This document contains an RFI log and details for a federal solicitation to replace X-ray equipment at the VA Medical Center in Buffalo, New York. Key details include the solicitation number 36C24222B0041 with a proposed posting date of May 15th, 2022 and proposed award date of July 15th, 2022. The project involves demolishing an existing X-ray room and installing new X-ray equipment from Siemens. The RFI log addresses questions from contractors regarding the scope of asbestos abatement, lead shielding requirements, specifications, and coordination with Siemens for equipment installation. Responses clarify responsibilities for removing old equipment, air monitoring, schedules, and other logistical items.

View the file

Other files

File Type Posted
36C24222B0041 0006.docx DOCX document
36C24222B0041 0005.docx DOCX document
S02 Wage Determination - Erie.pdf PDF
36C24222B0041 0004.docx DOCX document
528-19-104 ED DEPT VA BUFFALO Final Bid Submission X-Ray Specifications (1).pdf PDF
Sign-in sheet Walkthrough_2022_07_22_10_51_23_910.pdf PDF
36C24222B0041 0003.docx DOCX document
36C24222B0041 0002.docx DOCX document
P07 Wage Determination.pdf PDF
528-19-104 ED DEPT VA BUFFALO Final Bid Submission X-Ray Drawings.pdf PDF
36C24222B0041 0001.docx DOCX document
36C24222B0041_1.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Log RFI LOG Status Current as of: 02-Aug-2022

