 01 15 provided
01 91 00 - General Commissioning Requirements, not required – see revised 00 01 10
02 82 11 - Traditional Asbestos Abatement, not required – use provided specification 02
82 13.13 Glovebag Asbestos Abatement
09 06 00 - Schedule for Finishes, not required – see revised 00 01 10
09 91 00 – Painting, not required – see revised 00 01 10
22 05 19 - Meters and Gages for Plumbing Piping, not required – see revised 00 01 10
27 53 19 - Distributed Radio Antenna (Within Building) Equipment and System, not required – see revised 00 01 10
23. Question: Please provide the duration for the Martinsburg Seed project.
Answer: 120 calendar days (4 months)