Arc-Flash_Report_-_-SEPT-15-2021.pdf

PDF 9 MB Posted

Attached to
J061--526-23-110 Electrical Switchgear Replacement Phase 1 Federal contract opportunity
Solicitation number
36C24224B0031
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

This document is an Arc-Flash Study for the James J. Peters VA Medical Center in Bronx, NY. The study evaluates the electrical system at the facility, including a review of the single line model, load flow, short circuit analysis, protective device coordination, and arc flash incident energy calculations. Key findings include:

The facility is served by four independent 5kV feeds from ConEdison, with two 3575 kVA diesel generators providing backup power. The 480V system consists of two main secondary switchgear networks that feed the majority of the loads. The study identified some voltage drop issues, protective device coordination challenges, and high arc flash incident energy levels in certain areas that need to be addressed. Several code and safety violations were also noted related to missing panels, exposed live parts, and inadequate working clearances. The report provides recommendations to upgrade equipment, improve coordination, and resolve safety issues throughout the electrical system.

View the file

Other files for this federal contract opportunity

Other files attached to J061--526-23-110 Electrical Switchgear Replacement Phase 1, newest first.
File Type Posted
36C24224B0031 0003.docx DOCX document
S06 Brand Name or Equal Product Salient characteristics - Electrical Switchgear Replacement Phase 1.pdf PDF
S06 IFB 36C24224B0031 Electrical Switchgear Pre-bid walkthrough Sign in Sheet 4-11-2024.pdf PDF
S05 RFI Answers -Electrical Switchgear Replacement 36C24224B0031.pdf PDF
VA-BRONX-SINGLE-LINE-Electrical Switchgear Replacement Phase 1.pdf PDF
REVISED VA-BRONX-SOW-Electrical Switchgear Replacement Phase 1-rev1.docx DOCX document
36C24224B0031 0002.docx DOCX document
36C24224B0031 0001.docx DOCX document
P01 Safety REQUIREMENTS -SECTION 01 35 26-Electrical Switchgear Replacement Phase 1.docx DOCX document
P01 Section262921-ENCLOSED SWITCHES AND CIRCUIT BREAKERS-Electrical Switchgear Replacement Phase 1.docx DOCX document
P07 Wage Determination Electrical Switchgear replacement.pdf PDF
P01 GENERAL REQUIREMENTS-010000-Electrical Switchgear Replacement Phase 1.docx DOCX document
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (DEVIATION).pdf PDF
FAR 52.225-2 BUY AMERICAN CERTIFICATE.docx DOCX document
P01 QC-SECTION 01 45 00-Electrical Switchgear Replacement Phase 1.docx DOCX document
P01 SECTION 26 05 11-REQ FOR ELECTR INSTALL -Electrical Switchgear Replacement Phase 1.docx DOCX document
36C24224B0031_1.docx DOCX document
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

23 Mechanic Street Springville, NY 14141

2745 Broadway Buffalo, NY 14227 encorus.com 716.592.3980

Arc-Flash Study

J. J. Peters VAMC Arc-Flash Evaluation

Prepared For:

J. J. Peters VAMC

Order# 36C24221C0085

Engineer of Record

“Unauthorized alteration or additions to any plans, specifications or reports bearing a Licensed Professional

Engineer’s seal is a violation of Section 7209, subdivision 2, of the New York State Education Law”.

September 15, 2021

REP-21041-06-001 REV. 1

REV 1 – Edits from the VA review

Encorus Project # 21041

9/14/2021

Arc-Flash Study J. J. Peters VAMC Arc-Flash Evaluation

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

TABLE OF CONTENTS

1.0 EXECUTIVE SUMMARY

2.0 METHODOLOGY

3.0 RESULTS

4.0 DEFICIENCIES

4.1.1 NEC 110.26 Required Clearance Space

4.1.2 NEC 490.48(B) Single Line Drawings and Protection Schemes

4.1.3 NEC 408.7 Unused Openings

5.0 REFERENCES

APPENDIX A ONE-LINE DIAGRAMS

APPENDIX B LOAD FLOW STUDY

APPENDIX C SHORT CIRCUIT STUDY

APPENDIX D TIME-CURRENT COORDINATION

APPENDIX E ARC-FLASH INPUT/OUTPUT MATRIX

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

1.0 EXECUTIVE SUMMARY

The following report is to update the engineering model of the electrical system at the James J.

Peters VAMC in Bronx NY. The previous report was written by Schweitzer Engineering Laboratories’ Government Engineering Solutions department (SEL GES) in 2015. The model that was updated in 2015 was the basis of this evaluation. This report will re-evaluate the Single Line Model of the campus along with calculate and report on the Load Flow and Generation Capacity, Short Circuit, System Coordination and finally Arc Flash Analyses.

Along with a technical analysis this report will review the installed equipment for code, system integrity, and “health” of the installed system.

The final goal of this report is to review the as found condition of the equipment during the visual inspection portion of the project. During this visual inspection the system was photographed and reviewed for code compliance, in installation, upkeep and system integrity. The deficiencies from the previous SEL report in 2015 was also reviewed to see if they have been completed or not.

DESCRIPTION OF THE ELECTRICAL SYSTEM

5kV System

The site is served at four independent locations by Consolidated Edison, Inc. (ConEdison). The first two points of service supplies transformers 1X-32 and 1X-21. Each feed consists of one 3000kVA, 13.2kV // 4160V transformer supplying power to a 5kV bus.

The third and fourth points supplies transformers 1X-28 and 1X-29. Each of these feeds also consist of one 3000kVA, 13.2kV // 4160V transformer supplying power to a 5kV bus.

The four 5kV buses are backed up by a pair 3575kVA, 4160V Diesel Generators. Each generator has its own synchronized bus and ties all four 5kV supply busses together via a coordinated breaker system. This system allows any of the four 5kV buses to be fed loads individually or tied through the generator’s sync bus. The generators are also synchronized to back up the system independently or run along with the utility for support.

480V System

The “Main Secondary Switchgear” (MSS) Networks feed the majority of the 480V loads across the site via a bus duct network within the main hospital and research building.

Each of the four above mentioned 5kV buses supplies power to five 2500kVA, 480VAC transformers one 500kVA and one 300kVA transformer. The 2500kVA transformers feed 480VAC buses that are broken into two MSS networks on the north and south ends of the campus and one 480V switchgear dedicated to CHILLER 3.

The MSS are two double ended 480V switchgear that feed the bulk of the 480V load on the site.

The third “network” is a single ended feed to a dedicated switchgear for the 480VAC Chiller in the powerhouse.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

The 5kV feed to the 500kVA transformer is for the “MDS” switchgear in the Community Living Center (CLC). The MDS feeds the CLC, chapel and pool.

The final 5kV feed is tied to the primary side of the MDS switchgear and feeds a 300kVA transformer for the Fisher housing areas.

Emergency Systems

The emergency system is broken between Equipment, Critical and Life Safety system per the NEC 700 requirements.

