Amendment to Invitation for Bid No. 36C24227B0003
This document is an Amendment to Solicitation/Modification of Contract (Standard Form 30) issued by the Department of Veterans Affairs, Samuel S. Stratton VA Medical Center, for Project 561-26-103 involving the upgrade of electrical and plumbing systems in Building 18B. The amendment extends the solicitation receipt deadline from November 30, 2026 at 11:00 AM EST to December 14, 2026 at 11:00 AM EST and publishes a Request for Information (RFI) answers list for interested contractors. All other terms and conditions of the original solicitation remain unchanged. Offerors must acknowledge receipt of this amendment prior to the extended deadline using one of three methods: completing Items 8 and 15 and returning one copy, acknowledging receipt on each copy of the offer submitted, or providing written or electronic communication referencing both the solicitation and amendment numbers.
The accompanying RFI Questions and Answers document addresses 25 specific inquiries from potential bidders regarding project scope, specifications, and execution requirements. Key clarifications include: the 150-calendar-day performance period (not 608 days); allowance for combining the Site Safety and Health Officer, Construction Quality Control System Manager, and Superintendent roles into one or two qualified individuals; confirmation that Data Closet Room 18-140 is located in Building 18A approximately 26 feet 8 inches from Building 18B's entrance; specification of CAT6A unshielded twisted pair cable with jacket ratings selected based on actual installation environment; cast iron pipe with heavy-duty no-hub couplings for the 4-inch sanitary sewer line; contractor responsibility for field verification of existing conditions and documentation of sanitary pipe locations; removal of surface-mounted TV conduit only (not televisions or brackets); contractor responsibility for identifying and replacing existing CAT5 cabling and furnishing all required surface-mounted metal raceways and cable supports; basis-of-design lighting fixtures (RAB Lighting SMP-2x2 4K and SMP-2x4 4K); prohibition on reusing existing power circuits and conduits; painting requirements only for disturbed surfaces; main sanitary line tie-in permitted during normal daytime hours with seven calendar days' notice; and contractor responsibility for trade coordination and scheduling telecommunications installation within the overall construction period.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
0005 11-20-2026
561-26-103
36C242
Department of Veterans Affairs Samuel S . Stratton VA Medical Center 113 Holland Avenue (2-90NCA) Albany NY 12208-3410
36C242
Department of Veterans Affairs Samuel S . Stratton VA Medical Center Network Contracting Activity 113 Holland Avenue (2-90NCA) Albany NY 12208-3410
To all Offerors/Bidders
36C24227B0003
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: December 14th, 2026 @11AM EST
N/A x 1
Amendment to Invitaton For Bid No. 36C24227B0003, Project 561-26-103 Upgrade Electrical and Plumbing in building 18B
The purpose of this amendment is to
- Extend the solicitation end date from Nov 30th 2026 @11AM EST to December 14th 2026 @11AM EST
- Publish an RFI answers list for interested contractors
All other terms and conditions of the original solicitation remains unchanged.
Dayna Dickson-Miller
RFI Questions and Answers
Upgrade electrical and plumbing in Building 18B | 36C24227B0003
RFI 1 — Period of performance
The Bid Pricing Sheet (Section 1.1) states a period of performance of 608 calendar days from NTP. The SF1442 and Statement of Work Section 11 state 150 calendar days. Please confirm which duration governs.
The Statement of Work (SOW) shall govern. The required period of performance for this project is 150 calendar days from Notice to Proceed (NTP), as specified in the Statement of Work and SF 1442.
RFI 2 — SSHO, CQC and superintendent staffing
Specification Section 01 35 26, paragraph 1.9, calls for a full-time Site Safety and Health Officer who is separate from the Superintendent and Quality Control Manager.
Given the size and magnitude of this project, will the VA allow the SSHO, CQC System Manager and Superintendent roles to be combined in one or two qualified individuals?
The Government will allow the Site Safety and Health Officer (SSHO), Construction Quality Control (CQC) System Manager, and Superintendent roles to be combined. For this project, these responsibilities may be performed by qualified individuals, provided the assigned personnel meet all applicable contract qualification requirements and are capable of effectively fulfilling the duties associated with each role throughout the duration of the project.
