This is Amendment 0003 to a solicitation for construction services at the Albany VA Medical Center in Albany, New York. The amendment responds to contractor questions regarding the Consolidate Primary Care Reception project (Solicitation 36C24227B0006), which involves constructing a new reception area approximately 5,000 square feet to accommodate six Medical Support Assistants desks and a waiting lobby, along with relocating the Agent Cashiers office. The project follows a phased construction approach with 295 calendar days for performance and includes restrictions on construction timing due to multiple ongoing projects on site.

The amendment addresses key questions regarding staffing, project logistics, and technical requirements. Notable clarifications include: the Site Safety and Health Officer (SSHO) and superintendent cannot be the same person and must both be full-time; the QA/QC personnel must also be full-time and separate from other positions; site superintendent may be dual-hatted as QC person subject to VA approval; dedicated Conex and office trailer locations will be determined post-award through negotiation; staging, storage, and material transportation routes will be finalized after award; multiple phases may proceed concurrently with Contracting Officer Representative (COR) approval provided no conflicts arise; non-disruptive activities may occur during normal business hours subject to VA approval; federal tax exemption applies; the contractor is responsible for fire watch personnel during fire alarm or sprinkler shutdowns; and the sprinkler flow test will be performed by a certified designer hired by the contractor and subject to VA approval. The amendment notes that the contractor and owner must each retain separate industrial hygiene consultants for air monitoring and clearance testing per Code Rule 56. The contracting activity is the Department of Veterans Affairs Network Contracting Office (NCO) located in Buffalo, New York.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 11-25-2026 528A8-22-814 36C528 Department of Veterans Affairs Network Contracting Office (NCO) 2 3495 Bailey Avenue Building 3, 2nd floor Buffalo NY 14215 36C528 Department of Veterans Affairs Network Contracting Office (NCO) 2 3495 Bailey Avenue Building 3, 2nd floor Buffalo NY 14215 To all Offerors/Bidders

36C24227B0006 11/06/2026

X X X X See attached document.

Michael Spivack

CONTINUATION PAGE

This amendment answers the contractor listed below. This amendment does not include all contractor questions received, a follow on amendment responding to the remaining questions shall be posted in a subsequent amendment to the solicitation.

1. Please provide the site visit sign in sheet Response: See attached document

1. Can the site superintendent be dual hatted and be the QC person?

Response: Yes, the individual needs to be qualified for both positions. Subject to VA approval.

1. Is there a dedicated space for a Conex and office trailer?

Response: Due to multiple ongoing projects on site, the exact location of a new Conex and office trailer on site will be determined by negotiation with the VA after award.

1. Is there a proprietary fire alarm vendor?

Response: No, there is not a singular fire alarm vendor. Notifier Fire Alarm Systems for devices. Alarm & Suppression is the licensed contractor that can work on them.

1. Is there a proprietary security vendor?

Response: No, there is not a singular security vendor. Lenel is the proprietary software. HID is the proprietary hardware. Subcontractor must be Lenel S2 certified.

1. Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?

Response: No, the superintendent and the SSHO cannot be the same person.

1. If no to the question above, will the SSHO need to be full-time for this project?

Response: Yes, they must be full-time for this project.

1. If no to the question above, will the QA/QC need to be full time for this project?

Response: Yes, they must be full time for this project.

1. Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?

Response: No, the superintendent cannot cover all three positions.

1. Please confirm that sales tax is to be included in our bid.

Response: Federal Government contracts are Tax Exempt. A tax exemption form will be provided upon request.

1. Outside public corridors, may non-disruptive activities that do not constitute heavy construction or deck attachments be performed during normal business hours?

Response: Yes, non-disruptive activities that do not constitute heavy construction may be performed during normal business hours. These activities will still be subject to VA approval.

1. Are the four two-week VA relocation periods included in the 295-calendar-day performance period?

Response: Yes, construction shall still take place during the relocation periods.

1. How will critical-path delays and extended general conditions be addressed if VA relocations exceed two weeks?

Response: This shall be addressed through contract modification or Request for Equitable Adjustment depending on the situation.

1. Please provide the adjacent Primary Care project's anticipated completion schedule and identify shared access, utilities, staging and activities affecting this contract.

Response: Construction is anticipated to be completed by late Spring 2027 or during summer 2027.

1. Please identify staging, storage, dumpster, loading dock and approved material transportation routes.

Response: Due to multiple ongoing projects on site, additional information cannot be provided at this time, these details will be negotiated after award.

1. May multiple phases proceed concurrently with COR approval, or must all five phases be strictly sequential?

Response: Generally, yes, work on multiple phases is permitted as long as it creates no conflicts between the phases. Any removals required because one phase has interfered with another will be the responsibility of the contractor.

1. Please clarify the approved procedure for construction progress photography for Autodesk Build. Can this requirement be fulfilled by a full-time member of the contractor’s on-site personnel?

Response: Yes, a full-time member of the contractor’s on-site peroneal can fulfill this requirement.

1. Please clarify who retains and pays the independent industrial hygiene consultant for air monitoring, final clearance testing and reoccupancy authorization.

Response: Code Rule 56 requires that both the contractor and owner have separate industrial hygiene consultants. Both must agree that the site has been properly cleaned and ready to have the barriers removed.

1. With MD101-5, MH101-5 and MP101-5 excluded, please identify remaining Phase 5 mechanical coordination, temporary services, tie-ins, testing or balancing responsibilities.

Response: This is part of the base contract with the contractor.

1. Please provide sprinkler flow test location, date, static pressure, residual pressure and flow rate, or confirm whether the contractor must perform a new test.

Response: This is proposed/performed by the certified designer hired by the contractor. Subject to VA approval

1. Who provides fire watch personnel during approved fire alarm or sprinkler impairments?

Response: It is the contractor’s responsibility to have personnel on fire watch during fire alarm or sprinkler shutdowns (service impairments). This will be coordinated with the VA.

1. Please confirm required security and ballistic resistance ratings, if any, for Agent Cashier transaction windows, glazing, frames and assemblies.

Response: Please refer to the most recently updated VA Physical Security and Resiliency Design Manual, and VA Handbook 0730 for security requirements. Additional information, if any can also be found in the VA TIL.

All other terms and conditions remain the same.

See attached document: Walk Through Sign in Sheet.