NDP – Normal Distribution Panel EED - Emergency Equipment Distribution CPD- Critical Power Distribution LSD- Life Safety Distribution

Each of the MSS Networks have their own NDP (Normal Distribution Panel). These panels feed the normal power side of Automatic Transfer Switches to LSPD (Life Safety Distribution Panel), CPDP (Critical Power Distribution Panel), EEDP (Emergency Equipment Distribution Panel).

The emergency side of the transfer switches are feed from five generators connected to two generator buses. Network #1’s generator bus (South side) has generators G1, G3 and Network #2’s bus (North side) has G2, G4 and G5. The two generator buses are connected with tie breakers.

Refer to the Single Line drawings in Appendix <A> for details.

2.0 METHODOLOGY

The update to the electrical system started with a review of the existing drawing and SKM models and previous SEL study. These documents were reviewed and set against the most up to date drawings to identify areas upgraded from the last study.

A site investigation was then conducted to photograph, update the drawings and document the changes to the site. The photos can be found in the BIM site connected with this project. The changes have also been outlined and shown on the Single Line drawings see appendix <A>.

The updates to the site have been entered into the latest edition of SKM ver. 9.0.1.1 And a new version of the Single Line Diagrams has been developed and added to this report.

3.0 RESULTS

See attached appendices for one-line diagrams, Load Studies, Short Circuit Studies and an arc-flash input/output matrix. The following results show where areas of deficiency are in the current system as it was found in our investigation.

These areas will be reviewed and catalogued for engineering support and potential upgrades depending on the results shown below.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Load Study

The voltage drop analysis evaluates the level of voltage drop at each point in the system as compared to that allowed by the 2020 National Electrical Code (NEC).

See Appendix (B)

- Example Load Flow Summary

The Load Flow Calculator will show each bus in the model as in or out of service and compare the buses rated design voltage against the calculated loaded voltage. From this calculation is determined the % Voltage Drop at each bus. This is displayed in both %VD and PU (per unit) value.

Design Settings

The load study is based on a global demand load for each voltage level (i.e., 13.2kV, 4.16kV, 0.48kV, and 0.28kV). For this study the global demand was set at 100% for the 13.2kV level, 20% for the 4.16kV level, 20% for the 0.48kV level, and 25% for the 0.28kV level.

Currently, ConEdison is replacing transformer 1X28, which has caused an increase in the voltage drop throughout the system. To show this, we provided a load study with the 1X-28 transformer in

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041 and out of service. Note: When placing transformer 1X28 back in service we estimated the transformer’s impedance from the other existing transformers.

Results and Worst-Case Load Scenarios

• Results with 1X28 out of Service

This is the current running condition and also the worst-case utility scenario. The results shown in Appendix (B) show significant voltage drop (greater than 5%) in areas across the south side of the campus without the voltage support of transformer 1X28.

The NEC recommends that the maximum combined voltage drop for both the feeder and branch circuit shouldn't exceed 5%. Excessive voltage drop in a circuit can cause lights to flicker or burn dimly, heaters to heat poorly, and motors to run hotter than normal and burn out. This is because the load has to work harder with less voltage pushing the current.

Our recommendation would be to bring transformer 1X28 in service when available. Until this is available, if any of the above conditions are seen in the hospital, shedding some of the load or tapping up supporting transformers may be temporarily necessary.

Results with 1X28 in Service

Note: A Common impedance has been estimated for 1X28 to generate these results. This load shows the “normal” running conditions once 1X28 is back in service. The summary of these results is included in Appendix (B).

With transformer 1X28 back in service the model shows the high voltage drop shown on the south side of the campus lowers below 5% in most cases. In the Research Building,105, the model stills shows a higher than desirable voltage drop. This may be due to over-estimation in the modeling but if the above negative conditions are still in the hospital areas the loads and voltages should be measured and monitored so corrective actions can be made.

• Results on 4160 Generation Only – A bus summary has been added to show the voltage drop when the Utility is out of service and the 4160V Generation backs up the hospital. As expected, voltage sag is very high in this temporary condition, however no bus’s fault in this scenario which shows the current emergency generation is sufficient for the current load.

Short Circuit Analysis

The short circuit analysis evaluates the adequacy of the electrical system equipment to withstand or to interrupt the calculated maximum available short circuit current at its location.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

See Appendix (C)

- Example Short Circuit Study

The short circuit report summarizes the maximum available fault duties, using SKM PTW Comprehensive Short Circuit Study setup, when the system is being supplied by the utility.

The types of unsymmetrical faults occurred due to the short circuit conditions, namely single phase or line to ground (SLG) fault, phase to phase (LL) fault and double line to ground (LLG) fault.

A single line-to-ground (LG) fault is one of the most common faults and experiences show that 70-80 percent of the faults that occur in power system are of this type.

A line-to-line fault occur when a live conductor comes in contact with another live conductor.

In double line to ground faults, two lines come into the contact with each other as well as with ground.

A Symmetrical or balanced three phase fault is where all three phase are faulted together. This is the most severe but also the least likely, happening in about 2% of total system faults.

Because of its severity, symmetrical three phase fault analysis is necessary for determining the size of a circuit breaker for largest short circuit current.

The results found in Appendix C are broken up by bus, contributing branch circuits and available Symmetrical and Asymmetrical fault categories as described above.

Fault Scenarios

• 1X28 out of Service

A summary of this scenario has been included as the current case in the current service of the campus.

REP-21041-06-001 REV. 1

September 15, 2021

• 1X28 in Service and Normal Utility in Service

A summary of this scenario has been included as the “normal” case once the 1X28 Transformer is back in service.

Note: A Common impedance has been estimated for 1X28 to generate these results. This summary was added to show the fault contributions when normal operating conditions are returned.

Short Circuit Results and Equipment Ratings

The results of the short circuit analysis are used to feed the available energy for the Arc Flash study.

The second purpose of these results are to compare the available fault current to the protection devices interrupting rating. This will determine a devices ability to withstand a short circuit or overload energy. This is shown in SKM as the device’s equipment rating.

Equipment Ratings

This appendix is a list of the buses including Switchgear, Motor Control Centers, Distribution, panel boards and main protective devices. The purpose is to compare the buses and protective devices rated voltage, ampacity and interrupt rating versus the calculated load and available fault current. If the available fault current is larger than the buses’ fault interrupt rating it is flagged as deficient and our recommendations for upgrade or replacement.

The equipment study shows all the equipment ratings meet or exceed the short circuit fault rating.

The equipment that was failed from the 2015 study has been replaced and the new equipment meets the short circuit requirements.

REP-21041-06-001 REV. 1

September 15, 2021

Protective Device Coordination

The protective device coordination study determines the suggested settings and ampere ratings for all electrical power system protective devices in order to achieve the desired system protection and electrical service continuity goals.

Included in this section are coordination curves for the major buses within the hospital electrical network. The complete TCC results of the Coordination study can be seen in Appendix D. Listed below are TCC examples where miscoordinations were found and suggestions to improve the system coordination.

