36C24224B0031_1.docx

DOCX document 298 KB Posted

Attached to
J061--526-23-110 Electrical Switchgear Replacement Phase 1 Federal contract opportunity
Solicitation number
36C24224B0031
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

This document is a solicitation for a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside procurement to replace electrical switchgear equipment at the James J. Peters VA Medical Center in the Bronx, New York.

The scope of work includes replacing the existing Federal Pacific and Federal Pioneer 480V circuit breakers within the MSS1 and MSS2 substations with new Schneider Electric drawout circuit breakers. The new breakers will have improved arc flash protection capabilities and "Maintenance Mode" features to allow servicing the feeder breakers. The contractor will be responsible for coordinating the equipment replacement, scheduling work during off-hours, and minimizing outages. The contract is for a firm-fixed price with a period of performance of 180 calendar days after the Notice to Proceed. The magnitude of construction is between $2 million and $5 million. A pre-bid site visit is scheduled for April 9, 2024, and bids are due by May 2, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to J061--526-23-110 Electrical Switchgear Replacement Phase 1, newest first.
File Type Posted
36C24224B0031 0003.docx DOCX document
Arc-Flash_Report_-_-SEPT-15-2021.pdf PDF
S06 Brand Name or Equal Product Salient characteristics - Electrical Switchgear Replacement Phase 1.pdf PDF
36C24224B0031 0002.docx DOCX document
S06 IFB 36C24224B0031 Electrical Switchgear Pre-bid walkthrough Sign in Sheet 4-11-2024.pdf PDF
S05 RFI Answers -Electrical Switchgear Replacement 36C24224B0031.pdf PDF
VA-BRONX-SINGLE-LINE-Electrical Switchgear Replacement Phase 1.pdf PDF
REVISED VA-BRONX-SOW-Electrical Switchgear Replacement Phase 1-rev1.docx DOCX document
36C24224B0031 0001.docx DOCX document
P01 Safety REQUIREMENTS -SECTION 01 35 26-Electrical Switchgear Replacement Phase 1.docx DOCX document
P01 QC-SECTION 01 45 00-Electrical Switchgear Replacement Phase 1.docx DOCX document
P01 SECTION 26 05 11-REQ FOR ELECTR INSTALL -Electrical Switchgear Replacement Phase 1.docx DOCX document
P01 Section262921-ENCLOSED SWITCHES AND CIRCUIT BREAKERS-Electrical Switchgear Replacement Phase 1.docx DOCX document
P07 Wage Determination Electrical Switchgear replacement.pdf PDF
P01 GENERAL REQUIREMENTS-010000-Electrical Switchgear Replacement Phase 1.docx DOCX document
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (DEVIATION).pdf PDF
FAR 52.225-2 BUY AMERICAN CERTIFICATE.docx DOCX document
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24224B0031

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (

Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24224B0031 X 03-29-2024 526-24-2-5053-0001 526-23-110 36C242 Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx NY 10468-3904 Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx NY 10468-3904 Kurian, Akkil A.

718-584-9000 x 5267 This project is to furnish all necessary professional Construction services to replace the Electrical Switchgears in accordance to the project Statement of Work and specifications for the James J. Peters VA Medical Center, Bronx Campus.

The Contractor shall furnish all materials, supplies, equipment, personnel and supervision to accomplish Project 526-23-110 Electrical Switchgear Replacement Phase 1.

Completion Time: 180 Calendar Days from the Notice to Proceed This is a 100% Service-Disabled Veteran Owned Small Business set aside procurement.

All prospective bidders must be registered in SAM (www.sam.gov), and are verified/visible/certified with the SBA as a SDVOSB (https://veterans.certify.sba.gov) at the time of offer submission and before award of this procurement. Offerors must submit their annual Vets4212 Report. Magnitude of Construction: Between $2,000,000 and $5,000,000. The North American Industry Classification System Code (NAICS) is 238210- Business Size is $19 Million.

Contractor will be responsible to coordinate and schedule work and shall be expected to plan work typically during duty hours of 8 AM to 4:30 PM eastern time except as noted in the general conditions and as approved by the CO. Work shall comply with VA Specifications and regulations, all applicable Federal, State and Local codes, including specific regulations related to working at the VA Bronx Campus.

