Arc-Flash_Report_-_-SEPT-15-2021.pdf
PDF 9 MB Posted
- Attached to
- J061--526-23-110 Electrical Switchgear Replacement Phase 1 Federal contract opportunity
- Solicitation number
- 36C24224B0031
About this file
This document is an Arc-Flash Study for the James J. Peters VA Medical Center in Bronx, NY. The study evaluates the electrical system at the facility, including a review of the single line model, load flow, short circuit analysis, protective device coordination, and arc flash incident energy calculations. Key findings include:
The facility is served by four independent 5kV feeds from ConEdison, with two 3575 kVA diesel generators providing backup power. The 480V system consists of two main secondary switchgear networks that feed the majority of the loads. The study identified some voltage drop issues, protective device coordination challenges, and high arc flash incident energy levels in certain areas that need to be addressed. Several code and safety violations were also noted related to missing panels, exposed live parts, and inadequate working clearances. The report provides recommendations to upgrade equipment, improve coordination, and resolve safety issues throughout the electrical system.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
23 Mechanic Street Springville, NY 14141
2745 Broadway Buffalo, NY 14227 encorus.com 716.592.3980
Arc-Flash Study
J. J. Peters VAMC Arc-Flash Evaluation
Prepared For:
J. J. Peters VAMC
Order# 36C24221C0085
Engineer of Record
“Unauthorized alteration or additions to any plans, specifications or reports bearing a Licensed Professional
Engineer’s seal is a violation of Section 7209, subdivision 2, of the New York State Education Law”.
September 15, 2021
REP-21041-06-001 REV. 1
REV 1 – Edits from the VA review
Encorus Project # 21041
9/14/2021
Arc-Flash Study J. J. Peters VAMC Arc-Flash Evaluation
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
TABLE OF CONTENTS
1.0 EXECUTIVE SUMMARY
2.0 METHODOLOGY
3.0 RESULTS
4.0 DEFICIENCIES
4.1.1 NEC 110.26 Required Clearance Space
4.1.2 NEC 490.48(B) Single Line Drawings and Protection Schemes
4.1.3 NEC 408.7 Unused Openings
5.0 REFERENCES
APPENDIX A ONE-LINE DIAGRAMS
APPENDIX B LOAD FLOW STUDY
APPENDIX C SHORT CIRCUIT STUDY
APPENDIX D TIME-CURRENT COORDINATION
APPENDIX E ARC-FLASH INPUT/OUTPUT MATRIX
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
1.0 EXECUTIVE SUMMARY
The following report is to update the engineering model of the electrical system at the James J.
Peters VAMC in Bronx NY. The previous report was written by Schweitzer Engineering Laboratories’ Government Engineering Solutions department (SEL GES) in 2015. The model that was updated in 2015 was the basis of this evaluation. This report will re-evaluate the Single Line Model of the campus along with calculate and report on the Load Flow and Generation Capacity, Short Circuit, System Coordination and finally Arc Flash Analyses.
Along with a technical analysis this report will review the installed equipment for code, system integrity, and “health” of the installed system.
The final goal of this report is to review the as found condition of the equipment during the visual inspection portion of the project. During this visual inspection the system was photographed and reviewed for code compliance, in installation, upkeep and system integrity. The deficiencies from the previous SEL report in 2015 was also reviewed to see if they have been completed or not.
DESCRIPTION OF THE ELECTRICAL SYSTEM
5kV System
The site is served at four independent locations by Consolidated Edison, Inc. (ConEdison). The first two points of service supplies transformers 1X-32 and 1X-21. Each feed consists of one 3000kVA, 13.2kV // 4160V transformer supplying power to a 5kV bus.
The third and fourth points supplies transformers 1X-28 and 1X-29. Each of these feeds also consist of one 3000kVA, 13.2kV // 4160V transformer supplying power to a 5kV bus.
The four 5kV buses are backed up by a pair 3575kVA, 4160V Diesel Generators. Each generator has its own synchronized bus and ties all four 5kV supply busses together via a coordinated breaker system. This system allows any of the four 5kV buses to be fed loads individually or tied through the generator’s sync bus. The generators are also synchronized to back up the system independently or run along with the utility for support.
480V System
The “Main Secondary Switchgear” (MSS) Networks feed the majority of the 480V loads across the site via a bus duct network within the main hospital and research building.
Each of the four above mentioned 5kV buses supplies power to five 2500kVA, 480VAC transformers one 500kVA and one 300kVA transformer. The 2500kVA transformers feed 480VAC buses that are broken into two MSS networks on the north and south ends of the campus and one 480V switchgear dedicated to CHILLER 3.
The MSS are two double ended 480V switchgear that feed the bulk of the 480V load on the site.
The third “network” is a single ended feed to a dedicated switchgear for the 480VAC Chiller in the powerhouse.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
The 5kV feed to the 500kVA transformer is for the “MDS” switchgear in the Community Living Center (CLC). The MDS feeds the CLC, chapel and pool.
The final 5kV feed is tied to the primary side of the MDS switchgear and feeds a 300kVA transformer for the Fisher housing areas.
Emergency Systems
The emergency system is broken between Equipment, Critical and Life Safety system per the NEC 700 requirements.
NDP – Normal Distribution Panel EED - Emergency Equipment Distribution CPD- Critical Power Distribution LSD- Life Safety Distribution
Each of the MSS Networks have their own NDP (Normal Distribution Panel). These panels feed the normal power side of Automatic Transfer Switches to LSPD (Life Safety Distribution Panel), CPDP (Critical Power Distribution Panel), EEDP (Emergency Equipment Distribution Panel).
The emergency side of the transfer switches are feed from five generators connected to two generator buses. Network #1’s generator bus (South side) has generators G1, G3 and Network #2’s bus (North side) has G2, G4 and G5. The two generator buses are connected with tie breakers.
Refer to the Single Line drawings in Appendix <A> for details.
2.0 METHODOLOGY
The update to the electrical system started with a review of the existing drawing and SKM models and previous SEL study. These documents were reviewed and set against the most up to date drawings to identify areas upgraded from the last study.
A site investigation was then conducted to photograph, update the drawings and document the changes to the site. The photos can be found in the BIM site connected with this project. The changes have also been outlined and shown on the Single Line drawings see appendix <A>.
The updates to the site have been entered into the latest edition of SKM ver. 9.0.1.1 And a new version of the Single Line Diagrams has been developed and added to this report.
3.0 RESULTS
See attached appendices for one-line diagrams, Load Studies, Short Circuit Studies and an arc-flash input/output matrix. The following results show where areas of deficiency are in the current system as it was found in our investigation.
These areas will be reviewed and catalogued for engineering support and potential upgrades depending on the results shown below.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Load Study
The voltage drop analysis evaluates the level of voltage drop at each point in the system as compared to that allowed by the 2020 National Electrical Code (NEC).
