S06 - PreBid RFI Log Response to Contractors.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Z1DA--528A6-17-627 UPGRADE VENTILATION B76 Federal contract opportunity
Solicitation number
36C24220B0064
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

This document contains a pre-solicitation notice and federal contract opportunity related to upgrading the ventilation system in Building 76 at the Bath VA Medical Center. The pre-solicitation notice informs that the VA will be posting a solicitation on or about October 7, 2020 for project number 528A6-17-627. The general scope of work is to install a new central air distribution system on the 4th and part of the 5th floors, construct a chaseway for future ductwork, and connect certain piping systems. This is a 100% SDVOSB set-aside with a NAICS code of 238220 and an estimated value between $1-5 million. The solicitation will provide site visit details. A 20% bid bond and performance/payment bonds will be required. The federal contract opportunity restates much of this information and provides the solicitation number 36C24220B0064.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--528A6-17-627 UPGRADE VENTILATION B76, newest first.
File Type Posted
36C24220B0064 0004.docx DOCX document
20201130 PreBid RFI Log Response to Contractors Updated.xlsx XLSX spreadsheet
36C24220B0064 0003.docx DOCX document
528A6-19-614 Upgrade Ventilation B76 Revised Specifications.pdf PDF
528A6-19-614 Upgrade Ventilation B76 Drawings - Revised.zip ZIP file
S06 - 9550-A VA Bath Healthcare Center Additional Limited ACM Survey Revised 6-10-2020_opt.pdf PDF
36C24220B0064 0002.docx DOCX document
S04 - Pre-Bid Attendance Sheet.pdf PDF
36C24220B0064 0001.docx DOCX document
36C24220B0064_1.docx DOCX document
S02 - 528A6-19-614 Upgrade Ventilation B76 Specifications.pdf PDF
S02 - 528A6-19-614 Upgrade Ventilation B76 Drawings.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 RFI Log-Project No 528A6-17-627, Upgrade Ventilation B-76 Date: 23 Nov 2020

RFI#Date SubmittedDescription of RFIResponsibilityResponseStatus
110/22/20Per our conversation , please note teat the specifications appear to be missing the specific divisional table of contents. Please provide update as your schedule allows.WatsonConcur-this is complete and will be provided with updated spec-book.Answered/Additional Information Forthcoming
2a11/2/20What is the scope of work for the ceiling mastic that is on the 4th floor plaster ceiling above the drop ceiling? do we remove all of it , or only what is necessary for the other trades to do their work ? there is no note on the drawings indicating we do anything with itC&SCeiling demolition shall follow description on mechanical demo drawings. Also see Asbestos Abatement specification. "Brown ceiling glue dots" have been identified as asbestos to be abated. Approximate quantities are indicated.Answered/RFI Closed
2b11/2/20On drawing H-105 it calls for removal of the black duct wrap, it appears this was previously removed as during the pre bid walk thru we could not find it, Please confirm if it is there and it's locations.ECSPlease ensure close review of specification 02 82 11 and the ECS asbestos survey report dated 4 June 2020. In the ECS Report 9550-A, we have included edits to provided drawings indicating a broad extent of where materials were found in the survey. These areas are not all inclusive and materials could be found outside of these areas. The black duct wrap is marked on Drawing M-102/M-106/M-107 in Appendix II drawings. There are several areas with black HVAC duct wrap (room 434 air handler, 6th floor). Appendix III, photos 2 & 3 (black tar coating/black duct wrap) shows the exact material we are referencing.Answered/RFI Closed
3a11/2/20There’s new windows called out on MD101 KN#2? Could you please provide specs for those?Watson/VA/C&STo clarify, the windows called out shall have the existing window AC units removed and demolished, insulating panel with cut-out for AC unit removed and demolished, and new glazing installed to match existing. Only new glazing will for these windows will be required under this project. Additional details, to include spec 08 80 00 shall follow.Answered/Additional Information Forthcoming
3b11/2/20Also, the “windows” more like skylights on AD-107…are there photos of the existing so we have a plan of attack for the removal? Who is the roofing warranty with?C&S/VAThe windows are vertical, located in roof dormers, not skylights. See typical dormer louver infill elevation A2/A-108. See photo at link. https://drive.google.com/file/d/18GNSKf_wcLTHzUUC6dnkokvKK97BVJFa/view?usp=sharing
The existing roof is slate, constructed in 1938. There is no existing warranty.Answered/RFI Closed
4a11/3/20During the site visit meeting, it was observed that between the ACT ceiling, and existing secondary ceiling, down the corridors and in the rooms on the forth and fifth floors, that a significant amount of conduits, pipes, cables, Unistrut, all-thread supports and more are present. It was mentioned that the intent is re-locate all existing items as needed to run the new ductwork and new piping as required. Please advise if there are any As-built drawings and if any information that can be provided to quantify the amount of items to be relocated.WatsonNo as-built drawings are available that detail above ceiling equipment and are impossible to be created until the ceiling is removed. Please refer to mechanical demolition notes #1 and #2, which describes exactly the scope of work as it applies to above ceiling work and see drawings for extent of demolition work.Answered/RFI Closed
4b11/3/20Demolition Note# 4 on the “MD” drawings indicate that a full set of coordinated shop drawings will be required for all work above the existing ceilings. Please advise if a list describing the existing elements/trades will be provided to the contractor (i.e. Fire Suppression, Fire Alarm Electrical, Plumbing, Comm, etc.). If As-Built drawings and quantities of existing items to be relocated cannot be determined, please advise if approximate quantities for each element/trade will be provided for fair bidding purposes.WatsonA full set of coordinated shop drawings (in CAD) shall be provided per note #4 on MD drawings. Trades shall include HVAC ductwork, HVAC piping, plumbing (including MEDGAS), electrical (including fire alarm and telecom), sprinkler, and structural steel. Also see specification 01 33 23, technical definition of coordination drawings on specification 01 91 00, specification 22 05 11 section 1.4I, specification 23 05 11 section 1.4H and notes #3, #4, and #10 on drawing M001 for additional details and requirements.Answered/RFI Closed
4c11/3/20During the site visit, it was noted that there is an existing secondary drop ceiling above the ACT. This secondary ceiling tile removal/abatement and associated materials is indicated to be removed per Specification Section 02 82 11 / 1.1.2 Extent of Work. The drawings do not appear to delineate this work. Please advise if the scope of work in the specifications for the ceiling removal will be illustrated on the drawings.ECS/C&Ssee response to RFI 2aAnswered/RFI Closed
4d11/3/20Drawing Sheet# M-302 / Detail C6 indicates to extend 3” piping and run 6” piping alongside the building. Please advise if a detail illustrating the preferred piping support method alongside the building will be provided.WatsonDetail and additional information shall follow. Also see specification 23 05 11, secton 3.5.Answered/Additional Information Forthcoming
4e11/3/20Drawing Sheet# M-302 / Detail C6 indicates to run 3” piping to connection points in the basement. Please advise if a drawing will be provided to show the desired connection locations in the basement, connection details, etc.WatsonSee partial plan C9/MP-102. This is mislabeled as demolition work and will be updated.Answered/RFI Closed
4f11/3/20Please advise the facility’s existing Fire Alarm contractor.VAFire Alarm Contractor is Johnson ControlsAnswered/RFI Closed
4g11/3/20The drawings indicate they are 100% submission drawings, but are not stamped by a PE. Please advise if the provided drawings without a PE stamp will be those used for bidding and construction.WatsonA final set of drawings, addressing these RFIs as appropriate, that shall be issued for final bidding and construction.Answered/RFI Closed
5a11/3/20Also, if you can tell us if the glazing would be able to be done from the inside as apposed to from the outside with a crane, that would be helpful.C&SBased on our field investigation, all windows appear to be interior glazed (i.e. accessible from inside). We are in the process of determining if any windows exist where this is not the case and if any exterior glazed windows exist, those will be called out on drawings. For bidding purposes, all windows should be assumed to be interior glazed.Answered/Additional Information Forthcoming
6a11/10/20Major equipment like Air Handling Unit, Coils including filters: basis of design (BOD)/ manufacturer are not specified. Is TRANE providing the AHUs as BOD/ manufacturer?WatsonPlease use TRANE as BOD.Answered/RFI Closed
6b11/10/20Please provide us drawing detail assembly for major equipment aside from schematic diagrams and points list.WatsonAn updated BOD selection from TRANE shall be shared as part of the bid package.Answered/Additional Information Forthcoming
7a11/11/20As for concern#2, I/we were able to solve this issue except for a verification on symbols or tags V-1, V-2, V-3, V-4, V-5, V-7, V-8, V-9 in drawing MP104 and MP105. These symbols appears to be butterfly valves, no V-6 found. For your information only.WatsonAcknowledged and yes, butterfly valves.Answered/RFI Closed
8a11/12/20Our main concern is the access to B-76 for demo of Air Handler Units; one on 6th Floor and two in Attic; for new AHU, we will install one on 6th Floor and one in Attic. If access will be via elevators, please specify location in the drawings (w/ size and height).Watson/VAService elevators available for use per proper coordination and approval by VA. Elevator service available up to 6th floor only, then stairs (single flight) required for access into attic. Contractor responsible for field verifying and determining means/methods for transporting equipment into/out of renovation spaces. Also please note: Elevators are shown on Drawing MP102. They are directly across from the center stairwell. Each car is 88-1/2"H X 85"L X 54"W.Answered/RFI Closed
8b11/12/20I/we would like to request information of the existing expansion tank (tagged ET-3); manufacturer/brand, physical & working condition (w/ photo if available).Watson/VAET-3 is shown drawing MP104 and is scheduled on M601. This expansion tank is existing and needs to be re-located to where indicated. Please note that chilled water system is 40% ethylene glycol and glycol used to fill system shall be Dynalene.Answered/RFI Closed
911/12/20See attachedWatson1) see ans to RFI 7a above; 2) concur, sheet labeling will be adjusted; 3) concur, pipe sizes to be provided. See answer to RFI 8b regarding expansion tank.Answered/Additional Information Forthcoming
1011/12/20This is duplicated from RFI 9 - same attachmentWatsonsee answer to RFI 9 aboveAnswered/RFI Closed
1111/12/20This is duplicated from RFI 9 - same attachmentWatsonsee answer to RFI 9 aboveAnswered/RFI Closed
1211/12/20Will you able to provide standard detail drawings of the equipment (AHU and Heat & Cooling Coil, Heat Exchanger Skid and VAV Terminal) for this project?Watsonsee answer to RFI 17 belowAnswered/RFI Closed
1311/12/20This is duplicated from RFI 9 - same attachmentWatsonsee answer to RFI 9Answered/RFI Closed
14a11/12/20Is project tax exempt?VAProject is tax exempt.Answered/RFI Closed
14b11/12/20Can superintendent also be the SSHO?VASee answer to RFI 14dAnswered/RFI Closed
14c11/12/20Can superintendent also be the QA/QC?VASee answer to RFI 14dAnswered/RFI Closed
14d11/12/20Can superintendent also be the SSHO & QA/QC?VAFor this size of project, the superintendent May be both SSHO ( assuming that this stands for Site Safety and Health Officer) as well as the QA/QC officer.Answered/RFI Closed
14e11/12/20Provide location of project trailer lay-down area and size to be allocated.

- Provide specification of site fencing to be utilized

- Is screening required?VALay down area is across the gate and the railroad tracks. It is a very large area and will accommodate as much lay down material as you want. As it is already gated, fencing will not be required.Answered/RFI Closed
14f11/12/20What is existing thickness of existing concrete slab(s) to be removed?C&SGC responsible to Field verify all existing conditions. Existing drawings indicate 2" thick slabs in scope areas. See detail C6/S-501.Answered/RFI Closed
14g11/12/20What is thickness of concrete pan joist of floor slab? Overall depth and thicknessC&SGC responsible to Field verify all existing conditions. Existing drawings indicate 6" and 8" additional thickness below bottom of slab field condition appears to correspond. See detail C6/S-501.Answered/RFI Closed
14h11/12/20Confirm that existing concrete does not contain ACM materialsECSWe did not sample concrete since this would have been a destructive activity. Additionally, NY Code 56-5.1 f (1 does not list concrete as a suspect ACM).Answered/RFI Closed
14i11/12/20Will pre / post tension cables be cut during the demolition process of slabs?C&SNone known to exist. Existing drawings indicate only rebar.Answered/RFI Closed
14j11/12/20Provide details for support of AHU as called out, E7/S-103. Provide information of existing bearing spreader channels

- What is existing steel size for drilling?

- Can holes be burned?

- What is anchor specification?C&SSee A6/S-501, Existing is a C6, web bearing on the floor per details. Anchor unit as normal per unit mfgr specs to floor if required, just install any anchors through channel web to the floor. Careful hole burning could be used offsite but is not permitted inside the building. New C6 option noted on details if salvage is not fabricator preference. No additional detailing required.Answered/RFI Closed
14k11/12/20Sheet S-104, detail E3 calls out section F9/S-501. Is this to be F6-S-501?C&SYes, detail box for F6 also includes area of F9Answered/RFI Closed
14l11/12/20Sheet S-501; Detail F4: what is floor to floor heights?C&SBuilding floor ot floor height is 12'-0" (typ.). Field verify.Answered/RFI Closed
14m11/12/20Provide specific architectural finishes for all locations undergoing abatement or new finishesC&SNew finishes are to match existing unless specifically noted otherwise. See specifications for painting and acoustic ceilings.Answered/RFI Closed
14n11/12/20Provide schedule of finishesC&SNew finishes are to match existing unless specifically noted otherwise. See specifications for painting and acoustic ceilings.Answered/RFI Closed
14o11/12/20Provide missing finishes for millwork sheet A-105C&SModifications to the existing casework on A-105 are to match existing construction and finishes. GC to verify in field.Answered/RFI Closed
14p11/12/20Provide specific replacement glass details and requirement for new glass window composition. Total overall glass window thickness. Refer to note 1 / MD 101 and note 2 / MD 101, sheet MD 102 / MD 103C&SSee answer to RFI 3aAnswered/RFI Closed
14q11/12/20Detail C1/A-106; What is wood sill specification / detailC&S1x pressure treated wood sill, painted.Answered/RFI Closed
14r11/12/20Louver details / masonry wall construction. Provide overall masonry wall thickness
- Provide facebrick specification / manufacturer. Pricing varies based on specificationC&SSee Unit Masonry specification. Face brick is to match existing. At new louver locations the existing drawings indicate multi-wythe masonry, approximately 18 inches overall thickness. GC to verify in the field.Answered/RFI Closed
14s11/12/20Reflected ceiling plans

- Plans call out all ceilings being darker. Are all ceilings to be replaced?

- Confirm no ceiling work sheet A-110. Nothing called out

- A-111. Provide ceiling soffit details for repairs. Finishes?C&SOn drawings A-109, A-110 and A-111 (Fourth & Fifth Floor Reflected Ceilings) the shaded areas are ceilings to be removed and replaced. Non-shaded areas are existing ceilings to remain. Drawing A-110 shows new ceilings. A2/A-111 calls for the cutting and patching of an existing painted soffit. Patching is to match existing soffit construction and finish, GC to verify in field.Answered/RFI Closed
14t11/12/20Provide details / wall section for clarification of note 2 / MH 101. Sizes, details and specifications required.C&SSee answer to RFI 3aAnswered/RFI Closed
14u11/12/20Who is EMS and controls vendor for HVAC equipment?Watson/VABuilding automation and temperature controls is TRANE. We are not sure what is meant by "EMS." Once clarified, we will gladly respond.Answered/RFI Closed
1511/13/20Clarify extent of sprinkler work and provide specification.WatsonSprinkler work is limited to relocating existing sprinkler pipe in order to allow for trade coordination above ceiling. See answers to RFIs #4a & #4b above.Answered/RFI Closed
1611/13/20This is duplicated from RFI 9 - same attachmentWatsonsee answer to RFI 9 aboveAnswered/RFI Closed
1711/13/201) Can you please issue the following details for hydronic piping systems, as none were issues with the bid documents: a) air terminal unit piping final connection detail; b) Air Handling Unit Hot and Cold Water coil connection details; c) Steam Heat Exchanger water and steam side final connection details; d) In line pump and vertical in line pump final connection details 2) Is the chilled water system able to be shut down and drained for the new chilled water connection tie-in? Or will a hot tap be required on the new system? 3) Are the steam and condensate line tie-in locations for the HX-1 on drawing MP-105 located in the attic space or the floor below?Watson1) concur, will provide requested VA standard details; 2) yes, however coordination and approval required by VA; 3) they are located in attic spaceAnswered/Additional Information Forthcoming
1811/16/20Repeat RFI-see RFI 17 aboveWatsonsee answer to RFI 17Answered/RFI Closed
1911/16/20Can you please provide the size of the existing chilled water line size located in the basement/crawlspace that were are to tie into this project?Watsonsee answer to RFI 9Answered/RFI Closed
2011/18/20The Hazardous Materials Abatement drawings show the areas of work and the materials requiring abatement in those areas. Specification Section 028211 includes quantities of building materials that were sampled and are trace for asbestos. As an example: Specification for the 4th floor list 9,730 SF of plaster ceiling (surface material and skim coat), 30,000 SF of ceiling glue dots above drop ceiling, 200 SF of grout associated with ceramic flooring and 500 SF of grout associated with ceramic walls. The ceiling materials are not shown for removal on the Hazardous Materials drawings. The ceramic floor grout is shown for removal on the hazardous materials drawings but the ceramic walls are not.The only other material listed as trace for asbestos is the black tar coating on fiberglass duct insulation. Typically, trace materials (<1% asbestos) are not considered as asbestos containing and do not fall under the regulations for asbestos abatement.Should the bidder follow the scope on the drawings or the specification? Please clarify.ECSsee note #2 on H-drawings, which shall be followed for both bidding purposes and construction.Answered/RFI Closed
2111/18/20The dimensions shown in the air handling unit schedule for AHU-4 and AHU-5-N do not appear to be complete, the length of each unit is shown as 8”. The dimensions shown in the schedule do not match the dimensions of the AHUs shown on the floor plans. Will you please confirm the desired dimensions (LxWxH) of the AHUs?Watsonyes, see answer to RFI 6b aboveAnswered/RFI Closed