SOW Replace Steam Traps Phase One DB.pdf

PDF 285 KB Posted

Attached to
Z1DA--595-24-106 Replace Steam Traps Phase 1 D/B (VA-24-00024837)
Solicitation number
36C24424R0084
Issued by

About this file

This document is a Scope of Work (SOW) for a Design-Build contract to replace steam traps at the Lebanon VA Medical Center in Lebanon, PA. The project is to replace 93 steam traps with 87 new steel steam traps, including all necessary connections, unions, and piping. The contractor will also re-pipe the check valves associated with four specific steam traps. The Design-Build team will provide all professional design and construction services, including site investigation, contract drawings and specifications, construction period services, and installation.

The SOW provides detailed requirements for the 35% and 100% design submissions, as well as the construction document submission. It specifies a 180-day construction schedule, with all work to be performed between April 15th and October 15th. The contractor will be required to collaborate with the VA's Pipe Shop during the project. The document includes an attachment listing the existing steam trap locations, sizes, and recommended replacement details.

The related federal contract opportunity is a Pre-Solicitation for a Design-Build contract to replace the steam traps. It is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside solicitation, with an estimated construction value between $250,000 and $500,000. The contract will be awarded as a Firm-Fixed-Price contract with a 270-day period of performance.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lebanon VA Medical Center Lebanon, PA 17042

Design-Build (DB) Scope of Work Replace Steam Traps Phase 1 D-B

595-24-106

Construction Documents Ready by 90 days after Notice to Proceed (NTP) issued Construction Complete by 180 days after NTP issued Contracting Officer: Christopher McDevitt Contracting Officers Representative (COR): Matt Donmoyer

-- Services --

• Provide all labor, materials, tools and equipment, and the design-build services necessary for design and construction of a project described herein as well as other specific tasks as further defined by this Request for Proposal (RFP) the Design-Build Project No. 595-24-106, Replace Steam Traps Phase 1 D-B. This procurement shall provide required design completion of the aforementioned project and perform construction of completed design work. Project shall be designed and completed in accordance with VA Criteria, ASHRAE, and VA Specifications developed for the project.

• This Request for Proposal (RFP) document is intended to generally define the scope and design parameters to be included in this project. It is the responsibility of the Design-Build team to provide a complete set of approved design documents in a manner consistent with the VA guidelines, specifications, and design standards in order to complete construction within a 180-day schedule.

• Offeror shall be prepared for a 180-day schedule as indicated below in the Project Schedule.

Offeror may propose an alternate schedule, in addition to the 180-day schedule, which will be reviewed by the VA. Schedules shall indicate the following:

o The design period which shall include provisions for VA reviews.

o Phasing plans and outage plans o All outages shall occur on weekends between 15 April and 15 October o Construction period services including:

• Mobilization

• Demolition

• Procurement and installation of equipment

• Provisions for overtime or shift work shall be included in the contract offer.

• Equipment unloading, placing, inspection, testing, commissioning, and reports

PROVIDE:

Professional Design-Build (DB) construction services to include but not limited to:

• Site investigation – mechanical/plumbing and any other engineering services as needed.

• Contract drawings and specifications for construction.

• Construction period services for DB A/E - review of shop drawing submissions, provide recommendations regarding contractor change proposals and requests for information (RFI), DB A/E shall visit site per VA's request, add to drawings as-built conditions from contractor's record drawings; DB A/E shall respond on site within a two-hour period when requested.

• Construction and Installation services of the Steam Traps, including all Management, Supervision, Labor, Transportation, Equipment and Materials and to perform work to include demolition, general construction, alterations, mechanical and electrical work, and certain other items as required by project drawings and specifications to create a complete and useable facility.

-- Project Scope --

GENERAL:

Provide sufficient construction documents for a project that shall replace failed steam traps at various locations throughout the Lebanon VAMC campus. Offeror shall make layout changes, calculations, and provide documentation to support their design. Replacement steam traps shall be designed and installed as per the specifications and drawings approved through the Design and Project Design Team (PDT) process.

SPECIFICS:

The project is intended to replace 93 steam traps with 87 steam traps, along with all necessary connections, unions, and piping, at various locations across the campus. A complete list of the steam traps, their sizes, locations, recommended replacement size and recommended replacement type is part of Attachment A. All new steam traps and associated components must be steel as shown in VA Specification Section 232213. Cast iron is not acceptable in this contract.

• The contractor shall also re-pipe the check valve associated with steam traps #63, 64, 65 and

66.

