Y1DA--NRM-CONST 630A4-17-433 Replace Boiler Plant Main Electrical Switchgear
Solicitation number
36C24226B0042
Issued by

About this file

This is Amendment 1 to Solicitation 36C24226B0042, issued by the Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office on May 12, 2026, for the replacement of the Boiler Plant Main Electrical Switchgear (Project 630A4-17-433) at the VA New York Harbor Healthcare System–St. Albans Campus in Bronx, New York. The amendment extends the response deadline from May 14, 2026 to May 26, 2026 at 12:00 PM EDT and shifts bid opening from May 15, 2026 to May 27, 2026 at 1:00 PM EDT. The project involves design-bid-build construction with a 730-calendar-day completion timeline and an estimated magnitude between $1,000,000 and $5,000,000. Bidders are pricing Base Bid only, with Alternate No. 1 removed from consideration.

The scope encompasses replacement of Substations #1 and #2, Motor Control Centers #1 and #2, and Transformers A and B in Building #64, including demolition and installation of new switchgear units, 5KV feeders, cables, conduits, and associated equipment, along with architectural firestopping and patching, mechanical ventilation system upgrades to accommodate heat loads, and compliance with New York State Mechanical Code requirements. The amendment includes responses to 59 frequently asked questions clarifying critical project requirements: the contractor must conduct full field investigation and equipment verification prior to work; existing transformers must be surveyed for PCBs with hazardous disposal included; new short-circuit, coordination, and arc-flash studies are required; aluminum conductors are strictly prohibited with copper-only specification required; transformers must be floor-mounted; concrete pad bases must be demolished and replaced; work shall occur during normal business hours (Monday–Friday, 8:00 AM–4:30 PM) unless special circumstances apply; the contractor is responsible for obtaining work permits including asbestos abatement and crane safety permits; and dust barriers with Class II precautions must be implemented with coordination through the Contracting Officer's Representative. A Davis-Bacon wage determination attachment is referenced as corrected in this amendment.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24226B0042 Amendment 1 630A4-17-433 Replace Boiler Plant Main Electrical Switchgear

36C24226B0042 Amendment 1 630A4-17-433 Replace Boiler Plant Main Electrical Switchgear

36C24226B0042 Amendment 1 630A4-17-433 Replace Boiler Plant Main Electrical Switchgear

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 05-12-2026 630A4-17-433 36C242 Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx

NY

10468-3904 36C242 Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx

NY

10468-3904 To all Offerors/Bidders

36C24226B0042

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 05-26-2026 12:00PM EDT See CONTINUATION Page X The purpose of Amendment 0001 is to submitted response to RFI's. Response date is changed for May 14, 2026 to May 26, 2026 at 12:00PM EDT. Bid opening is changed from May 15, 2026 to May 27, 2026 1:00PM EDT.

Please see the attached.

Vladimir Stoyanov Contracting Officer

CONTINUATION PAGE

1. Please confirm the correct Davis-Bacon wage determination. The solicitation currently includes a New York 'Heavy Dredging' wage determination, which appears unrelated to this building electrical project.

VA CO: See attachment

2. Please clarify whether bidders are pricing Base Bid only, or Base Bid plus Alternate No. 1. If Alternate No. 1 remains, provide a clear bid schedule.

VA COR: Base Bid only

4. Please confirm whether this is strictly design-bid-build. The solicitation references 100% IFC drawings, but the SOW also states the contractor is responsible for the 'design' of replacement systems.

VA COR: It’s considered design-bid-build.

5. Please provide complete existing equipment data for substations, transformers, MCCs, ATSs, breakers, and feeders (manufacturer, ratings, dimensions, weights, available fault current, trip settings, etc.).

VA COR: VA has limited information from its database. GC to conduct full investigation and field verification before work.

6. Please confirm whether existing transformers contain PCBs and provide testing documentation. If unknown, confirm whether an allowance will be issued for hazardous disposal.

VA COR: AE shall confirm if the survey was done based on the initial contract. If not, please include service(s) during CPS.

7. Please define allowable outage windows for each shutdown/load transfer, including permitted days, times, duration limits, and blackout periods.

VA COR: COR to communicate with St. Albans M&O for shutdown coordination. GC to provide phasing plans and area of work.

8. Please confirm whether shutdowns must occur after hours/weekends and whether premium labor should be included in bids.

VA COR: utility shutdown can be performed during normal business hours, depending on location and time. OFF hours work can be established when affecting facility’s normal operation.

13. Please identify who is responsible for utility switching/LOTO of the 5kV system (VA staff, utility provider, contractor, or third party).

VA COR: Applies to all. Work can be coordinated in between parties, depending on work area and needs.

14. Please confirm whether new short-circuit, coordination, and arc flash studies are required and whether existing studies are available VA COR: Yes, it is required since the contractor shall install a complete new equipment – AE shall confirm as well.

18. Please provide hazardous materials survey information for asbestos, lead paint, refrigerants, contaminated oil, and other regulated materials in demolition areas.

VA COR: Hazardous sampling and abatement are required. GC to provide abatement service, A/E to provide Air Monitoring service.

20. Please confirm all required permits (NYC DOB, FDNY, utility, environmental, crane permits, etc.) and identify whether the contractor or VA is responsible for obtaining them VA COR: GC is responsible for work permits. VAMC is a federal facility, however, certain city permit is required i.e.. Asbestos abatement, Fire suppression system related, crane safety .etc.

23. Please provide complete existing equipment data for substations, transformers, MCCs, ATSs, breakers, and feeders (manufacturer, ratings, dimensions, weights, available fault current, trip settings, etc.)