See Appendix (B)
- Example Load Flow Summary
The Load Flow Calculator will show each bus in the model as in or out of service and compare the buses rated design voltage against the calculated loaded voltage. From this calculation is determined the % Voltage Drop at each bus. This is displayed in both %VD and PU (per unit) value.
Design Settings
The load study is based on a global demand load for each voltage level (i.e., 13.2kV, 4.16kV, 0.48kV, and 0.28kV). For this study the global demand was set at 100% for the 13.2kV level, 20% for the 4.16kV level, 20% for the 0.48kV level, and 25% for the 0.28kV level.
Currently, ConEdison is replacing transformer 1X28, which has caused an increase in the voltage drop throughout the system. To show this, we provided a load study with the 1X-28 transformer in
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041 and out of service. Note: When placing transformer 1X28 back in service we estimated the transformer’s impedance from the other existing transformers.
Results and Worst-Case Load Scenarios
• Results with 1X28 out of Service
This is the current running condition and also the worst-case utility scenario. The results shown in Appendix (B) show significant voltage drop (greater than 5%) in areas across the south side of the campus without the voltage support of transformer 1X28.
The NEC recommends that the maximum combined voltage drop for both the feeder and branch circuit shouldn't exceed 5%. Excessive voltage drop in a circuit can cause lights to flicker or burn dimly, heaters to heat poorly, and motors to run hotter than normal and burn out. This is because the load has to work harder with less voltage pushing the current.
Our recommendation would be to bring transformer 1X28 in service when available. Until this is available, if any of the above conditions are seen in the hospital, shedding some of the load or tapping up supporting transformers may be temporarily necessary.
Results with 1X28 in Service
Note: A Common impedance has been estimated for 1X28 to generate these results. This load shows the “normal” running conditions once 1X28 is back in service. The summary of these results is included in Appendix (B).
With transformer 1X28 back in service the model shows the high voltage drop shown on the south side of the campus lowers below 5% in most cases. In the Research Building,105, the model stills shows a higher than desirable voltage drop. This may be due to over-estimation in the modeling but if the above negative conditions are still in the hospital areas the loads and voltages should be measured and monitored so corrective actions can be made.
• Results on 4160 Generation Only – A bus summary has been added to show the voltage drop when the Utility is out of service and the 4160V Generation backs up the hospital. As expected, voltage sag is very high in this temporary condition, however no bus’s fault in this scenario which shows the current emergency generation is sufficient for the current load.
Short Circuit Analysis
The short circuit analysis evaluates the adequacy of the electrical system equipment to withstand or to interrupt the calculated maximum available short circuit current at its location.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
See Appendix (C)
- Example Short Circuit Study
The short circuit report summarizes the maximum available fault duties, using SKM PTW Comprehensive Short Circuit Study setup, when the system is being supplied by the utility.
The types of unsymmetrical faults occurred due to the short circuit conditions, namely single phase or line to ground (SLG) fault, phase to phase (LL) fault and double line to ground (LLG) fault.
A single line-to-ground (LG) fault is one of the most common faults and experiences show that 70-80 percent of the faults that occur in power system are of this type.
A line-to-line fault occur when a live conductor comes in contact with another live conductor.
In double line to ground faults, two lines come into the contact with each other as well as with ground.
A Symmetrical or balanced three phase fault is where all three phase are faulted together. This is the most severe but also the least likely, happening in about 2% of total system faults.
Because of its severity, symmetrical three phase fault analysis is necessary for determining the size of a circuit breaker for largest short circuit current.
The results found in Appendix C are broken up by bus, contributing branch circuits and available Symmetrical and Asymmetrical fault categories as described above.
Fault Scenarios
• 1X28 out of Service
A summary of this scenario has been included as the current case in the current service of the campus.
REP-21041-06-001 REV. 1
September 15, 2021
• 1X28 in Service and Normal Utility in Service
A summary of this scenario has been included as the “normal” case once the 1X28 Transformer is back in service.
Note: A Common impedance has been estimated for 1X28 to generate these results. This summary was added to show the fault contributions when normal operating conditions are returned.
Short Circuit Results and Equipment Ratings
The results of the short circuit analysis are used to feed the available energy for the Arc Flash study.
The second purpose of these results are to compare the available fault current to the protection devices interrupting rating. This will determine a devices ability to withstand a short circuit or overload energy. This is shown in SKM as the device’s equipment rating.
Equipment Ratings
This appendix is a list of the buses including Switchgear, Motor Control Centers, Distribution, panel boards and main protective devices. The purpose is to compare the buses and protective devices rated voltage, ampacity and interrupt rating versus the calculated load and available fault current. If the available fault current is larger than the buses’ fault interrupt rating it is flagged as deficient and our recommendations for upgrade or replacement.
The equipment study shows all the equipment ratings meet or exceed the short circuit fault rating.
The equipment that was failed from the 2015 study has been replaced and the new equipment meets the short circuit requirements.
REP-21041-06-001 REV. 1
September 15, 2021
Protective Device Coordination
The protective device coordination study determines the suggested settings and ampere ratings for all electrical power system protective devices in order to achieve the desired system protection and electrical service continuity goals.
Included in this section are coordination curves for the major buses within the hospital electrical network. The complete TCC results of the Coordination study can be seen in Appendix D. Listed below are TCC examples where miscoordinations were found and suggestions to improve the system coordination.
• TCC NAME – EDSN / GEN4 / ATS 6 (North side Generator Bus)
The Generator and EDSN mis-coordinate. The large clear time of the molded case Siemens breaker overlaps the generator bus breaker. The generator breaker can be slightly adjusted to improve this overlap of these breakers (see the charts below)
Current Settings Proposed Settings
LTPU: 1 – 12 LTPU: 1 – 12
STPU: 6 STPU: 6
STD: 0.1 STD: 0.4
INST: 15 INST: 15
REP-21041-06-001 REV. 1
September 15, 2021
The Arc Flash Incident Energy at bus EDSN is unaffected by this change.
• TCC NAME – EEDP(Normal) (Nursing Home MDS Gear Room)
The Normal side of the NHEATS mis-coordinates with the main in MDS. Again, a delay to MDS long time delay would improve this coordination.
Current Settings Proposed Settings
LTPU: .8 LTPU: 1
LTD: 4 LTD:15
STPU: 5 STPU: 5
STD: .1 STD: 0.1
INST: M1 INST: M1
REP-21041-06-001 REV. 1
September 15, 2021
The Arc Flash Incident Energy at bus MDS is unaffected by this change.
• TCC NAME –In places on the Main Distribution Buses MSS-1 and MSS- 2 fused disconnects are the installed in place of Main Panel Breaker. The fuses typically either mis-coordinate with the main breaker or are set so high they are oversized for the application. In the examples below The two breakers are in much better coordination.