• The contractor shall determine the appropriate PSI rating for each replacement steam trap based on its usage. In general steam traps rate below 30 psi shall be replaced with steam traps rated 30 psi.

• The contractor shall remove and re-pipe the parallel traps at six locations in the gym, replacing them with single traps

• Cast Iron components and traps are not acceptable, contractor shall provide steel traps and components from manufacturers that meet the quality and certification standards from specification section 232213.

• All work must be completed to current codes and standards

• All work must be re-insulated

• All on-site work must be performed between 15 April and 15 October. Shutdowns shall only occur on weekends and shall require scheduling and approval by the VA. Installation will be required to occur during times that will minimize impact to the patients, staff and hospital in general, and outages shall be kept to an absolute minimum and scheduled at the convenience of the government.

• Collaboration between Design-Build team, COR and Lebanon VAMC Pipe shop will be required during the project.

• All work shall comply with the IBC, National Fire Protection Association (NFPA) 70 (National Electrical Code), 70B, 70E, 72, 99, 101, 20, 24, 25 Occupational Safety and Health Administration (OSHA) regulations and the VA Plumbing and HVAC Design manuals.

• All work must comply with OSHA and Lebanon VAMC lockout/tagout requirements

• All equipment tags must be restored on the replacement equipment and the contractor shall add an

“A” to the tag number to indicate the replacement of the steam trap.

• All steam traps shall be tested, and testing logs provided to the VA.

• Design drawings shall be stamped by a Mechanical Engineer licensed in the state of Pennsylvania.

Construction shall be addressed in phases to allow operations to continue during construction to the greatest extent possible. Phasing shall be determined during the 35% design review. Phasing must work within budget and allow the VA to continue operations at minimal interference.

The DB A/E is responsible for providing certified industrial hygiene services to perform asbestos survey investigations, bulk sampling, development of specifications and drawings, and construction period services. All designs shall be accomplished in accordance with VA guidelines and specifications, which are available on the Internet at http://www.cfm.va.gov/til/. DB A/E shall pay particular attention to NFPA, BOCA, VA Handbook 7610 space criteria and VA program guide PG-18-

14. SPECIAL NOTE: Be reminded that the VA guidelines are just a guide, and the project is not bound by them. If current healthcare trends dictate a different design approach is needed, we shall follow that approach.

The DB A/E shall provide professional architectural and engineering and construction services for the project and is responsible for providing all services necessary for design of this project – i.e.

mechanical/plumbing, electrical, structural, etc.

The DB construction contractor shall provide all Management, Supervision, Labor, Transportation, Equipment and Materials and perform work to include demolition, general construction, alterations, mechanical and electrical work, and certain other items as required by project drawings and specifications complete the Replace Steam Traps Phase 1 Project.

-- Site Investigations --

EXPECTATION: The DB A/E shall make site visits as necessary to survey existing conditions.

Make site visits as required to determine existing as-built conditions affecting this project. NOTE:

Information including drawings and other documentation provided to the DB A/E is used as reference only. All additional references and specifications are available in VHA’s Technical Information Library at address: http://www.cfm.va.gov/til/. AutoCAD background drawings will be provided by the VA upon request. The DB A/E shall field verify all dimensions. The DB A/E shall field verify every aspect that relates to the project. Coordinate site visits with the Contracting Officer Representative (COR) as determined after award.

-- Project Schedule --

EXPECTATION: Submit review packages so they are received on the noted day

SUBMISSIONS:

Submit review packages so they are received on the noted day (calendar days after NTP) or earlier:

Initial PDT Meeting ............................................................................................. 0 days

Design Development Documents (35%) ..................................................... 27 days (PDT Meeting) ............................................................................................ 41 days

Design Development Documents (100%) ......................................................... 62 days (PDT Meeting) ............................................................................................ 76 days

Construction Documents .................................................................................. 90 days Begin Construction on or before .................................................................... 120 days

Complete Construction on or before ............................................................... 180 days

Note: The issuance of the Notice to Proceed (NTP) for design will be at the first Project Design Team (PDT) Meeting. The Design-Build Team Contractor shall be required to attend and take minutes of each PDT meeting. Minutes shall be submitted electronically to the Project Manager and Contracting Officer within three calendar days of each meeting for approval and to be added to the official contract file.

