This document provides details for a federal design-build contract opportunity for demolition services. The Department of Veterans Affairs seeks a prime contractor to update previous design documents and provide design-build services for the demolition of Building 3 at the Butler VA Health Care System campus in Butler, Pennsylvania. The project estimate is between $250,000 and $500,000. Only Service-Disabled Veteran-Owned Small Businesses will be considered for this two-phase solicitation. Phase I proposals will be evaluated based on criteria in the forthcoming solicitation to select offerors to submit proposals for Phase II. The applicable NAICS code is 238910 for site preparation contractors with a size standard of $16.5 million. Responses for Phase I will be due on or around March 29, 2021, and the period of performance is 200 calendar days from notice to proceed.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODECODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

A0002 05-06-2021 529-21-2-565-0005 529-22-100

00244

Department of Veterans Affairs Network Contracting Office 4

00244

Department of Veterans Affairs Network Contracting Office 4

To all Offerors/Bidders

36C24421R0024

04-15-2021

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to:

X 1

Project 529-22-100 Building #3 Demo

This amendment being issued to post questions and answers to be included as part of the requirement (see page 2).

All other Items remain unchanged unless amended.

Jeffrey Zbezinski Contracting Officer

CONTINUATION PAGE

Q1. Can we use the Harrell, Saltrich, Hopper CAD drawings to edit?

A1. The awardee of the project will be given the CAD files from Harrell, Saltrich and Hopper to be updated to current VA, Local, State and Federal Codes and Standards.

Q2. Are digital files available for use and editing?

A2. The awardee of this project will be given the specifications in Microsoft Word format and the drawings in AutoCAD format.

Q3. Can we use specifications from 2016 project to edit?

A3. Yes, these specifications and drawings are to be brought up to current VA, Local, State and Federal Standards and Codes.

Q4. Is a demolition permit required from Summit Township?

A4. All required local, state, and federal permits are to be obtained by contractor. The project is in Butler Township.

Q5. Appears project could be close to one acre of disturbance-is an NPDES Permit required?

A5. The limit of work is to be determined in the updating of the documents and design during the design portion of the Design/Build Project. All permits required by local, state, and federal agencies are to be obtained by contractor.

*A Construction entrance to Duffy Road is to be added to the design revision.

Contractor MUST obtain permissions/permits from local, state, and federal agencies to accomplish this. No construction traffic will be permitted on the Butler VAMC roads and parking areas.