As these serve the same branch feeder they do not need to be replaced we are pointing out
- The different applications within the same system
- That if the fuse opens up the downtime is typically longer as the fuses need to be replaced
- The coordination of the breakers is much better and easier to maintain.
Our recommendation is that the switch over gets completed throughout MSS-1 and 2 as the breakers are easier to coordinate and will lead to fewer nuisance outages.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
• TCC NAME – NQ Dist Pnl (The feeder to the Chapel Building)
The breaker is very limiting to the full load ampacity of the transformer feeding it. This may have been done intentionally due to the reduced loading in the area. No action is required we are pointing out a possible nuisance point if the load in the area is ever increased.
• TCC NAME – EDSS / EDSN (The 480VAC Generator Buses)
The TCC Curves shown in this report were from the existing data and could not be verified during our initial inspections because the generators could not be run.
The TCC settings show proper coordination and should be field verified to ensure these settings are still accurate when possible.
• MSS 1 and MSS 2 Bus System
The main feeders for building 100 are feed from federal pacific busways out of MSS1 and MSS2.
These busways go from the ground floor all the way to the top of the hospital and are tapped at each floor in the designated electrical rooms for their floor. These taps are typical made with 400 or 800A fused disconnects which then feed main distribution panels in the electrical rooms. These main distribution panels are sometimes MLO (Main Lug Only) which means there is no main circuit breaker in the panels and these panels rely on fuses in the disconnect to protect the panels. In some cases, these fuses do not exist or do not coordinate with the panels or the busway circuit breakers in MSS1 and MSS2. This is a code violation and dangerous condition where a fault in these panels would build until the circuit breaker in the MSS would have to open the busway to interrupt the fault.
When the distribution panel includes a main circuit breaker, the coordination is significantly improved.
REP-21041-06-001 REV. 1
September 15, 2021
Showing MLO panel LGD SEC1 protected by fused disconnect overlapping main MSS feeder breaker.
Showing Breaker to Breaker coordination from MSS1-A to L1DA
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
To properly protect these panels our recommendation would be to add a main circuit breaker in the MLO distribution panels and coordinate them with the MSS breaker feeding the busway as shown in the chart above.
Alternatively, properly sized and coordinated fuses could be added to the fused disconnect switches to accomplish this protection scheme. However, as seen in the chart above the Main Circuit Breaker and the fuse are trying to protect the same panel at the same current and coordinating the two protection devices will be difficult or impossible.
Protective Device Coordination Results
With only the few exceptions found above the protective device coordination was found to be in order. Our recommendation would be to make the few adjustments shown above. Secondly, a single protection scheme has to be determined for the MSS busway networks and properly installed to protect the electrical floors distribution panels. Our suggestion would be to coordinate the Mains on the distribution panels with the MSS busway feeder breakers consistently throughout.
REP-21041-06-001 REV. 1
September 15, 2021
Arc Flash Analysis
Flash Evaluation is a program that calculates the incident energy and arc flash boundary for each location of the power system. The study automatically reads the short circuit duties at each bus and through each protective device. The arcing fault current through the protective devices is then calculated from the bolted fault value and used to automatically find the time duration of the arc from the time current coordination (TCC) curves. Incident energy and arc flash boundaries are calculated based on the bus 3 phase fault current and arcing duration. Clothing requirements are specified from a user defined personal protective equipment table.
Example Arc Flash Incident Energy Chart - Appendix (E)
Hazard-Risk Tables
The following table is the Hazard-Risk Table from the SKM Power Tools Arc Flash Module.
The Personal Protective Equipment (PPE) Table and is taken from NFPA 70E Informative Annex H.
The Risk-Hazard table is divided based on a range of incident energy (IE), measured in calories/cm^2 (cal/cm^2), representing the available arc flash heat energy. The threshold value of incident energy that can cause 2nd degree burns to the uncovered skin is 1.2 cal/cm^2 (citation needed, read from https://electrical-engineering-portal.com/what-is-incident-energy-caused-by-arc-flash).
The required level of PPE per incident energy level is shown below and ranges from levels 0, 3, 4, and Dangerous.
PPE level 0 corresponds to the range 0.0 to 1.2 cal/cm^2.
PPE level 3 corresponds to the range 1.2 to 12 cal/cm^2.
PPE level 4 corresponds to the range 12.0 to 40.0 cal/cm^2.
PPE level Dangerous corresponds to anything above 40.0 cal/cm^2.
REP-21041-06-001 REV. 1
September 15, 2021
Incident Energy From
(cal/cm^2)
Incident
Energy To
IE Low
Marginal (cal/cm^2
IE High
Marginal (cal/cm^2
PPE Level
PPE Level
Clothing Layers
Required Minimum Arc
Rating of
PPE
Note s
0.0
1.
0.000
1.190
Nonmelting or Untreated Fiber
N/ A
H.3
1.2
12.0
1.210
11.800
Arc-Rated Shirt & Pants + Arc-rated Coverall
+ Arc-Rated Arc Flash Suit
2 or 3
12.
40.0
12.200
38.000
Arc-Rated Shirt & Pants + Arc-Rated Coverall
+ Arc-Rated Arc Flash Suit
3 or more
40.
999.0
41.000
998.000
Dangerous!
Level
Backgroun d Color
Level
Foregroun d Color
Warning Label Text
Head & Eye & Hearing Protection
Hand & Arm Protection
Foot
Protection
PPE Others 1
WARNING
Safety Glasses or Goggles + Ear Canal Inserts
Leather Gloves
N/A
Safety glasses
Hardhat + Safety Glasses or Goggles + Ear Canal Inserts + Leather
Work Shoes
Arc-rated Gloves
Leather work shoes
Safety glasses, electrically rated hard hat with hood and face shield.
Hearing protection.
Hardhat + Arc-Rated Arc Flash Suit Hood + Safety Glasses or Goggles + Ear Canal Inserts +
Leather Work Shoes
Arc-rated Gloves
Leather work shoes
Safety glasses, electrically rated hard hat with hood and face shield.
Hearing protection.
DANGER
REP-21041-06-001 REV. 1
September 15, 2021
PPE Others 2
PPE Others 3
PPE Others 4
PPE Others
PPE Pictures 1
PPE Pictures 2
PPE Pictures 3
Non-melting or untreated natural fiber (cotton/wool/rayon/silk
4.5 oz/sq yd), shirt
(long-sleeve), pants (long).
> 50V voltage rated tools +
Class 0 (minimum) gloves
Dielectric shoes or insulating mat (step and touch potential).
..\bin\resource\Cat egory0.bmp
..\bin\Resource\P
P
E_Category_0.b m p
25 cal/sq cm, Arc-rated shirt (long-sleeve) plus Arc-rated pants (long) plus Arc-rated coverall, plus arc rated arc flash suit jacket, pants, & hood, Arc-rated rainwear as needed.