-- Design Requirements/Submissions --

EXPECTATIONS: Submit complete review package in accordance with the following requirements and guidelines outlined in http://www.cfm.va.gov/til/aeDesSubReq.asp Please pay http://www.cfm.va.gov/til/ http://www.cfm.va.gov/til/ http://www.cfm.va.gov/til/aeDesSubReq.asp specific attention to the schematic, design and construction submission requirements. As appropriate and depending upon the complexity of the design, the DB A/E may elect to delete individual submissions where not required (i.e. Do not address Site Development, Landscaping for interior renovation projects)

DELIVER:

Submit all design/bid submission packages directly to the Contracting Officer Representative on the established dates to allow the VA time to review. Include all information as follows and as outlined in the attachments for each submission. Information required for each submittal is outlined in Program Guide PG-18-15 Volume C November 2008. The manual is available at the following address:

http://www.cfm.va.gov/til/aeDesSubReq.asp

Area of Construction: See Attachment “A”.

Design Development 35%: Attachment “B” 35% Submission Requirements

• Requirements for the 35% Design Development Documents Submission.

• Define the design elements based on the presented option and submit all information required by the PG-18-15 (35% Design Development).

• Identify Working Drawings scope within the construction budget.

• Identify all design calculations.

• Identify impact of existing asbestos.

• Develop plans and marked up specifications to meet all applicable federal and state

• codes/requirements, including but not limited to IBC, OSHA, DEP, EPA, NEC, NFPA 20, 24, 25, 70, 72, 99, 101, 110.

• Identify all design calculations.

• Identify all existing utilities and utilities requirements.

• Identify all potential bid deduct alternatives.

• Identify all phasing requirements for construction.

• Develop Infection Control Risk Assessment (VA EC-43)

Design Development 100%: Attachment “C” 100% Submission Requirements

• Requirements for the 100% Design Development Documents Submission.

• Address all comments from the 35% review.

• Consolidate all necessary submittals by specification section on an Excel spreadsheet.

Checklist to be utilized to track/monitor submittal process.

• Revise and update cost estimate.

• Finalize all design calculations.

• Finalize all phasing requirements for construction.

• Finalize impact of existing asbestos.

• Finalize Infection Control Risk Assessment (VA EC-43)

• Address all comments from the VISN Safety & Fire Protection Review.

Construction Documents (CD): Attachment “D” Construction Documents Submission Requirements Submit a complete set of documents of all contract requirements. The Cover Page shall be submitted for approval signatures. If necessary, update and submit until approved by the VA.

-- Construction Period Services --

Expectations: Respond to submittals and other requests in a timely manner.

PROVIDE:

http://www.cfm.va.gov/til/aeDesSubReq.asp

• Review all shop drawing submissions and provide recommendations to the VA within five calendar days upon request.

• Make site visits on requests of the VA and prepare written reports to include agreed upon changes in design as determined necessary during the construction. Visits made based on errors and omissions in design shall be at no cost to the VA.

• Participate in partial and/or final acceptance inspections as scheduled and generate punch list items for completion. The punch list shall reference the contract documents for specific deficiencies (i.e. specification section, drawing detail, etc.)

• Prepare as-built drawings on original set with DB A/E’s stamp, based on record drawings that the contractor kept during construction. Transpose contractor’s as-built’s to AutoCAD 2007 – 2019 and in PDF form and provide a set of updated as-built’s on CD within 30 days to the COR

ATTACHMENT “A”

See attached excel spreadsheet “SOW Attachment A Steam Traps”

Current Steam Trap Installed Building Location FL Tag Elev Size Mfg Model Psig Equip. Comments