• TCC NAME – EDSN / GEN4 / ATS 6 (North side Generator Bus)

The Generator and EDSN mis-coordinate. The large clear time of the molded case Siemens breaker overlaps the generator bus breaker. The generator breaker can be slightly adjusted to improve this overlap of these breakers (see the charts below)

Current Settings Proposed Settings

LTPU: 1 – 12 LTPU: 1 – 12

STPU: 6 STPU: 6

STD: 0.1 STD: 0.4

INST: 15 INST: 15

REP-21041-06-001 REV. 1

September 15, 2021

The Arc Flash Incident Energy at bus EDSN is unaffected by this change.

• TCC NAME – EEDP(Normal) (Nursing Home MDS Gear Room)

The Normal side of the NHEATS mis-coordinates with the main in MDS. Again, a delay to MDS long time delay would improve this coordination.

Current Settings Proposed Settings

LTPU: .8 LTPU: 1

LTD: 4 LTD:15

STPU: 5 STPU: 5

STD: .1 STD: 0.1

INST: M1 INST: M1

REP-21041-06-001 REV. 1

September 15, 2021

The Arc Flash Incident Energy at bus MDS is unaffected by this change.

• TCC NAME –In places on the Main Distribution Buses MSS-1 and MSS- 2 fused disconnects are the installed in place of Main Panel Breaker. The fuses typically either mis-coordinate with the main breaker or are set so high they are oversized for the application. In the examples below The two breakers are in much better coordination.

As these serve the same branch feeder they do not need to be replaced we are pointing out

- The different applications within the same system

- That if the fuse opens up the downtime is typically longer as the fuses need to be replaced

- The coordination of the breakers is much better and easier to maintain.

Our recommendation is that the switch over gets completed throughout MSS-1 and 2 as the breakers are easier to coordinate and will lead to fewer nuisance outages.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

• TCC NAME – NQ Dist Pnl (The feeder to the Chapel Building)

The breaker is very limiting to the full load ampacity of the transformer feeding it. This may have been done intentionally due to the reduced loading in the area. No action is required we are pointing out a possible nuisance point if the load in the area is ever increased.

• TCC NAME – EDSS / EDSN (The 480VAC Generator Buses)

The TCC Curves shown in this report were from the existing data and could not be verified during our initial inspections because the generators could not be run.

The TCC settings show proper coordination and should be field verified to ensure these settings are still accurate when possible.

• MSS 1 and MSS 2 Bus System

The main feeders for building 100 are feed from federal pacific busways out of MSS1 and MSS2.

These busways go from the ground floor all the way to the top of the hospital and are tapped at each floor in the designated electrical rooms for their floor. These taps are typical made with 400 or 800A fused disconnects which then feed main distribution panels in the electrical rooms. These main distribution panels are sometimes MLO (Main Lug Only) which means there is no main circuit breaker in the panels and these panels rely on fuses in the disconnect to protect the panels. In some cases, these fuses do not exist or do not coordinate with the panels or the busway circuit breakers in MSS1 and MSS2. This is a code violation and dangerous condition where a fault in these panels would build until the circuit breaker in the MSS would have to open the busway to interrupt the fault.

When the distribution panel includes a main circuit breaker, the coordination is significantly improved.

REP-21041-06-001 REV. 1

September 15, 2021

Showing MLO panel LGD SEC1 protected by fused disconnect overlapping main MSS feeder breaker.

Showing Breaker to Breaker coordination from MSS1-A to L1DA

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

To properly protect these panels our recommendation would be to add a main circuit breaker in the MLO distribution panels and coordinate them with the MSS breaker feeding the busway as shown in the chart above.

Alternatively, properly sized and coordinated fuses could be added to the fused disconnect switches to accomplish this protection scheme. However, as seen in the chart above the Main Circuit Breaker and the fuse are trying to protect the same panel at the same current and coordinating the two protection devices will be difficult or impossible.

Protective Device Coordination Results

With only the few exceptions found above the protective device coordination was found to be in order. Our recommendation would be to make the few adjustments shown above. Secondly, a single protection scheme has to be determined for the MSS busway networks and properly installed to protect the electrical floors distribution panels. Our suggestion would be to coordinate the Mains on the distribution panels with the MSS busway feeder breakers consistently throughout.

REP-21041-06-001 REV. 1

September 15, 2021

Arc Flash Analysis

Flash Evaluation is a program that calculates the incident energy and arc flash boundary for each location of the power system. The study automatically reads the short circuit duties at each bus and through each protective device. The arcing fault current through the protective devices is then calculated from the bolted fault value and used to automatically find the time duration of the arc from the time current coordination (TCC) curves. Incident energy and arc flash boundaries are calculated based on the bus 3 phase fault current and arcing duration. Clothing requirements are specified from a user defined personal protective equipment table.

Example Arc Flash Incident Energy Chart - Appendix (E)

Hazard-Risk Tables

The following table is the Hazard-Risk Table from the SKM Power Tools Arc Flash Module.

The Personal Protective Equipment (PPE) Table and is taken from NFPA 70E Informative Annex H.

The Risk-Hazard table is divided based on a range of incident energy (IE), measured in calories/cm^2 (cal/cm^2), representing the available arc flash heat energy. The threshold value of incident energy that can cause 2nd degree burns to the uncovered skin is 1.2 cal/cm^2 (citation needed, read from https://electrical-engineering-portal.com/what-is-incident-energy-caused-by-arc-flash).

The required level of PPE per incident energy level is shown below and ranges from levels 0, 3, 4, and Dangerous.

PPE level 0 corresponds to the range 0.0 to 1.2 cal/cm^2.

PPE level 3 corresponds to the range 1.2 to 12 cal/cm^2.

PPE level 4 corresponds to the range 12.0 to 40.0 cal/cm^2.

PPE level Dangerous corresponds to anything above 40.0 cal/cm^2.

REP-21041-06-001 REV. 1

September 15, 2021

Incident Energy From

(cal/cm^2)

Incident

Energy To

IE Low

Marginal (cal/cm^2

IE High

Marginal (cal/cm^2

PPE Level

PPE Level

Clothing Layers

Required Minimum Arc

Rating of

PPE

Note s

0.0

1.

0.000

1.190

Nonmelting or Untreated Fiber

N/ A

H.3

1.2

12.0

1.210

11.800

Arc-Rated Shirt & Pants + Arc-rated Coverall

+ Arc-Rated Arc Flash Suit

2 or 3

12.

40.0

12.200

38.000

Arc-Rated Shirt & Pants + Arc-Rated Coverall

+ Arc-Rated Arc Flash Suit

3 or more

40.

999.0

41.000

998.000

Dangerous!

Level

Backgroun d Color

Level

Foregroun d Color

Warning Label Text

Head & Eye & Hearing Protection

Hand & Arm Protection

Foot

Protection

PPE Others 1

WARNING

Safety Glasses or Goggles + Ear Canal Inserts

Leather Gloves

N/A

Safety glasses

Hardhat + Safety Glasses or Goggles + Ear Canal Inserts + Leather

Work Shoes

Arc-rated Gloves

Leather work shoes

Safety glasses, electrically rated hard hat with hood and face shield.