VA COR: duplicate of question No. 5

24. Please confirm whether existing transformers contain PCBs and provide testing documentation. If unknown, confirm whether an allowance will be issued for hazardous disposal.

VA COR: duplicate of question No. 6

25. Please define allowable outage windows for each shutdown/load transfer, including permitted days, times, duration limits, and blackout periods.

VA COR: duplicate of question No. 7

26. Please confirm whether shutdowns must occur after hours/weekends and whether premium labor should be included in bids.

VA COR: duplicate of question No. 8

28. Please provide temporary power requirements including capacities, connection points, conductor routing, grounding requirements, and acceptable temporary equipment locations.

VA COR: proposed action plan or phasing plan is required before any coordination with the VA.

31. Please identify who is responsible for utility switching/LOTO of the 5kV system (VA staff, utility provider, contractor, or third party) VA COR: duplicate of question No. 13

32. Please confirm whether new short-circuit, coordination, and arc flash studies are required and whether existing studies are available.

VA COR: duplicate of question No. 14

36. Please provide hazardous materials survey information for asbestos, lead paint, refrigerants, contaminated oil, and other regulated materials in demolition areas VA COR: duplicate of question No. 18

37. Please identify rigging/logistics constraints including access routes, crane requirements, loading limitations, door openings, and staging areas for large electrical equipment replacement.

VA COR: staging areas is available. GC to conduct field investigations and condition verification for proper work requirements. COR to establish communication in between parties.

38. Please confirm all required permits (NYC DOB, FDNY, utility, environmental, crane permits, etc.) and identify whether the contractor or VA is responsible for obtaining them VA COR: duplicate of question No. 20

39. Spec section General Requirements page no.2 states ALTERNATE NO.1: BASE BID except minus 2nd switchgear unit. – But the Bid pricing sheet does not have any alternate listed. If there is any alternate work, then please modify the bid pricing sheet accordingly VA COR: Base bid only.

43. Spec section 01 90 00 has General Commissioning Requirements. Please confirm the Commissioning agent will be hired by VA.

VA COR: A/E to cover or responsible for Commissioning service on behalf of the VA.

45. The time limit to complete this project is 730 calendar days. Why is the agency anticipating such a long time for completion?

VA COR: extended timeline to cover, equipment lead-time/ delivery / contracting and paperwork process in terms of any new proposed work.

46. The work of demolition of concrete pads, construction of new concrete pads and switchgear replacement is on the lower level. Please advise if there is access at the exterior street from this lower level to haul the construction materials in and out.

VA COR: Multiple exits and stairway are available.

47. Please confirm work hours are regular M-F 8:00 am to 4:30 pm VA COR: All work shall be performed under normal business hours, unless otherwise, special circumstances and specific timeline applies.

48. Is the 5KV wiring being replaced from the substations back to the manhole 2A?

VA COR: No, the 5kV wiring is being replaced from the substation back to the splice enclosure inside the same electrical room.

49. Where are the starting and the ending points for the feeder’s replacement?

VA COR: In accordance with drawings ED-101 and ED-601, the 5KV feeders extending from the splice enclosure to the transformer are to be replaced both located inside the electrical room. Also, see drawing cut below for clarification.

50. Is the walkthrough sign sheet available?

VA COR-Yes. Will be attached to the Amendment.

51. Will the concrete bases for substations 1 and 2 need to be replaced, or can they be reused?

VA COR- No, due to differences in dimensions and positioning for the new equipment, the existing pad must be removed and replaced with a new one. Also, conditions and capacities of existing concrete pads are unknown.

52.What is the distance from the substations to the splice point for the 5KV medium voltage wire?

VA COR-: Refer to drawing ED-101 enlarged plan D6. Both the substation and the splice enclosure are located within the electrical room.

53. Will aluminum conductors be allowed or only copper conductors?

VA COR: Aluminum conductors and materials are strictly prohibited. Refer to the VA specifications and construction manual for compliance requirements, use copper only.

54. How many floor mounted transformers are being replaced? 54.1. D2X/Ramboll - Refer to drawing ED-101 and ED-601. Two 300KVA transformers, two load interrupter switches and two motor control centers are being replaced.

55. Can the transformers being replaced be mounted in the air?

VA COR: No, the new transformer is a 300kVA transformer and needs to be floor mounted.

56. Specifications call for the installation of a chain link fence around the construction area. Is this in addition to the dust barrier?

VA COR: Yes. Chain link fence is in addition to the dust barrier.

57. Will the duct barrier require venting to the outside of the facility? 57.1. 5/5/26-VA agreed item 9 Will the duct barrier require venting to the outside of the facility? Should read ”Will the Dust barrier require venting to the outside of the facility?”

VA COR: Venting/exhaust to the exterior is not specifically required for the Class II dust-control barrier shown, unless required by the Contractor’s approved dust control plan, VA Infection Control, or if work conditions require negative-pressure containment. If exhaust is used, the Contractor must verify that construction exhaust is not reintroduced into the medical center through intakes or openings, and HEPA filtration is required where exhaust dust may reenter the facility. This needs approval by the COR.

58. Will the facility hoist be allowed to be used to lower equipment to the lower level of the facility? VA COR: No.

59. What is the required height of the Dust Barrier in the work zone?

VA COR: For the Class II precautions identified on GI-003, provide dust-control barriers as shown and as required by Section 01 35 26. Where a full containment barrier is required or directed by VA Infection Control/COR, the barrier shall extend from floor to ceiling with seams sealed to prevent dust migration. Final barrier limits and door locations shall be coordinated in the field with and approved by the VA COR.

See attached document: Switchgear Sign-in Sheet04-27-2026-125933.