36C10F19R0086-0002001.pdf
PDF Posted
- Attached to
- Replace Boiler Plant and Steam Distribution System Federal contract opportunity
- Solicitation number
- 36C10F19R0086
About this file
This sources sought notice requests capability statements from small business contractors for a design-bid-build construction project to replace an existing boiler plant and steam distribution system at a VA medical center located in Pineville, Louisiana. The project scope involves renovating an 8,000 square foot existing boiler plant and constructing a 2,087 square foot addition to house three new boilers, a 400KW emergency generator, electrical and control rooms, and personnel facilities. The estimated budget is between $10-20 million. Responses were requested by October 3, 2019 to be emailed to the specified contracting officer and must include company information, small business certification status, construction experience of similar projects, and a capability statement not exceeding five pages. This notice is issued for market research only and does not constitute a solicitation.
36C10F19R0086 0002 Alexandria Boiler Plant Amendment #2 All RFI Responses 2-3-20.pdf
View the file
Other files for this federal contract opportunity
Show all 50
Replace Boiler Plant and Steam Distribution System has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Harrell Design Group, PC
AMENDMENT #2
February 3, 2020
REPLACE BOILER PLANT & STEAM DISTRIBUTION SYSTEM
ALEXANDRIA VA HEALTH CARE SYSTEM PINEVILLE, LA
VA Project Number 502-14-102V
I. BIDDER COMMENTS / RESPONSES (Refer to separate Bidder Question / Response Sheets).
II. SPECIFICATIONS
1. New Spec Sections
A. 07 11 13 Bituminous Dampproofing
B. 07 13 52 Modified Bituminous Sheet Waterproofing
C. 10 51 13 Metal Lockers
D. Reference Document titled “VHA Boiler Plant and Associated Plant Safety Device Testing
Manual, 5th Edition.”
2. Modified Spec Sections (included in their entirety to reflect Bidder Questions and Responses.
See Bidder Comment / Response Sheets for additional spec modifications).
A. 00 01 10 Table of Contents
B. 00 01 15 List of Drawings
III. DRAWINGS (Refer to attached drawings for clouded changes. See Bidder Comment /
Response Sheets for additional drawing modifications).
1. The following drawings are revised and reissued:
A. GI501:
a. Partition type M clarified direction to grout-fill all cells.
B. AS100:
a. Keynote 02.69 clarified to identify boundary line distinctly from fence.
b. Keynote 32.15 removed--stationary dock lift deleted.
c. Removed solid black hatch to illustrate Fence per Keynote 32.18.
C. AD104:
a. Clarified Keynote 02.64 to identify an estimated replacement quantity, in linear feet.
b. General Sheet Note C expands on notes for palletizing existing roof tile.
c. General Sheet Note B clarifies where existing guy wires attach to adjacent building guy wires will only be disconnected (leaving adjacent building penetrations and antenna supports intact).
D. AE101:
a. Keynote 07.36 expounded to describe roof-to-wall and wall-to-wall expansion joint applications.
b. D1: Deleted note to sand-fill all cells pointing to shaft wall.
c. D1: Corrected note to grout-fill all CMU cells.
E. AE102:
a. Keynote 07.36 expounded to show roof-to-wall and wall-to-wall expansion joint applications.
b. D1: Added louver type Tag 4 where missing.
c. D1: Deleted metal ramp.
F. AE201:
a. Keynote 07.36 expounded to show roof-to-wall and wall-to-wall expansion joint applications.
G. AE501:
a. Keynote 03.03 corrected concrete slab elevation at addition.
b. Keynote 03.12 added clean gravel note.
c. Keynote 03.13 added compacted soil note.
d. Keynote 07.36 expounded to show roof-to-wall and wall-to-wall expansion joint applications.
e. Keynote 07.49 added bituminous damp proofing.
f. Keynote 07.50 added bituminous modified sheet waterproofing.
g. Keynote 07.51 added bituminous mastic sloped downward, away from footing.
h. C2: Shifted furring wall adjacent to shaft wall to align with plans.
i. C2: Amended foundation to slab on grade and added vapor barrier below clean gravel.
j. C1: Added slab on grade and bituminous damp proofing notes.
H. AE601:
a. A5: Door schedule amended to show door gate size cross-referencing D5 / AE601.
I. AF101
a. D1: added Keynote 3.08 resinous to replace previous epoxy material.
J. AF601:
a. A1: Finish legend porcelain tile updated to show tile size per application and resinous flooring added.
b. A2: Room finish schedule rooms with resinous floors updated with corresponding integral base.
c. A2: Room finish schedule room 1A116 room name corrected to Biomed.
d. General sheet note E removed epoxy paint base since utilizing resinous integral base, per revised finish schedule.
K. MS102A:
a. D1: Added adjacent building site context to aid locating Manhole A.
L. PP001:
a. Revised fixture tag P418 to P414 in Plumbing Fixture Schedule.
b. Added P707 to Fixture Schedule.
c. Revised fixture tag P103 to P101 in Fixture Schedule.
d. Revised basis of design toilet model number for P101 from “2257.0001” to
“3641.001.”
e. Revised “14-BFH-1” to “14BFE-1” in Backflow Preventer Schedule.
f. Revised drawing number P001 to PP001.
END OF AMENDMENT #2
36C10F19R0086 Amendment #2
Questions (Q) from prospective offerors and Answers (A) from VA
1. Q. Plan Sheet SF501 is listed on the Title Sheet however not issued. Instead, Sheet
SB501 is issued twice. Please Advise.
A. Plan Sheet SF501 was issued in Amendment #1 dated January 15, 2020 as an additional structural drawing.
2. Q. Reference: Division 01 - General Requirements Specification Section 07 32 13
The above references indicate Clay Tile Roof is part of this project. Plan details indicate that the new roof for the Boiler Building is to be a Standing Seam Metal Roof. Please clarify.
A. Disregard spec section 07 32 13 Clay Roof Tile from: 1) Table of Contents spec section 00 01 00; and 2) spec book. Plan details showing standing seam metal roof are correct—see spec section 07 40 00 Roofing Panels for new standing seam metal roof. Cross-reference question #92.
3. Q. Have you chosen a size for the floor and wall tile for the bathroom and shower yet? Any information on this would be appreciated.