1 Service Room B 117 5 3/4" SO 52 25 Drip

1 Service Room B 119 2 1/2" SO 52 25 Drip

1 Service Room B 132 4 3/4" SO TD52 80 Drip

1 541 Mech Rm 5 261 2 3/4" SO B1H 25 Drip

1 A Side Attic 6 248 5 3/4" SO FT15 20 HUH

1 B Side Attic 6 258 6 3/4" SO FT30 20 HUH

2 Basement B 221 5 3/4" SO 52 10 Drip

2 Attic 4 217 4 3/4" AG 811 10 Drip

3 Storage in pit B 352 -2 1/2" SO 52 5 Drip Condensate pump

4 Mech Rm B 349 3 1/2" SO TD52 80 Drip

5 Mech Rm B 347 7 1/2" SO 52 5 Drip

6 Mech B 83 7 3/4" SO FT15 5 HUH

7 Storage 2 B 75 6 3/4" SO FT15 10 Drip

7 Pipe storage B 77 5 3/4" SO FT15 10 Drip

7 Pipe storage pit B 78 -2 3/4" SO TD52 80 Drip

7 SW corner G SW 15 3/4" SO FT15 10 HUH From landing doc

7 By machines G M 8 3/4" SO FT15 10 HUH

10 Basement pump B 146 5 1/2" SO TD52 100 Drip

10 Tunnel entrance B 150 1 1/2" SO TD52 100 Drip

10 Boiler storage G 143 9 3/4" SO B1H 40 VUH

10 Chiller G 154 9 1" SO 30 40 HUH

10 Chiller G 158 15 1" SO 30 40 HUH

10 Chiller G 159 15 3/4" SO 30 40 HUH

17 Service Room B 315 4 1/2" SO 52 25 Drip

17 Service Room B 318 3 1/2" SO 52 25 Drip

17 Crawl B 332 4 3/4" WM 1031 80 Drip

17 Stairs 3 Crawl B 333 4 1/2" SO TD52 80 Drip

17 Stairs 3 Crawl B 335 5 3/4" SO FT15 5 Drip

17 Stairs 3 Crawl B 341 2 1" WM FT30 20 Drip Behind 333

17 Attic 5 282 3 1/2" SO 52 20 Drip

17 Attic 5 289 1 1 1/4" MEP 44-530 10 STS 3/4" line

17 Attic 5 294 5 3/4" NN FTN 25 HUH

17 Attic 5 304 1 1/2" SO FT15 12 Drip

17 Attic 5 309 5 3/4" NN FTN 25 HUH

18 Service Room B 189 5 1/2" SO 52 25 Drip

18 Service Room B 190 6 3/4" SO FT15 25 Drip

18 Service Room B 193 5 3/4" SO FT15 5 Drip

18 Tunnel B 201 2 1" SO FT15 5 Drip

18 Tunnel B 202 2 1" SO FT15 5 Drip

18 Tunnel B 203 2 3/4" SO FT15 5 Drip

18 Roof Access 1 1 184 3 1 1/4" NN FTN 25 AHU

18 Attic A Side 5 162 4 3/4" NN 805 25 Drip

18 Attic A Side 5 165 3 2" NN FTN 25 HEX Control valve failed

18 Attic A Side 5 166 4 3/4" NN 805 25 Drip

18 B Side 5 174 1 3/4" NN FTN 15 Drip

19 Basement B 16 3 1/2" SO 52 25 Drip

19 Basement B 20 1 1/2" SO 30 25 Drip

19 Crawl B 24 3 3/4" SO FT15 5 Drip

19 Attic Mech A 1 4 3/4" SO 30 25 Drip

22 Basement B 41 3 1/2" SO 52 15 Drip

22 Basement B 42 4 1/2" SO 52 15 Drip Insulation

22 Basement B 49 9 3/4" SO FT15 5 Drip

23 118 B 58 7 1" AG B4 25

23 118 B 62 4 1/2" AG TVS811 80 Drip

23 Roof access AHU 1 R 63 3 3/4" AG B3 25 Drip Check Valve Piped Wrong

23 Roof access AHU 1 R 64 3 3/4" AG B3 25 AHU Check Valve Piped Wrong

23 Roof access AHU 2 R 65 3 3/4" AG B3 25 AHU Check Valve Piped Wrong

23 Roof access AHU 3 R 66 3 3/4" AG B3 25 AHU Check Valve Piped Wrong

24 Mech B 34 4 1/2" SO 52 25 Drip

24 Mech B 37 9 1/2" SO 52 25 Drip

24 Gymnasium 1 S 20 1/2" SO 52 25 VUH 2 traps parallel per

VUH

24 Gymnasium 1 S 20 1/2" SO 52 25 VUH Remove one w/replacement

24 Gymnasium 1 E 20 1/2" SO 52 25 VUH 2 traps parallel per

VUH

24 Gymnasium 1 E 20 1/2" SO 52 25 VUH Remove one w/replacement

24 Gymnasium 1 NE 20 1/2" SO 52 25 VUH 2 traps parallel per

VUH

24 Gymnasium 1 NE 20 1/2" SO 52 25 VUH Remove one w/replacement

24 Gymnasium 1 NE 20 1/2" SO 52 25 Drip under insulation

24 Gymnasium 1 N 20 1/2" SO 52 25 VUH 2 traps parallel per

VUH

24 Gymnasium 1 N 20 1/2" SO 52 25 VUH Remove one w/replacement

24 Gymnasium 1 N 20 1/2" SO 52 25 Drip under insulation

24 Gymnasium 1 N 20 3/4" SO 30 25 ZRH

24 Gymnasium 1 NW 20 1/2" SO 52 25 VUH 2 traps parallel per

VUH

24 Gymnasium 1 NW 20 1/2" SO 52 25 VUH Remove one w/replacement

24 Gymnasium 1 W 20 1/2" SO 52 25 VUH 2 traps parallel per

VUH

24 Gymnasium 1 W 20 1/2" SO 52 25 VUH Remove one w/replacement

24 Gymnasium 1 W 20 1/2" SO 52 25 Drip under insulation

24 Gymnasium 1 W 20 1/2" SO 30 25 Drip

24 Gymnasium 1 W 20 3/4" SO 30 25 ZRH

24 Outside access 1 39 2 1" SO 30 20 Drip

24 Outside access 1 40 6 1" SO 30 20 Drip

101 14 Mech Rm G 274 4 1 1/4" SO FT30 20 HEX

104 Mech Rm B 228 1 1/2" SO TD52 80 Drip

104 Mechanical Room 3 84 3 3/4" SO FT15 80 Drip