Hearing protection.

Hardhat + Arc-Rated Arc Flash Suit Hood + Safety Glasses or Goggles + Ear Canal Inserts +

Leather Work Shoes

Arc-rated Gloves

Leather work shoes

Safety glasses, electrically rated hard hat with hood and face shield.

Hearing protection.

DANGER

REP-21041-06-001 REV. 1

September 15, 2021

PPE Others 2

PPE Others 3

PPE Others 4

PPE Others

PPE Pictures 1

PPE Pictures 2

PPE Pictures 3

Non-melting or untreated natural fiber (cotton/wool/rayon/silk

4.5 oz/sq yd), shirt

(long-sleeve), pants (long).

> 50V voltage rated tools +

Class 0 (minimum) gloves

Dielectric shoes or insulating mat (step and touch potential).

..\bin\resource\Cat egory0.bmp

..\bin\Resource\P

P

E_Category_0.b m p

25 cal/sq cm, Arc-rated shirt (long-sleeve) plus Arc-rated pants (long) plus Arc-rated coverall, plus arc rated arc flash suit jacket, pants, & hood, Arc-rated rainwear as needed.

Class 0 (minimum) gloves and leather protectors

(flash).

Leather shoes

(flash) as needed.

Dielectric shoes or insulating mat (step and touch potential).

..\bin\resource\Cat egory3.bmp

..\bin\Resource\P

P

E_Category_3.b

40 cal/sq cm, Arc-rated shirt (long-sleeve) plus Arc-rated pants (long) plus Arc-rated coverall, plus arc rated arc flash suit jacket, pants, & hood, Arc-rated rainwear as needed.

Class 0 (minimum) gloves and leather protectors

(flash).

Leather shoes

(flash) as needed.

Dielectric shoes or insulating mat (step and touch potential).

..\bin\resource\Cat egory4.bmp

..\bin\Resource\P

P

E_Category_4.b

..\bin\resource\Cat egory4.bmp

..\bin\Resource\P

P

E_Category_Dan g er.bmp

Adjustments to Incident Energies - Arc Flash Analysis

Buses EDSS and EDSN have different Arc Flash incident energies depending on the number of generators running in the scenario when they fault. The Arc Flash incident energies are shown in Appendix E.

The highest incident energy levels are when all the generators and utility are running paralleled and in this case the bus cannot be worked on live. The Arc Flash labels will reflect this condition.

Network buses MSS-1 and MSS-2 have very large incident energy levels and these also cannot be worked on live. Reducing the incident energy levels of these buses is difficult due to the equipment currently installed. The currently installed breakers do not have the adjustment ranges or maintenance modes of more modern equipment. Additional equipment could be installed around MSS1 and 2 to reduce the incident energy levels but this is would require an upgrade to the Network Buses.

Alternatively, MSS 1 and 2 buses are near the end of their effective service life and cost-benefit of replacing these items with more modern arc flash equipment compared to trying to extend their life by adding equipment around them should be looked at.

The MDS bus has a high incident energy level and is near the maximum allowable limit for live work.

If it is desirable to perform live work on the MDS bus arc flash reduction breakers with maintenance mode settings or changing the primary fusing on the incoming bus would be recommended.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

4.0 DEFICIENCIES

The purpose of this section is to review areas where repeated installation, safety or code violations were found. A list of the common violations along with photos and recommendations is included below. All building, floor/room locations are listed in the tables below. An exhaustive list of all the inspection photographs have been uploaded to BIM360 for your review.

4.1.1 NEC 110.26 Required Clearance Space

The required working area around electrical equipment is defined by the NEC. Many Panels, motors, pull boxes did not have the proper required working space around them.

4.1.2 NEC 490.48(B) Single Line Drawings and Protection Schemes

A working set of up-to-date drawings are required by the NEC. Diagrams shall clearly identify interlocks, isolation means, and all possible sources of voltage to the installation under normal or emergency conditions, and the marking on the switchgear shall cross-reference the diagrams. In many cases throughout the campus these diagrams either do not exist or are obsolete or inaccurate.

4.1.3 NEC 408.7 Unused Openings

Unused openings for circuit breakers and switches shall be closed using identified closures, or other approved means that provide protection substantially equivalent to the wall of the enclosure.

REP-21041-06-001 REV. 1

September 15, 2021

Panel Deficiency Building 100 Ground Floor

PGA SEC4: open breaker slots, back panel is incorrect size.

LGD SEC1: Panel cover not installed correctly, no back panel exposed live wiring.

LGD SEC 2 Panel cover not installed correctly, no sched.

Panel Deficiency Building 100 Ground Floor / GD and Kitchen

GD-213 Open Wireway / exposed live wiring.

KPGEA and KPGEA – N, No Schedule

SPSA – Panel cover is the incorrect size, live wiring is exposed

REP-21041-06-001 REV. 1

September 15, 2021

Panel Deficiency Building 100 – Ground & 1st Floor

Fire Pump Area (outside Network 1 Rm) Open wireway

L1C SEC 1 - Exposed Breaker Slots

L1C SEC 2 - Exposed Breaker Slots

Panel Deficiency Building 100 - 1st Floor

P1D Sec 1 – Missing back panel, Exposed Live Wiring

P1DA Sec 1 – Missing back panel, Exposed Live Wiring

P1DA Sec 2 – Missing back panel, Exposed Live Wiring

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Panel Deficiency Building 100 - 1st Floor & 2nd Floor

P1DA Sec 3 – Missing back panel, Exposed Live Wire

EQ1C – Missing back panel, Exposed Live Wiring

CC2B – Missing back panel, Exposed Live Wire

Panel Deficiency Building 100 - 2nd Floor

EQ2B – Missing back panel, Exposed Live Wire

EQ2C – Missing back panel, Exposed Live Wire

P2D1 – Back Panel is the incorrect size and leave live exposed wiring.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Panel Deficiency Building 100 - 2nd Floor & 3rd Floor

ELG2 – Exposed Breaker Slots

EL3C – Exposed Breaker Slots

Panel Deficiency Building 100 – 6th Floor

L6B – Exposed Breaker Slots P6C-SEC2 – Exposed Breaker Slots

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Panel Deficiency Building 105 Research

EE1HA – Missing Back Panel, exposed live wiring.

M2RA – Missing Back Panel Exposed live wiring.

3B-1G Panel is missing back panel and has exposed live wiring.

Panel Deficiency Building 105 4th Floor

PGR4 – Wrong Back panel, Exposed live wiring.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Panel Deficiency Building 101 Boiler Room Powerhouse

EP1K – Main Breaker installed upside down

Panel Deficiency Building NH / CLC

EEDP – Main was removed, breakers slots are exposed, live wiring is exposed.

The missing main moves the trip coordination to the breakers in the ATS. This appears to be deliberate to remove dual breakers causing nuisance trips. If this is the case our only recommendation would be to cover the breaker slot and note in the LOTO procedure that the main disconnect means for this panel includes locking out the ATS.