A. Tile sizes are now shown on Amendment 2 revised Room Finish Schedule on Drawing AF601.
4. Q. Please confirm that the only new lightning protection system required is shown on sheet EP103.
A. Yes, this is the only new lightning protection system required.
5. Q. Please provide photos of the marble partition that is called to be reused, shown on sheet AD103 sheet note 02.67
A. See attached RFI 5 Marble Partition images
6. Q. Please provide specifications for BIM modeling as required per the coordination note on sheet GI001”
A. BIM Model not required. Contractor to provide AutoCAD drawings in lieu of BIM.
7. Q. The door schedule on sheet AE601 says “RE:C4/AE602 under the size column for door no’s 1A100.2, 1A100.3, 1A100.4. There is now detail C4 on sheet AE602, please provide the correct detail and page number that references the door sizes for these doors.
A. See Amendment 2 revised Door Schedule on Drawing AE601 which now correctly identifies detail for door size.
8. Q. Please confirm which of the overhead coiling doors will be automatic type openers and which will be manual chain hoist operable
A. All overhead coiling doors on this project are motorized, automatic, per spec section 08 33 00. There are no manual overhead coiling doors.
9. Q. Spec section 10 26 00 for wall protection has been provided, however no locations are shown on the finish schedule. Please clarify if wall protection is required and provide a finish schedule listing the locations.
A. Disregard spec section 10 26 00 Wall and Door Protection from: 1) Table of
Contents spec section 00 01 00; and 2) spec book.
10. Q. Please confirm if it will be the contractor’s responsibility to include the cost of the mobile office as listed on sheet GI701 note 13.04.
A. Confirmed, it is Contractor’s responsibility to include cost of mobile office, as listed on sheet GI701 note 13.04.
11. Q. Will the mobile office listed on sheet listed GI701 note 13.04 require any furnishings to be provided by the contractor? Please provide descriptions of any furnishings that the contractor will be responsible to provide.
A. Refer to spec section 01 00 00 article 1.16 for required furnishings.
12. Q. Please provide specifications for the dock lift required per note 32.15 on sheet
AS100.
A. Per Amendment 02 revised drawing D1/AS100, Disregard note 32.15.
13. Q. Please provide a quantity of damaged wood roof planks that are expected to be replaced per note 2.64 on sheet AD104.
A. Refer to Amendment 02 revised Note 02.64 on drawing AD104 for linear feet of damaged wood planks to be replaced.
14. Q. Please describe how the contractor is to treat the pallets of roof tiles that are to be returned back to the VA per note 2.64 on sheet AD104. Is there a maximum height that they are to be stacked to? preferred size of pallet? Will they require transport by the contractor, or will the VA transport the tiles once they are stacked onsite and turned over the VA?
A. Refer to Amendment 02 revised Note 02.64 on sheet AD104 for added instructions on palletizing existing clay roof tiles and returning to VA.
15. Q. Please provide specifications for the breakroom lockers located in room 1A103.
A. Refer to Amendment 02 added spec section 10 51 13 Metal Lockers. Also, add spec section 10 51 13 to Table of Contents spec section 00 01 10. Cross reference question #105.
16. Q. Please provide specifications for millwork/ casework.
A. Refer to spec section 06 20 00 Finish Carpentry.
17. Q. Who is responsible for any necessary repairs or maintenance of temp boiler #1 for the duration of the project?
A. A. The VA will be responsible for maintenance and repairs of Temporary Boiler #1. Note: this will serve as the redundant boiler for the duration of the project. Boiler #2 will be provided, maintained and repaired by the General Contractor.
18. Q. Please confirm that temp boiler #1 will be repaired and fully operational prior to the beginning of this project.
A. A. The VA anticipates Temporary Boiler #1 will be fully operational prior to construction beginning.
19. Q. Please provide the existing manufacturers’ information including as-builts and weights for Temporary Boiler 1 (VA Provided).
A. A. 99,480 lbs. (Shipping Weight), 132,000 lbs. (Operating Weight).
20. Q. Will the VA supply the Fuel oil needed for the temporary boilers?
A. GC to filter, polish existing fuel into temp tank. VA will provide additional fuel for temporary boilers serving hospital needs. GC to provide fuel for testing and other construction purposes by monitoring fuel consumption by meter.
21. Q. If the contractor is to provide the fuel oil, what is the anticipated usage per month for boiler #1?
A. GC to provide fuel for testing and other construction purposes by monitoring fuel consumption by meter.
22. Q. What is the current steam load capacity per month provided by the current boiler plant?
A. 13,000, to 15,000 lbs. per hour.
23. Q, Will the VA supply the Fuel oil needed for testing and fill-up of the generator?
A. Contractor provides fuel for generator testing and other related construction activities. Contractor to fill tanks at end of testing.
24. Q. Note 4 on sheet MD100A states that the contractor is to test the soil along the existing piping and tank farm and submit a plan for soil remediation. It states that the VA has tested the soil and found no contamination. If hydrocarbons are found and remediation is required, will it be considered a modification to the contract?
A. Yes, a contract modification may be required in the event hydrocarbons are identified.
25. Q. The existing Guy wires appear to be anchored to the adjacent buildings, but the new plan shows the Guy wires anchoring to Building 14. Please describe what repairs/if any are required at the existing Guy wire locations.
A. Guy wires anchored to adjacent buildings are for antennae to remain. These guy wires are existing to remain. See revised note B on Sheet AD104.
26. Q. Sheet ES102 general sheet note D says “add alt 2”. Please clarify.
A. Disregard general note D on ES102. It does not apply.
27. Q. Sheet ES102 sheet note #9 says to eliminate work to power gates under deduct alternate #2. The CLIN schedule does not mention this work in this alternate.
Please clarify if this work is deducted and also the extent of the deduct, IE wire, conduit, breakers etc.
A. All work to provide power to the gates is eliminated under Bid Item 2, Deduct Alternate 1. This includes conduit, wire, circuit breakers and connections to power the gates.
28. Q. Please confirm that liquidated damages will begin to accrue only when the contractor has failed to achieve substantial completion of the work by the date specified in the contract.