104 Mechanical Room 3 86 3 1 1/4" SO FT15 80 Drip On 1" pipe

104 Mechanical Room 3 87 3 1 1/4" SO 30 25 Drip 1" pipe

104 Mechanical Room 3 96 1 3/4" AG 811 80 Drip

104 Mechanical Room 3 99 2 3/4" AG 811 10 Drip

104 Mechanical Room 3 103 5 3/4" PEN PT63 10 Drip

104 Mechanical Room 3 105 3 3/4" AG 811 10 Drip

104 Mechanical Room 3 116 3 1 1/2" AG 125 80 HEX

106 Service Room G 54 4 1" SO TD52 80 Drip

136 In service room G 69 2 3/4" SO 30 25 Drip

136 In service room G 70 2 3/4" NN FTN 25 Drip

ATTACHMENT “B”

Design Development 35% Submission Requirements

Deliver the following (labeled with 35% submission) and include this attachment as a checklist with your submission:

• 1 Copy of a narrative report forwarding the design develop 35% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager, and any design calculations or analysis.

• 3 sets of all drawings updating all previous comments required by project and produced in AutoCAD

2007 – 2019 and in PDF form.

• 1 Copy of updated itemized cost estimate by spec section or trade (labor, material and equipment) and also by VA criteria, NRM, Minor, BSER and BSEA.

• 1 Copy of custom edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.

• 1 set of all drawings and specifications, to send for 3rd party Life Safety Review.

• 1 copy of drawings in AutoCAD 2007 – 2019 and in PDF form and specifications in Microsoft Word

2007 or higher on (CD)

ATTACHMENT “C”

Design Development 100% Submission Requirements

Deliver the following (labeled with 100% submission) and include this attachment as a checklist with your submission:

• 1 Copy of a narrative report forwarding the design develop 100% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager and any design calculations or analysis.

• 2 sets of all drawings updating all previous comments required by project produced in

AutoCAD 2007 – 2019 and in PDF form.

• 1 Copy of the proposed construction schedule.

• 1 Copy of final itemized cost estimate by spec section or trade (labor, material and equipment) and also by VA criteria, NRM, Minor, BSER and BSEA.

• 1 Copy of final edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.

• 1 CD containing o All drawings in AutoCAD 2007 - 2019 and in PDF form.

o All specifications in Microsoft Word 2007 or higher on (CD)

ATTACHMENT “D”

Contract Document Submission Requirements

Expectation: Submit complete contract documents for final review prior to Notice to Proceed for Construction. Continue to submit contract documents until all changes are incorporated by the DB A/E for final signature prior to Notice to Proceed for Construction. Upon approval duplicate copies as required.

Deliver the following (labeled with Contract Documents Submission) and include this attachment as a checklist with your submission:

• 1 copy of the Cover Sheet (AutoCAD) for final VA signatures.

• 2 sets of all drawings updating all previous comments required by project, produced in

AutoCAD 2007 – 2019 and in PDF form – for final VA review. If approved final sets to be submitted with signed off cover sheet.

• 1 Copy of final project specification (bound) prepared in Microsoft Word 2007 or higher.

Include a master submittal list in the specifications.

• CD containing o All drawings in AutoCAD 2007 – 2019 and in PDF form.

o All specifications in Microsoft Word 2007 or higher.

o Submittal Spreadsheet – identifying all the submittals required to be submitted by the contractor for review. The list shall be organized by division and specification.

Upon signature approval, provide three (3) sets of final Contract Documents (complete with VA signed Cover Sheet). Provide two (2), half (1/2) size sets of final drawings.

ATTACHMENT “E”

Contract Specifications

010000 Lebanon General Requirements

013526 Lebanon Safety Requirements

2322133 Steam and Condensate Heating Piping

File details come from the government source that posted it. Updated .