A pre-bid site visit is scheduled for Tuesday, 04/09/2024 at 10:00 AM EST. Prospective bidders shall meet at the James J. Peters VAMC, Building 100 GC-106 Engineering Lobby 130 West Kingsbridge Road, Bronx, NY 10468.

NOTE: NO OTHER SITE VISITS WILL BE ALLOWED. INTERESTED BIDDERS ARE STRONGLY ENCOURAGED TO ATTEND.

To preserve the integrity of the procurement process, all questions and request for information must be submitted in writing to Akkil Kurian, Contract Specialist via email at akkil.kurian@va.gov.

Questions must be received no later than Tuesday, April 23, 2024 at 4:00PM EST.

The bid opening will be held online via a Cisco Webex Teleconference. Details will be sent via a solicitation amendment. ONLY EMAILED BIDS to AKKIL.KURIAN@VA.GOV shall be accepted. The bids shall include copies of the original bid bond . The bid opening shall take place on Thursday, May 2, 2024 at 10:00am EST.

Limitations on Subcontracting Certificate is a separate requirement attached & inserted on pages 68-69.

FAR 52.225-2 Buy American Act Certificate is a separate requirement attached to the solicitation.

The signed certificates must be received with the bid.

FAR Part 36.209 Construction contracts with architect-engineer firms. No contract for the construction of a project shall be awarded to Northeast Infrastructure, LLC or its subsidiaries or affiliates.

NOTE: CONTRACTORS MUST ACKNOWLEDGE ALL SOLICIATION AMENDMENTS.

x x 52.211-10 X 10 days 10:00am

EDT

05-02-2024 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

526-3640162-5053-854200-2543 23NR4BS08

36C242 Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx NY 10468-3904 Tungsten Network http://www.tungsten-network.com/us/en veterans -affairs

Daniel Barone Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
Statement of Work5
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS19
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS20
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)20
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)20
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)20
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)21
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)22
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)23
2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)23
2.8 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)24
2.9 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)25
2.10 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019)25
REPRESENTATIONS AND CERTIFICATIONS27
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (FEB 2024)27
3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)31
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)32
GENERAL CONDITIONS35
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)35
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)36
4.3 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)37
4.4 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (FEB 2024)37
4.5 52.219-27 NOTICE OF SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (FEB 2024)39
4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (FEB 2024)41
4.7 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)43
4.8 52.236-4 PHYSICAL DATA (APR 1984)48
4.9 52.244-6 SUBCONTRACTS FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (FEB 2024)49
4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS51
4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)52
4.12 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)55
4.13 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)55
4.14 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023)55
4.15 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)64
4.16 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)65
4.17 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)68
4.18 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)69
4.19 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)70
4.20 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)70
4.21 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)73
4.22 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)74
4.23 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019)75
4.24 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)75
4.25 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)76
4.26 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)76
4.27 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)77
4.28 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)77

Statement of Work James J. Peters VA Medical Center the Bronx, NY Electrical Switchgear Replacement Phase 1 VA Project # 526-23-110

Introduction & Mission The VA is dedicated to optimizing the health care and overall physical environment and ensuring the seamless operation of the facility. A major objective is the prevention of Engineering related and Construction - Maintenance related Safety Hazards. The VA continues to strive to assure the continuous operation of essential patient services to our Veterans and rapid response to conditions which may interfere with such services. This project details requirements to support the Mission above.

Background As a result of the research and development of the Electrical Master Plan, the following equipment was found to require direct replacement with new equipment.

1) Federal Pacific and Federal Pioneer 480 Volt Circuit Breakers within MSS1

2) Federal Pacific and Federal Pioneer 480 Volt Circuit Breakers within MSS2

The prior Arc Flash Study, completed in 2021 by Encorus Group (Order # 36C24221C0085), indicated that these older Federal Pacific Electric (FPE) circuit breakers (MSS1 and MSS2) are “near the end of their effective service life” and the condition of the Circuit Breaker Current Limiting Fuses cannot be verified, and therefore might not be able to interrupt a fault. The NEC and other Standards require that a Protective Device can interrupt the available fault current. This is necessary for the protection of personnel, equipment, and other assets.

