36C24226B0034.docx

DOCX document 133 KB Posted

Attached to
Z1DA--NRM-CONST 630-26-202 Inspect and Repair Fire Dampers
Solicitation number
36C24226B0034
Issued by

About this file

This is a Standard Form 1442 Solicitation, Offer, and Award document for a sealed bid construction contract. The Department of Veterans Affairs, Veterans Health Administration, VISN 2 is soliciting bids for Project 630-26-202: Inspect and Repair Fire Dampers at the Margaret Cochran Corbin VA Medical Center, Manhattan Campus, located at 423 East 23rd Street, New York, NY 10010. The solicitation number is 36C24226B0034, with an estimated project magnitude between $250,000 and $500,000. This is a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside procurement, and only contractors registered in SAM with a verified/certified SDVOSB status in the Small Business Administration's certification database are eligible for award. The contract will be a firm-fixed-price agreement with a 365-calendar-day performance period from Notice to Proceed. Sealed bids must be submitted via email to lester.griffith@va.gov by 11:00 AM EDT on March 19, 2026, with bid opening occurring online via Microsoft Teams at 12:00 PM EST the same day. A mandatory pre-bid site visit is scheduled for February 26, 2026, at 11:00 AM EST at Building 2, First Floor, Engineering Room 133A. The deadline for submitting written Requests for Information (RFIs) is March 5, 2026, at 2:00 PM EST. Offerors must provide a bid bond equal to 20% of the bid price (not to exceed $3,000,000), acknowledge all solicitation amendments, and submit certifications including the Buy American Act Certificate and VAAR 852.219-75 Limitations on Subcontracting Certificate with their bids. Contractors must certify they have a minimum of five years' experience inspecting and repairing fire dampers in healthcare facilities and five years of NFPA experience.

The scope of work includes updating Life Safety and damper drawings per Joint Commission and VHA guidelines, conducting a comprehensive Life Safety Building Assessment in Buildings 1 and 6, performing inspections for barrier compliance, fire door compliance, and interstitial/wire sprinkler compliance, and executing fire damper repairs including installation of Belimo Motors on smoke dampers, access door installation, damper retesting, and linkage adjustments. Work shall be performed during normal hours (8:00 AM to 4:30 PM Monday-Friday, excluding holidays) with off-hours work required for ICRA constraints, and all demolished materials must be removed during off-hours (5:00 PM to 11:30 PM). The contractor must comply with NFPA standards, VA specifications, federal OSHA regulations, state and local codes, and provide required documentation including Pre-Construction Risk Assessment (PCRA), Interim Life Safety Measures (ILSM), Infection Control and Risk Assessment (ICRA), and Environmental Impact Assessment Process (EIAP) prior to construction start. The contractor must utilize VISN 2's Autodesk Build Construction Cloud (ACC) platform for project management and official correspondence, request access within 14 days of award, and complete required ACC training within 12 calendar days. All contractor personnel must obtain VA-issued identification badges, OSHA training certifications, TB test certifications, and complete VA Privacy Training. The NAICS code is 238990 (Business Size: $19 Million), and the government acceptance period for bids is 120 calendar days from the bid due date. Contractors are prohibited from subcontracting more than 75% of the amount paid by the government for contract performance (excluding material costs) to firms that are not certified SDVOSBs or VOSBs.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24226B0034 X 02-04-2026 630-26-202 630-26-202 36C242 Department of Veterans Affairs Network Contracting Office (NCO) 2 2094 Albany Post Rd Montrose NY 10548 "Via email at lester.griffith@va.gov"

Griffith, Les lester.griffith@va.gov The Contractor shall furnish all materials, supplies, equipment, personnel and supervision for Project 630-26-202 Inspect and Repair Fire Dampers in accordance with the drawings and specifications at the Margaret Cochran Corbin VA NYHHS Manhattan Campus.

Completion Time: 365 Calendar Days from the Notice to Proceed.

This is a 100% Service-Disabled Veteran Owned Small Business (SDVOSB) set aside procurement.

