View the file

Other files for this federal contract opportunity

Other files attached to Q526--VISN04 - Multi-Station - Virtual Pharmacy Services - Closes 23Feb @ 0900, newest first.
File Type Posted
36C24421Q0153_2.docx DOCX document
Attachment A - PWS - Amend 1.pdf PDF
Attachment B - Price Schedule - Amend 1.docx DOCX document
Q_A Set 1.docx DOCX document
36C24421Q0153_1.docx DOCX document
Attachment G - Records Management Language.docx DOCX document
Attachment D - 36C24421Q0153_1 - SF1449.docx DOCX document
Attachment C _ Service Contract Act Wage Determinations.docx DOCX document
Attachment F - Past Performance Questionnair_Virtual Pharmacy.docx DOCX document
Attachment H - VA Privacy Training.pdf PDF
Attachment B - Price Schedule.docx DOCX document
Attachment A - PWS.pdf PDF
36C24421Q0153 - Combo.docx DOCX document
36C24421Q0153.docx DOCX document
Attachment E - QASP.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q1. Page 2, Provision FAR 52.212-1 Instructions To Offerors – Commercial Items (OCT 2018) applies to this acquisition, Paragraph (1) Introductory/Ancillary Information states, “…SF 1449 page 2, and all other applicable documents.” Please confirm if offerors are to include SF 1449 which was not included in the solicitation.

A1. A completed SF 1449 is to be included in the submitted quote packages. Blocks 17, 30a, b, c, pg 2 B.1a, and 4 if applicable.

Q2. Page 3, the solicitation states, “Offerors shall submit: Page 1 of SF1449” and “Page 2 of SF1449,” please confirm if offerors are to include SF 1449 which was not included in the solicitation.

A2. A completed SF 1449 is to be included in the submitted quote packages. Blocks 17, 30a, b, c, pg 2 B.1a, and 4 if applicable.

Q3. Page 3, the solicitation states, “All quotes shall be submitted on or before the offer due date shown on page 1 of the Standard Form 1449; in Block 8.” Please confirm if offerors are to include SF 1449 which was not included in the solicitation.

A3. A completed SF 1449 is to be included in the submitted quote packages. Blocks 17, 30a, b, c, pg 2 B.1a, and 4 if applicable.

Q4. Solicitation did not include FAR Clause 52.217-8, Option To Extend Services; please confirm if clause will not be included in the solicitation and resultant contract.

A4. FAR Part 52.217-8 will not be included in the contract.

Q5. Solicitation did not include FAR Clause 52.216-22, Indefinite Quantity; please confirm if Government will include FAR Clause 52.216-22 in the solicitation and resultant contract.

A5. As stated in the RFQ, this will be an IDIQ contract. FAR Part 52.216-22 Indefinite Quantity was not included in error. It should have been included. See below:

FAR Part 52.216-22 Indefinite Quantity.

As prescribed in 16.506(e), insert the following clause:

INDEFINITE QUANTITY (OCT 1995)

(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the "maximum." The Government shall order at least the quantity of supplies or services designated in the Schedule as the "minimum."

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after 31 March 2026.

(End of clause)