P1B-1 – Back panel is the incorrect size, wiring is exposed.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Panel Deficiency Building NH / CLC

P2C2 – Back panel is the incorrect size. Live wiring is exposed.

Room 2E-1-

Working space violations, the panels are inaccessible

Bldg 100 1st &2nd floor – Working Space blocks

Working space violations due to installed and uninstalled transformers. 208V panels require 3’ clearance.

Working space violations RM 1F-100 Panel L1F2 doesn’t open 90 degrees

2B-13 Working space violations due to installed and uninstalled transformers. Bldg 100 2nd floor

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Building 100 Penthouse

Building 100 Penthouse – The demolition of the AHU has left exposed wire, unlabeled and open panelboards, unsupported conduit, exposed panelboards and debris over and around electrical equipment. The demo in this area should be completed and work areas clearly marked.

Building 100 Penthouse – Continued

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Unlabeled panels

Room 1E-72 Panel is unlabeled

Room 02-7A

– Panel is unlabeled

Room 1D-63 –

Panel is unlabeled

Unlabeled panels

Room 2C Elec &

MECH –

Panel is unlabeled

Room 3D-

MECH –

Panel is unlabeled

Room 3E-MECH -4 Panel is unlabeled

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

Unlabeled panels

Room 4C-MECH –

Panel is unlabeled

NH MDS –

2 Panels are unlabeled

NH-1st

NH First Floor hallway.

Panel is unlabeled

To make proper Arc Flash labels for the panels we are suggesting the following names.

Unlabeled Panel Room Suggested Name for the Panel

1D-63 E1D1

1E-72 EQL1E

2A-07 L2A1

2C ELEC & MECH EQL2C

3D-MECH EQL3D

3E-MECH EQL3E

4C-MECH EQL4C

MDS ROOM (2) panels P-COR-1 and L-COR

NH 1st Floor NH1

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

5.0 RESULTS AND RECOMMENDATIONS

One Line

A working set of up-to-date drawings are required by the NEC 490.48(B). The existing set of single lines are incomplete or inaccurate. One complete set of singles lines should be updated and corrected. The single lines attached to report are accurate to the panel bus level. These were used for the Arc Flash analysis but are incomplete at the branch circuit level.

Load Flow

The model results show a voltage drop greater than 5% in areas across the south side of the campus without the voltage support of transformer 1X28.

If any negative conditions as listed in the report are seen in the hospital, a more selective and detailed data collection will be required. In the short-term load shedding or tapping up supporting transformers may be temporarily necessary to help with voltage support. Bringing transformer 1X28 in service when available will also help bring up some of the voltage sag seen in the model.

Short Circuit / Protective Device Coordination

The protective device coordination was found to be mostly in order. Our recommendation would be to make the few adjustments shown in Device Coordination section. Secondly, a protection scheme has to be determined for the MSS busway networks and properly installed to protect the electrical floors distribution panels.

Arc Flash

The final evaluation of the Arc Flash model found that the majority of the buses and panels throughout the campus are in a low energy level arc flash risk. A renovation of the transformers, panelboards and main protective devices from the last study has shown improvement in many areas of the campus. A few exceptions are the MSS buses and busway system, MDS Bus and the 480 Chiller Bus. These systems should be upgraded with arc flash maintenance protection, upgraded with more modern equipment or not worked on live.

Code and Equipment Deficiencies

The panel deficiencies in section 4.0 should be addressed, these include unlabeled panels, open wireways and circuit openings, exposed busing, incorrect or missing backplates or panel faces and cluttered / inaccessible electrical spaces.

REP-21041-06-001 REV. 1

September 15, 2021

Encorus Project # 21041

6.0 REFERENCES

[1] National Fire Protection Association, NFPA 70E National Electric Code, Annex D.4, 2021.

[2] IEEE 1584 2018 Guide for performing Arc-Flash Hazard Calculatoins

Use IEEE style and the built-in IEEE style references generator to generate the reference section.

REP-21041-06-001 REV. 1

September 15, 2021

APPENDIX A ONE-LINE DIAGRAMS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

TITLE SHEET AND DRAWING INDEX 100% CONSTRUCTION

DOCUMENTS

UPDATE ARC FLASH AND

ELECTRICAL COORDINATION STUDY

FOR JJPVAMC

130 W KINGSBRIDGE RD

BRONX, NY 10468

2021-07-15

GI001

526-19-133A

DGA CJR

REV 0 ISSUED FOR CONSTRUCTION 2021-07-15

REV 1 VA COMMENTS 2021-09-15

DRAWING INDEX

DRAWING NUMBER DRAWING TITLE

GENERAL

GI001 TITLE SHEET AND DRAWING INDEX

ELECTRICAL

E-001 ELECTRICAL NOTES AND LEGENDS

E-601 SITE ELECTRICAL SINGLE LINE DIAGRAM

E-602 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100

E-603 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100

E-604 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100

E-605 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 106 AND FISHER HOUSE

E-606 ELECTRICAL SINGLE LINE DIAGRAM - 480 GEN 1 AND 3

E-607 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 101 AND 106

E-608 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 101

E-609 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100

E-610 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100

E-611 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 105

E-612 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100

E-613 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 105

E-614 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 105

E-615 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100

E-616 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 105

E-617 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 106

E-618 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 106

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text one quarter inch = one foot

AutoCAD SHX Text

BRONX VAMC

AutoCAD SHX Text UPDATED ARC FLASH AND ELECTRICAL COORDINATION STUDY FOR JJPVAMC 130 W KINGSBRIDGE RD BRONX, NY 10468

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

ELECTRICAL NOTES AND LEGENDS 100% CONSTRUCTION

DOCUMENTS

UPDATE ARC FLASH AND

ELECTRICAL COORDINATION STUDY

FOR JJPVAMC

130 W KINGSBRIDGE RD

BRONX, NY 10468

2021-07-15 E-001

526-19-133A

DGA CJR

REV 0 ISSUED FOR CONSTRUCTION 2021-07-15

REV 1 VA COMMENTS 2021-09-15

G

ELECTRICAL SYMBOLS - POWER PLAN

DUCT BANK

VFD

UNDERGROUND ELECTRICUE

GENERAL LINETYPES

EXISTING DUCT BANK

ABANDON DUCT BANK

DB

BUS DUCT

CABLE

BUS / SWITCHGEAR

CBL-XXXX CABLE NAME ( REFER TO SKM MODEL FOR DETAILS)

NAMING DESIGNATIONS FOR ELECTRICAL BUS/SWITCHGEAR

480, 3PH, 4W, 1200A, 100 kAIC

VOLTAGE

PHASE

SYSTEM AMPACITY

INTERRUPT RATING

VARIABLE FREQUENCY DRIVE

MEDIUM VOLTAGE DRAWOUT BREAKER

LOW-VOLTAGE DRAWOUT AIR CIRCUIT BREAKER

MOLDED CASE CIRCUIT BREAKER

FUSE WITH RATING

SWITCH, SINGLE BREAKER

FUSED SWITCH

CURRENT TRANSFORMER WITH RELAY DEVICE

GENERATOR, POWER

ATS - AUTOMATIC TRANSFER SWITCH

MTS - MANUAL TRANSFER SWITCH

EARTH GROUND

WYE CONNECTION

TRANSFORMER

RECTIFIER

MOTOR, SINGLE-PHASE

LOAD DEVICE RESISTIVE OR TRANSIENT

PANEL BOARD WITH PANEL BOARD NAME

XXXX

PAGE CONNECTOR

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text one quarter inch = one foot

UTIL-0001

TX 1x32 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75

LOAD BUS 1

CH3

T-LOAD BUS1

2500 kVA PRI 4.16 kV

SEC 480 V

Z% = 4.27

SYNC BUS 1-2

UTIL-0002

TX 1x21 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75

LOAD BUS 2

T-LOAD BUS 2

2500 kVA PRI 4.16 kV

SEC 480 V

Z% = 7.96

UTIL-0003

LOAD BUS 3

CH2

T-LOAD BUS 3-1 (MSS2-B)

2500 kVA PRI 4.16 kV

SEC 480 V

Z% = 7.84

BUS DUCT - 201B

UTIL-0004

LOAD BUS 4

T-LOAD BUS 4

2500 kVA PRI 4.16 kV

SEC 480 V

Z% = 7.88

BUS DUCT - 201A

SYNC BUS 3-4

T-LOAD BUS 3-2 (NH)

500 VA

PRI 4.16 kV

SEC 480 V

Z% = 4.80

PD-0001

PD-0002

PD-0003

PD-0005

PD-0004

PD-0007 PD-0006

PD-0011

PD-0008

PD-0010 PD-0012

PD-0009PD-0013 PD-0015 PD-0014

PD-0019 PD-0016 PD-0018

PD-0017

PD-0021

PD-0020

PD-1554 PD-1556

PD-1557 PD-1559

PD-1558

PD-1560

PD-1561

PD-1562

PD-10000

CLASS E

PD-10001PD-10002 PD-10003

PD-10004

PD-10005 PD-10006

PD-10007

PD-10008

PD-10009

PD-10010 PD-10011

PD-10012 PD-10013

PD-10014 PD-10015

PD-10016

BUS DUCT - 101A

PD-1613

PD-1614 PD-1615 PD-1616

PD-1617 PD-1618 PD-1619 PD-1620

TX CHILLER 3

2500 kVA PRI 4.16 kV

SEC 480 V

Z% = 5.60

CBL-006

G G1 4160V 3575 kVA

CBL-013_G1

CBL-010

600 HP

CBL-017

CBL-018

CBL-013

CBL-013_LB2

CBL-019

CBL-014

CBL-014_G2

CBL-011

CBL-021

CBL-014_LB4

CBL-023 CBL-022

CBL-012

CBL-020

TO DRAWING E-604

MSS1-B

TO DRAWING E-602

MSS1-A

TO DRAWING E-609

MSS2-B

TO BUILDING E-611

MSS2-A

TO DRAWING E-605

NURSING HOME

MDS

4160, 3PH, 3W, 1200A, 35 kAIC

BUS DUCT - 101B

TX 1x28 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75

TX 1x29 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75

4160, 3PH,3W,1200A,35 kAIC 4160, 3PH, 3W, 1200A, 35 kAIC 4160, 3PH, 3W, 1200A, 35 kAIC

G G2 4160V 3575 kVA

CHILLER SWGR

4160, 3PH, 3W, 1200A, 35 kAIC

4160, 3PH, 3W, 1200A, 35 kAIC

CHILLER 3

T-PPL-1

30 kVA

PRI 480 V

SEC 208 V

Z% = 3.4

CB TO PPL-1

LOAD-0786

CB TO PPH-1 CB TO DS-MT-1 CB TO

DS-ES-1

CB TO

CHILLER 3

LOAD-0787 LOAD-0788

PPH-1 DS-MT-1 DS-ES-1

CBL-1704 CBL-1708 CBL-1709 CBL-1710

CBL-1707

PD-1659

CBL-1711

CBL-1712

PPL-1

600 HP

480, 3PH, 4W, 4000A, 100 kAIC

TO DRAWING E-605

FISHER HOMES

CBL-1739

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

SITE ELECTRICAL SINGLE LINE

DIAGRAM

100% CONSTRUCTION

DOCUMENTS

UPDATE ARC FLASH AND

ELECTRICAL COORDINATION STUDY

FOR JJPVAMC

130 W KINGSBRIDGE RD

BRONX, NY 10468

2021-07-15 E-601

SITE

526-19-133A

DGA RJB

REV 0 ISSUED FOR CONSTRUCTION 2021-07-15

REV 1 VA COMMENTS 2021-09-15

GENERAL NOTES

1.

2.