RFI 3 — Data closet location and rack capacity
Drawing E-101, General Data Cabling Notes 5 and 6, routes all cabling to existing data closet 18-140. Room 18-140 is not labeled on the plan. Please identify its location, confirm the existing rack has space for the new 48-port CAT6A patch panels, and confirm whether patch cords (Section 27 15 19) are contractor-furnished or furnished by VA OI&T.
Room 18-140 is located in Building 18A, within the common hallway connecting Building 18A and Building 18B. A snippet identifying the location of Room 18-140 is provided below for reference. The approximate distance from Room 18-140 to the entrance of Building 18B is 26’-8”.
Contractors shall use this information for bidding purposes and field verify all routing and installation conditions prior to commencing work.
Patch cords required to connect patch panels to network switches will be provided and installed by VA OI&T. The Contractor shall furnish and install the new CAT6A cabling, terminate all cabling on the specified patch panels, perform required testing and labeling, and provide a complete installation. The Contractor is not responsible for patching into network switches.
It is anticipated that sufficient space exists within the existing rack infrastructure in Room 18- 140 to accommodate the required new CAT6A patch panels. However, the Contractor shall field verify existing rack conditions and available space prior to installation. Should unforeseen conditions be encountered that affect patch panel installation, the Contractor shall notify the COR for resolution prior to proceeding with the affected work.
RFI 4 — CAT6A cable type
Please confirm whether the CAT6A cable is to be plenum-rated (CMP) or riser-rated (CMR), and whether shielded (F/UTP) or unshielded (UTP) cable is required under VA ISTS v5.0 for this installation.
The Contractor shall provide CAT6A unshielded twisted pair (UTP) cable for this installation.
Cable jacket ratings shall be selected based on the actual installation environment and applicable code requirements. Where cabling is installed in environmental air-handling (plenum) spaces, plenum-rated (CMP) cable shall be provided. Where cabling is installed in non-plenum spaces, riser-rated (CMR) cable may be utilized where permitted by code. The Contractor shall field verify installation conditions and provide cable meeting the applicable code and installation requirements.
RFI 5 — Sanitary line existing conditions and pipe material
Drawing P-101 and Section 22 05 11 do not state the existing sanitary pipe material, invert depth or slab thickness, and no pipe material is specified for the new 4-inch line. Please provide the required pipe material and joint type, and any available as-built drawings from the 2022 Building 18 renovation showing the underground sanitary layout.
The new 4-inch sanitary sewer piping shall be cast iron pipe. Joints shall be made using heavy-duty no-hub couplings (Husky or approved equal) installed in accordance with the manufacturer's recommendations and applicable code requirements.
The existing sanitary pipe material, invert depth, and slab thickness are unknown and have not been verified by the Government. The Contractor shall be responsible for determining these existing conditions through field investigation and verification prior to commencing work.
As noted on Drawing P-101:
THE LOCATION OF THE 4-INCH SANITARY PIPE SHOWN ON THE DRAWING IS
APPROXIMATE ONLY. THE CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR
FIELD VERIFYING AND IDENTIFYING THE ACTUAL LOCATION OF THE SANITARY
PIPE PRIOR TO COMMENCING ANY RELATED WORK. ALL DISCREPANCIES
BETWEEN THE DRAWING AND FIELD CONDITIONS SHALL BE BROUGHT TO THE
ATTENTION OF THE COR FOR CLARIFICATION BEFORE PROCEEDING.
As-built drawings from the 2022 renovation showing the underground sanitary piping layout are not available. In addition, as-built documentation related to the sanitary pipe restoration work is not available.
Contractors shall rely on all necessary field investigation, verification, and coordination required to determine existing sanitary piping locations and conditions. Any discrepancies encountered between field conditions and the contract documents shall be reported to the COR prior to proceeding with the affected work.
RFI 6 — Wall-mounted televisions
The E-101 legend states "wall-mounted television, to be removed at all offices."
Attachment A lists only TV wire/conduit removal. Please confirm whether the contractor removes the televisions and brackets, and whether they are turned over to the VA.
Demolition Note 5 on Drawing E-101, which states, “Remove all TV wiring in surface-mounted conduit, including conduit, cabling, and related accessories,” is intended to require removal of the surface-mounted conduit system identified on the drawing below (item circled in red), in all applicable rooms.
Additionally, in accordance with Demolition Note 8, “Patch and repair all wall and ceiling surfaces disturbed by demolition work. Repair and restore finishes to match existing adjacent conditions in texture, color, and material.”
