36C24118R0279-0005001.docx

DOCX document 20 KB Posted

Attached to
Construct Clinical Services Bldg. Minor Project# 608-314 VHA1-608-2016-28254
Solicitation number
36C24118R0279
Issued by

About this file

36C24118R0279 0005 S05 RFI 1-13.docx

View the file

Other files

File Type Posted
36C24119C0062-000.docx DOCX document
36C24118R0279-0008000.docx DOCX document
36C24118R0279-0008002.pdf PDF
36C24118R0279-0008001.pdf PDF
36C24118R0279-0007001.pdf PDF
36C24118R0279-0007000.docx DOCX document
36C24118R0279-0006000.docx DOCX document
36C24118R0279-0005002.pdf PDF
36C24118R0279-0005000.docx DOCX document
36C24118R0279-0004000.docx DOCX document
36C24118R0279-0003000.docx DOCX document
36C24118R0279-0002002.pdf PDF
36C24118R0279-0002001.pdf PDF
36C24118R0279-0002000.docx DOCX document
S02_FINAL_CONSTRUCTION_DOCUMENTS_DRAWING_SET.pdf PDF
S02_P07_NH190021_1.25.2019_NH21.pdf PDF
S02_LOCATION_CSB_WALK_THROUGH.pdf PDF
S02_P09_Statement_of_Items.docx DOCX document
S02_PRE-AWARD_CONTRACTOR_EVALUATION_FORM.docx DOCX document
S02_Manchester_Parking_Lots.pdf PDF
S02_SUBCONTRACTOR_INFORMATION_AND_CONSENT_FORM.docx DOCX document
S02_FINAL_SPECIFICATIONS_BOOKLET.pdf PDF
S02_FINAL_GEOTECH_REPORT.pdf PDF
S02_Past_Performance_Sheet_for_Contractors.docx DOCX document
S02_P09_Pre-Award_Contractor_Eval_Safety_Form.docx DOCX document
S02_Self_Performed_Calculation_Form.docx DOCX document
S02_Itemized_Cost_Breakdown.docx DOCX document
S02_IL_049-06-04_JOINT_VENTURES.pdf PDF
S02_FINAL_HAZMAT_INSPECTION_REPORT.pdf PDF
36C24118R0279-100.docx DOCX document
36C24118R0279-005.docx DOCX document
36C24118R0279-005.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCT CLINICAL SERVICES BUILDING

PROJECT #608-314

SOLICITATION 36C24118R0279

SUBMITTED RFI QUESTIONS:

Question 1-

Does the Presolicitation posted as solicitation number 36C24118R0279 on FBO contain requirements similar to a existing contract or will this be a new requirement?

This was out as sources sought so that may be the confusion.

If possible, please provide the current contract number.

Solicitation number on FBO is 36C24118R0279

Question 2-

When will this project bid start or construction?

Proposals are due March 14, 2019 @ 4:00pm EST

Question 3-

We are requesting the addition of FAR clause 52.208-9 which adds the Mandatory purchase requirements for AbilityOne products to Solicitation 36C24118R0279.

This is not a contract for supplies or services that fall under FAR 52.208-9. If mandatory source schedule items are identified or that specific contract schedule is in best interest of the overall project then clause will be considered. This is for acquisition of non-commercial Construction services.

Question 4-

We would just like to confirm that this solicitation is Full & Open as stated on page 1 of the solicitation.

Yes, this solicitation is Full & Open competition, prior to publishing it was cleared through SBA/OSDBU.

Question 5-

I was wondering where are the Quantities posted for the Asbestos Abatement, Could you please inform me

Refer to final hazmat inspection report as part of solicitation

Question 6-

RFI: HVAC

1.) Is the Pro-press method of connecting pipe, valves and fittings be an acceptable alternative in specification 23 21 13 Hydronic Piping?

If it is not in the specification it is not allowed.

WBRC A/E 2019-2-27: Section 23 21 13 does not include press type mechanical joints.

2.) Please advise why is gas piping shown on the HVAC drawings and not on the plumbing drawings?

WBRC A/E 2019-2-27: gas piping is intended to be Div 23 Mechanical scope.

3.) Specification section 23 74 13 Packaged, Outdoor, Central Station Air Handling Units, Part 2.1, B-2 (page 6) identifies the rooftop unit to be installed on a roof curb. Furthermore, detail D2 on drawing AS503 identifies a curb beneath the RTU. Does this rooftop unit sit on a curb? If so, please provide a specification for the rooftop unit curb

WBRC A/E 2019-2-27: Intent is roof curb provided by the RTU manufacturer as indicated drawing C6/M-501. Provide double wall insulated roof curb.

4.) Please confirm that specification section 23 09 23 Direct Digital Control System for HVAC, is, in fact is an extension of an existing Johnson Control system.

Yes – DDC must be Johnson Controls Metasys utilizing the existing server WBRC A/E 2019-2-27: Concur.

Question 7-

What edition of NFPA 99: Health Care Facilities Code was used as the basis of design for the medical gas and vacuum systems on the project?

WBRC A/E 2019-2-27: 2015. At the time of design, the 2018 edition was not yet available or applicable. Documents (drawings and specs are dated 2017.11.16). Provide inspection and testing per the most current edition of NFPA 99.

Background:

In the most current editions (2015 & 2018) of NFPA 99, there are many new requirements for inspection and testing of these systems. This may add substantial time and cost to this scope of work.

Previous editions (2012 and prior) did not have these requirements.

Question 8-

Signage:

Please advise below on the following signs on the exterior but no details, specs or sizes.

AS200 – URGENT CARE

AS200 – AMBULANCE

AS201 – VA US Department of Veteran Affairs & Logo Can you please provide additional information on the interior/exterior signage?

WBRC A/E 2019-2-27: Per Section 10 14 00 all signage size, location & quantity to be determined by Creative Signage Systems. Signage to match VAMC Manchester standards.

Question 9-

The Below says Owner Supplied – Owner Installed Equipment, can you please let me know if the Liko Patient Lifts will be solicited in this solicitation?

No – lifts will be purchased through activations funding at a later time

Will the Liko Patient Lifts be solicited at a different timeframe?

Yes or is the Liko Patient Lifts already purchased?

No lifts have not been purchased, the manufacturer looks as if it has changed to Arjo (Maxi Sky 2) https://www.arjo.com/en-us/products/patient-handling/ceiling-lift/maxi-sky-2/

Question 10- Do you have a list of General contractors so we can reach out to bid on the insulation part of the scope of work ?

All interested parties are available on FBO.

Question 11-

Request:

Relative to proposal sub‐factor C, will an offeror that has not constructed medical facilities in the past five years, but does have similar building construction within five years and extensive experience in medical facilities prior to that be considered for award?

To be evaluated as acceptable the offeror must provide a narrative that addresses prior projects that are directly related in scope, complexity, magnitude, and cost to this requirement completed within the past five (5) years.

Question 12- RFI: Tele/Data

1. Should cabling be Plenum or riser rated?

WBRC A/E 2019-3-1: Refer to specifications for requirements of plenum and riser rated cabling. Any site specific telecommunications requirements shall work in concert with the specifications.

2. Should a half-shaded split triangle have 4 Category 6 cables per legend or only where noted on plans with 2V/2D?

WBRC A/E 2019-3-1: Each is to receive 4 cables per the legend. If a device is labeled with more than 4 jacks (i.e. 4V/4D), provide an additional jack to accommodate the need for more than 4 cables.

3. A triangle with a V is to represent video, can you provide cable requirement for each of these locations?

WBRC A/E 2019-3-1: Each is to receive (1) RG-6/U and (1) Cat. 6 cable.

4. Is all voice and data cabling to be Category 6 terminated onto rack mount patch panels in the IT room? Should these panels be dedicated to voice or data, or should all cables terminate onto the same patch panel fields?

WBRC A/E 2019-3-1: All horizontal cabling is to terminate in rack mounted patch panels. Each workstation jack is to receive (4) cables. Each of these (4) cables shall terminate in a separate patch panel. (i.e. The top left jack in each faceplate will terminate in the same patch panel until it is full. The same for the top right jack, and so forth). Cabling from video outlets shall terminate in a separate patch panel.

5. Drawing E-401 depicts 4 data racks, are these to be 2 post open frames with vertical cable management on each side? Please clarify racks required and if vertical cable managers are required is there a desired width or manufacturer and part number?

WBRC A/E 2019-3-1: Racks shown are to be 4-post open frame meeting requirements specified for cable management, size and load capacity in section 271100.

6. Drawing ET100B Note 5 depicts 5 outlet locations with 4v/4d for assumed furniture are you looking for a add/deduct price for these outlet locations? Are we to assume these outlets will remain in the wall or be extended into office furniture?

WBRC A/E 2019-3-1: The tel/data jacks noted are to be provided as the Base Bid. If the deduct alternate is accepted, the cables will be extended and connected to Owner provided systems furniture from this location instead.

7. Drawing ET101A just above comms room 106 there is a half-shaded triangle with an “A” what does the A represent? Will it require something special at this location?

WBRC A/E 2019-3-1: “A” indicates device mounted 3” above counter or backsplash. Refer to mounting heights noted on Sheet E-001.

8. Is it a correct assumption that all telecommunications cabling in the basement and first floors parts A and B will be distributed from Tel/Data Room 145?

WBRC A/E 2019-3-1: Yes.

9. Is there any backbone requirement to Tel/Data Room 145? If so, what is it and where should it originate?

WBRC A/E 2019-3-1: Refer to Sheet E-100 for origination and proposed path. Provide 12 strands of single-mode fiber, and 50-pair Cat. 5e copper backbone cabling. Refer to Detail F8/E-501; revise Tel/Data 25 to Tele/Data 145.

10. Is there a rack elevation for what is to be provided for panels and accessories required at each rack location indicated?

WBRC A/E 2019-3-1: Refer to answers to questions above.

Question 13-

RFI: Site 1/2 Questions 1.) At column line 1 & 2 at the north – north west corner of the new addition – at the triangle section referred to as the connector – we expect a cut to subgrade in ledge, we also see a bottom of footing elevation of 449’8” – what we do not see is a proposed slab elevation in that area. The detail reference SF-501 &SB-301 are not clear and actually confusing. Please advise what the slab is supposed to be in that area?

Becker Structural 3/1/2019 Provide 3” mat slab over vapor barrier at 1’-0” above top of footing.

2.) Also – at this same area – for purposes of bidding – with the existing footing elevation for the existing building that has an existing floor of EL455.00 – what should be planned? This seems to be an unknown without a scope or budget? If in fact the bottom of the new footing is to be placed 5’ below the existing slab, we may be looking at being about 3’ to 4’ below the existing footing. This situation will need a very clear underpin plan with shoring. Seems like an item that needs structural engineer guidance. Please advise.

Becker Structural 3/1/2019 Reference Note 2 as noted on new footings. Top of new footing to match top of existing footing. This will need to be verified in field. This should not create an undermining condition.