Class 0 (minimum) gloves and leather protectors
(flash).
Leather shoes
(flash) as needed.
Dielectric shoes or insulating mat (step and touch potential).
..\bin\resource\Cat egory3.bmp
..\bin\Resource\P
P
E_Category_3.b
40 cal/sq cm, Arc-rated shirt (long-sleeve) plus Arc-rated pants (long) plus Arc-rated coverall, plus arc rated arc flash suit jacket, pants, & hood, Arc-rated rainwear as needed.
Class 0 (minimum) gloves and leather protectors
(flash).
Leather shoes
(flash) as needed.
Dielectric shoes or insulating mat (step and touch potential).
..\bin\resource\Cat egory4.bmp
..\bin\Resource\P
P
E_Category_4.b
..\bin\resource\Cat egory4.bmp
..\bin\Resource\P
P
E_Category_Dan g er.bmp
Adjustments to Incident Energies - Arc Flash Analysis
Buses EDSS and EDSN have different Arc Flash incident energies depending on the number of generators running in the scenario when they fault. The Arc Flash incident energies are shown in Appendix E.
The highest incident energy levels are when all the generators and utility are running paralleled and in this case the bus cannot be worked on live. The Arc Flash labels will reflect this condition.
Network buses MSS-1 and MSS-2 have very large incident energy levels and these also cannot be worked on live. Reducing the incident energy levels of these buses is difficult due to the equipment currently installed. The currently installed breakers do not have the adjustment ranges or maintenance modes of more modern equipment. Additional equipment could be installed around MSS1 and 2 to reduce the incident energy levels but this is would require an upgrade to the Network Buses.
Alternatively, MSS 1 and 2 buses are near the end of their effective service life and cost-benefit of replacing these items with more modern arc flash equipment compared to trying to extend their life by adding equipment around them should be looked at.
The MDS bus has a high incident energy level and is near the maximum allowable limit for live work.
If it is desirable to perform live work on the MDS bus arc flash reduction breakers with maintenance mode settings or changing the primary fusing on the incoming bus would be recommended.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
4.0 DEFICIENCIES
The purpose of this section is to review areas where repeated installation, safety or code violations were found. A list of the common violations along with photos and recommendations is included below. All building, floor/room locations are listed in the tables below. An exhaustive list of all the inspection photographs have been uploaded to BIM360 for your review.
4.1.1 NEC 110.26 Required Clearance Space
The required working area around electrical equipment is defined by the NEC. Many Panels, motors, pull boxes did not have the proper required working space around them.
4.1.2 NEC 490.48(B) Single Line Drawings and Protection Schemes
A working set of up-to-date drawings are required by the NEC. Diagrams shall clearly identify interlocks, isolation means, and all possible sources of voltage to the installation under normal or emergency conditions, and the marking on the switchgear shall cross-reference the diagrams. In many cases throughout the campus these diagrams either do not exist or are obsolete or inaccurate.
4.1.3 NEC 408.7 Unused Openings
Unused openings for circuit breakers and switches shall be closed using identified closures, or other approved means that provide protection substantially equivalent to the wall of the enclosure.
REP-21041-06-001 REV. 1
September 15, 2021
Panel Deficiency Building 100 Ground Floor
PGA SEC4: open breaker slots, back panel is incorrect size.
LGD SEC1: Panel cover not installed correctly, no back panel exposed live wiring.
LGD SEC 2 Panel cover not installed correctly, no sched.
Panel Deficiency Building 100 Ground Floor / GD and Kitchen
GD-213 Open Wireway / exposed live wiring.
KPGEA and KPGEA – N, No Schedule
SPSA – Panel cover is the incorrect size, live wiring is exposed
REP-21041-06-001 REV. 1
September 15, 2021
Panel Deficiency Building 100 – Ground & 1st Floor
Fire Pump Area (outside Network 1 Rm) Open wireway
L1C SEC 1 - Exposed Breaker Slots
L1C SEC 2 - Exposed Breaker Slots
Panel Deficiency Building 100 - 1st Floor
P1D Sec 1 – Missing back panel, Exposed Live Wiring
P1DA Sec 1 – Missing back panel, Exposed Live Wiring
P1DA Sec 2 – Missing back panel, Exposed Live Wiring
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Panel Deficiency Building 100 - 1st Floor & 2nd Floor
P1DA Sec 3 – Missing back panel, Exposed Live Wire
EQ1C – Missing back panel, Exposed Live Wiring
CC2B – Missing back panel, Exposed Live Wire
Panel Deficiency Building 100 - 2nd Floor
EQ2B – Missing back panel, Exposed Live Wire
EQ2C – Missing back panel, Exposed Live Wire
P2D1 – Back Panel is the incorrect size and leave live exposed wiring.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Panel Deficiency Building 100 - 2nd Floor & 3rd Floor
ELG2 – Exposed Breaker Slots
EL3C – Exposed Breaker Slots
Panel Deficiency Building 100 – 6th Floor
L6B – Exposed Breaker Slots P6C-SEC2 – Exposed Breaker Slots
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Panel Deficiency Building 105 Research
EE1HA – Missing Back Panel, exposed live wiring.
M2RA – Missing Back Panel Exposed live wiring.
3B-1G Panel is missing back panel and has exposed live wiring.
Panel Deficiency Building 105 4th Floor
PGR4 – Wrong Back panel, Exposed live wiring.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Panel Deficiency Building 101 Boiler Room Powerhouse
EP1K – Main Breaker installed upside down
Panel Deficiency Building NH / CLC
EEDP – Main was removed, breakers slots are exposed, live wiring is exposed.
The missing main moves the trip coordination to the breakers in the ATS. This appears to be deliberate to remove dual breakers causing nuisance trips. If this is the case our only recommendation would be to cover the breaker slot and note in the LOTO procedure that the main disconnect means for this panel includes locking out the ATS.
P1B-1 – Back panel is the incorrect size, wiring is exposed.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Panel Deficiency Building NH / CLC
P2C2 – Back panel is the incorrect size. Live wiring is exposed.
Room 2E-1-
Working space violations, the panels are inaccessible
Bldg 100 1st &2nd floor – Working Space blocks
Working space violations due to installed and uninstalled transformers. 208V panels require 3’ clearance.
Working space violations RM 1F-100 Panel L1F2 doesn’t open 90 degrees
2B-13 Working space violations due to installed and uninstalled transformers. Bldg 100 2nd floor
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Building 100 Penthouse
Building 100 Penthouse – The demolition of the AHU has left exposed wire, unlabeled and open panelboards, unsupported conduit, exposed panelboards and debris over and around electrical equipment. The demo in this area should be completed and work areas clearly marked.