In addition, the Study of Encorus Group on September 15, 2021 indicates the following:

“Network buses MSS-1 and MSS-2 have very large incident energy levels and these also cannot be worked on live. Reducing the incident energy levels of these buses is difficult due to the equipment.

currently installed. The currently installed breakers do not have the adjustment ranges or maintenance modes of more modern equipment. Additional equipment could be installed around MSS1 and 2 to reduce the incident energy levels but this would require an upgrade to the Network Buses.”

The available Arc Flash Incident Energy for MSS1 and MSS2 is shown as 96.0 to 105.9 cal/cm2, therefore no available PPE exists to allow any type of maintenance while energized.

Objective Upgrade the two (2) groups of electrical power circuit breakers (substations MSS1 and MSS2) to new equipment, while maintaining the existing equipment structure; and providing for minimal outages during the transition to the new circuit breakers. The expectation is that the direct replacement circuit breakers will be designed to be inserted into the existing electrical structures, therefore minimizing the outage time to the time required to replace a circuit breaker. Work scheduling, for the direct replacement of the circuit breakers, will be off-hours. If it is determined that any downstream load will or may be affected by the replacement of each circuit breaker, this must be clearly identified and notification provided of any potential downstream outage, with back-up resources provided as necessary.

In addition, the new 480 Volt circuit breakers will provide additional arc flash protection capabilities. The “Direct Replacement Circuit Breakers” will be equipped with a “Maintenance Mode”, therefore allowing the feeder circuit breakers to be serviced, when the Main Circuit Breaker is adjusted to its Maintenance Mode. This is shown as the “Arc Flash Maintenance Switch (1 per Circuit Breaker).

SCOPE OF WORK Specific Requirements

1) Federal Pacific and Federal Pioneer 480 Volt Circuit Breakers 50HL-2 (1600A Frame) within MSS1 and MSS2.

a. The only known direct replacements can be provided by Schneider Electric Canada Services (SCS)to supply only a Cradle in Cradle (CIC) solution to replace QTY -21 (10 for MSS1 + 9 for MSS2 + 2 spares), 50HL-2 breaker in FPE Federal Pacific switchgear 480/277V, 3ph, 4w, and match existing kA.

b. NOTE: There are two (2) existing circuit breakers TYPE 50HL-3 (1600-amp frame and 1200-amp relay). The direct rack-in replacements MUST also accommodate these circuit breakers.

c. This will consist of a cradle-in-cradle design utilizing the "Future Ready" Masterpact MTZ drawout circuit breaker. The cradle-in-cradle concept will consist of an outer frame that will fit directly in the FPE 50HL-2 or in the FPE 25HL-2 circuit breaker cells without modification. Mounted within the outer frame will be the Masterpact MTZ Breaker and Cradle. The new breaker will utilize the Masterpact MTZ racking capabilities for future maintenance operations.

d. The new drawout circuit breakers will be rated for the full available fault current (~ 70kA) without fuses and copper bus links will be included with the direct replacement circuit breakers to allow for direct insertion into the existing cubicles without modifications. The new replacement MTZ2 circuit breaker will be rated for 85kA.

e. This will include Qty - 21, Drawout, manually operated Masterpact MTZ2-16H2 1600A 3P ACB, ANSI, complete with Micrologic Trip Unit 6.0X (LSIG) and with a cradle.

i. Qty - 21, Neutral CT

ii. Qty - 21, Engineered CIC Kit

iii. Qty - 21, New compartment door

f. Description of new breaker types (1600A and 800A):

i. Masterpact MTZ Model No. MTZ2-16H2 3-Pole ANSI C37/UL1066/CSA C22.2 No.268 and Masterpact MTZ2-08H2 800A 3P ACB:

ii. Drawout Circuit Breaker

iii. Rated 1600 Amps, 100% Rated for the 50HL-2 replacements (Quantity: 21)

iv. Rated 800 Amps, 100% for the 25HL-2 replacements (Quantity: 16)

v. AIR - 85kA/85kA/85kA @ 254/508/635 Vac 1600 Amp Sensor

vi. Micrologic 6.0 X (LSIG) Trip Unit

vii. Energy Reduction Maintenance Settings

viii. Energy Reduction Maintenance Setting selected Voltage Power supply included.

ix. ULP Port Wiring

x. 4 OF Contacts (standard)

xi. Shunt Trip with Communication - 48-60Vdc Closing Coil with Communication - 48-60Vdc Overcurrent Trip (SDE) contact standard Padlockable Push Button Cover

xii. Ready to Close Switch

xiii. No Locking Provision Provided with Padlock attachment.