Clarification: The TV-related items shown in the photograph below, including but not limited to TV mounting brackets, coaxial wall outlets (TV jacks), and associated accessories located at or near ceiling height, are not included in the demolition scope of work and shall remain in place. Any existing televisions and TV mounting brackets remaining within the project area are also to remain and are not to be removed by the Contractor.
RFI 7 — Room occupancy and storage room route Please confirm whether offices will be vacated by the VA for the work on a room-by-room basis, or whether work is expected in occupied rooms or during off-hours. Also, P-101 states the sanitary line crosses "either Storage Room 18-122A or 18-122."
Please confirm which room, and whether the VA will clear its contents.
The offices affected by the work will be vacated by the Government to accommodate construction activities. The Contractor shall plan and perform the work during normal business hours. Pricing shall be based on work being performed in unoccupied rooms during regular daytime working hours.
The Government is unable to confirm whether the existing sanitary line passes through Storage Room 18-122A or Storage Room 18-122. Determination of the actual pipe location shall be the responsibility of the Contractor through field investigation and verification.
As noted on Drawing P-101:
THE LOCATION OF THE 4-INCH SANITARY PIPE SHOWN ON THE DRAWING IS
APPROXIMATE ONLY. THE CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR
FIELD VERIFYING AND IDENTIFYING THE ACTUAL LOCATION OF THE SANITARY
PIPE PRIOR TO COMMENCING ANY RELATED WORK. ALL DISCREPANCIES
BETWEEN THE DRAWING AND FIELD CONDITIONS SHALL BE BROUGHT TO THE
ATTENTION OF THE COR FOR CLARIFICATION BEFORE PROCEEDING.
RFI 8 — Circuit numbering The Electric Circuit Diagram on E-101 shows home runs to Panel NP1 circuits 21, 34 and 38, which are not listed in General Electric Note 5 (circuits 19, 20, 22, 24, 30, 32, 35, 36, 37, 39 and 41). Please confirm the intended circuiting and the total number of new 20-amp circuits.
The intent of Drawing E-101, General Electrical New/Modification Notes Items 5 and 6, is to identify and establish capacity for fifteen (15) new 20-amp, single-pole branch circuits within Panels NP-1 and NP-2. Item 5 requires the Contractor to remove specific two-pole breakers and replace them with single-pole breakers as indicated. Item 6 identifies additional available panel spaces for the installation of new 20-amp single-pole breakers. Together, these notes are intended to demonstrate that Panels NP-1 and NP-2 have sufficient available space and capacity to accommodate the required new circuits.
RFI 9 :
Are all employees (Including subcontractors) to have PIV1?
Contractor and subcontractor personnel shall comply with all contract requirements related to facility access, badging, and security. The Contractor shall coordinate access requirements with the COR prior to commencing work.
RFI 10:
Can the SSHO, CQC, and project supervisor be one employee? Or is a separate CQC manager required?
See RFI 2 above
RFI 11:
Slab Details for the Sanitary Trench (Drawing P-101):
What is the existing slab thickness and reinforcement in Rooms 18-138, 18-118, 18-122/18- 122A, and Corridor 18-101? Also, when we pour back the trench, will you require epoxy-dowelled rebar and a new under-slab vapor barrier?
The Government does not have information identifying the existing slab thickness, reinforcement, or under-slab construction in Rooms 18-138, 18-118, 18-122/18-122A, or Corridor 18-101. Contractors shall field verify existing conditions and include all necessary investigation required to complete the work. Following installation of the new sanitary piping, the Contractor shall restore the slab and floor system to match the existing construction and structural integrity. Any exposed reinforcing steel damaged or removed during demolition shall be replaced or supplemented as required. The Contractor shall provide doweling, reinforcement, vapor barrier repairs, and other measures as necessary to restore the slab and maintain the performance of the existing assembly. All restoration work shall comply with applicable codes, industry standards, and project requirements. Any unforeseen conditions encountered shall be brought to the attention of the COR prior to proceeding with the affected work.
Can the main sanitary line tie-in in Room 18-118 and related utility shutdowns be done during normal daytime work hours with 7 days' notice, or should we price that tie-in for nights/weekends?
The main sanitary line tie-in in Room 18-118 and associated utility shutdowns may be performed during normal daytime working hours, provided the Contractor submits a shutdown request and coordinates the work with the Government a minimum of seven (7) calendar days in advance. Bidders should base their pricing on performance of this work during normal daytime hours.
RFI 12: Existing CAT 5 Data Wiring Are we required to remove the existing CAT 5 data cables, or can they remain in place above the ceiling?
Yes. All superseded CAT5 cabling identified for replacement under this project shall be completely removed from the workstation outlet to the telecommunications rack/termination point, including removal from existing cable trays, conduits, supports, and pathways where accessible. The Government's intent is to comply with applicable VA ISTS requirements regarding the removal of superseded telecommunications infrastructure.
RFI 13: Lighting Fixtures Are there any specific lighting fixtures or manufacturers you would like us to use for this project? Please provide the fixture specifications, if available.
The basis of design is RAB Lighting SMP-2x2 4K and RAB Lighting SMP-2x4 4K surface-mounted LED fixtures. Approved equal fixtures may be proposed provided they generally match the basis-of-design products in size, mounting configuration, light output, color temperature and performance characteristics.
RFI 14: Existing Power In areas where existing power is available and suitable for the new installation, are we permitted to utilize the existing power, or are we required to run new circuits from the electrical panel?
No. The Contractor shall not utilize existing power circuits for the new installation. New circuits shall be provided from the appropriate electrical panel(s) as required by the contract documents and applicable codes. Any deviation from this requirement shall require prior review and approval by the COR.
RFI 15: Existing Conduits In areas where existing conduits are available and suitable for the new installation, are we permitted to reuse them, or are we required to remove them and install new conduits?
No. Existing conduits shall not be reused for the new installation. The Contractor shall remove existing conduits and furnish and install new conduits to support the new work. Any deviation from this requirement shall require prior written approval from the COR.
Clarification:
Drawing E-101, General Electrical New/Modification Note 7 states: “RELOCATE EXISTING
SURFACE-MOUNTED OUTLETS TO 18 INCHES AFF; EXTEND OR MODIFY SURFACE-
MOUNTED CONDUIT AS REQUIRED.”
The Contractor may remove the existing outlet, install a blank cover plate at the existing outlet location, and extend the surface-mounted raceway to provide the relocated outlet at 18 inches AFF using wire mold/raceway matching the existing installation. Existing wire mold, conduit, wiring, and accessories that previously served the removed light fixture shall be demolished and removed. The Contractor shall patch, repair, and paint all surfaces disturbed by the demolition work to match adjacent existing conditions. See Photo below:
RFI 16:
Will all items on the attached list be required for billing approval? (see 20261116092636.pdf)
Yes, the VA Project Engineer/COR will review the payment application against the progress on site and associated contract documents including all items on the attached list.
RFI 17:
Will painting be needed in any of the rooms that have work going on
Painting shall be required only where existing surfaces are disturbed by demolition, patching, repair, or new installation work. In accordance with Demolition Note 8 on Drawing E-101, “Patch and repair all wall and ceiling surfaces disturbed by demolition work. Repair and restore finishes to match existing adjacent conditions in texture, color, and material.” No additional painting beyond that necessary to restore affected surfaces and finishes is included in the scope of work.
RFI 18:
Have the sewer lines been scoped
See RFI 7 The Government was unable to definitively determine the location of the sanitary line.
Contractors shall base their bids on the information provided in the contract documents and shall perform all necessary field investigation and verification required to complete the work.
Any discrepancies encountered in the field shall be brought to the attention of the COR prior to proceeding with the affected work.
RFI 19:
Are we going through storage room 18-122A to replace the plumbing lines
See RFI 7
RFI 20:
Existing CAT5 Cable Removal
Does the project require complete physical removal of all superseded CAT5 cabling from the workstations back to the telecommunications racks, including extraction from existing, heavily populated cable trays?
The VA ISTS v5.0 standard requires removal of superseded infrastructure. Given the condition of the existing pathways, this could represent a significant undertaking beyond installing replacement cabling.
Yes. All superseded CAT5 cabling identified for replacement under this project shall be completely removed from the workstation outlet to the telecommunications rack/termination point, including removal from existing cable trays, conduits, supports, and pathways where accessible. The Government's intent is to comply with applicable VA ISTS requirements regarding the removal of superseded telecommunications infrastructure.