Building 100 Penthouse – Continued
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Unlabeled panels
Room 1E-72 Panel is unlabeled
Room 02-7A
– Panel is unlabeled
Room 1D-63 –
Panel is unlabeled
Unlabeled panels
Room 2C Elec &
MECH –
Panel is unlabeled
Room 3D-
MECH –
Panel is unlabeled
Room 3E-MECH -4 Panel is unlabeled
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
Unlabeled panels
Room 4C-MECH –
Panel is unlabeled
NH MDS –
2 Panels are unlabeled
NH-1st
NH First Floor hallway.
Panel is unlabeled
To make proper Arc Flash labels for the panels we are suggesting the following names.
Unlabeled Panel Room Suggested Name for the Panel
1D-63 E1D1
1E-72 EQL1E
2A-07 L2A1
2C ELEC & MECH EQL2C
3D-MECH EQL3D
3E-MECH EQL3E
4C-MECH EQL4C
MDS ROOM (2) panels P-COR-1 and L-COR
NH 1st Floor NH1
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
5.0 RESULTS AND RECOMMENDATIONS
One Line
A working set of up-to-date drawings are required by the NEC 490.48(B). The existing set of single lines are incomplete or inaccurate. One complete set of singles lines should be updated and corrected. The single lines attached to report are accurate to the panel bus level. These were used for the Arc Flash analysis but are incomplete at the branch circuit level.
Load Flow
The model results show a voltage drop greater than 5% in areas across the south side of the campus without the voltage support of transformer 1X28.
If any negative conditions as listed in the report are seen in the hospital, a more selective and detailed data collection will be required. In the short-term load shedding or tapping up supporting transformers may be temporarily necessary to help with voltage support. Bringing transformer 1X28 in service when available will also help bring up some of the voltage sag seen in the model.
Short Circuit / Protective Device Coordination
The protective device coordination was found to be mostly in order. Our recommendation would be to make the few adjustments shown in Device Coordination section. Secondly, a protection scheme has to be determined for the MSS busway networks and properly installed to protect the electrical floors distribution panels.
Arc Flash
The final evaluation of the Arc Flash model found that the majority of the buses and panels throughout the campus are in a low energy level arc flash risk. A renovation of the transformers, panelboards and main protective devices from the last study has shown improvement in many areas of the campus. A few exceptions are the MSS buses and busway system, MDS Bus and the 480 Chiller Bus. These systems should be upgraded with arc flash maintenance protection, upgraded with more modern equipment or not worked on live.
Code and Equipment Deficiencies
The panel deficiencies in section 4.0 should be addressed, these include unlabeled panels, open wireways and circuit openings, exposed busing, incorrect or missing backplates or panel faces and cluttered / inaccessible electrical spaces.
REP-21041-06-001 REV. 1
September 15, 2021
Encorus Project # 21041
6.0 REFERENCES
[1] National Fire Protection Association, NFPA 70E National Electric Code, Annex D.4, 2021.
[2] IEEE 1584 2018 Guide for performing Arc-Flash Hazard Calculatoins
Use IEEE style and the built-in IEEE style references generator to generate the reference section.
REP-21041-06-001 REV. 1
September 15, 2021
APPENDIX A ONE-LINE DIAGRAMS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
TITLE SHEET AND DRAWING INDEX 100% CONSTRUCTION
DOCUMENTS
UPDATE ARC FLASH AND
ELECTRICAL COORDINATION STUDY
FOR JJPVAMC
130 W KINGSBRIDGE RD
BRONX, NY 10468
2021-07-15
GI001
526-19-133A
DGA CJR
REV 0 ISSUED FOR CONSTRUCTION 2021-07-15
REV 1 VA COMMENTS 2021-09-15
DRAWING INDEX
DRAWING NUMBER DRAWING TITLE
GENERAL
GI001 TITLE SHEET AND DRAWING INDEX
ELECTRICAL
E-001 ELECTRICAL NOTES AND LEGENDS
E-601 SITE ELECTRICAL SINGLE LINE DIAGRAM
E-602 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100
E-603 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100
E-604 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100
E-605 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 106 AND FISHER HOUSE
E-606 ELECTRICAL SINGLE LINE DIAGRAM - 480 GEN 1 AND 3
E-607 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 101 AND 106
E-608 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 101
E-609 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100
E-610 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100
E-611 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 105
E-612 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100
E-613 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 105
E-614 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100 AND 105
E-615 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 100
E-616 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 105
E-617 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 106
E-618 ELECTRICAL SINGLE LINE DIAGRAM - BUILDING 106
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text one quarter inch = one foot
AutoCAD SHX Text
BRONX VAMC
AutoCAD SHX Text UPDATED ARC FLASH AND ELECTRICAL COORDINATION STUDY FOR JJPVAMC 130 W KINGSBRIDGE RD BRONX, NY 10468
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
ELECTRICAL NOTES AND LEGENDS 100% CONSTRUCTION
DOCUMENTS
UPDATE ARC FLASH AND
ELECTRICAL COORDINATION STUDY
FOR JJPVAMC
130 W KINGSBRIDGE RD
BRONX, NY 10468
2021-07-15 E-001
526-19-133A
DGA CJR
REV 0 ISSUED FOR CONSTRUCTION 2021-07-15
