36C10D23R0006 0005.docx

DOCX document 2 MB Posted

Attached to
Z1DA--Construction of Perimeter Fence at the St Petersburg VA Regional Office
Solicitation number
36C10D23R0006
Issued by

About this file

This solicitation seeks proposals for the construction of a perimeter fence at the St. Petersburg VA Regional Office. The scope of work involves installing approximately 500 linear feet of hurricane-rated fencing and pedestrian gates to enclose parking areas and buildings 46 and 47. Excluded work includes electrical components, lighting, gates, bollards and landscaping. Proposals are due by August 31, 2023 at 4:00pm EST. Contractors must follow all VA security protocols and safety requirements, including submitting a site-specific safety plan and activity hazard analyses. The selected contractor will be responsible for coordination, project management, and ensuring all work complies with OSHA standards and EM 385-1-1 requirements.

View the file

Other files

File Type Posted
323119DecoMetalFencesGates.docx DOCX document
Detail.docx DOCX document
SOW.pdf PDF
Fence Layout 0005.pdf PDF
36C10D23R0006 0004.docx DOCX document
Fence Layout.pdf PDF
36C10D23R0006 0003.docx DOCX document
Revised RFIs 36C10D23R0006 0002.pdf PDF
Statement of Work SOW.pdf PDF
36C10D23R0006 0002.docx DOCX document
S04 Sign in Roster 36D10D23R006.pdf PDF
36C10D23R0006 0001.docx DOCX document
AMIGUARD 5000 Brochure.pdf PDF
AE Drawings Perimeter Fence.pdf PDF
SOW Perimeter Fence 3-24-23 Final.docx DOCX document
S02 P07 WD FL20230222 SAM.pdf PDF
AMIGUARD 6000 _ 7000 Meshes.pdf PDF
36C10D23R0006_1.docx DOCX document
zS02 St Pete Perimeter Fence - PAST OR PRESENT PERFORMANCE SURVEY.pdf PDF
Specs AE Perimeter Fence.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

VA

VB3237

00101 Department of Veterans Affairs Veterans Benefits Administration Acquisition Directorate 1800 G. Street N.W.

Washington

DC

20006 00101 Department of Veterans Affairs Veterans Benefits Administration Acquisition Directorate 1800 G. Street N.W.

Washington

DC

20006

36C10D23R0006

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to:

August 31, 2023 @ 4:00pm EST See CONTINUATION Page X Amendment 0005 is FINAL clarification questions about SOW, answer submitted RFI questions details are attached as well as SOW to be utilized for RFP submission

Due date of proposal submission is herby extended to: August 31, 2023 @ 4:00pm EST No further RFI submissions will be accepted.

All other terms and conditions of solicitation remain the same.

RFI questions for CLARIFICATION - Solicitation 36C10D23R0006

1. If not in the Scope of Work, why is it clearly indicated as work on the drawings?

Drawing were issued to allow contractors to see where the fence was being installed (as a reference). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. Had the RFI answers not been asked, would the SOW be per the VA’s own direction which is quite different that the issued plans and specs?

See # 1, SOW attached.

1. Is there other SOW shown on the plans that the VA believes isn’t in the SOW?

There is only one SOW that was included in the solicitation, separate from the plans.

1. If yes to the above, how do we know that if the VA’s SOW is different than what the drawings clearly indicate?

See # 3, disregard drawings except as for site reference.

1. It’s not even clear if JCI has scope in this. There is scope of work for them scattered all over the plans with specific mentions and call outs.

At site visit, contractors were informed JCI was removed.

1. ES100 calls for 39 trees to get demoed in the west parking lot because they are in the way of the new light poles. The demo is clearly shown on the plans but RFI’s now saw not in SOW. Why is it shown?

Disregard plans. The plans were only for reference of the location of the fence. The SOW does not include lighting.

1. Most of the VA response related to electrical state “Not in SOW”, but a few do make references to electrical SOW to remain in the contract.

There is no electrical in the SOW that was issued in the solicitation.

1. It seems like selective deletion of SOW in the drawings is what’s happening, but there is no document that clearly explains what SOW is to remain and what SOW is to be deleted. Ex. JCI’s power wiring seems to be deleted, but what about the wiring for the gates, lighting, etc?

See # 1, Drawing were issued to allow contractors to see where the fence was being installed (as a reference-ONLY). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. Whatever the response is to the above, how would contractors know this?

Attending the site visit would have clarified this.

1. Can the VA clarify which type of fencing they want? See below from the fencing subcontractor.

Included in the SOW.

1. Clarify if Spec SECTION 32 31 19 DECORATIVE METAL FENCES AND GATES is included in this solicitation.

Yes, see attached SECTION 32 31 19 DECORATIVE METAL FENCES AND GATES

1. the “Plans and Drawings (are there both Plans and Drawings?) are for guidance & reference points for layout of [the] facility ONLY”. What does that mean? Are we to disregard the Drawings and Specifications and just bid on the sketch of the Scope of Work?

Again if the contractor looks at the plans that were issued only as a reference to the fence layout it is matched by the sketch and the locations of the gates.

1. “no bollards, no electrical components, no lights or light poles, no need for (JCI-specified) controls…” So, what IS the Scope?

Install a fence around the building that is hurricane rated.

1. “Fencing only, see attached drawing” is the third item of the Amendment. “Drawing” is a loose term, more like a sketch. There’s a blue line, hand drawn that is supposed to represent what? The fence line? What is the Scope of Work? Where are the details?

See # 13

1. Clarification of exclusions (are these excluded?):

14. Lighting- excluded

14. Power to gates- excluded

14. Controls to gates- excluded

14. Card Readers excluded -

14. Cameras- excluded

14. Vehicle barriers- excluded

14. Guardrails- excluded

14. Handrails- excluded

14. Sidewalks/ramps/stoops- excluded

14. Planters- excluded

14. Landscape demolition- excluded

14. Bollards - excluded

14. Signage- excluded ALL these items are excluded.

1. If not in the Scope of Work, why is it clearly indicated as work on the drawings?

See # 1- Drawing were issued to allow contractors to see where the fence was being installed (as a reference). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. Had the RFI answers not been asked, would the SOW be per the VA’s own direction which is quite different that the issued plans and specs?

See # 1- Drawing were issued to allow contractors to see where the fence was being installed (as a reference). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. Is there other SOW shown on the plans that the VA believes isn’t in the SOW?

See # 1- Drawing were issued to allow contractors to see where the fence was being installed (as a reference). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. If yes to the above, how do we know that if the VA’s SOW is different than what the drawings clearly indicate?

See # 1- Drawing were issued to allow contractors to see where the fence was being installed (as a reference). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. It’s not even clear if JCI has scope in this. There is scope of work for them scattered all over the plans with specific mentions and call outs.

See # 1- Drawing were issued to allow contractors to see where the fence was being installed (as a reference). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. ES100 calls for 39 trees to get demoed in the west parking lot because they are in the way of the new light poles. The demo is clearly shown on the plans but RFI’s now saw not in SOW. Why is it shown?

See # 1- Drawing were issued to allow contractors to see where the fence was being installed (as a reference). As stated at the site visit the electrical, gates, and bollards were not to be included. Only fence and installation.

1. Most of the VA response related to electrical state “Not in SOW”, but a few do make references to electrical SOW to remain in the contract.

The SOW issued with the solicitation does not have any electrical work included.

1. It seems like selective deletion of SOW in the drawings is what’s happening, but there is no document that clearly explains what SOW is to remain and what SOW is to be deleted. Ex. JCI’s power wiring seems to be deleted, but what about the wiring for the gates, lighting, etc?

The only gates listed in the SOW are for pedestrians. No wiring or lighting included.

1. Whatever the response is to the above, how would contractors know this?

This was answered via several amendments in sequence, please refer to SOW only.

See attached document: SOW.

See attached document: 323119DecoMetalFencesGates.

See attached document: Fence Layout 0005.

See attached document: Detail.

CONTINUATION PAGE

A.1 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
GRAND TOTAL
__________________

A.2 DELIVERY SCHEDULE

ITEM NUMBER
QUANTITY
DELIVERY DATE

Solicitation # 36C10D23R0006 Construction of Perimeter Fence at the St Petersburg VA Regional Office Amendment to clarify FINAL RFI questions and extend due date to 8/31/23 @ 4:00pm EST image1.png

File details come from the government source that posted it. Updated .