VA ProjectArchitect/EngineerConstruction Contractor
Project Number:528-19-104Contract Number:Contract Number:SOLISITATION 36C24222B0041
Project Name:ED X-ray equipmentVendor:ACELAVendor:TBD
Project Engineer:Thomas Heldwein
No Change - Clarification of Existing ScopeAnswered
No Change - Convenience of ContractorNo Action
RFI Rescinded
A/E Contract Change
Construction Contract Change
A/E and Construction Contract Change
RFI IDRFI TopicSubmittalDatesIn Process
(days)StatusRemarks
VA IDA/E IDCont. IDQuestionAnswerResultSubmissionA/E ResponseVA Response
001Project PhotographyWalk-Through: The SOW states that a professional photographer is to hired. Is that required on this project?The purpose of the photography is to document the project and protect both the VA and Contractor. VAMC Buffalo engineering has not received good results from construction contractors and is requiring this in the SOW for all future projects. The Buffalo engineering department has investigated several companies that provide this service and like the following company for ourselves as a cost effective option.
https://www.multivista.com/services/construction-photo-documentation/No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
002Copy of SpecificationsWalk-Through: A copy of the specifications was not in the bid package.The specifications were posted to Betasam along with these RFI answers.No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
003Drawing CorrectionWalk-Through: General question on lead lining in floor and walls.See RFI's 011 and RFI 013 for more detailed answers on lead.No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
004Scope for SiemensWalk-Through: What is the SOW for Siemens under VA contract for X-ray equipment?The Siemens drawings are included in the drawing package AQ 102 to 106. The Siemens construction consultant will visit the site and provide guidance prior to demolition, during construction and when room is considered ready for equipment. Siemens SOW starts at this point to completely install the equipment and test functionality. The Unistrut above the ceiling is to be exposed, walls and floor completed, electrical conduits run, and general cleaning completed. The patient lift and ceiling completion are the only two items that must wait until the equipment is confirmed as functioning properly.No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
005Disposal of Existing EquipmentWalk-Through: Who takes care of the existing X-ray equipment? How?Old equipment disposal is part of the SOW. The equipment should be recycled as much as possible for metal scrap.No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
006Asbestos AbatementWalk-Through: What method of abatement is expected, chemical or mechanical for the floor mastic?The drawings, containment, and air monitoring were all designed for mechanical removal of mastic and wiring whips.No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
007AC UnitWalk-Through: There is a water fed AC unit in the North-West corner of the room. Is abatement and new flooring under the unit?The Contractor is to shutdown, remove and reinstall the AC unit. The flooring and walls are to be finished prior to reinstallation. The AC unit to be sent to the 3rd floor of building 20 for as long as needed. The VA will be able to store and service the unit while work is being completed and picked up for reinstallation.No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
008Air MonitoringWalk-Through: What is being done for Air Monitoring?Buffalo VAMC will contract a company to do air monitoring during abatement. The test results are taken in daily and results come back the following day. This contract is not yet awarded.No Change - Clarification of Existing Scope20-Jul-202202-Aug-202213Answered
009AISC CertificationCan the VA waive the AISC certification in the specifications, since it is waived on 90% of all projects in the area.Should the Contractor engage a Non-AISC certified fabricator, a special inspector will be hired by the Contractor to provide confirmation of the steel fabrication. This will provide some level of protect for both the Contractor and VA from substandard work.No Change - Clarification of Existing Scope21-Jul-202202-Aug-202212Answered
010ScheduleWill schedule updates be required at progress meetings, with invoices and monthly?After the initial construction schedule is submitted and approved prior to the construction kick-off meeting, at a minimum, the updated schedule will be provided to the COR and CO at time of invoicing. This should show progress, completions, and any changes to keep the completion date.No Change - Clarification of Existing Scope23-Jul-202202-Aug-202210Answered
011Lead ShieldingGC 102 shows several details where lead shielding is to be installed, can the VA please confirm locations where these details apply?The room is currently fully lead lined. The window must be accessed for negative air, which will breach the lead in that wall. The repair to that wall will need to follow the INFILL OPENING detail. Where new conduit pipe breaches a wall or floor the PIPE PENETRATION detail and the PIPE FLOOR PENETRATION detail would be used. The other details are for reference in the case that damage to the existing wall or conduits is inadvertently made for proper repair.No Change - Clarification of Existing Scope27-Jul-202202-Aug-20226Answered
012Patient LiftWhat is existing patient lift manufacturer?The patient lift is a Go Lift by Amico.No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
013Floor Lead LiningAre lead lined flooring transitions required (AE101 1st floor new work plan keynote 7), even though (GC102 Lead detail – Floor) it says no lead expected / required for floor shielding?There is no lead expected or required for this room. If lead in the floor is found during abatement of the asbestos mastic, then a change order would be required for unknown conditions.No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
014Wall ColorDrawing AI101 Wall finish note 1 calls for all walls to be painted P-1, but keynote 2 calls for all walls to be painted P-2. Which is right?Wall finish note is technically correct, as the walls are noted to be painted using P-2 and WALL FINISH PLAN (view 2) show the areas to be P-3 and WP-1.No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
015ICRA sub-basementSpace below work area will need to be accessed. What is ICRA level of this space?The spaces below are cleaning staff areas consisting of a small storage room and large floor ceiling equipment room.No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
016Ceilings in sub-basementAre there any hard ceilings below work area?No hard ceilings below the X-ray room in the sub-basement. The ceilings are drop tiles in grid.No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
017SpecificationsWill there be a specification for this project?Repeated question (see RFI 002).No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
018Existing EquipmentWill existing X-Ray unit and devices be turned over once removed?The existing X-ray equipment is not part of Siemens scope (see RFI 004 & RFI 005).No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
019New EquipmentWill new X-Ray Unit have to be brought in through loading dock and up elevators or can another entrance on the 1st floor be used?This is in Siemens SOW (see RFI 004). Disposal of existing is contract SOW (see RFI 005).No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
020DumpsterWhere can a dumpster be placed?A dumpster location will be confirmed at the Construction Kick Off meeting. The COR will designate a location on site as close to the loading dock as possible.No Change - Clarification of Existing Scope13-Jul-202202-Aug-202220Answered
021Off-hours WorkIs any of the work to be performed off hours?There is no requirement for off-hours work. Contractor may do off-hours work after confirming with the COR (reference to RFI 010).No Change - Convenience of Contractor13-Jul-202202-Aug-202220Answered
0
0
0
0
0
0
0
0
0
0
0
0
0

Filtered List

Submittal ID
ERROR:#REF!
TypeDescriptionMakeStatusReason
Letter of Affidavit of Compliance
Shop Drawings
Data Sheets
Brochure
Physical Sample
Manufactures Literature or Catalog Cuts
Test Reports
Other
Approved
Approved as Noted
Revise and Resubmit
Rejected, Resubmit
No Action
No Action, Resubmit

Header

2271442161515168220151516822015
SUBMITTAL LOGVA ProjectArchitect/EngineerConstruction Contractor
Project Number:Contract Number:Contract Number:
Project Name:Vendor:Vendor:
VAMC Project Engineer:Bryan SilverblattVAMC Contracting Specialist:VAMC Contracting Specialist: