S02_Itemized_Cost_Breakdown.docx

DOCX document 20 KB Posted

Attached to
Construct Clinical Services Bldg. Minor Project# 608-314 VHA1-608-2016-28254
Solicitation number
36C24118R0279
Issued by

About this file

S02 Itemized Cost Breakdown

View the file

Other files

File Type Posted
36C24119C0062-000.docx DOCX document
36C24118R0279-0008000.docx DOCX document
36C24118R0279-0008002.pdf PDF
36C24118R0279-0008001.pdf PDF
36C24118R0279-0007001.pdf PDF
36C24118R0279-0007000.docx DOCX document
36C24118R0279-0006000.docx DOCX document
36C24118R0279-0005002.pdf PDF
36C24118R0279-0005000.docx DOCX document
36C24118R0279-0005001.docx DOCX document
36C24118R0279-0004000.docx DOCX document
36C24118R0279-0003000.docx DOCX document
36C24118R0279-0002002.pdf PDF
36C24118R0279-0002001.pdf PDF
36C24118R0279-0002000.docx DOCX document
S02_FINAL_CONSTRUCTION_DOCUMENTS_DRAWING_SET.pdf PDF
S02_P07_NH190021_1.25.2019_NH21.pdf PDF
S02_LOCATION_CSB_WALK_THROUGH.pdf PDF
S02_P09_Statement_of_Items.docx DOCX document
S02_PRE-AWARD_CONTRACTOR_EVALUATION_FORM.docx DOCX document
S02_Manchester_Parking_Lots.pdf PDF
S02_SUBCONTRACTOR_INFORMATION_AND_CONSENT_FORM.docx DOCX document
S02_FINAL_SPECIFICATIONS_BOOKLET.pdf PDF
S02_FINAL_GEOTECH_REPORT.pdf PDF
S02_Past_Performance_Sheet_for_Contractors.docx DOCX document
S02_P09_Pre-Award_Contractor_Eval_Safety_Form.docx DOCX document
S02_Self_Performed_Calculation_Form.docx DOCX document
S02_IL_049-06-04_JOINT_VENTURES.pdf PDF
S02_FINAL_HAZMAT_INSPECTION_REPORT.pdf PDF
36C24118R0279-100.docx DOCX document
36C24118R0279-005.docx DOCX document
36C24118R0279-005.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEMIZED COST BREAKDOWN FOR BASE ITEM

Base Item - Cost Breakdown

Project No.:
631-17-100

Date:

Project Title:
Renovate BLDG 1 Specialty Care Clinics
Project Location:
VAMC Leeds, MA

Offerer Company Name and Address:

Item Description

Labor Cost

Material Cost

Total Cost

Division 1 - General Requirements

Division 2 - Existing Conditions

Division 3 - Concrete

Division 4 - Masonry

Division 5 - Metals

Division 6 - Wood and Plastic

Division 7 - Thermal and Moisture Protection

Division 8 - Doors and Windows

Division 9 - Finishes

Division 10 - Specialties

Division 11 - Equipment

Division 12 - Furnishings

Division 13 - Special Construction

Division 14 - Conveying Equipment

Division 21 - Fire Suppression

Division 22 - Plumbing

Division 23 - Heat, Ventilating, and Air Conditioning

Division 26 - Electrical

Division 27 - Communications

Division 28 - Electronic Safety and Security

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Division 34 - Transportation

Subtotal

Overhead (xx %)

Profit (xx %)

Bond (xx %)

Total Base Offer Cost