A. Correct. Liquidated damages will accrue after the period of performance period, 1095 calendar days after issuance of Notice to Proceed.
29. Q. This is a phased project, please confirm that liquidated damages will not be assessed for the late delivery of an individual phase.
A. Liquidated damages will be for the entirety of the project. Not individual phases.
30. Q. If the contractor proposes an alternative number of calendar days for completion of the project (i.e., 1100 days), please confirm that liquidated damages will not begin to accrue until the expiration of 1200 days, which represents the number of days specified in the solicitation and contract.
A. Proposals submitted with alternate calendar days are not acceptable. Proposal will be considered Non-Responsive.
31. Q. Should the contractor include in its price compensation for security personnel at t the project, after work hours, for the duration of the project. Should the contractor include in its price compensation for security personnel at the project, after work hours, for the duration of the project.
A. The Prime Contractor is responsible for security of the project. If the contractor does not provide onsite security, the VA is not responsible for ensuring the overall security of the project.
32. Q. Should the contractor include in its price compensation for video surveillance of the project site for the duration of the project.
A. Provide video surveillance as required by bid documents, for new construction, per spec 28 23 00. Video surveillance monitoring construction work activities is not required.
33. Q. Is the government expecting the contractor to hire a professional photographer for this project? Can contractor personnel provide the photographic documentation of this project?
A. Provide photographic documentation per 01 00 00 General Conditions articles 1.30 and 1.31.
34. Q. Is the government expecting the contractor to furnish an online domain/web hosting and redundant server to house project related documents, including photographs?
A. Yes, Refer to spec section 01 00 00 article 1.30 & 1.31.
35. Q. Part 1A of the Technical Proposal Criteria, includes a statement “prime contractor only”. Is the government expecting the response to Part 1A to be limited to only the prime contractor’s corporate experience and project? Will the government consider a key subcontractor’s experience in response to this Part?
A. No. Prime Contractor shall demonstrate relevant corporate experience as stated in 1A.
36. Q. What will the contractor do with the Temporary Boiler # 1 following completion;
are we to leave it in place, relocate it somewhere on-site? Please describe and provide location it is to be moved to if required.
A. Temporary Boiler #1 will be left in place by the Contractor upon project completion.
37. Q. Detail D5 on MP403 is missing, please provide.
A. Disregard reference to D5/MP403 on drawing MS101.
38. Q. Sheet MS101 area noted C5/MP405 has keynote 7 (deduct 2). Is this a deduct option as it does not match the location description of the plan note.
A. Disregard Keynote 7/MS101 callout on plan adjacent to reference C5/MP405 between buildings 16 and 45.
39. Q. Can the General Contractor use CPARS in lieu of the Past Performance
Questionnaire included in the solicitation?
A. No.
40. Q. Please provide the current fuel oil vendor and contact information.
A. Lott Oil Company, Inc. Phone # 318-352-2055
41. Q. Please provide the current Fire Alarm System Manufacturer and Vendor information.
A. Refer to Sheet FA001, “ADDRESSABLE FIRE ALARM SYSTEM RISER”, for the manufacturer. The vendor is Concepts Electronic, Inc.; Baton Rouge, LA.
42. Q. Please provide the current water treatment vendor and contact information.
A. Joel Holland
Thorton, Musso & Bellemin Inc.
318-237-6776
Joel@tmbwater.com www.tmbwater.com
43. Q. Will the VA supply the fill-up of fuel oil for the new permanent tanks?
A. GC to filter, polish existing fuel into temp tank. VA will provide additional fuel for temporary boilers serving hospital needs. GC to provide fuel for testing and other construction purposes by monitoring fuel consumption by meter.
mailto:Joel@tmbwater.com mailto:Joel@tmbwater.com http://www.tmbwater.com/ http://www.tmbwater.com/
44. Q. Specification 23 50 1; Specification 23 50 11, page 26, 2.7 Fuel Oil Pumping
Equipment, A. ‘Oil pump and motor assembly shall be factory assembled in an epoxy-enamel coated carbon steel waterproof enclosure with external threaded connections for pump suction and discharge...’
Page 28. F. ‘Pumps, motors, valves, piping and accessories shall be furnished as a factory-built unit. All items of equipment shall be mounted.a steel drip pan base with an area sufficient to extend beyond the limits of all equipment…’. These are conflicting statements. Which is correct?
A. Article 2.7.A applies to the temporary pump skid serving portable boilers. Article
2.7.F. applies to permanent pumps 14-FOPS1. In article 2.7.A, revise “(for below grade installation)” to “(for temporary pump skid serving portable boilers)”. In article 2.7.F, add tag to read “Arrangement (14-FOPS1 Pump Set)”.
45. Q. Drawing MP7.03; Drawing MP7.03 shows the back-pressure regulator appropriately placed in the fuel oil system. There appears to be an additional pressure device with 3-valve bypass at the discharge of the pump set. Please provide clarification as to what this is and its purpose.
A. The indicated valve is a pressure relief bypass.
46. Q. Drawing MP403, D3; Specification 23 50 11; The flash tank detailed on MP403, D3 is not indicated on the Mechanical Schedules.
Additionally, Specification 23 50 11, page 26, 2.6 Flash Tank, C, 7. Condensate Pipe: Provided perforated schedule 80 steel pipe inside tank as shown. No condensate pipe is shown on detail D3, MP403. Does this exist?
A. Correct, there is no flash tank schedule. Provide flash tank in accordance with the dimensions on D3/MP403. Provide perforated condensate inside tank as specified. This pipe is typically available from tank manufacturers and extends approximately half way into the length of the tank.
47. Q. Page "10 of 181" & "Page 80 of 181"; The solicitation states that "Offers are required to submit an original and five (5) copies plus five (5) CDs of the technical evaluation factors/responses spiral bound (no 3 ring binders)…"
As the printing and assembly process of proposals usually comes down to the wire, we request that the VA please allow 3-ring binders for ease of assembly. Spiral binding our proposal will require us to outsource our printing/assembling needs.
A. Absolutely no 3-ring binders are allowed. You will be considered non-responsive.
48. Q. Page "91 of 181"; Factor 2 - Past Performance; In lieu of Past Performance
Questionnaires, we ask the VA to please allow the submission of CPARS evaluations. Main points of contact for several of relevant, recent projects (as outlined as acceptable in the solicitation requirements) have retired or are no longer employed by the VA; obtaining completed PPQs from these individuals will be a challenge.
A. No
49. Q. Project Duration; The solicitation indicates the Contractor shall complete the Project within (1200) calendar days after receiving notice to proceed.
Section 01 32 16.15 1.5.A “The Complete Project Schedule Submittal” states “…The final Project Schedule in its original form shall contain no contract changes or delays which may have been incurred during the final network diagram development period and shall reflect the entire contract duration as defined in the bid documents”.
The solicitation (page 94 of 181),“Short Schedules”, states the offeror must provide for completion within the time frame (number of days after receipt of the Notice to Proceed). The maximum anticipated days of completion for this project is indicated on the Standard Form 1442. This duration shall establish the contract completion date. Short schedules will not be accepted. Critical path activity durations shall total the number of days indicated on Standard Form 1442”.
Drawing Number GI702 indicates Phase 2 Duration of one (1) Year (365) calendar days. Since “short schedules” are not allowed and the Government owns all the float (i.e. Contractor has no chance for equitable adjustment based on potential Government delays), does the Contractor need to carry labor, travel, general conditions and indirect overhead costs for a period of (1200) calendar days? This will result in substantial costs. Based on the Phase 2 Duration (i.e. 365 calendar days) the (1200) calendar days is unrealistic (too long) and will result in inflated costs to the Government. Request duration is reduced to (730) calendar days.
A. Revised Period of Performance reduced to 1,095 days.
50. Q. Factor 1B "Project Personnel Experience" requires biographical data for seven (7) different personnel. The Specifications do not outline that a dedicated SSHO or QA/QC Specialist is required on this Project. Specifically, there is no QA/QC specification.
Please confirm the Project Superintendent can serve all three (3) roles on-site, and the Contractor is only required to have one (1) full-time person on-site (i.e. the Project Superintendent).
A. Yes. One person can serve as the SSHO& QA/QC roles as well as the Site Superintendent.
51. Q. Specification 23 50 11, Page 22, Section 2.3; The blowdown tank Specification 23
50 11 and the scheduled Blowdown Separator Schedule on Drawing MP601 are inconsistent.
The Specification calls for the, "blowdown tank volume to be twice the volume of a 4" blowoff from the largest boiler connected to the tank." Schedule depicts the blowdown separator to be 1'-8" diameter x 6'-5" length. The Specification calls for a 40 PSIG ASME Vessel, and the Schedule shows a 150 PSIG MAWP pressure rating. Please clarify which is correct.
A. Provide blowdown tank as scheduled. Disregard the last sentence of article
2.3.A: “Tank volume shall be twice the volume of a 100 mm (4 inch) blowoff (reduction in boiler water level) from the largest boiler connected to the tank.” In article 2.3.C.3., revise design tank working pressure from 40 psig to 150 psig.
52. Q. Drawing MP705, Detail D3; Indicates the requirement for Opacity Monitors, however 230911 2.8 states that Opacity Monitors are "not used". Please advise if Opacity Monitors are required and if so, please provide a spec. If Opacity Monitors are required to be outdoors based on installation requirements, please outline NEMA rating and outdoor requirements.
A. Disregard opacity monitor on detail D3/MP705.
53. Q. Solicitation, Page 75 of 181; The requested document "Contractor Vendorization
Form - VA10091" was not provided with the Solicitation. Please provide.
A. Form – VA10091 is attached
54. Q. Please confirm the size of the existing fuel oil tanks that need to be demolished.
A. Three (3) 25,000-gal USTs, one (1) 550-gal UST, 8000-gal aboveground day tank
55. Q. Please confirm the Government wants a Photographic Documentation indexing and navigation system (similar to Multivista), as outlined in Specification 01 00 00 1.23.
A. Yes, confirmed, bid documents require photographic documentation.
56. Q. Stainless Steel Tubing, Specification 23 09 11 (stainless-steel tubing); Please confirm that the stainless-steel tubing requirements (as outlined in 23 09 11) are COMPLETELY depicted on the drawings. It is assumed that all the mechanical details and P & ID’s on the drawings outline the extent of the stainless-steel tubing.
A. Stainless steel tubing specified in 23 09 11 applies to factory- piped control panels, in and on the panels. Factory-piped control panel tubing is not depicted on the drawings. Chemical feed system stainless steel tubing is shown on the drawings.
57. Q. Please confirm that the controls series drawings depict the complete extent of required interconnecting conduit and wiring as required for a complete system (as outlined in Specification 23 09 11) – including, but not limited to, the Automatic Boiler/Burner Control System, Burner Management System with Safety Interlocks and Accessories, Main Instrumentation and Control Panel, Boiler/Burner Control Panels, Computer Workstation, Flue Gas Oxygen Analyzers, Flow Meters, Pressure sensors and transmitters, Boiler draft gages, temperature sensors and transmitters, recorders, and Boiler Plant Building Dangerous Gas Detection System.
A. Boiler Plant control drawings do not depict typically conduit and wiring. Provide a complete conduit system as specified in section 23 09 11.
58. Q. Please confirm the Government is paying the natural gas company to set the meter and regulation station, as well as handling all upstream gas piping to the M & R Station.
A. Cost to set the meter and regulation station is to be covered by the Prime Contractor.
59. Q. What phase is the steam/condensate distribution piping to occur in?
A. Provide site distribution piping indicated on drawing MS102A in Phase 1.
Provide all other site distribution piping in Phase 2.
60. Q. Please confirm the Government will furnish all fuel oil for filling the tanks.
A. GC to filter, polish existing fuel into temp tank. VA will provide additional fuel for temporary boilers serving hospital needs. GC to provide fuel for testing and other construction purposes by monitoring fuel consumption by meter.
61. Q. Is the Contractor to include a tap fee for connection to existing sanitary manhole on Sheet PL101?
A. Yes, this fee is to be covered by the Prime Contractor.
62. Q. Sheet MS102A, Note 1; Please provide photograph(s) of location of pumped condensate road bore.
A. Buildings 7, 40 and 41 were added to MS102A site plan to clarify location of the piping road bore.
63. Q. Have the Gaskets for the valves that are to be demoed for this project been checked for asbestos?
A. Correction to spec section 02 82 11 as follows. After article 1.1.2.B text, add additional text as follows: “Also, see Drawings HA101 and HA102 for additional ACM quantities. And, (100) quantity valves to be demolished have asbestos-containing gasket material. Cut pipe before and after valve, wrap valve as single component, and dispose, all in accordance with ACM abatement procedures.”
64. Q. Please clarify the floor finish for the following rooms:
• Room 1A100 Boiler Room
• Room 1A101 Chemical Storage Area
• Room 1A107 IT
• Room 1A110 Electrical Room
• Room 1A111 Generator Room
• Room 1A114 Pit
The Finish Schedule on AF106 has these rooms listed as Epoxy P-2(5), which is designated as a waterborne catalyzed epoxy paint in the Finish Legend.
Plan Sheets AF102 and AF101 designate them as resinous flooring (Section 09-
6723.20 Resinous epoxy base with vinyl chip broadcast). Please clarify.
A. Clarifications for rooms stated above are now shown on D1/AF101 and
Room Finish Schedule / AF601.
65. Q. Will the VA supply the latest revision of the control system program that is currently being used for the rest of the campus with the Edwards EST 3X Series fire alarm and monitoring system?
A. The Prime Contractor is responsible to coordinate with subcontractors for full system functionality.
66. Q. What type of underground lines must be quoted for fuel of generator tanks
(example-double wall fiberglass?)
A. Provide piping as specified in Section 23 10 00.
67. Q. Is there going to be an automatic tank gauge (ATG) system used for release detection on new UST's?
A. Provide tank level monitoring and leak detection as specified in Section 23 10 00 and shown on D5/MP705.
68. Q. Do we also quote transition sumps where the lines go from underground to above-ground?
A. Transition sumps are not required. See drawings and Section 23 10 00 for monitoring wells/sumps.
69. Q. Are there a total of 4 underground storage tanks and one above ground storage tank to be removed in this project?
A. Yes.
70. Q. How many above ground storage tanks are gong to be installed and what are their sizes? What type of piping is required for the above ground storage tanks?
A. There is one above ground day tank, specified in Section 26 32 13. Provide piping as specified in Section 23 10 00.
71. Q. Sheet PL101 calls for a P414 in room 1A104, the Plumbing fixture schedule on sheet P0001 does not have a P414 listed. Please specify a P414.
A. Revise fixture tag P418 to P414 in fixture schedule on drawing P001. P414 is currently specified in 22 40 00 – 2.10.C.
72. Q. Sheet PL102 calls for a P707 in room 1A101, the Plumbing fixture schedule on sheet P0001 does not have a P707 listed. Please specify a P707.
A. Added P707 to fixture schedule on drawing P001. P707 is currently specified in 22 40 00 – 2.14.A.
73. Q. Sheet PL101 calls for a P101 in room 1A104, the Plumbing fixture schedule on sheet P0001 does not have a P101 listed. Please specify a P101.
A. Revised fixture tag P103 to P101 in fixture schedule on drawing P001. Revise Basis of Design toilet model number for P101 from “2257.0001” to “3641.001”.
P101 is currently specified in 22 40 00 – 2.7.A. Revise last sentence of article 2.7.A. to “Top of seat shall be 450 mm (18 inches) above finished floor.”
74. Q. Sheet PP102 calls for a 14-BFE-1 outside, the P001 does not have a 14-BFE-1 listed. Please specify a 14-BFE-1.
A. Revised “14-BFH-1” to “14BFE-1” in Backflow Preventer Schedule on drawing P001.
75. Q. Sheet PP101 calls for an HB in several places, the Plumbing fixture schedule on sheet P0001 does not have an HB listed. Is there a specific hose bib specification?
A. Hose bibbs are specified in Section 22 40 00 – 2.15.B.
76. Q. Several drawing refer to sheet PP001? Is there a sheet PP001 in the drawings?
If so, please provide a copy of direction to PP001.
A. Revised drawing number P001 to PP001 on that sheet, on drawing GI001 and in Section 00 01 15, List of Drawing Sheets.
77. Q. Is the existing VA owned portable boiler that is to be relocated next to building 13 going to be the primary or back-up boiler during construction?
A. Temporary Boiler #1 is provided by the VA, to serve at the redundant boiler for the project. Temporary Boiler #2 is provided by the contractor, is to serve as the primary boiler.
78. Q. On sheet PP101, note 4 states, "provide temporary portable eyewash station in
M111 until P709 is made active in Phase 2"
a. Where is M111?
b. Can you specify a specific type of portable eyewash to provide?
A. Disregard Keynote 4/PP101. P709 will be available for use at the end of Phase
1.
79. Q. What is the height, width and weight of each of the 3 existing boilers inside building 14?
A. Boiler #1 Cleaver Brook – Width: 10 ft, Height: 127 inches, Length: 26ft
Boiler #2 Wicks - Width: 10 ft, Height: 165 inches, Length: 21 ft
Boiler #3 Nebraska - Width: 13 ft, Height: 20.5 ft, Length: 13 ft
80. Q. Will the VA furnish AutoCAD files for this project for use to generate the drawings called out for on cover sheet GI001.
A. Yes
81. Q. What are the sizes of the underground tanks that are to be removed?
A. Three (3) 25,000-gal USTs, one (1) 550-gal UST.
82. Q. The tank schedule on MP601 and Tank Details on MP502 conflict. MP601 shows Fiberglass. MP502 shows steel. Please advise.
A. No reference to steel tanks could be found on C4/MP502. Provide fiberglass tanks as scheduled and specified.
83. Q. Please clarify, the specified duplex pump assembly referenced below grade in specification 23 50 11 article 2.7.A is shown above grade on drawing MP703.
Which are we to construct?
A. Article 2.7.A applies to the temporary pump skid serving portable boilers. Article 2.7.F. applies to permanent pumps 14-FOPS1. In article 2.7.A, revise “(for below grade installation)” to “(for temporary pump skid serving portable boilers)”. In article 2.7.F, add tag to read “Arrangement (14-FOPS1 Pump Set)”.
84. Q. Is a steel waterproof pump enclosure required as drawing MP703 states? It is located inside the building.
A. No mention of an enclosure is found on drawing MP703. Provide enclosure for the temporary pump skid serving portable boilers. Enclosure is not required for 14-FOPS1. See response to related question #83.
85. Q. The return and supply flow meters have no specification, please provide.
Reference plan sheet MP703
A. Provide flow meters as specified in Section 23 09 11 article 2.7.C.
86. Q. What is controlling the tank selection control valves? Is this to be done by the duplex pump control panel?
A. Provide fuel oil controls in accordance with D5/MP705.
87. Q. In regards to Specification 23 50 11 Item 2.7H. Please indicate the spec section and drawing numbers indicated in this paragraph. We are unable to locate these drawings and schematics. Please advise.
A. Section 23 50 11 – 2.7.H. references Section 26 29 11 for motor controllers. See diagram D5/MP705 for fuel oil controls.
88. Q. Are any of the valves located in the typical burner piping box on Plan MP703 detail B3 the responsibility of the fuel oil piping contractor? We believe these valves are to be provided by the boiler manufacturer, please advise.
A. Work indicated within the dashed box noted “Typical Burner Piping” is typically furnished by the burner manufacturer. Regardless of who furnishes it, provide the work.
89. Q. Please confirm that any warranty referenced in the specifications, even if it modifies FAR clause 52.246-21, beyond one year is intended to only be a manufacturer’s warranty for the product as referenced in the specification section.
90. Q. One RFI with multiple questions
Mechanical: 1. Do we include a tap fee for connection to existing sanitary manhole on sheet PL101?
A. The Prime Contractor is responsible for paying necessary tap fees.
2. Please refer to sheet MS102A note 1. Please provide photograph of location of pumped condensate road bore.
A. See attached RFI 62 Road Bore Image
3. Have the Gaskets for the valves that we demo on this project been checked for asbestos?
A. Make correction to spec section 02 82 11 as follows. After article 1.1.2.B text, add additional text as follows: “Also, see Drawings HA101 and HA102 for additional ACM quantities. And, (100) quantity valves to be demolished have asbestos-containing gasket material. Cut pipe before and after valve, wrap valve as single component, and dispose, all in accordance with ACM abatement procedures.”
4. Will the government furnish AutoCAD files for this project for use to generate the drawing called out on cover sheet G1 001? Look at the requirement for 3-dimension coordination drawings in Rivet.
A. Yes, 3D rendering will not be required. AutoCAD, 2D drawing will be in lieu of
Revit files.
5. Sheet PL101 calls for a P414 in room 1A104, the Plumbing fixture schedule on sheet P001 does not have a P414 listed.
A. Revised fixture tag P418 to P414 in fixture schedule on drawing P001.
P414 is currently specified in 22 40 00 – 2.10.C.
6. Could the VA provide photos of boilers and their tags, all associated piping and equipment to be demoed?
A. See attached RFI 90.6 Images
7. Is the exit point level with the ground?
A. It is unclear what is referred to as “the exit point” in the question.
8. Will 3D coordination drawings (BIM) be required for this job?
A. Yes, see Section 23 05 10 – 1.4.H.1. and Coordination Notes on drawing
GI001.
Electrical: 1. Who is supplying the extra temporary boiler?
A. Temporary Boiler #1 is provided by the VA, to serve at the redundant boiler for the project. Temporary Boiler #2 is provided by the contractor, is to serve as the primary boiler.
2. What is the time period allowed for the existing boilers to be shut down for installation/connection of the temporary boiler? Does this work need to be scheduled after hours? weekends? etc.?
A. The boiler can be isolated at the main header for relocation while existing boilers supply the facility with steam.
3. What is the time period allowed for the temporary boiler control room connection? Does this work need to be scheduled after hours? weekends? etc.?
A. Phase 1 – Boiler Plant staff to relocate to the temporary control room once both temporary boilers are relocated and online. This work does not need to be scheduled after hours.
4. Will there need to be temporary backup generator on site to back up the two temporary boilers for the length of the project?
A. At the end of Phase 1 construction, the temporary boilers will be connected to the new generator installed in Phase 1. This provides the necessary emergency power to the temporary boilers for Phase 2 construction.
Structural: 1. Page SF501 is missing from the structural drawings, could you please provide?
A. Plan Sheet SF501 was issued in Amendment #1 dated January 15, 2020 as an additional structural drawing.
Fencing: 1. What page or pages does it show how much or where the security fence goes? Sheet AE502 only provides the details.
A. Refer to Sheet AS100 for security fence locations.
General Requirements: 1. Will the contractor be required to provide unarmed guards at the project site after construction hours?
A. The Prime Contractor is responsible for security of the project. If the contractor does not provide onsite security, the VA is not responsible for ensuring the overall security of the project.
91. Q. Project Insurance Requirements - Please clarify the Insurance Requirements and limits for the following:
General Liability Insurance
Builder's Risk Insurance
Owner Contractor Protective Policy
A. Prime Contractor responsible for all insurances. Please see attached liability insurance.
92. Q. Clay Tile Roof at Boiler Building Reference: Division 01 - General Requirements
Specification Section 07 32 13. The above references indicate Clay Tile Roof is part of this project. Plan details indicate that the new roof for the Boiler Building is to be a Standing Seam Metal Roof. Please clarify.
A. Disregard spec section 07 32 13 Clay Roof Tile from: 1) Table of Contents spec section 00 01 00; and 2) spec book. Plan details showing standing seam metal roof are correct—see spec section 07 40 00 Roofing Panels for new standing seam metal roof. Cross-reference question #2.
93. Q. Footing Step Clarification Reference SB101, plan North
On the new addition, footing step location and elevation changes are noted on plans. However, on the top right corner of the plan there is a "FTG STEP" called out with no apparent elevation change. Please clarify if this step is intended to denote an elevation change, and if so, please clarify the elevation(s) at this area.
A. On Drawing C3/SB101, Disregard extraneous note stating “FTG STEP” in upper right corner of new addition (near generator pad) east of column line J.
94. Q. Testing -Reference Spec Section 01 00 00 Spec Section 01 45 29
Section 01 00 00 indicates testing by VA. Section 01 45 29 indicates testing by contractor.Please clarify.
A. Section 01 00 00 article 1.2.C states, “Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans
Affairs, the Contractor shall notify the COR in sufficient time…(emphasis added).” This means GC shall notify COR in sufficient time for those tests identified to be performed by VA. For tests not subject to testing by VA, including but not limited to testing identifed in spec section 01 45 29 Testing Laboratory
Services, GC provides testing.
95. Q. Security Fencing Clarification Reference: Plan sheet AS100, Notes 32.18 and
02.69
On AS100, it appears that some of the fencing is not clearly visible on the issued sheet. Please clarify the extent of the fencing, and related components to be included in Deductive Alternate #1.
A. Refer to Amendment 2 revised Sheet AS100 for clarified fencing. Cross reference question #103.
96. Q. Masonry Grout Fill Clarification Reference: SB501, Detail B1
Detail B1 on SB501 is calling for all CMU (above and below grade) to be grouted solid throughout. However, some notes and details only discuss filling cells solid below grade and periodically at verticle reinforcement locations above grade. Is detail B1 on SB501 intending for cells above grade to be filled at reinforcment only, or are the entire walls to be filled? Please advise.
A. In drawing B1/SB501, revise not to state, ”…GROUT CMU SOLID ALL
CELLS.”
97. Q. Site Surveys Reference: Spec Section 02 21 13
A specification for site surveys is included in the bid documents. The plans include several sheets of surveys. Please clarify if additional surveys will be required beyond what is included in the bid documents.
A. Yes, additional surveys are required per spec sections 01 00 00 and 02 21 13, and other spec sections, as well.
98. Q. Building Expansion Joint Clarification Reference: Plan AE101 note 07.36; Plan
AE501, detail D3, note 07.36
Note 07.36 on the above referenced sheets calls for Nystrom EWCF-200W expansion assemblies. These appear to be for roof-to-roof and roof-to-wall applications, and may not funtion correctly at some of the locations shown on plans. Please advise.
A. Refer to Amendment 2 for revised note 07.36 on AE101, which provides additional clarification on expansion joint assemblies.
99. Q. Tax Exempt Status Is this a tax exempt project? Please advise. Will the government provide tax exempt certificate?
A. Attached.
100. Q. Prevailing Wages - Will prevailing wages per the Davis-Bacon Act be required?
A. Prevailing Wages are now called Construction Wage Rate Requirements and the current Construction wage Rate Requirements dated January 3 2020 are posted as part of the solicitation.
101. Q. Energy Management System Controls -Is Siemens the only approved manufacturer for the energy management system controls? Please advise.
102. Q. Security Fence and Gates Reference Spec Sections 11 12 00 and 32 31 40
Section 11 12 00 does not reference Section 32 31 40.
32 31 40 does not reference Section 11 12 00.
A. AE RESPONSE: Spec sections 11 12 00 and 32 31 40 are revised as follows:
I. Spec section 11 12 00, under article 1.2, add, “I. High Security Fences and
Gates: Section 32 31 40, HIGH SECURITY FENCES AND GATES.”
II. Spec section 32 31 40, under article 1.2, add, “C. Parking Control: Section
11 12 00, PARKING CONTROL EQUIPMENT.”
103. Q. Sheet AS100 Reference Sheet AS100.
Shading / Graphics are very hard to read. The "gray" areas are actually black in color and cannot read notes and arrows that are placed on top. Impossible to determine the fencing information and the fencing layout does not match the electrical site plan. Please re-issue.
A. Refer to Amendment 02 revised Sheet AS100 for clarified fencing. Cross reference similar question #95.
104. Q. Temporary Control Room Specification Section 01 00 00, page 18 indicates 8' x
16'. Note 13.04 / AS100 indicates 8' x 20'. Please clarify.
A. Modify spec section 01 00 00 article 1.16.A.1 as follows: “8’ x 20’ box size (160 square feet) plus hitch.”
105. Q. Metal Locker Specifications Reference: Plan AE101 note 10.18
Please provide a specifation for metal lockers.
A. Refer to Amendment 02 added spec section 10 51 13 Metal Lockers. Also, add spec section 10 51 13 to Table of Contents spec section 00 01 10. Cross reference question #15.
106. Q. Section 01 32 16.15 (Design/Bid/Build)
Section 01 32 16.15 indicates "(Small Projects - Design / Bid / Build). Please clarify.
A. Section 01 32 16.15 correctly applies to this project, as this project is a design, bid, then build project.
107. Q. Sand-Filled Partitions Reference: Sheet GI501 Partition Types, and Sheet
AE101
In room Generator 1A111, there is a note pointing to partition type "R" that states
"sand-fill all cells". This is a shaft wall assembly, and not CMU construction.
However, partition type "M8S" is a sand-filled partition per sheet GI501. Please advise if this note is intended for the nearby "M8R" (CMU) walls.
A. Refer to Amendment 02 revised drawing D1/AE101. Note indicating sand-filling shaft wall has been removed. Also, on GI501, Partition Type M, revise asterisk notation to state, “* GROUT-FILL ALL CELLS.”
108. Q. Add Alternate #2 Indicated on Electrical Sheet Reference Sheet ES103.
Note 13 indicates ADD ALTERNATE #2. Spec Section 01 00 00, Page 2 does not list any ADD Alternates. Please advise.
A. There are no Add Alternates. Refer to Item 110 below for revised Keynote 13.
109. Q. Security Guard Clarification Reference: 01 00 00 / C
The above referenced specification notes the GC shall provide unarmed guards at the project site (if required by VA) after construction hours. Please advise if provisions for guards are required.
A. The Prime Contractor is responsible for security of the project. If the contractor does not provide onsite security, the VA is not responsible for ensuring the overall security of the project.
110. Q. Security Fence Clarifications
1. Can we get some sort of clarification on what equipment is wanted i.e. The
AS100 and ES103 sheets show slide gates at 3 location with readers. The specs call for barrier gates and readers and there is no mention if cards for these locations are required or what type of reader is to be provided i.e. proximity, barcode, or AVI.
A. The card readers at the gates are part of the Physical Access Control
System (PACS) and along with the gate security hardware are to be fully connected and operated through the PACS. The card readers are specified
Section 28 13 00 Physical Access Control System.
2. On the ES103 drawing Number 13 key note to provide PACS work for gates and doors noted under ADD Alternate #2 can someone provide clarification this?
A. Response:
1) Replace Keynote 9 with the following: "NEW PACS DOOR/GATE
HARDWARE, CARD READERS AND ACCESSORIES. REFER TO THE
"SECURITY DOOR/GATE HARDWARE AND ACCESS CONTROL
MATRIX" ON SHEET E503 FOR REQUIREMENTS. FULLY CONNECT ,
INTEGRATE AND CONTROL ALL GATES AND DOORS INTO THE NEW
BUIDING 14 PACS"
2) Replace Keynote 13 with the following: "ELIMINATE PACS WORK FOR
INDICATED DOORS AND GATES UNDER BID ITEM 2, DEDUCT
ALTERNATE 1."
3. There is mention on the drawings that the readers at some location are to owner furnished, does this go for all location as this is not fully described as to new or not?
A. There are no notes on the drawings that card readers are furnished by the owner. All card readers are new and shall be furnished by the Contractor as part of the new PACS System.
111. Q. Note 11 on Sheet CU107 There is a note 11 pointing to an item of work.
However, Note 11 indicates "RESERVED". Please clarify.
A. Disregard Keynote 11 call-out on plan at west parking area on drawing
CU107.
112. Q. Toilet Accessory Specifications Reference: Plan QH601 / Toilet Accessory
Groups, and Specification 10 28 00 / 2.2
The following items are contractor-funished / contractor-installed per drawing
QH601, but do not have a specification for pricing:
Soap Dispensers are shown on the Toilet Accessory schedule, but specification
10 28 00 / 2.2 does not list soap dispensers. Please advise.
A. In Specialty Equipment Schedule on QH601, for Mark A5075 Soap
Dispenser, change acquisition responsibility code to VV (GC still provides blocking per Miscellaneous Note J).
Hand Sanitizer Dispensers are shown on the Toilet Accessory schedule, but specification 10 28 00 / 2.2 does not list hand sanitizer dispensers. Please advise.
A. Hand Sanitizers are VA-furnished, VA-provided.
Toilet Seat Cover Dispensers are shown on the Toilet Accessory schedule, but specification 10 28 00 / 2.2 does not list toilet seat cover dispensers . Please advise.
A. Toilet Seat Cover Paper Dispensers are VA-furnished, VA- provided.
Baby Changing Stations are shown on the Toilet Accessory schedule, but specification 10 28 00 / 2.2 does not list baby changing stations. Please advise.
A. On Sheet QH601 Toilet Accessory Schedule, disregard Baby Changing
Stations.
Toilet Paper Dispensers are shown on the Toilet Accessory schedule, but specification 10 28 00 / 2.2 does not list toilet paper dispensers. Please advise.
A. AE RESPONSE: In Specialty Equipment Schedule on QH601, for Mark A5200
Toilet Tissue Dispenser, change acquisition responsibility code to VV (GC still provides blocking per Miscellaneous Note J).
Towel Bars are shown on the Toilet Accessory schedule, but specification 10 28
00 / 2.2 notes towel bars are "not used". Please advise.
A. AE RESPONSE: In spec section 10 28 00 article 2.10 Towel Bars, Disregard
"Not Used" and add the following:
A. Fed. Spec. WW P 541/8B, Type IV, Bar, Surface mounted; Class 1, towel.
B. Stainless steel, or chromium plated copper alloy.
C. Bar Length: 450 mm (18 inches) as shown.
D. Finish brackets and supports to match bar.
Shower Curtains are shown on the Toilet Accessory schedule, but specification
10 28 00 / 2.2 does not list shower curtains. Please advise.
A. VA provides shower curtains. GC provides shower curtain rods per spec section 10 28 00 article 2.8.
Fold Down Shower Seats are shown on the Toilet Accessory schedule, but specification 10 28 00 / 2.2 does not list fold down shower seats. Please advise.
A. For fold down shower seats, GC to provide basis of design (or approved equal) shower seat as manufactured by Dreamline, Shower Seat Model SHST-
01-PL (or equal). GC provides shower seat, blocking and installation per manufacturer’s instructions.
113. Q. Note 12 Clarification - Sheet CU107
Please indicate the extent of work for Note 12 on Sheet CU107. This note is indicated at back of Building 14.
A. Keynote 12/CU107 indicates remediation of pavement after demolition and temporary utility work is complete as shown on Mechanical drawings.
114. Q. Removable Metal Ramp Reference Sheet AE102.
Note indicates Removable Metal Ramp. Please furnish details and other information necessary.
A. See Amendment 2 revised drawing D1/AE102—removable metal ramp is deleted.
115. Q. Waterproofing at Tunnel Reference Detail C1/SB502
Note indicates waterproofing, See Architectural. We do not find details on the architectural sheets. Please furnish details and information necessary.
A. In Section C1/SB502 titled “Section at New Exterior Trench,” disregard note stating “REF. ARCH. DRWGS FOR WATERPROOFING, TYP.” In disregard note’s place, add “SEE SPEC SECTION 07 13 52 FOR WATERPROOFING.
WATERPROOF ALL VERTICAL SIDES TO LID COLD JOINT”
116. Q. Masonry Clarification Reference: Specification 07 21 13 / 2.2 / E
Please clarify if masonry fill insulation is required. I was unable to find this requirement in the plans.
A. Disregard “Masonry Fill Insulation” article 2.2.F in spec section 07 21 13. Note article 2.2.E is “Masonry Cavity Wall Insulation.”
117. Q. Temporary Construction Fencing Plan notes indicate the Temporary
Construction Fencing will be determined by the COR.
For bidding purposes please mark on a plan sheet the locations where the fence will be required.
A. For temporary fencing, see Amendment 2 revised Drawing AS100.
118. Q. Would the VA allow value engineered options for the project assuming they don’t change the outputs of the boiler system and they meet all VA design criteria and documentation to include the VA Program Guides, VA Design Guides, VA
Design Manuals, VA Directives and all other pertinent requirements for…
This is the start of the file's text. The full file is on GovTribe.