KEYED NOTES

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

PD-APTSPD-ECL-CPD-NDSSPD-LDA

MCC 3

PD-0062

CB NP

MAIN

NP

PD-0066PD-0070PD-0029

PD-0079

CB L1DA

MAIN

PD-0080

CB TO P2DA

T-L2DA

75 kVA

PRI 480V

SEC 208V

Z% = 5.11

CB P2DA

SEC1

MAIN

P2DA SEC2

PD-0157

P2DA SEC1

CB TO P2DA1

P2DA1

LOAD-158

CB TO STARBUCKS

T-L1DA

30 kVA

PRI 480 V

SEC 208V

Z% = 5.41

STARBUCKS

LOAD-157

PD-0125

L2C SEC2

PD-0127

L4C

PD-0128

L5C

CB TO P4C

PD-0129

L6C

CB TO P5C

PD-0130

L7C

CB P4C

MAIN

P4C

PD-0131

L8C

CB P5C

SEC1

MAIN

P5C SEC1

P5C SEC2

PD-0132

L9C

CB TO P9C

P5C SEC3

LOAD-141

T-L9C 75 kVA

PRI 480 V

SEC 208 V

Z% = 4.27

CB P9C

SEC1

MAIN

P9C SEC1

P9C SEC2

P9C SEC3

LOAD-143

CB TO P2C LAB

CB P2C LAB

MAIN

P2C LAB

LOAD-147

LOAD-130

MTRI-128 CHP

PD-0104 PD-0102 PD-0103PD-0105 PD-0137

MTRI-HV-3 MTR CWP 8-11

PD-0058

PD-MCC3

MTR CWP 2-4,6MTR CWP 1,5 MTR CWP 7

FROM DRAWING E-601

LOAD BUS 2

NDSS

25 HP

CBL-111 CBL-109

CBL-182

CBL-187

CBL-183

CBL-188

CBL-185

CBL-190

CBL-201

CBL-202

CBL-753

CBL-674

CBL-673

CBL-273

CBL-671 CBL-272

CBL-670

CBL-283

CBL-271

CBL-277

CBL-267

CBL-275

CBL-270 CBL-258

CBL-266

CBL-269

CBL-224CBL-265

CBL-223

CBL-105

T-L5C 45 kVA

PRI 480 V

SEC 208 V

Z% = 4.27

T-L4C 45 kVA

PRI 480 V

SEC 208 V

Z% = 4.27

T-L2C SEC2

45 kVA

PRI 480 V

SEC 208 V

Z% = 4.27

480, 3PH,3W,3000A,100 kAIC

25 HP 75 HP 30 HP 75 HP

50 HP

MSS 1-A CONTINUED

TO DWG E-603

TO DRAWING E-606

N-ATS3

TO DRAWING E-606

N-ATS2

TO DRAWING E-606

N-ATS1

T-L6C 45 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

CB NL-6C-1

MAIN

NL-6C-1

CB NL-6C-2

MAIN

NL-6C-1

LOAD-0783

CB TO NL-6C

LOAD-0799

LOAD-0798

CB P4C

SEC1

MAIN

P4C SEC1

P4C SEC2

LOAD-140

CBL-1727

CBL-1728

CBL-1698

CBL-1697

BUS DUCT - 186

BUS DUCT - 111

CB MSS1-A

MAIN

BUS DUCT - 128

BUS DUCT - 136

BUS DUCT - 264

BUS DUCT - 268

BUS DUCT - 274

BUS DUCT - 276

BUS DUCT - 282

BUS DUCT - 669

BUS DUCT - 142

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

ELECTRICAL SINGLE LINE DIAGRAM

- BUILDING 100

100% CONSTRUCTION

DOCUMENTS

UPDATE ARC FLASH AND

ELECTRICAL COORDINATION STUDY

FOR JJPVAMC

130 W KINGSBRIDGE RD

BRONX, NY 10468

2021-07-15 E-602

BLDG 100

526-19-133A

DGA RJB

REV 0 ISSUED FOR CONSTRUCTION 2021-07-15

REV 1 VA COMMENTS 2021-09-15

GENERAL NOTES

1.

2.

KEYED NOTES

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

PD-B16

PD-ECL-F

PD-MCC2 PD-MRI

PD-0064

PD-0073

PD-0068

PD-0027

MCC 2

PD-0033

DB-LCT-TO BLDG 16

225 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

CB NP1

MAIN

NP1

CB TO BCB TO APT 109 CB TO APT 108CB TO APT 209 CB TO APT208CB TO APT 308 CB TO APT 309

CB B

MAIN

B

APT 109 APT 108APT 209 APT 208APT 308 APT 309

CB P16-2

MAIN

P16-2

LOAD-131 LOAD-136 LOAD-135 LOAD-133

LOAD-138

LOAD-132 LOAD-134 LOAD-137

PD-0075

LGF SEC1

PD-0082

L1F SEC1 LGF SEC2

PD-0083

L2F

CB TO P2F

SEC1

T-L2F 75 kVA

PRI 480 V

SEC 208 V

Z% = 5.41

CB P2F

SEC1

MAIN

P2F SEC1

P2F SEC2

P2F SEC3

LOAD-154

CB TO P1F

L1F SEC2

T-L1F SEC1

75 kVA

PRI 480 V

SEC 208 V

Z% = 5.41

CB P1F

SEC1

MAIN

P1F SEC1

P1F SEC2

P1F SEC3

LOAD-152

LOAD-151

CB TO PGF

T-LGF SEC2

45 kVA

PRI 480 V

SEC 208 V

Z% = 5.41

CB PGF

SEC1

MAIN

PGF SEC1

PGF SEC2

PGF SEC3

LOAD-153

PD-0090PD-0091

MTRI-110 CHPCB TO DP-CH CB TO CT

DP-CH CT

MTRI-211MTRI-212

LOAD-156 LOAD-155

PD-0712PD-0713

MP1

PD-0714

LP1

LOAD-159PD-0715

ML1

LOAD-160

25 HP

CBL-106

CBL-117

CBL-131

CBL-131-9

CBL-131-7 CBL-131-6 CBL-131-3 CBL-131-4 CBL-131-2 CBL-131-5 CBL-131-8

CBL-108

CBL-110 CBL-112CBL-181

CBL-177

CBL-0586

CBL-293

CBL-294

CBL-295

CBL-296

CBL-298

CBL-297

CBL-292 CBL-189

CBL-291 CBL-184

CBL-290 CBL-180

CBL-178CBL-289

CBL-177B0

CBL-288 CBL-177B

CBL-212 CBL-211

CBL-0931 CBL-134 CBL-125

CBL-145

CBL-139

CBL-150

T-DP-LC

45 kVA

PRI 480 V

SEC 208 V

Z% = 5.00

T-MP1

15 kVA

PRI 480 V

SEC 208 V

Z% = 5.00

1 1

50 HP

30 HP

TO DRAWING E-604

MSS 1-B

480, 3PH, 3W, 3000A, 100 kAIC MSS 1-ACONTINUED

FROM DWG E-602

TIE BREAKER

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

ELECTRICAL SINGLE LINE DIAGRAM

- BUILDING 100

100% CONSTRUCTION

DOCUMENTS

UPDATE ARC FLASH AND

ELECTRICAL COORDINATION STUDY

FOR JJPVAMC

130 W KINGSBRIDGE RD

BRONX, NY 10468

2021-07-15 E-603

BLDG 100

526-19-133A

DGA RJB

REV 0 ISSUED FOR CONSTRUCTION 2021-07-15

REV 1 VA COMMENTS 2021-09-15

GENERAL NOTES

1.

2.

KEYED NOTES

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

NURSING QUARTERS

MSS1-B

PD-SPARE 1PD-MCC3A PD-MCC2APD-ELS1 PD-SPARE 2PD-ECL-D PD-SPARE3PD-SPARE 4 PD-NQ DPPD-LFP PD-ELS4

PD-0034PD-0036

MCC 3A

PD-0037

MCC 2A

PD-0040

ELS1

PD-0042PD-0043 PD-0046PD-0049 PD-0051PD-0054

PD-1432

PD-0055

ELS4

PD-0097

T-TO EP1

10.0 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

EP1

LOAD-0373

PD-0098

LGD SEC1 PD-0185

L1D

PD-0186

L3D

PD-0187

EN

ATS L1D

CB TO P3D

CB P3D

SEC1

MAIN

P3D SEC1

P3D SEC2

CB TO P4D

P3D SEC3

P4D

LOAD-0370

CB P3D1

MAIN

P3D1

LOAD-0371

CB TO L1D ATS

KLGE-2

CB TO LAS ATSCB TO L1E ATS CB TO LES ATS CB TO KGLE-2 SUB

ATS-LAS EATS-L1E E ATS-LES E

PD-0026

GEN LIFE SPRT

KLGE-2 SUB

T-L1D 45 kVA

PRI 480 V

SEC 208 V

Z% = 5.04

CB P1D SEC1

MAIN

P1D SEC1

P1D SEC2

LOAD-0372

MTRI-114 CHPPD-0094 MTRI-FP CHP

MTRI-CWP

EN

AUTO-0024

E-FIREPUMP

PD-0095MTRI-115 CHP PD-0096

MTRI-0018 MTRI-BOILER

PD-0099

TUN WESTINGHOUSE

T-TO NQ DIST PANEL P

CB TO T.T.