In order to be eligible for award, Contractor must be registered in SAM (www.sam.gov) with a Unique Entity Identifier and verified/certified as SDVOSB in the Small Business Search https://search.certifications.sba.gov/ at the time of bid/offer submission and before award of this procurement. Offerors must submit their annual Vets4212 Report. The North American Industry Classification System Code (NAICS) is 238990 - Business Size is $19 Million.

Magnitude of Construction: Between $250,000 and $500,000.

Contractor will be responsible for to coordinate and schedule work and shall be expected to plan work typically during duty hours of 8 AM to 4:30 PM eastern time except as noted in the general conditions and as approved by the CO. Work shall comply with VA Specifications and regulations, all applicable Federal, State and Local codes, including specific regulations related to working at the New York VAMC.

A pre-bid site visit is scheduled for February 26, 2026, at11:00AM EST. Prospective bidders shall meet at the New York VAMC located at 423 East, 23rd Street, New York, NY 10010.

NOTE: NO OTHER SITE VISITS WILL BE ALLOWED. INTERESTED BIDDERS ARE STRONGLY ENCOURAGED TO ATTEND.

To preserve the integrity of the procurement process, all questions and requests for information (RFIs) must be submitted in writing to the Contracting Officer at lester.griffith@va.gov.

Questions must be received no later than March 05, 2026, by 2:00PM EST.

The bid opening will be held online via Microsoft Teams on March 19, 2026, at 12:00PM EST. Details are on page 16.

ONLY EMAILED BIDS to lester.griffith@va.gov will be accepted. The bids shall include copies of the original bid bond.

VAAR 852.219-75 Limitations on Subcontracting Certificate is a separate requirement Attached or Page Numbers.

FAR 52.225-2 Buy American Act Certificate is a separate requirement attached in the solicitation.

The signed certificates must be received with the bid.

FAR Part 36.209 Construction contracts with architect-engineer firms. No contract for the construction of a project shall be awarded Rascap LLC Acceptance Engineering or its subsidiaries or affiliates.

NOTE: CONTRACTORS MUST ACKNOWLEDGE ALL SOLICIATION AMENDMENTS.

X X 52.211-10 X 11:00am

EDT

03-19-2026 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C242 Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx NY 10468-3904 Tungsten Network https://www.tungsten-network.com/ customer-campaigns/veteransaffairs/

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS5
Scope of Work5
2.Code and Regulation Compliance:7
3.Personnel Qualifications:7
4.Performance Period and Hours of Work:8
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS14
1.1 BID PRICING SHEET15
2.2 Special Notes regarding FAR 52.229-3: Federal, State and Local Taxes:17
2.1 52.216-1 TYPE OF CONTRACT (NOV 2025) (DEVIATION)18
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (NOV 2025) (DEVIATION)18
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)18
2.4 52.228-1 BID GUARANTEE (SEP 1996)19
2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)20
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)20
2.7 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)21
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)25
2.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)25
2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)25
2.11 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008)26
REPRESENTATIONS AND CERTIFICATIONS27
3.1 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)27
3.2 52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (FEB 2024)29
3.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)32
GENERAL CONDITIONS35
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)35
4.2 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)35
4.3 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (NOV 2025) (DEVIATION)38
4.4 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (NOV 2025) (DEVIATION)39
4.5 SUPPLEMENTAL INSURANCE REQUIREMENTS40
4.6 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION)40
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)50
4.8 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)50
4.9 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (NOV 2025) (DEVIATION)56
4.10 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)58
4.11 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)58
4.12 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)61
4.13 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)63
4.14 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)64
4.15 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)65
4.16 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)65
4.17 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)66
4.18 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)67
4.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)67

36C24226B0034

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

Page 1 of

Page 1 of

Scope of Work Project Title: Inspect and Repair Fire Dampers Project Number: 630-26-202

Contractor shall provide all labor, materials, equipment and supervision as specified by the Scope of Work and Specifications. All work shall be performed at the Veterans’ Affairs Medical Center located on 423 East, 23rd Street, New York, NY 10010.

Scope of Work:

1. Update Life Safety and Damper drawings for the following requirements:

A. Update of Life Safety Drawings is per the latest Joint Commission and VHA guideline requirements to ensure the correct type of fire damper is properly coordinated with the fire and life safety system, boundaries, and HVAC requirements.

B. Meet with Key Engineering staff to review Life Safety Drawings and discuss the current Life Safety Management program.

C. Review existing Life Safety Drawings for smoke zones, suite sizes, hazard areas, and other pertinent information required.

D. Evaluate for proper boundary and fire damper coordination.

E. Identify understood deficiencies, penetrations in Smoke/Fire or corridor walls, and decks where applicable.

F. The survey and evaluation of all rated shafts, chutes, and chases identified on Organizations SOC / Life Safety prints.

G. The below ceiling survey includes but is not limited to: Means of egress, exits, locked doors, discharge, and travel distances, evaluation of smoke/fire/corridor doors for smoke tight integrity, sprinkler coverage, hazardous areas, and identification of sleeping and non-sleeping suites.

H. All life safety deficiencies will be documented and noted on the Hospital’s Life Safety drawings in pdf and CAD format.

I. The estimated square footage is derived from current life safety drawings.

J. Assist in budget development of our deficiency findings.

K. Evaluate the known fire damper deficiencies based on the updated life safety drawings for new, repair, de-commissioning, or change of damper function as needed for budgeting for corrective action.

L. Contractor shall consult with VA Facility Safety Specialist/Engineer to discuss all the current life safety deficiencies prior to start the survey.

M. Deliverable: Contractor to provide 100% Life Safety drawings in both PDF and AutoCAD format.

Hard copies of requirements:

95% design review, 4 sets of C-Size (17” x 22”) color print, 2 sets for LSD and 2 sets for DD 100% design review, 4 sets of C-Size (17” x 22”) color print, 2 sets for LSD and 2 sets for DD Final 100% drawings, 8 sets of C-Size (17” x 22”) color print, 4 sets for LSD and 4 sets for DD

2. Buildings 1 and 6 Inspection Services:

A. Barrier inspection for compliance B. Fire door inspection for compliance C. Conduct a Life Safety Building Assessment for compliance with the Joint Commission LS.01.01.01 EP3 D. Interstitial/wire on sprinkler inspection for compliance E. Life Safety Assessment Survey (Below Ceiling) inspection for compliance

3. Buildings 1 and 6 Fire Damper Repairs per previous Acceptance Engineering’s issued fire damper inspection reports:

A. Installation of Belimo Motors on smoke dampers per failure list.

B. Install access doors sized appropriately of ductwork size.

C. Upon corrective action completion, perform retest of damper.

D. Adjust linkages and recalibrate motors in order to operate properly.

E. Coordinate with COR for PCRA, ILSM and ICRA measures to be required and enforced during the project.

F. Install new fire and smoke dampers as noted on the deficiency list.

G. Contractor shall hook up dampers to existing power, if no power is present the facility will be responsible to bring power from the panel to the device location.

H. Contractor cannot run new legs of 120v or 24v to dampers listed as having “no power” with the information known at this time.

I. Keys, access, and/or support to the areas for coordination by/with FMS.

J. Security ID Badges as required by FMS.

K. Scope is based on Deficiency Report summary provided.

L. Work is planned for regular hours 1st shift.

M. Please allow 4-8weeks for mobilization and parts ordering from NTP.

N. Upon installation of Access doors and retesting there may be additional work and repairs needed beyond scope.

2. Code and Regulation Compliance:

The Contractor shall comply with the public laws and statutes including all changes and amendments of federal, state and local environmental statutes and regulations in effect of date of issuance of this contract, including, most current requirements of VHA and the applicable portions of the documents cited in the basic contract and below.

A. National Fire Protection Association (NFPA):

B. NFPA 99 Healthcare Facilities Code C. NFPA 101 – Life Safety Code D. NFPA 105-Chapter 7 Testing and Maintenance of Smoke Dampers and Combination Fire/Smoke Dampers

E. NFPA 80

F. NFPA 92-Chapter 8 Testing and Chapter 2 of NFPA 1001 Mandatory References G. JCAHO standards EC.5.40.14 H. 29 CFR 1910 Federal Occupational Safety and Health Act (OSHA) I. 29 CFR 1926 Safety and Health Regulations for Construction

3. Personnel Qualifications:

Contractors shall have a minimum of five years’ experience inspecting and repairing fire dampers in healthcare facilities and five years of NFPA experience. Contractors shall have a minimum of five years’ experience reading shop drawings to determine all locations (Damper Code).

4. Performance Period and Hours of Work:

The total project duration from issuance of Notice to Proceed is 365 calendar days. Work under this contract shall be accomplished during normal hours and off schedule. Manhattan VAMC normal working hours are 8:00 am through 4:30 pm Monday through Friday, excluding holidays. However, off work hours will be required due to ICRA constraints and/or impact on patients, staff and critical patient care areas when air handlers have to be shut down. Contractor shall inform COR 48 hours in advance when working off hours is required.

5. All demolished materials shall be removed off the site on a regular basis and during off hours (5:00 PM – 11:30 PM). All disposal and rubbish removals are the contractor’s responsibility.

6. Hold Bi-Weekly construction meetings and prepare meeting minutes.

7. Coordinate all fire alarm, sprinkler system and utility shutdowns with facility representative and attend utility shutdown meetings as requested by the Resident Engineer.

8. All work shall be performed in accordance with NFPA, Life Safety, VA Standards and Regulations, VA Policy and requirements, OSHA regulations, and manufacturer specification.

9. The Contractor shall provide his own storage for materials. The VA is not responsible for loss of tools, materials, equipment, etc.

10. Contractor shall provide following documentation for review and approval prior to start construction:

A. Pre-Construction Risk Assessment (PCRA) B. Interim Life Safety Measures (ILSM) C. Infection Disease Control and Risk Assessment (ICRA) D. Environmental Impact Assessment Process (EIAP)

11. Contractor shall be required to provide the following documentation for all of his/her personnel working on VA property:

A. VA issued identification badges B. OHSA Training certifications C. Construction Safety and Accident Prevention plans D. TB tuberculin test certifications

12. Since contractors will not access VA information or VASI, the C&A requirements do not apply, and a Security Accreditation Package is not required.

13. Privacy Training:

VA Privacy Training for Personnel without Access to VA Computer Systems or Direct Access to or the Use of VA Sensitive Information.

All contractor employees and subcontractors participating under this contract are required to complete the VA's Privacy training requirement - “VA Privacy Training for Personnel without Access to VA Computer Systems or Direct Access to or the Use of VA Sensitive Information” Contractors must provide certifications of completion to the COR during each year of the contract. Training expires 365 days after the training is taken. This requirement is in addition to any other training that may be required of the contractor and subcontractor(s). The COR for the contract is responsible for ensuring the contractor takes the training and to follow up with the annual requirements.

14. Project Management Platform Requirement:

1. Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2 Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative (COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.

1. Contractor shall accomplish and complete the following tasks upon award of contract:

1. Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award.

1. Only staff that shall utilize the platform to be granted access. Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc.

1. The access request shall be in writing and include a list of staff. The list shall include the following information:

· Full Name

· Company Name

· Email Address

· Role/Position on the project (i.e., Project manager, site super)

1. Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days.

1. Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 business days.

1. Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period.

1. Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above.

1. The contractor shall only use the ACC platform for contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration include but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys.

1. Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertain to staff who were granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor’s ability to maintain required utilization of the platform.

1. Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training.

15. Record Management Requirements:

A. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

B. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

C. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created while performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

D. [Agency] and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of [Agency] or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to [Agency]. The agency must report promptly to NARA in accordance with 36 CFR 1230.

E. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to [Agency] control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

F. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and [Agency] guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

G. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with [Agency] policy.

H. The Contractor shall not create or maintain any records containing any non-public [Agency] information that are not specifically tied to or authorized by the contract.

I. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

J. The [Agency] owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which [Agency] shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.

K. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take [Agency]-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.

CONSTRUCTION MANAGEMENT PLATFORM REQUIREMENTS:

1. Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2 Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative (COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.

1. Contractor shall accomplish and complete the following tasks upon award of contract:

1. Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award.

1. Only staff that shall utilize the platform to be granted access. Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc.

1. The access request shall be in writing and include a list of staff. The list shall include the following information:

· Full Name

· Company Name

· Email Address

· Role/Position on the project (i.e., Project manager, site super)

1. Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days.

1. Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 business days. \

1. Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period.

1. Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above.

1. The contractor shall only use the ACC platform for contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration include but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys.

1. Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertains to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor’s ability to maintain required utilization of the platform.

Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

GENERAL INTENTION

Contractor shall provide the labor and materials to include but not limited to the provided drawings and specifications for the Inspect and Repair Fire Dampers project located at the New York VA Medical Center. The period of performance is 365 calendar days from receipt of Notice to Proceed (NTP).

SITE VISIT

Bidders are urged and encouraged to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing these services. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

There will only be one (1) organized site visit. It will be held on February 26, 2026 @ 11:00 AM (EST). Participants will meet at the New York VAMC Building 2, First Floor, Engineering Room 133A. Please bring a government issued photo ID.

Parking will not be available.

Attendance is not mandatory; however, all bidders are strongly encouraged to attend.

REQUESTS FOR INFORMATION (RFI):

To obtain clarifications and/or additional information concerning the contract requirements or specifications, submit a written RFI via email to lester.griffith@va.gov.

RFIs will be responded to as necessary in amendment format which will be posted on www.sam.gov.

The deadline for submission of RFIs for this solicitation is March 05, 2026 at 2:00 PM (EST). No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone RFIs will not be accepted or returned.

DELIVERY OF BIDS

1. In accordance with FAR 14.202-8, the government is authorizing electronic bids on this solicitation. ALL bids shall be emailed to Les Griffith, Contracting Officer, at lester.griffith@va.gov and timestamped by 11:00am (EST) prior to the bid opening time. The bids shall include copies of a bid bond. The bid opening shall take place on March 19, 2026, at 12:00pm (EST). No hand-carried or mailed bids will be accepted.

2. The bid opening will take place via Microsoft Teams conference call. To access the conference, please access:

To join by phone please dial 1-347-566-4838 Phone conference ID: 909 885 534# Bids received after this time will be rejected.

Any exception to the terms and conditions of this Invitation for Bid (IFB) will result in a non-responsive bid.

Failure to provide a definitive price will result in a non-responsive bid.

Receipt of bids must be in accordance with the terms and conditions of this IFB.

Bidders must acknowledge (in writing only) amendments to this solicitation, otherwise a bid may be determined non-responsive.

The winning bidder must be determined as "responsible" by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.

BASIS FOR AWARD

Contract award will be made using FAR Part 14 Sealed bidding procedures, selecting the responsive, responsible bidder whose bid is conforming to the invitation for bids will be most advantageous to the Government, considering only price and the price-related factors included in the invitation. The selected bid must be determined to be a fair and reasonable price.

RESPONSIBILITY REQUIREMENTS

A Determination of Responsibility shall be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information may result in a determination of “non-responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause a negative Determination of Responsibility may make the bidder/offeror ineligible for award.

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

1.1 BID PRICING SHEET

IFB No.: 36C24226B0034 Project No.: 630-26-202

Bids providing less that 120 Calendar Days of Government Acceptance after the date bids are due will not be considered and will be rejected.

The bidder agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this bid is accepted by the Government in writing within 120 calendar days after the date bidders are due.

BASE BID

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Contractor shall provide all labor, materials, equipment and supervision as specified by the Scope of Work and Drawings and Specifications.

The Contract period of performance for Base Bid construction shall be 365 calendar days from Notice to Proceed (NTP).