xiv. Automatic Spring Discharged Interlock Standard Description of cradle:

xv. Description of Cradle:

1. Cradle with backmold 3 Pole Device

2. Rated 1600 Amps ULP Port / 800 Amps for 25HL-2 replacements

3. No Provision for Keylock No Position Locking

4. Secondary disconnect wiring for auxiliary contacts - Push-in

5. Closing Coil XF

6. Ready to Close Contact (PF) Secondary disconnect wiring.

7. Shunt trip MX

8. Cradle Rejection Kit – Standard

9. Door Escutcheon included as Standard Description of accessories:

xvi. Description of Accessories:

1. Neutral CT 400/2000 Sensor MTZ2

2. Voltage Power Supply for Micrologic X

xvii. Controls / PTs with installation during on-site work.

xviii. Provide twenty (20) internal secondary contact blocks. Some of these internal blocks have been broken during removal and installation of circuit breakers. These will be replaced on a as-needed basis and will be required to be replaced during a separate complete outage. The pricing section requests the cost for the secondary contact blocks and the labor to perform the replacement during an off-hours / possibly weekend pre-scheduled outage.

g. NOTE: The proposal shall include an option to replace the Tie Breaker, currently a Federal Pacific FD75, 3000 ampere circuit breakers. It is expected that a “direct rack-in replacement circuit breaker” might not be available for the Tie-Breaker location and this would require alternations to the existing internal switchgear bus-work, therefore also requiring a major power outage of both sides of the Switchgear. The details of providing this work shall be included in the proposal and this option will be evaluated as an alternate to the Base Bid.

2) Federal Pacific and Federal Pioneer 480 Volt Circuit Breakers 25HL-2 (800A Frame) within MSS1 and MSS2.

a. Schneider Electric Canada Services (SCS) to supply only a Cradle in Cradle (CIC) solution to replace QTY -16 (7 units for MSS1 + 7 units for MSS2 + 2 spares), 25HL-2 breakers in FPE Federal Pacific switchgear 480/277V, 3ph, 4w, and match existing kA.

b. NOTE: There is one (1) existing circuit breakers TYPE 30HL-3 (600-amp frame and 600-amp relay). The direct rack-in replacements MUST also accommodate this circuit breaker.

c. See MSS1

d. See MSS1

e. This will include: Qty - 16, Drawout, manually operated Masterpact MTZ2-08H2 800A 3P ACB, ANSI, complete with Micrologic Trip Unit 6.0X (LSIG) and with a cradle.

i. Qty - 16, Neutral CT

ii. Qty - 16, Engineered CIC Kit

iii. Qty - 16, New compartment door

f. See MSS1

g. Provide twenty (20) internal secondary contact blocks. Some of these internal blocks have been broken during removal and installation of circuit breakers. These will be replaced on a as-needed basis and will be required to be replaced during a separate complete outage. The pricing section requests the cost for the secondary contact blocks and the labor to perform the replacement during an off-hours / possibly weekend pre-scheduled outage.

h. NOTE: The proposal shall include an option to replace the Tie Breaker, currently a Federal Pacific FD75, 3000 ampere circuit breaker, or equivalent. It is expected that a “direct rack-in replacement circuit breaker” might not be available for the Tie-Breaker location and this would require alternations to the existing internal switchgear bus-work, therefore also requiring a major power outage of both sides of the Switchgear. The details of providing this work shall be included in the proposal and this option will be evaluated as an alternate to the Base Bid.

3) The following provides the details of the circuit breakers to be replaced within MSS1.

The Supplier shall visit the site and confirm the information below:

4) The following provides the details of the circuit breakers to be replaced within MSS2.

The Supplier shall visit the site and confirm the information below:

Only Breakers that are currently in the "ON" position are included in the count for replacements, while we do have four (4) spares if needed for other locations.