REV 1 VA COMMENTS 2021-09-15
G
ELECTRICAL SYMBOLS - POWER PLAN
DUCT BANK
VFD
UNDERGROUND ELECTRICUE
GENERAL LINETYPES
EXISTING DUCT BANK
ABANDON DUCT BANK
DB
BUS DUCT
CABLE
BUS / SWITCHGEAR
CBL-XXXX CABLE NAME ( REFER TO SKM MODEL FOR DETAILS)
NAMING DESIGNATIONS FOR ELECTRICAL BUS/SWITCHGEAR
480, 3PH, 4W, 1200A, 100 kAIC
VOLTAGE
PHASE
SYSTEM AMPACITY
INTERRUPT RATING
VARIABLE FREQUENCY DRIVE
MEDIUM VOLTAGE DRAWOUT BREAKER
LOW-VOLTAGE DRAWOUT AIR CIRCUIT BREAKER
MOLDED CASE CIRCUIT BREAKER
FUSE WITH RATING
SWITCH, SINGLE BREAKER
FUSED SWITCH
CURRENT TRANSFORMER WITH RELAY DEVICE
GENERATOR, POWER
ATS - AUTOMATIC TRANSFER SWITCH
MTS - MANUAL TRANSFER SWITCH
EARTH GROUND
WYE CONNECTION
TRANSFORMER
RECTIFIER
MOTOR, SINGLE-PHASE
LOAD DEVICE RESISTIVE OR TRANSIENT
PANEL BOARD WITH PANEL BOARD NAME
XXXX
PAGE CONNECTOR
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text one quarter inch = one foot
UTIL-0001
TX 1x32 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75
LOAD BUS 1
CH3
T-LOAD BUS1
2500 kVA PRI 4.16 kV
SEC 480 V
Z% = 4.27
SYNC BUS 1-2
UTIL-0002
TX 1x21 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75
LOAD BUS 2
T-LOAD BUS 2
2500 kVA PRI 4.16 kV
SEC 480 V
Z% = 7.96
UTIL-0003
LOAD BUS 3
CH2
T-LOAD BUS 3-1 (MSS2-B)
2500 kVA PRI 4.16 kV
SEC 480 V
Z% = 7.84
BUS DUCT - 201B
UTIL-0004
LOAD BUS 4
T-LOAD BUS 4
2500 kVA PRI 4.16 kV
SEC 480 V
Z% = 7.88
BUS DUCT - 201A
SYNC BUS 3-4
T-LOAD BUS 3-2 (NH)
500 VA
PRI 4.16 kV
SEC 480 V
Z% = 4.80
PD-0001
PD-0002
PD-0003
PD-0005
PD-0004
PD-0007 PD-0006
PD-0011
PD-0008
PD-0010 PD-0012
PD-0009PD-0013 PD-0015 PD-0014
PD-0019 PD-0016 PD-0018
PD-0017
PD-0021
PD-0020
PD-1554 PD-1556
PD-1557 PD-1559
PD-1558
PD-1560
PD-1561
PD-1562
PD-10000
CLASS E
PD-10001PD-10002 PD-10003
PD-10004
PD-10005 PD-10006
PD-10007
PD-10008
PD-10009
PD-10010 PD-10011
PD-10012 PD-10013
PD-10014 PD-10015
PD-10016
BUS DUCT - 101A
PD-1613
PD-1614 PD-1615 PD-1616
PD-1617 PD-1618 PD-1619 PD-1620
TX CHILLER 3
2500 kVA PRI 4.16 kV
SEC 480 V
Z% = 5.60
CBL-006
G G1 4160V 3575 kVA
CBL-013_G1
CBL-010
600 HP
CBL-017
CBL-018
CBL-013
CBL-013_LB2
CBL-019
CBL-014
CBL-014_G2
CBL-011
CBL-021
CBL-014_LB4
CBL-023 CBL-022
CBL-012
CBL-020
TO DRAWING E-604
MSS1-B
TO DRAWING E-602
MSS1-A
TO DRAWING E-609
MSS2-B
TO BUILDING E-611
MSS2-A
TO DRAWING E-605
NURSING HOME
MDS
4160, 3PH, 3W, 1200A, 35 kAIC
BUS DUCT - 101B
TX 1x28 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75
TX 1x29 3000 kVA PR 13.2 kV SEC 4.16 kV %Z = 5.75
4160, 3PH,3W,1200A,35 kAIC 4160, 3PH, 3W, 1200A, 35 kAIC 4160, 3PH, 3W, 1200A, 35 kAIC
G G2 4160V 3575 kVA
CHILLER SWGR
4160, 3PH, 3W, 1200A, 35 kAIC
4160, 3PH, 3W, 1200A, 35 kAIC
CHILLER 3
T-PPL-1
30 kVA
PRI 480 V
SEC 208 V
Z% = 3.4
CB TO PPL-1
LOAD-0786
CB TO PPH-1 CB TO DS-MT-1 CB TO
DS-ES-1
CB TO
CHILLER 3
LOAD-0787 LOAD-0788
PPH-1 DS-MT-1 DS-ES-1
CBL-1704 CBL-1708 CBL-1709 CBL-1710
CBL-1707
PD-1659
CBL-1711
CBL-1712
PPL-1
600 HP
480, 3PH, 4W, 4000A, 100 kAIC
TO DRAWING E-605
FISHER HOMES
CBL-1739
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
SITE ELECTRICAL SINGLE LINE
DIAGRAM
100% CONSTRUCTION
DOCUMENTS
UPDATE ARC FLASH AND
ELECTRICAL COORDINATION STUDY
FOR JJPVAMC
130 W KINGSBRIDGE RD
BRONX, NY 10468
2021-07-15 E-601
SITE
526-19-133A
DGA RJB
REV 0 ISSUED FOR CONSTRUCTION 2021-07-15
REV 1 VA COMMENTS 2021-09-15
GENERAL NOTES
1.
2.
KEYED NOTES
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
PD-APTSPD-ECL-CPD-NDSSPD-LDA
MCC 3
PD-0062
CB NP
MAIN
NP
PD-0066PD-0070PD-0029
PD-0079
CB L1DA
MAIN
PD-0080
CB TO P2DA
T-L2DA
75 kVA
PRI 480V
SEC 208V
Z% = 5.11
CB P2DA
SEC1
MAIN
P2DA SEC2
PD-0157
P2DA SEC1
CB TO P2DA1
P2DA1
LOAD-158
CB TO STARBUCKS
T-L1DA
30 kVA
PRI 480 V
SEC 208V
Z% = 5.41
STARBUCKS
LOAD-157
PD-0125
L2C SEC2
PD-0127
L4C
PD-0128
L5C
CB TO P4C
PD-0129
L6C
CB TO P5C
PD-0130
L7C
CB P4C
MAIN
P4C
PD-0131
L8C
CB P5C
SEC1
MAIN
P5C SEC1
P5C SEC2
PD-0132
L9C
CB TO P9C
P5C SEC3
LOAD-141
T-L9C 75 kVA
PRI 480 V
SEC 208 V
Z% = 4.27
CB P9C
SEC1
MAIN
P9C SEC1
P9C SEC2
P9C SEC3
LOAD-143
CB TO P2C LAB
CB P2C LAB
MAIN
P2C LAB
LOAD-147
LOAD-130
MTRI-128 CHP
PD-0104 PD-0102 PD-0103PD-0105 PD-0137
MTRI-HV-3 MTR CWP 8-11
PD-0058
PD-MCC3
MTR CWP 2-4,6MTR CWP 1,5 MTR CWP 7
FROM DRAWING E-601
LOAD BUS 2
NDSS
25 HP
CBL-111 CBL-109
CBL-182
CBL-187
CBL-183
CBL-188
CBL-185
CBL-190
CBL-201
CBL-202
CBL-753
CBL-674
CBL-673
CBL-273
CBL-671 CBL-272
CBL-670
CBL-283
CBL-271
CBL-277
CBL-267
CBL-275
CBL-270 CBL-258
CBL-266
CBL-269
CBL-224CBL-265
CBL-223
CBL-105
T-L5C 45 kVA
PRI 480 V
SEC 208 V
Z% = 4.27
T-L4C 45 kVA
PRI 480 V
SEC 208 V
Z% = 4.27
T-L2C SEC2
45 kVA
PRI 480 V
SEC 208 V
Z% = 4.27
480, 3PH,3W,3000A,100 kAIC
25 HP 75 HP 30 HP 75 HP
50 HP
MSS 1-A CONTINUED
TO DWG E-603
TO DRAWING E-606
N-ATS3
TO DRAWING E-606
N-ATS2
TO DRAWING E-606
N-ATS1
T-L6C 45 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
CB NL-6C-1
MAIN
NL-6C-1
CB NL-6C-2
MAIN
NL-6C-1
LOAD-0783
CB TO NL-6C
LOAD-0799
LOAD-0798
CB P4C
SEC1
MAIN
P4C SEC1
P4C SEC2
LOAD-140
CBL-1727
CBL-1728
CBL-1698
CBL-1697
BUS DUCT - 186
BUS DUCT - 111
CB MSS1-A
MAIN
BUS DUCT - 128
BUS DUCT - 136
BUS DUCT - 264
BUS DUCT - 268
BUS DUCT - 274
BUS DUCT - 276
BUS DUCT - 282
BUS DUCT - 669
BUS DUCT - 142
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
ELECTRICAL SINGLE LINE DIAGRAM
- BUILDING 100
100% CONSTRUCTION
DOCUMENTS
UPDATE ARC FLASH AND
ELECTRICAL COORDINATION STUDY
FOR JJPVAMC
130 W KINGSBRIDGE RD
BRONX, NY 10468
2021-07-15 E-602
BLDG 100
526-19-133A
DGA RJB
REV 0 ISSUED FOR CONSTRUCTION 2021-07-15
REV 1 VA COMMENTS 2021-09-15
GENERAL NOTES
1.