T-TO NQ DIST PANEL

150 kVA

PRI 480 V

SEC 208 V

Z% = 4.7

LOAD-0368

PD-0475

NQ DIST PANEL

CB TO NQ SQDCB TO NQ LPGS CB TO CHAPELCB TO NQ LPGN CB TO

NQ LPG

NQ SQDNQ LPGS CHAPELNQ LPGN NQ LPG

LOAD-0303 LOAD-0307LOAD-0305 LOAD-0304 LOAD-0306

T-TO T.T.

15 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

CB T.T.

MAIN

T.T.

LOAD-0367

ECPB

LOAD-0369

LGD SEC2

CB TO PGD

SEC1

PD-0724

T-LGD SEC2-2

75 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

CB PO

SEC1

MAIN

PO SEC1

PO SEC2

LOAD-0366

CB PGD

SEC1

MAIN

PGD SEC1

PGD SEC2

PGD SEC3

LOAD-0365

FIRE PUMP

MTRI-FIRE PUMP

FROM DRAWING E-601

LOAD BUS 1

FROM DRAWING E-603

MSS1-A

CBL-116 CBL-122 CBL-912 CBL-123

CBL-147

CBL-911

CBL-775

CBL-913

CBL-778

CBL-474

CBL-779CBL-781CBL-783ACBL-780 CBL-782

CBL-0572

CBL-143

CBL-0666CBL-311ECBL-304ECBL-234ECBL-462E

CBL-508

CBL-236

CBL-532

CBL-533

CBL-511

CBL-098CBL-509

CBL-241

CBL-256

CBL-255CBL-257

CBL-246CBL-254

CBL-239 CBL-149CBL-234CBL-252 CBL-240

CBL-238

CBL-235

CBL-233

CBL-231

CBL-148

300 HP

TO DRAWING

606 BUS EDSS

G

GEN-LIFE SPRT

TO DRAWING E-611

ATS-LAS

T-LGD SEC2-1

112.5 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

T-L3D 75 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

480, 3PH,3W,3000A,100 kAIC

2 2 2

50 HP 50 HP

30 HP200 HP25 HP

50 HP

BUS DUCT - 237

BUS DUCT - 232

BUS DUCT - 118 BUS DUCT - 114 BUS DUCT - 115

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

ELECTRICAL SINGLE LINE DIAGRAM

- BUILDING 100

100% CONSTRUCTION

DOCUMENTS

UPDATE ARC FLASH AND

ELECTRICAL COORDINATION STUDY

FOR JJPVAMC

130 W KINGSBRIDGE RD

BRONX, NY 10468

2021-07-15 E-604

BLDG 100

526-19-133A

DGA RJB

REV 0 ISSUED FOR CONSTRUCTION 2021-07-15

REV 1 VA COMMENTS 2021-09-15

GENERAL NOTES

1.

2.

KEYED NOTES

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

E N

NH EEATS

CB TO NH EEATS

MDS

CB TO PPTP CB TO NH L1ACB TO NH L2A CB TO NH L1BCB TO NH L2B CB TO MCC LTAPD-0442 CB TO L-COR1PD-0444

CB MDS

MAIN

PPTP NH L1ANH L2A NH L1BNH L2B MCC LTA

LOAD-0495

CB TO T-TO SIEMENS

T-TO SIEMENS P

PD-0242

T-TO SIEMENS S

CB EM2

MAIN

EM2

LOAD-0486

CB P2C3

MAIN

P2C3

CB P2C1

MAIN

P2C1

CB CC2A SIEMENS

MAIN

CC2A SIEMENS

CB P2C2

MAIN

P2C2

P2C2-1 P2C1-1 P2C3-1

LOAD-0487

LOAD-0488 LOAD-0489 LOAD-0490

CB TO RPT

PD-0465

RPT

PD-0466CB TO RPT1 MTR-CHP

HLPRPT1

CB SQD

MAIN

SQD

LOAD-0493

LOAD-0492

LOAD-0491

CB TO P1B-A

CB P1B-A MAIN

P1B-A

LOAD-0494

CB TO PTA

MTR-708 CHP

PTA

LOAD-0496

E N

ATS GEN

PD-0456

NH GEN

EEDP

CB TO EEQCB TO EEGH CB TO EELPCB TO ELEV P1 CB TO ELEV P2CB TO ELEV P3 CB TO EEP1B-BA

EEGH EEP1B-BA

LOAD-0498

ELEV P1

ELEV P2

ELEV P3

LOAD-0500

EEQ EELP

LOAD-0497 LOAD-0499

FROM DRAWING E-601

LOAD BUS 3

CBL-707 CBL-705 CBL-702 CBL-711A CBL-704 CBL-706 CBL-708

CBL-715

CBL-730

CBL-784

CBL-744 CBL-738 CBL-732 CBL-742

CBL-746 CBL-740 CBL-736

CBL-720

CBL-719 CBL-718

CBL-717

CBL-729

CBL-735

CBL-727 CBL-733

50 HP

CBL-711B CBL-711A0

CBL-711C

CBL-750 CBL-748 CBL-743 CBL-739 CBL-747 CBL-749 CBL-776

CBL-0923 CBL-0924

G

GEN NURSE

TO DRAWING E-606

EDSS

T-TO SIEMENS

112.5 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

480, 3PH,3W,1200A,100 kAIC

T-PPTP

112.5 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

T-NH L1B

75 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

T-MCC LTA

15 kVA

PRI 480 V

SEC 208 V

Z% = 5.0

T-TO EELP

15 kVA

PRI 480 V

SEC 208 V

Z% = 6.0

T-TO EEQ

30 kVA

PRI 480 V

SEC 208 V

Z% = 6.0

1 1

1 1

50 HP

50 HP

31 HP

50 HP

CB TO LP1 #1

LP1 #1

CBL-1750

LOAD-0803

DP-H #1

CB TO LP2 #1

LP2 #1

CBL-1752

LOAD-0804

CB TO LPH #1

LPH #1

CBL-1746

LOAD-0805

CB TO

ELEVATORS #1

CBL-1748

ELEV FH #1

PD-1728

CBL-1740

CBL-1742

PD-1715

CB DP-H #1

MAIN

PD-1714

CBL-1739

TX-FISHER HOUSES

300 kVA PRI 4.16 kV

SEC 208 V

Z% = 6.0

PD-1716

CBL-1741

CBL-1743

CB DP-H 2

MAIN

CB TO LP1 #2

LP1 #2

CBL-1751

LOAD-0806

DP-H #2

CB TO LP2 #2

LP2 #2

CBL-1753

LOAD-0807

CB TO LPH #2

LPH #2

CBL-1747

LOAD-0808

CB TO

ELEVATORS #2

CBL-1749

ELEV FH #2

PD-1729

FROM…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .