STATEMENT OF ITEMS
A. ITEM I, GENERAL CONSTRUCTION: Work includes but is not limited the necessary supervision, labor, equipment, material, and plant required to complete work for the Parking Garage (Project#650- 336), in accordance with the Contract Documents. Construct New Clinical Services Building (CSB): Manchester VA Medical Center, Manchester, NH: Work includes the construction of a new 16,000sf Clinical Services Building (CSB) that will be attached to the Main Medical Center (Building #1). Included in the construction of the new CSB shall be the demolition of the following structures; 3, 4, 13 and 14.
TOTAL LUMP SUM ITEM 1: $___________________________
B. DEDUCT ALTERNATE 1:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Description: Remove Metal Roof Screen -Removed metal roof screen around mechanical system at roof level, including structural support steel.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 1: ($_____________________)
C. DEDUCT ALTERNATE 2:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Exposed Fastener Corrugated Metal Panel ILO Vert. & Hor. Metal Panel
- Description: Replace vertical and horizontal box ribbed metal panel systems with exposed fastener corrugated metal panel; maintain panel orientation and 6” trim detail.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 2: ($_____________________)
D. DEDUCT ALTERNATE 3:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
4’-0” High Ceramic Wall Tile ILO 8’-0” High at Bathroom Walls
- Description: Stop ceramic wall tile at 4’-0” AFF. Provide Painted GWB above tile. Coordinate location of wall mounted equipment and furniture including, but not limited to; mirrors, soap/hand wash dispensers, and paper towel dispensers. Properly prepare a flat and smooth surface for item installation.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 3: ($_____________________)
E. DEDUCT ALTERNATE 4:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Systems Furniture ILO Built-in Casework at Nurse’s Stations
- Description: Replace all casework at Nurse / Communication Station (012) and Reception / Check-in (003) with system furniture provided by Owner.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 4: ($_____________________)
F. DEDUCT ALTERNATE 5:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Deduct Roof Access Structure
- Description: Stair A (S101) to end at First Floor landing and provide roof access hatch within stair well. Along with roof hatch, provide metal ships ladder that spans from stair landing at First Floor to roof hatch.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 5: ($_____________________)
F. DEDUCT ALTERNATE 6:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Remove Spray Insulation
- Description: Replace 1” spray insulation in wall cavity with fiberglass batt insulation throughout.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 6: ($_____________________)
F. DEDUCT ALTERNATE 7:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Traditional Form CIP Concrete ILO Horizontal Wood Mold Form Liners
- Description: Remove horizontal wood mold form liners from cast-in-place concrete forms along column lines ‘1’ and ‘D’ and cast concrete into traditional forms.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 7: ($_____________________)
F. DEDUCT ALTERNATE 8:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Remove Luminous Sky-Image Ceilings
- Description: Remove luminous sky-image ceiling panels in Basement Level and associated soffits. Replace with typical acoustical ceiling tile and alternative lighting layout.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 8: ($_____________________)
F. DEDUCT ALTERNATE 9:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Deduct Exterior Path Bollard Lighting
- Description: -remove exterior path bollard lights
TOTAL LUMP SUM OF DEDUCT ALTERNATE 9: ($_____________________)
F. DEDUCT ALTERNATE 10:
This Deduct Alternate shall be removed from the BASE ITEM offer. This deduct alternate includes all work related to the following items in accordance with the contract documents.
Lower End Ceiling Tile ILO Spec’d Ceilings
- Description: Provide a less costly acoustical ceiling tile that meets specifications performance.
TOTAL LUMP SUM OF DEDUCT ALTERNATE 10: ($_____________________)
NOTE: The Government reserves the right to award only Item 1 or Item 1 plus any one, or combination of, or all of the deduct alternates as identified below subject to budgetary restraints. Deduct Alternates are listed in descending order of importance.
***Once technical acceptability has been determined, the intention of the Government is to award the base lump sum item contingent upon funding limitations to the lowest reasonable price. Should all proposals for the base lump sum, item 1, exceed the funding limitations for this project; the Government will evaluate Deduct Alternate items as follows.
DEDUCT ALTERNATES 1-10 WILL BE EVALUATED IN THE FOLLOWING ORDER
Base minus Deduct Alternate 1: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 and 2: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 3: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 4: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 5: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 6: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 7: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 8: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 9: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then…
Base minus Deduct Alternates 1 through 10: Lowest reasonable price within funding limitations will be awarded. If it exceeds funding limitations then the solicitation will be canceled.
COMPLETION TIME FOR ITEMS:
Total contract duration will be 668 calendar days after issuance of Notice to Proceed.