2.
KEYED NOTES
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
PD-B16
PD-ECL-F
PD-MCC2 PD-MRI
PD-0064
PD-0073
PD-0068
PD-0027
MCC 2
PD-0033
DB-LCT-TO BLDG 16
225 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
CB NP1
MAIN
NP1
CB TO BCB TO APT 109 CB TO APT 108CB TO APT 209 CB TO APT208CB TO APT 308 CB TO APT 309
CB B
MAIN
B
APT 109 APT 108APT 209 APT 208APT 308 APT 309
CB P16-2
MAIN
P16-2
LOAD-131 LOAD-136 LOAD-135 LOAD-133
LOAD-138
LOAD-132 LOAD-134 LOAD-137
PD-0075
LGF SEC1
PD-0082
L1F SEC1 LGF SEC2
PD-0083
L2F
CB TO P2F
SEC1
T-L2F 75 kVA
PRI 480 V
SEC 208 V
Z% = 5.41
CB P2F
SEC1
MAIN
P2F SEC1
P2F SEC2
P2F SEC3
LOAD-154
CB TO P1F
L1F SEC2
T-L1F SEC1
75 kVA
PRI 480 V
SEC 208 V
Z% = 5.41
CB P1F
SEC1
MAIN
P1F SEC1
P1F SEC2
P1F SEC3
LOAD-152
LOAD-151
CB TO PGF
T-LGF SEC2
45 kVA
PRI 480 V
SEC 208 V
Z% = 5.41
CB PGF
SEC1
MAIN
PGF SEC1
PGF SEC2
PGF SEC3
LOAD-153
PD-0090PD-0091
MTRI-110 CHPCB TO DP-CH CB TO CT
DP-CH CT
MTRI-211MTRI-212
LOAD-156 LOAD-155
PD-0712PD-0713
MP1
PD-0714
LP1
LOAD-159PD-0715
ML1
LOAD-160
25 HP
CBL-106
CBL-117
CBL-131
CBL-131-9
CBL-131-7 CBL-131-6 CBL-131-3 CBL-131-4 CBL-131-2 CBL-131-5 CBL-131-8
CBL-108
CBL-110 CBL-112CBL-181
CBL-177
CBL-0586
CBL-293
CBL-294
CBL-295
CBL-296
CBL-298
CBL-297
CBL-292 CBL-189
CBL-291 CBL-184
CBL-290 CBL-180
CBL-178CBL-289
CBL-177B0
CBL-288 CBL-177B
CBL-212 CBL-211
CBL-0931 CBL-134 CBL-125
CBL-145
CBL-139
CBL-150
T-DP-LC
45 kVA
PRI 480 V
SEC 208 V
Z% = 5.00
T-MP1
15 kVA
PRI 480 V
SEC 208 V
Z% = 5.00
1 1
50 HP
30 HP
TO DRAWING E-604
MSS 1-B
480, 3PH, 3W, 3000A, 100 kAIC MSS 1-ACONTINUED
FROM DWG E-602
TIE BREAKER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
ELECTRICAL SINGLE LINE DIAGRAM
- BUILDING 100
100% CONSTRUCTION
DOCUMENTS
UPDATE ARC FLASH AND
ELECTRICAL COORDINATION STUDY
FOR JJPVAMC
130 W KINGSBRIDGE RD
BRONX, NY 10468
2021-07-15 E-603
BLDG 100
526-19-133A
DGA RJB
REV 0 ISSUED FOR CONSTRUCTION 2021-07-15
REV 1 VA COMMENTS 2021-09-15
GENERAL NOTES
1.
2.
KEYED NOTES
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
NURSING QUARTERS
MSS1-B
PD-SPARE 1PD-MCC3A PD-MCC2APD-ELS1 PD-SPARE 2PD-ECL-D PD-SPARE3PD-SPARE 4 PD-NQ DPPD-LFP PD-ELS4
PD-0034PD-0036
MCC 3A
PD-0037
MCC 2A
PD-0040
ELS1
PD-0042PD-0043 PD-0046PD-0049 PD-0051PD-0054
PD-1432
PD-0055
ELS4
PD-0097
T-TO EP1
10.0 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
EP1
LOAD-0373
PD-0098
LGD SEC1 PD-0185
L1D
PD-0186
L3D
PD-0187
EN
ATS L1D
CB TO P3D
CB P3D
SEC1
MAIN
P3D SEC1
P3D SEC2
CB TO P4D
P3D SEC3
P4D
LOAD-0370
CB P3D1
MAIN
P3D1
LOAD-0371
CB TO L1D ATS
KLGE-2
CB TO LAS ATSCB TO L1E ATS CB TO LES ATS CB TO KGLE-2 SUB
ATS-LAS EATS-L1E E ATS-LES E
PD-0026
GEN LIFE SPRT
KLGE-2 SUB
T-L1D 45 kVA
PRI 480 V
SEC 208 V
Z% = 5.04
CB P1D SEC1
MAIN
P1D SEC1
P1D SEC2
LOAD-0372
MTRI-114 CHPPD-0094 MTRI-FP CHP
MTRI-CWP
EN
AUTO-0024
E-FIREPUMP
PD-0095MTRI-115 CHP PD-0096
MTRI-0018 MTRI-BOILER
PD-0099
TUN WESTINGHOUSE
T-TO NQ DIST PANEL P
CB TO T.T.