5) Arc Flash Maintenance Mode Accessories for all 480 Volt Circuit Breakers (MSS1 and MSS2)

a. The Supplier will activate (37) Masterpact MTZ breaker with the ERMS Digital Module feature, per NEC 240.87. This will allow the breaker to switch to a Maintenance Mode which, when used in conjunction with a proper study, will provide reduced arc flash incident energy (AFIE) by temporarily lowering the instantaneous pickup setting of the circuit breaker control unit.

b. Note: If left in Maintenance Mode, selective coordination is compromised, which could lead to nuisance tripping. Proper use of an ERMS system requires an arc flash study to determine the optimal settings for the breaker rip unit in Normal and Maintenance Mode and to determine the AFIE in both modes.

c. The Supplier will supply and install a physical ERMS switch to allow for activation at the breaker itself.

d. The Supplier will supply 37 - Selector Switch w/ Blue Pilot Light, Pad Lock Attachment, & Contact Block

6) The Supplier will coordinate the on-site UL inspection of the switchgear lineups MSS1 and MSS2. In addition to the UL inspection, the Supplier will provide field services representatives to assist with the de-energization and re-energization of the switchboard; and be present for the complete removal and installation of all circuit breakers. The Supplier shall provide training on the new replacement breaker operation and maintenance.

General Requirements

1. The supplier shall be required to have VA issued identification badges for all his/her personnel working on VA property. Anyone observed without VA identification will be asked to leave VA property.

2. A site visit is required to verify existing conditions, available information, etc.

3. There will be no smoking at this facility except in designated smoking locations. Those caught violating this requirement will be required to leave the facility and/or be escorted off the facility by Police.

4. The supplier is responsible for obtaining his/her own vehicle parking.

5. Supplier personnel must complete VA “privacy and information security awareness training.” This is mandatory training for all VA and non-VA employees working at this facility. This training must be completed annually. Completion certification must be provided for each employee that will be onsite, if applicable.

6. The supplier shall ensure that his/her personnel conduct themselves in a professional manner, i.e., no profanity; proper attire; no discourteous behavior to VA employees, etc.

7. In the performance of all work, the workers must be incompliance with safety regulations governing worker safety (OSHA: 29 CFR 1926 Safety and Health Regulations for Construction; NFPA, Life Safety Codes, etc.). The Contracting Officer or his/her designee will notify the supplier of any noncompliance with the foregoing provisions and the action to be taken. The Supplier shall, after receipt of such notice, immediately correct the conditions to which attention has been directed. Such notice, when served on the Supplier or his/her representative at the site of the work, shall be deemed sufficient for the purpose aforesaid. If the Supplier fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all and any part of the work and hold the Supplier in default. Proper PPE and Training must be provided to all employees.

8. The Supplier shall provide all labor, material tools, equipment, supervision, and other related items required to complete the project as per scope of work and specifications.

9. The Supplier must comply with the latest NFPA 101 Life Safety, NFPA 99 Health Care Facilities, and VA Design Standards.

10. All expenses towards mobilization at site and demobilization including bringing in equipment, workforce, and materials, dismantling the equipment, clearing the site etc. shall be deemed to be included in the firm-fixed price, or rates quoted, by the supplier. No separate payment of such expenses shall be entertained.

11. It is the responsibility of the supplier to verify all quantities, field conditions and measurements prior to starting work. The supplier shall notify the CO/COR of any differing site conditions prior to starting any work.

12. The Supplier shall always provide an English-Speaking working supervisor on-site when work is being performed and for the duration of this project. The project Supervisor must have a minimum of five (5) years of experience as a supervisor on five (5) similar projects.

13. The supplier shall provide his own storage for materials. The VA is not responsible for loss of tools, materials, equipment, etc. The Supplier shall secure the work-area after each working shift.

14. The Supplier shall post visible required warning signs and barriers prior to beginning any work.

15. The Supplier is responsible for any damage caused by his employees. All damages shall be repaired and/or replaced at no additional cost to the government.

16. Supplier shall submit a schedule to VA for approval. The Supplier shall not perform any work without prior coordination with the COR. The supplier shall not interfere with Hospital operations, and if the Supplier becomes aware of any condition which affects Hospital operations, they will immediately notify the COR.

17. The supplier shall perform cleanup at any time when the work area becomes cluttered and/or restricts traffic. The work area must be cleaned at the end of each work shift.

18. All work must be during regular hours. Normal work hours are 8:00AM to 4:30PM Monday through Friday except for Federal Holidays. If the Supplier desires to work on Saturday, Sunday, holidays, or outside the project site’s normal working hours the supplier must submit a written request for approval to the VA-COR at least seven (7) working days prior to the proposed start of such work.

19. The Supplier and their employees shall update the COR daily of activities completed and any issues identified.

20. No work beyond the contract shall be completed without written approval by the Contracting Officer (CO).

21. All work shall be done in accordance with contract drawings and specifications.

22. Supplier shall incorporate all necessary construction phasing and temp power as required to implement the construction, with minimal impact to the medical facility (preferably after hours and/or weekends). The schedule must include a “PHASING PROCESS” to ensure Hospital power and resources are available.

23. The Supplier will provide a Test Procedure for VA review and approval. The Test Procedure should verify normal, emergency, and abnormal operating conditions which may occur during the life of the equipment.

Autodesk Construction Cloud (ACC) Access Requirement

1. Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2 Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative (COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.

1. Contractor shall accomplish and complete the following tasks upon award of contract:

1. Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award.

1. Only staff that shall utilize the platform to be granted access. Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc.

1. The access request shall be in writing and include a list of staff. The list shall include the following information:

· Full Name

· Company Name

· Email Address

· Role/Position on the project (i.e., Project manager, site super)

1. Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days.

1. Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 business days.

1. Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period.

1. Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above.

1. The contractor shall only use the ACC platform for contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration includes but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys.

1. Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertains to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor ability to maintain required utilization of the platform.

1. Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training.

Safety Requirements

1. Supplier is responsible and shall continue management and implementation of a safety and health program throughout duration of the project.

2. The Contracting Officer and VA staff reserve the right to suspend work when patient, staff and supplier's safety and health program is inadequate or non-complying.

3. Supplier shall provide all Personal Protective Equipment for the workers as per the requirement of the site. Work will be stopped in case the proper protection equipment is not found with the workers and the lapse of time shall be at the Supplier’s expense.

4. All work must be in compliance with OSHA safety standards and NFPA Electrical work requirements. The supplier shall also be familiar with working on all applicable electrical equipment.

Supervision Requirements To ensure that this Project is successfully completed in a timely manner and to the satisfaction of the VA, project management items include but are not limited to the following:

1. Kickoff Meeting: The Project Manager (PM) and/or Technical Lead shall attend a kickoff meeting with the COR to define the goals of the project including expectation, schedule, communication, etc.

2. Monthly Project Progress Summary/Schedule Update: Provide written project status updates. These short memo type updates should include percent complete for each task; key task activities performed over the period; budget, scope, or scheduling issues; key activities to be performed over the next period and upcoming milestone dates. Invoices for the period covered in the report will not be paid until the monthly progress update is delivered to and approved by the VA.

3. Invoicing: A summary of work performed during the invoice period shall be provided with each invoice.

4. The Supervisor and/or Technical Lead shall hold biweekly progress meetings or calls with the VA to provide updates on overall project status and review on- going critical needs or action items.

5. The Supervisor and/or Technical Lead shall maintain an action item log (ON-SITE) with daily updates of work completed. This will be available to VA personnel to review at any time.

Period of Performance The supplier is expected to complete all work in 180 days after receipt of all materials. This should allow for scheduling with VA Hospital operations.

Place of Performance / Delivery All required equipment and materials are to be delivered to the warehouse/loading dock at the following location:

James J. Peters VA Medical Center the Bronx, NY All work is to be performed at the above address as well.

Inspection and Acceptance Procedure

1. The Supplier will provide a Test Procedure for VA review and approval.

2. The VA COR/POC shall inspect all work prior to demobilization of the supplier. The supplier shall illustrate to the VA COR/POC the specific work that was performed and demonstrate that the system is in operational order.

3. The Supplier must test all equipment as per VA and Electrical Codes.

4. Supplier to follow all phasing plan.

5. All repairs, testing, and calibration shall be performed as per manufacturer’s recommendations and/or common industry practice. Calibration equipment shall be in compliance with NFPA and/or the manufacturer's requirements.

6. The Supplier shall “SET” each circuit breakers trip-settings (Long-Time Pickup, Long-Time Delay, Short-Time Pick-up, Short-Time Delay, Instantaneous Pick-up, and Ground Fault Pick-up and Ground Fault Delay) at the Trip Settings provided by the VA.

7. The Supplier shall test the functionality of the equipment upon completion of the project. This shall include testing of all trip functions. Supplier shall ensure all functions are operational including normal and emergency power conditions including power transfers as applicable.