Base Bid $ ___________________________

Offers shall provide a complete package to include the completed bid sheet along with the following to be determined responsive, responsible, and considered for award:

o Bid Bond and associated documents on correct forms;

o Acknowledgement of all amendments;

o Completed 52.225-2 Buy America Certificate o Completed 852.219-75 VA Notice of Limitations in Subcontractors Compliance Certificate o Verified/visible/certified on the Small Business Administration Certification (VetCert) of VetBiz (https://veterans.certify.sba.gov); and/or Dynamic Small Business Search (DSBS) SBA - Dynamic Small Business Search o Proof of compliance with VETS 4212 Federal Contractor Reporting.

o Safety or Environmental Violation and Experience Modification Rate (EMR) (See further information on the next page)

Safety or Environmental Violations and Experience Modification Rate:

All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.

All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information will be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.

Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead may obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR will obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.

RESPONSIBILITY REQUIREMENTS

A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information may result in a determination of “non-responsibility” for the bidder/offeror.

NOTE: Any information received by the Government that would cause a negative Determination of Responsibility may make the bidder/offeror ineligible for award.

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

2.2 Special Notes regarding FAR 52.229-3: Federal, State and Local Taxes:

Offerors are hereby notified that under New York Consolidated Laws, Chapter 60 - Tax, Article 28 - Sales and Compensating Use Taxes, Part 3 – 1116 (2), the United States of America, any of its agencies and instrumentalities, is immune from taxation when it is the purchaser, user, or consumer, or when it sells services or property of a kind not ordinarily sold by private persons.

Pursuant to Chapter 60, Article 28, Part 3-1115(17), a contractor’s purchase of such building and construction materials within New York to be incorporated into the real property belonging to the U.S. Department of Veterans Affairs (VA) is subject to the exemption from the New York State sales and compensating use taxes. To take advantage of the tax exemption the successful offeror under this solicitation must complete ST-120.1 “Contractor Exempt Purchase Certificate” when it purchases construction materials for this contract and keep on file as required by the state of New York tax laws.

Notwithstanding FAR 52.229-3, all bids received in response to this solicitation are presumed to reflect this tax exemption and therefore should not include the New York’s state sales and compensating use taxes on sales of materials for incorporation into VA real estate under this contract.

2.1 52.216-1 TYPE OF CONTRACT (NOV 2025) (DEVIATION)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (NOV 2025) (DEVIATION) (a)(1) The offeror must notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror must request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror must request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.4 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20% percent of the bid price or 3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

(End of Provision)

2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Les Griffith email at lester.griffith@va.gov Hand-Carried Address:

N/A

Mailing Address:

N/A

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.7 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)

(a) Definitions. As used in this provision— Backhaul, covered article, covered telecommunications equipment or services, critical technology, FASCSA order, Intelligence community, interconnection arrangements, national security system, roaming, sensitive compartmented information, sensitive compartmented information system, source, and substantial or essential component have the meanings provided in the clause 52.240-91, Security Prohibitions and Exclusions.

Business operations means engaging in commerce in any form, including by acquiring, developing, maintaining, owning, selling, possessing, leasing, or operating equipment, facilities, personnel, products, services, personal property, real property, or any other apparatus of business or commerce.

Marginalized populations of Sudan means—

(1) Adversely affected groups in regions authorized to receive assistance under section 8(c) of the Darfur Peace and Accountability Act (Pub. L. 109-344) (50 U.S.C. 1701 note); and

(2) Marginalized areas in Northern Sudan described in section 4(9) of such Act.

Restricted business operations means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174). Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate—

(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;

(2) Are conducted under specific authorization from the Office of Foreign Assets Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;

(3) Consist of providing goods or services to marginalized populations of Sudan;

(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;

(5) Consist of providing goods or services that are used only to promote health or education; or

(6) Have been voluntarily suspended.

Sensitive technology—

(1) Means hardware, software, telecommunications equipment, or any other technology that is to be used specifically—

(i) To restrict the free flow of unbiased information in Iran; or

(ii) To disrupt, monitor, or otherwise restrict speech of the people of Iran; and

(2) Does not include information or informational materials the export of which the President does not have the authority to regulate or prohibit pursuant to section 203(b)(3) of the International Emergency Economic Powers Act (50 U.S.C. 1702(b)(3)).

(b) Procedures.

(1) Covered telecommunications and video surveillance. The Offeror shall review the list of excluded parties in the System for Award…