RFI 21:
Existing Circuit Identification and Mapping
Will VA IT provide identification and documentation of the existing cabling designated for replacement, or will the telecommunications subcontractor be responsible for tracing, toning, mapping, and verifying each circuit before removal?
The existing telecommunications room supports an active production environment, making positive circuit identification essential.
No. The Government will not provide identification, tracing, mapping, or documentation of the existing cabling designated for replacement. The Contractor shall be responsible for identifying the existing cabling within the telecommunications room/data closet and replacing the required cabling as specified in the contract documents.
Representatives from VA OI&T will be available during installation to address questions and assist with coordination as needed; however, responsibility for identifying and replacing the required cabling remains with the Contractor.
RFI 22:
Rack Capacity, Terminations, and Future Migration
Where are the new CAT6A patch panels intended to be installed?
The new CAT6A patch panels shall be installed in the existing data closet, Room 18-140, as indicated on Drawing E-101, General Data Cabling Notes.
The existing telecommunications room is extremely congested, with limited rack space and working clearances.
We also understand that the required 25 feet of overhead cable slack is intended to accommodate a future rack migration into an adjacent room. Please confirm the intended cable management arrangement and whether any additional rack infrastructure or modifications are anticipated under the current scope.
No. The current project scope does not include the installation of additional racks. The required cable slack shall be provided in accordance with the contract documents and applicable VA standards; however, there is no available space for additional racks within the existing data closet (Room 18-140) under the current scope of work.
RFI 23:
New Cabling Versus Existing Cable Replacement
Attachment A identifies new duplex data outlets along with several existing CAT5 cable replacements.
Can the VA confirm whether the identified replacement cables are additional to the scheduled new outlet installations or overlap with those quantities?
The quantities identified in Attachment A for CAT5 cable replacements are separate from and in addition to the quantities identified for new duplex data outlet installations. The replacement cables and new outlet installations do not overlap and shall be considered distinct scope items for bidding and construction purposes.
RFI 24:
Cable Pathways and Surface-Mounted Infrastructure
Please confirm whether the telecommunications subcontractor is responsible for furnishing all additional surface-mounted metal raceways, cable supports, conduit extensions, and associated penetrations.
Yes. To the extent required for a complete installation, the Contractor shall furnish and install all necessary surface-mounted metal raceways, cable supports, conduit extensions, sleeves, and associated penetrations. The Contractor shall field verify installation conditions and provide all materials and accessories required to route and protect the cabling in accordance with applicable codes and VA standards.
Additionally, please clarify responsibility for firestopping and any wall or ceiling restoration required to complete the installation.
The Contractor shall be responsible for all required firestopping and restoration work associated with the installation. Responsibility for firestopping, patching, repair, and restoration of walls, ceilings, floors, and other building surfaces may be performed by the Prime Contractor or its subcontractors; however, the Government will not perform any portion of this work. The Contractor shall restore affected areas to match adjacent existing conditions and maintain required fire-resistance ratings.
RFI 25:
VA IT Coordination and Construction Scheduling
Given the condition of the telecommunications room and the shared production infrastructure, will VA IT provide dedicated coordination and access for circuit identification, disconnections, and rack-side work?
VA OI&T will provide an escort for contractor personnel requiring access to the telecommunications/data closet. The Contractor shall coordinate access requirements in advance. VA OI&T personnel will be available to facilitate access and assist with coordination as required.
We would also appreciate clarification on the anticipated telecommunications installation sequence within the overall 90-day construction period, particularly concerning access to shared ceiling pathways while other trades are working.
The sequencing of telecommunications work within the overall construction schedule shall be the responsibility of the Prime Contractor. The Contractor shall coordinate the activities of all trades, including access to shared ceiling spaces, pathways, and work areas, to ensure timely completion of the project within the contract performance period. Coordination of telecommunications installation with other ongoing construction activities shall be included in the Contractor's project planning and scheduling efforts.
If available, existing telecommunications riser diagrams, rack elevations, and cable plant documentation would be extremely helpful.
Existing telecommunications riser diagrams, rack elevations, and cable plant documentation are not available. Existing documentation is outdated and is not considered reliable for design or construction purposes. Contractors shall perform any necessary field investigation, verification, tracing, and coordination required to identify existing telecommunications infrastructure and complete the work in accordance with the contract documents.
File details come from the government source that posted it. Updated .