8. The COR/POC will perform the inspection in the presence of the supplier personnel, prior to the supplier personnel leaving the facility. No invoices will be processed for payment prior to the completion of POC inspection.

Drawings and Other Attachments For illustrative purposes, MSS1 and MSS2 are shown below. All field data must be confirmed prior to submitting a proposal.

Government Furnished Property Supplier will be responsible for the proper disposition and/or disposal of all replaced equipment.

Applicable Codes and Standards All work Under this scope shall be completed in accordance with the latest edition of the noted codes and standards below.

1. NATIONAL ELECTRIC CODE (NEC)

2. NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

3. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

4. INSTITUTE OF ELECTRICAL AND ELECTRONIC ENGINEERS (IEEE)

5. INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)

6. AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

7. OSHA PART 191 O; SUBPART S, 191 0.308

8. VA SPECIFICATIONS

9. VA ELECTRICAL DESIGN MANUAL

10. VA PHYSICAL SECURITY AND RESILENCY DESIGN MANUAL

11. NFPA 101

12. OSHA STANDARDS

13. VA DIRECTIVE 1028

14. NFPA 70E

Warranty The supplier shall guarantee that all work performed will be free from all defects in workmanship and materials and that all installation will provide the capacities and characteristics specified. The contract further guarantees that if, for a period of one year from the date of the certificate of completion and acceptance of the work, any such defects will be repaired by the supplier at his own cost.

Project Number 526-23-110 Electrical Switchgear Replacement Phase 1 at the James J. Peters VAMC

BID PRICING SHEET

Bids providing less that 120 Calendar Days of Government Acceptance after the date bids are due will not be considered and will be rejected.

The bidder agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation if this bid is accepted by the Government in writing within 120 calendar days after the date bidders are due.

Base Bid (Item #1) General Construction - Contractor shall furnish labor and materials to perform work for Electrical Switchgear Replacement Phase 1 as required by the statement of work and specifications.

The scope of work shall generally consist of, but not limited to the following:

Contractor shall furnish all labor and materials and perform all work associated with the Electrical Switchgear Replacement Phase 1 statement of work.

This project is to upgrade the two (2) groups of electrical power circuit breakers (substations MSS1 and MSS2) to new equipment, while maintaining the existing equipment structure; and providing for minimal outages during the transition to the new circuit breakers. The expectation is that the direct replacement circuit breakers will be designed to be inserted into the existing electrical structures, therefore minimizing the outage time to the time required to replace a circuit breaker.

The period of performance for Base Bid (Item 1) construction will be 180 calendar days from Notice to Proceed (NTP)

BASE BID $ ______________________

Alternate Bid

The proposal shall include an option to replace the Tie Breaker, currently a Federal Pacific FD75, 3000 ampere circuit breaker or equivalent. It is expected that a “direct rack-in replacement circuit breaker” might not be available for the Tie-Breaker location and this would require alternations to the existing internal switchgear bus-work, therefore also requiring a major power outage of both sides of the Switchgear.

Alternate BID $ ______________________

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://sam.gov/ in electronic format only by searching for solicitation number 36C24224B0031. All interested parties (subs & primes) should register at https://sam.gov/ as an “Interested Vendor” so that others will know of our interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at https://sam.gov/ Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: : The Contractor shall furnish all necessary professional Construction services to provide complete scope of work for Project # 526-23-110 Electrical Switchgear Replacement Phase 1 in accordance to the project Statement of Work and specifications for the James J. Peters VA Medical Center in Bronx, New York.

Magnitude of Construction: $2,000,000.00 and $5,000,000.00

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm -fixed price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
22.6 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Daniel Barone Contracting Officer Hand-Carried Address:

Department of Veterans Affairs Franklin D. Roosevelt VA Medical Center Network Acquisition & Logistics(10N2NCO) 2094 Albany Post Road Montrose NY 10548-1454 Mailing Address:

Department of Veterans Affairs Franklin D. Roosevelt VA Medical Center Network Contracting Office 3 (10N2NCO) 2094 Albany Post Road, Bldg. 29 Room 310 Montrose NY 10548-1454

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— 04/09/2024 at 10AM EST

(c) Participants will meet at— Bronx VAMC Building 100 Engineering dept. GC-100 (End of Provision)

2.7 52.252-1 SOLICITATION PROVISIONS…