T-TO NQ DIST PANEL
150 kVA
PRI 480 V
SEC 208 V
Z% = 4.7
LOAD-0368
PD-0475
NQ DIST PANEL
CB TO NQ SQDCB TO NQ LPGS CB TO CHAPELCB TO NQ LPGN CB TO
NQ LPG
NQ SQDNQ LPGS CHAPELNQ LPGN NQ LPG
LOAD-0303 LOAD-0307LOAD-0305 LOAD-0304 LOAD-0306
T-TO T.T.
15 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
CB T.T.
MAIN
T.T.
LOAD-0367
ECPB
LOAD-0369
LGD SEC2
CB TO PGD
SEC1
PD-0724
T-LGD SEC2-2
75 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
CB PO
SEC1
MAIN
PO SEC1
PO SEC2
LOAD-0366
CB PGD
SEC1
MAIN
PGD SEC1
PGD SEC2
PGD SEC3
LOAD-0365
FIRE PUMP
MTRI-FIRE PUMP
FROM DRAWING E-601
LOAD BUS 1
FROM DRAWING E-603
MSS1-A
CBL-116 CBL-122 CBL-912 CBL-123
CBL-147
CBL-911
CBL-775
CBL-913
CBL-778
CBL-474
CBL-779CBL-781CBL-783ACBL-780 CBL-782
CBL-0572
CBL-143
CBL-0666CBL-311ECBL-304ECBL-234ECBL-462E
CBL-508
CBL-236
CBL-532
CBL-533
CBL-511
CBL-098CBL-509
CBL-241
CBL-256
CBL-255CBL-257
CBL-246CBL-254
CBL-239 CBL-149CBL-234CBL-252 CBL-240
CBL-238
CBL-235
CBL-233
CBL-231
CBL-148
300 HP
TO DRAWING
606 BUS EDSS
G
GEN-LIFE SPRT
TO DRAWING E-611
ATS-LAS
T-LGD SEC2-1
112.5 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
T-L3D 75 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
480, 3PH,3W,3000A,100 kAIC
2 2 2
50 HP 50 HP
30 HP200 HP25 HP
50 HP
BUS DUCT - 237
BUS DUCT - 232
BUS DUCT - 118 BUS DUCT - 114 BUS DUCT - 115
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
ELECTRICAL SINGLE LINE DIAGRAM
- BUILDING 100
100% CONSTRUCTION
DOCUMENTS
UPDATE ARC FLASH AND
ELECTRICAL COORDINATION STUDY
FOR JJPVAMC
130 W KINGSBRIDGE RD
BRONX, NY 10468
2021-07-15 E-604
BLDG 100
526-19-133A
DGA RJB
REV 0 ISSUED FOR CONSTRUCTION 2021-07-15
REV 1 VA COMMENTS 2021-09-15
GENERAL NOTES
1.
2.
KEYED NOTES
AutoCAD SHX Text one eighth inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three inches = one foot
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text one and one half inches = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 6"
AutoCAD SHX Text 6"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three quarters inch = one foot
AutoCAD SHX Text one half inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text three eighths inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
E N
NH EEATS
CB TO NH EEATS
MDS
CB TO PPTP CB TO NH L1ACB TO NH L2A CB TO NH L1BCB TO NH L2B CB TO MCC LTAPD-0442 CB TO L-COR1PD-0444
CB MDS
MAIN
PPTP NH L1ANH L2A NH L1BNH L2B MCC LTA
LOAD-0495
CB TO T-TO SIEMENS
T-TO SIEMENS P
PD-0242
T-TO SIEMENS S
CB EM2
MAIN
EM2
LOAD-0486
CB P2C3
MAIN
P2C3
CB P2C1
MAIN
P2C1
CB CC2A SIEMENS
MAIN
CC2A SIEMENS
CB P2C2
MAIN
P2C2
P2C2-1 P2C1-1 P2C3-1
LOAD-0487
LOAD-0488 LOAD-0489 LOAD-0490
CB TO RPT
PD-0465
RPT
PD-0466CB TO RPT1 MTR-CHP
HLPRPT1
CB SQD
MAIN
SQD
LOAD-0493
LOAD-0492
LOAD-0491
CB TO P1B-A
CB P1B-A MAIN
P1B-A
LOAD-0494
CB TO PTA
MTR-708 CHP
PTA
LOAD-0496
E N
ATS GEN
PD-0456
NH GEN
EEDP
CB TO EEQCB TO EEGH CB TO EELPCB TO ELEV P1 CB TO ELEV P2CB TO ELEV P3 CB TO EEP1B-BA
EEGH EEP1B-BA
LOAD-0498
ELEV P1
ELEV P2
ELEV P3
LOAD-0500
EEQ EELP
LOAD-0497 LOAD-0499
FROM DRAWING E-601
LOAD BUS 3
CBL-707 CBL-705 CBL-702 CBL-711A CBL-704 CBL-706 CBL-708
CBL-715
CBL-730
CBL-784
CBL-744 CBL-738 CBL-732 CBL-742
CBL-746 CBL-740 CBL-736
CBL-720
CBL-719 CBL-718
CBL-717
CBL-729
CBL-735
CBL-727 CBL-733
50 HP
CBL-711B CBL-711A0
CBL-711C
CBL-750 CBL-748 CBL-743 CBL-739 CBL-747 CBL-749 CBL-776
CBL-0923 CBL-0924
G
GEN NURSE
TO DRAWING E-606
EDSS
T-TO SIEMENS
112.5 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
480, 3PH,3W,1200A,100 kAIC
T-PPTP
112.5 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
T-NH L1B
75 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
T-MCC LTA
15 kVA
PRI 480 V
SEC 208 V
Z% = 5.0
T-TO EELP
15 kVA
PRI 480 V
SEC 208 V
Z% = 6.0
T-TO EEQ
30 kVA
PRI 480 V
SEC 208 V
Z% = 6.0
1 1
1 1
50 HP
50 HP
31 HP
50 HP
CB TO LP1 #1
LP1 #1
CBL-1750
LOAD-0803
DP-H #1
CB TO LP2 #1
LP2 #1
CBL-1752
LOAD-0804
CB TO LPH #1
LPH #1
CBL-1746
LOAD-0805
CB TO
ELEVATORS #1
CBL-1748
ELEV FH #1
PD-1728
CBL-1740
CBL-1742
PD-1715
CB DP-H #1
MAIN
PD-1714
CBL-1739
TX-FISHER HOUSES
300 kVA PRI 4.16 kV
SEC 208 V
Z% = 6.0
PD-1716
CBL-1741
CBL-1743
CB DP-H 2
MAIN
CB TO LP1 #2
LP1 #2
CBL-1751
LOAD-0806
DP-H #2
CB TO LP2 #2
LP2 #2
CBL-1753
LOAD-0807
CB TO LPH #2
LPH #2
CBL-1747
LOAD-0808
CB TO
ELEVATORS #2
CBL-1749
ELEV FH #2
PD-1729
FROM…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .