JAN 2025 TKY Schedule of Requirements - QA - Updated 6-16-2025.xlsx

XLSX spreadsheet 56 KB Posted

Attached to
6525--JAN 2025 Consolidation - HTME with Extended Installation Services (includes Turnkey Services)
Solicitation number
36A79725Q0005
Issued by

About this file

This document is a detailed Schedule of Requirements for the Department of Veterans Affairs (VA) National Acquisition Center's January 2025 High-Tech Medical Equipment (HTME) Consolidation solicitation, covering equipment procurement and installation across multiple VA healthcare networks. The schedule encompasses 23 medical imaging equipment replacements at VA facilities in 13 different states, including X-Ray, MRI, Cath Lab, Nuclear Medicine SPECT CT, and Radiology equipment for various VISN (Veteran Integrated Service Network) locations.

The solicitation (Solicitation Number: 36A79725Q0005) requires comprehensive turnkey services including equipment procurement, site preparation, installation, and extended installation services. Each location has specific technical requirements, site visit dates (primarily in April 2025), and unique facility modification needs such as flooring replacement, wall painting, millwork updates, electrical upgrades, and HVAC considerations. The equipment specifications are highly detailed, covering parameters like detector sizes, pixel resolution, patient table load capacities, workstation configurations, and specialized software requirements. Site-specific contacts are provided for each location, enabling vendors to coordinate site visits and gather additional information for their proposals.

View the file

Other files

File Type Posted
402B51025 - 581B52000 Updated TS and CM.zip ZIP file
626B54008 AHU-4 TAB.zip ZIP file
596B50022-B50024 Site Prep Documents (1).zip ZIP file
540B51004 - Additional Information.zip ZIP file
632B51003 NORTHPORT Shielding.zip ZIP file
Wilkes Barre PA Drawings.zip ZIP file
36A79725Q0005 0001.docx DOCX document
660B50001 - Additional Information.zip ZIP file
541B50033_VAMC CLEVELAND DRAWINGS AE-401.zip ZIP file
596B50022 - 5085B5008 Updated TS and CM.zip ZIP file
531B53001 Boise_Colleted CAD Files.zip ZIP file
544B52002 final submission Architectural GE20100174.zip ZIP file
679B52006 - Additional Information.zip ZIP file
650B51001 VA Providence 1st floor (1).zip ZIP file
Amendment 0001 - Continuation Page.pdf PDF
544B52007 Rad Room 2 2011 PRELIM.zip ZIP file
663B53002-663B53003 Pug - Jan 2025 TK Consolidation - AMLK X-Ray.zip ZIP file
Attachment 2 402B51206.zip ZIP file
544B52002 final submission Mechanical GE20100174.zip ZIP file
581B52000 - Additional Information (1).zip ZIP file
650B51001 VA Providence 1st floor.zip ZIP file
544Bxxxxx 100-f1.zip ZIP file
Fayetteville NC Additional Drawings.zip ZIP file
SOLICITATION-DESCRIPTION.docx DOCX document
Vendor Workup Spreadsheet - 36A79725Q0005.xlsx XLSX spreadsheet
Vendor Folders.zip ZIP file
664B54001 - 693B50015.zip ZIP file
596B50022 - 642B59002.zip ZIP file
Memorandum for Training.pdf PDF
664B54001.zip ZIP file
402B51205 - 509B52002.zip ZIP file
528B53014 - 531B53001.zip ZIP file
531B53002 - 540B51004.zip ZIP file
541B50033 - 565B59004.zip ZIP file
JAN 2025 Extended Install and Turnkey Consolidation - RFO.pdf PDF
JAN 2025 TKY Schedule of Requirements.xlsx XLSX spreadsheet
515B50004.zip ZIP file
531B53001.zip ZIP file
580B50004 - 581B52000.zip ZIP file
NAC Turnkey Rubric - Oct 2024.pdf PDF
581B52000.zip ZIP file
JAN 2025 TKY Consolidation Schedule.pdf PDF
36A79725Q0005_1.docx DOCX document
650B51000 - 663B53003.zip ZIP file
VA Directive 6550 - New Appendix A - published Jun. 2023.docx DOCX document
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Line Items

HTME VISNStationEquip POTKY POEquipment TypeQTYSite Visit POCSite Visit DateSite Visit Time
VISN 1: VA New England Healthcare System402 AUGUSTA, ME402B51205402B51206XR IR1Seth.Bickford@va.gov4/18/2025 4/25/20259am - 11am EST

9am - 11am EST

VISN 7: VA Southeast Health Care Network508 DECATUR, GA5085B5008508B52001XR CT1Nicholas.Thomas5@va.gov
4/14/2025 4/15/20259am - 4pm EST 9am - 4pm EST
VISN 7: VA Southeast Health Care Network509 AUGUSTA, GA509B52002509B52003NM SPECT CT1jan.bovier@va.gov
4/14/252pm - 3pm EST
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006XR MRI1Christopher.hover@va.gov4/17/2510am EST
VISN 2: VA Healthcare Network Upstate New York528 ALBANY, NY528B53014528B53013NM SPECT CT1elyse.deruzzio@va.gov4/23/257:30am - 2:30pm EST
VISN 20: VA Northwest Network531 BOISE, ID531B53001531B53000XR CATH LAB1Donald.sedlacek@va.gov4/18/252pm- 4pm MST
VISN 20: VA Northwest Network531 BOISE, ID531B53002531B53003XR MRI1Adelle.Milholland@va.gov4/18/251pm MST
VISN 5: VA Capitol Health Care Network540 CLARKSBURG, WV540B51004540B51007XR RAD1Taylor.niemi@va.gov4/23/259am EST
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B50035XR IR1Michael.Morgan7@va.gov4/16/251pm EST
VISN 7: VA Southeast Health Care Network544 COLUMBIA SC544B52002544B52010XR IR1dustin.schroeder@va.gov4/18/253pm - 4pm EST
VISN 7: VA Southeast Health Care Network544 COLUMBIA SC544B52007544B52009XR RAD1dustin.schroeder@va.gov4/21/253pm - 4pm EST
VISN 6: VA Mid-Atlantic Health Care Network565 FAYETTEVILLE, NC565B59001565B59005XR RF1breanna.roach@va.gov4/17/2512pm - 1pm EST
VISN 6: VA Mid-Atlantic Health Care Network565 FAYETTEVILLE, NC565B59002565B59008XR MRI1breanna.roach@va.gov4/24/2512:00pm - 1:30pm EST
VISN 6: VA Mid-Atlantic Health Care Network565 FAYETTEVILLE, NC565B59003565B59006XR RAD1breanna.roach@va.gov4/17/2512:00pm - 1pm EST
VISN 6: VA Mid-Atlantic Health Care Network565 FAYETTEVILLE, NC565B59004565B59007XR RAD1breanna.roach@va.gov4/17/2512:00pm - 1pm EST
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005XR CATH LAB1allen.onwuchekwa@va.gov, conrad.lewis2@va.gov4/21/259am CST
VISN 5: VA Capitol Health Care Network581 HUNTINGTON, WV581B52000581B52002XR CATH LAB1david.webb5@va.gov4/25/251pm EST
VISN 9: VA Mid South Healthcare Network596 LEXINGTON, KY596B50022596B50023XR CATH LAB1Bradley.Faulkenberg@va.gov4/21/258am EST
VISN 9: VA Mid South Healthcare Network596 LEXINGTON, KY596B50024596B50025XR IR1Bradley.Faulkenberg@va.gov4/21/258am EST
VISN 9: VA Mid South Healthcare Network626 MURFREESBORO, TN626B54008626B54016NM SPECT CT1Bryan.Wilson1@va.gov4/17/2025 4/22/202511am CST 11am CST
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004NM SPECT CT1Jeffrey.Donahue@va.gov4/14/2025 4/17/20259am - 10am EST 9am - 10am EST
VISN 4: VA Stars & Stripes Healthcare Network642 PHILADELPHIA, PA642B59002642B59003XR RAD1christina.harry@va.gov4/15/259am EST
VISN 1: VA New England Healthcare System650 PROVIDENCE, RI650B51000650B51001XR RAD1Scott.darosa@va.gov4/16/2510am EST
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002XR RF1Joseph.cretini@va.gov4/17/2025 4/18/202511am - 4pm MST 11am - 4pm MST
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B53000XR RAD1Johnny.huang@va.gov4/16/2510am - 12pm PST
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B53001XR RAD1Johnny.huang@va.gov4/16/2510am - 12pm PST
VISN 22: VA Desert Pacific Healthcare Network664 SAN DIEGO, CA664B54001664B54003NM SPECT CT1karen.bretz@va.gov4/18/2510:30am - 11:30am PST
VISN 7: VA Southeast Health Care Network679 TUSCALOOSA, AL679B52006679B52005XR RAD1Justin.jenkins2@va.gov4/16/251pm CST
VISN 4: VA Stars & Stripes Healthcare Network693 WILKES BARRE, PA693B50015693B50018XR RF1robert.calarco@va.gov
stanley.benoit@va.gov4/14/259am EST

QA

VISNStationEquipment Requisition NumberTurnkey Requisition NumberEquipment QuestionsTurnkey QuestionsGOVT Equipment ResponseGOVT Turnkey Response
VISN 1: VA New England Healthcare System402 AUGUSTA, ME402B51205402B512061. Unit physical specs

a. Min detector size 20x20 cm Question: Current system is a 40x25 cm. 20x20 cm is smaller - Do you want the same size detector that you're trading in?

3.Software Requirements

h. Enhanced roadmapping Question: Do you require software specific for prostate & liver tumors.

Question: Please confirm which specialties and procedures will be done in this room.1.Is there any work to be done in the control room?
2.Is the welded floor being replaced?
3.Can we confirm that the work to be done in the area below the room can be done during regular business hours.
4.Are there any requirements for Davis Bacon Wages? In the past on our GE projects this was not a requirement for our VA Work.
5.Where is the power source for the feed coming from
6.What type of switch gear are we coming out of is there a breaker available?1. a. Updated tech specs/compliance matrix

3. h. Software for prostate and liver tumors added to E. f. Added Value. Specialties and procuedures added to tech specs/compliance matrix in A. Requirement Overview. 1. Replace welded floor

2. Yes in all IR Rooms.

3. Assume after hours for this work.

4. This will have to be answered by contracting

5. Room E343, See Attachment 2.

6. See Attachment 2.

VISN 1: VA New England Healthcare System 650 PROVIDENCE, RI 650B51000 650B51001 2. Unit physical specifications

e. Minimum spatial resolution [lp/mm] - 3

Please adjust to 3.57 for competition.2.e. Minimum clinically acceptable spatial resolution is 3 lp/mm
VISN 1: VA New England Healthcare System650 PROVIDENCE, RI650B51000650B510011)Would you please provide us with CAD drawings?CAD drawings for the first floor will be provided. Note that these are for reference only and the Contractor shall field verify all dimensions.
VISN 1: VA New England Healthcare System650 PROVIDENCE, RI650B51000650B510011. Will we need to supply new power feeds?

If yes where from/ how far away?

HVAC

2. Is the existing HVAC system adequate for the new equipment?

Note there is a temp move & cool in the room now, will HVAC upgrades be required?

3. What is the deck height/ room above the ceiling?

What is the deck construction?

4. Concrete on metal deck and thickness?

Formed and poured concrete?

5. What is below the space?

Slab on grade or slab on deck?

6. Will there be any finish upgrades to the space?

7. Working restrictions What are the working hours?

What is the travel path? 1.) New feeders will be required for new equipment. Size and number of feeders will be based off which equipment is provided. Existing 3 Phase 480 in the room may be re-used if the Electrical Engineer determines it is adequate for the equipment selected If yes where from/ how far away? The required electrical cannot be determined until the equipment is selected HVAC This is not a question 2). a) SOW includes providing supplemental HVAC to meet equipment’s requirements.

b) SOW includes upgrades to the HVAC if needed to meet the new equipment’s needs. HVAC requirements cannot be determined until the new equipment is selected 3). a) 11’11” from floor to floor above

b) one-way concrete joist system with integral slab 4). a) No metal deck - one-way concrete joist system with integral slab. Typical slab thickness is 2-1/2” with a 1” topping slab. Total thickness is 3-1/2”

b) Yes 5.) a) Administrative space/rest room

b) one-way concrete joist system with integral slab 6.) SOW includes finish upgrades (flooring, paint etc) 7.) a) Normal working hours are 7A-3P, work that impacts hospital operations (noise, vibration, outages etc) will need to be conducted off hours and coordinated with the COR

b) Worksite is located in close proximity to the loading dock and is on the first floor of the hospital.

VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006During the site visit, the staff talked about the need for cabinets and storage areas in the MR room. Can we provide a solution as part of our turnkey and equipment quote?During the site visit, the staff talked about the need for cabinets and storage areas in the MR room. Can we provide a solution as part of our turnkey and equipment quote?Yes, a solution can be provided.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006UPS - Please reduce UPS run time to 7 minutes. If the desire is to purchase a FULL UPS please confirm and indicate where it will be sited.Please confirm whether to include a FUL UPS in the proposal and where it will be sited
Was the RF shield in the current space inspected/evaluated?Technical specification updated.No Full UPS No, site can provide if needed
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Current shield is aged and testing is needed to evaluate integrity. Will this be validated by the VA organization and the results shared with turnkey vendors and general contractors?Yes, this can be provided
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Line 24: Minimum field of view [cm] 1. 1cm appears to be a typo. Some systems are capable of 55cm. max FOV. Recommend changing this spec to 55cm as the benchmark.
Technical specification updated.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Line 85: Backup air coils; Please elaborate and provide more detail specific to air coils. What are they used for?
Required for small FOV and stuations where rigid coil is ill-fitted
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Do you want the UPS to support the chiller?No
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Line 93: b. Neuro. Do you also want to have black blood imaging?We would want both black blood imaging and bright blood imaging capability
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Compliance Matrix, Line 96 e. Cardiovascular. Do you want Cardiac Quant, and Coronary acquisition capabilities?Yes
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Compliance Matrix, Line 102 : k. Fiber Tracking software. Do you want the capability to do diffusion imaging and fiber tracking for both brain and spine?Yes
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Do we need to quote shielding replacement in our turnkey proposal?Yes, if evaluation deems it necessary
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B50004515B50006Current flooring underneath magnet is aged and testing is needed to evaluate integrity. Will this be validated by the VA organization and the results shared with turnkey vendors and general contractors?No, this will not be provided.
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B500351)Would you please provide us with CAD drawings?Drawings provided to NAC HTME
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B50035Turnkey Question - Please direct if new room is to be brought up to current Class 2 Imaging Room Standards? This would include, but not limited to, the following alterations: HVAC rework of airflow in the room, plumbing to remove sink from inside of the exam room, and removal of closet doors from inside of exam room to be accessed outside of exam room.HVAC: Perform an initial balance report to confrim airflow meets requirements. Balance room and adjacent rooms to provide proper flows if necessary. Removal of sink is not required; Changes to Equipmnent Closet are not required; New flooring to be installed in Room BB-605 as follows. "TARKETT IQ EMINENT UNISENSE 908 DUSTY GREY WG SHEET VINYL W/ 6" INTEGRAL COVE BASE" Remove existing grid ceiling in Room BB-605 in it's entirety and install a new gypsum board ceiling; provide new RA grilles and SA diffusers LED lighting and re-install all other devices.
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B500351a. Minimum detector size - please change to 30x30

2j and 2s. – Injector: Please confirm if you’d like pedestal mount, table mounted or both?

2l. IVUS – Please clarify if you are looking for vendors to include an IVUS system and want it to be integrated?1a Minimum detector size 30 x 30 2j and 2s Bayer configuration: Injector head on pedestal connected thru table base with electronics installed in equipment room and display and operator controls remoted to control room. 2l. IVUS capability can either be integrated i.e. built-in or separately interfaced
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B50035During the site visit, the staff mentioned the sliding door and operator are broken. Should we include replacement as part of our turnkey proposal?Yes – Sliding door, frame, and operator to be provided. Push plate on both sides of door near floor level and touchless plate on both sides of door.

Many service calls placed for current door, parts hard to obtain

VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B50035Line 22. "a. Minimum detector size [cm x cm]" - They only reference a single plane detector. Are they requiring a Bi-Plane system.This is a Bi-Plane system; minimum lateral detector 30cm x 30cm
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B50035Line 23. "b. Minimum patient table load capacity [lbs]”. What is the minimum Patient Weight that they are requiring?Minimum table load capacity 650lbs; minimum patient weight 450lbs
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B50035Line 25. "d. Minimum reconstruction rate [images/s]”. Can you confirm if they are referring to Acquisition Rate and not reconstruction rate?Minimum reconstruction rate 3 images/second; Acquisition 7.5 fps Fluoroscopy 30 fps
VISN 10: VA Healthcare System of Ohio541 CLEVELAND, OH541B50033541B50035During the site visit, the staff mentioned the control desk support legs have been weakened over time and are in need of replacement. Should we include replacement as part of our turnkey proposal?Asking that control desk/counter top supports be replaced. Can mirror the recent replacement supports in room B-B601 Yes, p-lam counter supports to be provided. Profile to be allow free movement of staff sitting at desk and coordinated with Tky COR.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500051. Please clarify the conflicting request in the Technical Requirements Section.

a. 1.g through 1.j – the request for a lateral gantry requirement which is for a biplane. Conflicts with

b. 2.a requesting a single plane

Tech specs updated. This is for a single plane.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Question; Please confirm that no response is required for 1.g through 1.j.Tech specs updated. This is for a single plane.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500051. Please clarify the following request in the Added Value Section.
a. Item h. Hemodynamic monitoring systemLeft heart catheterization (LHC), right heart cathetrization (RHC) and EP is needed for cath lab room 3. All of which need hemodynamic monitoring. This is the current set up of the system.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Question: please clarify if requesting an upgrade for this room or the department?Replacement with same modality.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500051. Please clarify the following request in the Trade In Section.
a. The install date on the document is in error.Installation Date of the current system was 08/20/2010.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Question = Please clarify the install date of the system.Installation Date of the current system was 08/20/2010
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Question: Can an estimated removal date be provided?
b. An estimated removal date will be necessary to provide a value for the system if there is one.Can be provided after kick off call to coordinate removal of equipment prior to construction work.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500051. There is no request for a ceiling mounted rad-shield or light.Existing in the suite.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Question: Are we to assume a boom vendor will be involved and provide these accessories?Yes a boom vendor will need to be involved and coordinated with to add a boom to the room.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500051. Is the station going with the Stryker ceiling system for this room?Vendor to utilize existing ceiling conditions if applicable to new equipment. If the current laminar airflow system is not adequate, then VA team will need to know.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500051. Is the station adding, removing, or modifying any booms in this room?Adding a boom.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500051. Is this room going to be required to be brought up to current VA TIL HVAC standards?TIL will be the standard for this room
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Please clarify if software is needed to provide the ability to fuse images from CT, MRI and ultrasound?Tech specs updated.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 27F. Please modify the SID range to 35-49 inches to allow competitionTech specs updated.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Please remove Lines 28,29,30,31 all referring to Bi-Plane and this benchmark is referring to a Single PlaneTech specs updated.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 32k Please modify the table height range from the floor to 29.5 inches as the current requirement is written for one vendor.Tech specs updated.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 34m Please modify the motion range max 125cm or +/-24.5 inches to allow competitionVendor can respond as appropriate. Current sepc, -30 to +30, range is broad for compeition.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 38q. Please modify the Radiographic mA range to 500-1000mA to allow competitionTech specs updated.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 39r. Please modify Radiographic kV range to 40-125kV to allow competitionVendor can respond as appropriate. Current spec, 40 to 130, range is broad for competition.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 40s Please modify Fluroscope mA range to 500-1000mA to allow competitionTech specs updated.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 41t. Please modify Fluroscope kV range to 40-125kV to allow competitionVendor can respond as appropriate. Current spec, 40 to 130, range is broad for competition.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 54g Please specify the size of the digital detectorDigital detector size of 19in x 14in included in added value
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B50005Line 104i. Please clarify UPS needed; Eaton UPS only allows 7-10 mins to complete the exam for safe shutdown. Do you have a location for the UPS would need a separate room?Make/model of UPS open for vendor choice. Note added value for specification. Location preferred in the mech room in the cath lab dependent on size. If it cannot, then it can be located where the current UPS is at the closest mech bay.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B50004580B500052)Would you please identify the room in which the UPS sits and the specifications for the current UPS? 3)Would you please provide a VPN to connect to remote diagnostics?1)Would you please provide us with CAD drawings?Location preferred in the mech room in the cath lab dependent on size. If it cannot, then it can be located where the current UPS is at the closest mech bay.
VPN for remote diagnostics is dependent on the vendor and VA memorandum of understanding for remote diagnostics.No CAD Drawings available.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Turnkey vendor verification with regard to facility standard finishes and extent of new finishes desired.New cabinets, countertops, one door replacement, and floors.

Floor: Welded seam sheet flooring (heat welded with rod) or resilient sheet flooring (chemically welded seals)

Door: One wooden door with a lead interior suitable for a Class 1 R/F room.

VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Additional Specifications: Row 52 c of compliance matrix, is the tube mount floor mounted?
We want one overhead tube and one floor mounted tube inside the table.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Additional Specifications: Row 52c of compliance matrix, is this the Fluoro Tube?Yes
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002With regard to Additional Specifications on the compliance matrix, row 71 v.: It states "UPS-maintains full functionality of the system for a minimum of 4 minutes during a power outage." QUESTION: Do you want capability of full UPS to run the system or a UPS to save the data? If yes, is there space/room to put a full UPS in the room?We want a UPS that can save the data during a power outage.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002With regard to Additional Specifications on the compliance matrix, row 73: It states "In Room monitors requested Ceiling Mounted" but row 76 aa states a mobile trolley. Which mounting solution is desired for the two monitors? Trolley or ceiling mounted?Ceiling mounted only
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002With regard to Additional Specifications on the compliance matrix, row 82. b: It states "Ability to tilt the imaging surface at Least 90 degrees". QUESTION: Is this supine stitching? Please explainWe want supine stitching, but this is a table that can tilt fully vertical so foot studies can be done on the patients.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002From a turnkey perspective, please verify facility standard finishes and extent of new finishes desired.New cabinets, countertops, one door replacement, and floors.

Floor: Welded seam sheet flooring (heat welded with rod) or resilient sheet flooring (chemically welded seals)

Door: One wooden door with a lead interior suitable for a Class 1 R/F room.

VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002From a turnkey perspective, please verify new doors required and which doors.One new door widened and replaced to fit new stretchers. 1D-66 X-ray 3 Bldg 1 door. Patient hallway side door on the south side of the room.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002From a turnkey perspective, please verify removal of equipment room wall.Yes
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002From a turnkey perspective, please verify replacement of cabinets and sink.Yes
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Please indicate location of full system UPS indicated as required in the VA Tech Specs ( 3. Additional Specifications, Item V)Stored underneath the control console
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Turnkey reqeusting to verify if new doors are required and which doors (where)?One new door widened and replaced to fit new stretchers. 1D-66 X-ray 3 Bldg 1 door. Patient hallway side door on the south side of the room.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Turnkey reqeusting facility to verify removal of equipment room wall.Yes
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Turnkey requesting verification of replacement of cabinets and sink.Yes
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Please indicate location of full system UPS indicated as required in the VA Tech Specs ( 3. Additional Specifications, Item V)Not full system UPS, just UPS large enough to save data. UPS stored under control console.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B50002Line 42- Please confirm if a Hemodynamic system is required (hardware and software)Not required.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B500021)Would you please provide us with CAD drawings?Provided to NAC HTME.
VISN 19: VA Rocky Mountain Network660 SALT LAKE CITY, UT660B50001660B500027.d Is Stitching required? During walkthrough it was mentioned that stitching is not clinically required for this room. Please varify and remove 7.d if agreed

3.v site indicated full UPS isnt required as long as a workstation UPS is included. Please verfiy and remove 3.v if agreed.

7.b Minimum patient weight (static) is 600 lbs. Please revise to 500 lbs for expanded competition.

7.c Minimum patient weight (dynamic) 400lbs. Please revise to 350 lbs for exapnded competition. Are new finishes to be included. If so, what finishes should be new.

Should doors and case opens be adjusted for ADA compliance, they currently are less than 48”

Is new flooring needed

What is the existing kVA capacity feeding room 1D66? The breaker in this room is 100A. But what is the distribution panel size feeding this room in kVA? Not amperage. New cabinets, countertops, and floors

Yes, need ADA compliance and ABAAS compliance (Architectural Barriers Act Accessibility Standards)

Yes

100 kVA transformer VISN 2: VA Healthcare Network Upstate New York 528 ALBANY, NY 528B53014 528B53013 Line 38, Please specify whether CZT detectors are required. 1. Is the entire floor being replaced? Or are we just doing a section in the middle of the room. I would suggest they do the whole floor so it can be leveled properly.

2.Is the ceiling / lighting / patient lift remaining? It is in good condition but I want to confirm 3.How many BTU's of cooling are available from the roof top HVAC unit supplying the scan room and control room? The facility person was going to check however he said we had to formally ask in order for him to tell us.

4.Confirm if we are including painting the scan room and or the control room and is there any new countertop / millwork planned 5.Can the electric panel in the scan room accommodate 90amps for the new disconnect / if not - how far is the nearest available source of 90 amps 480V 3 phase power? (the existing system has an 80 amp breaker in the panel in the scan room) CZT Detectors required. See revised documentation on Line 38. 1. Partial replacement. Requesting symmetrical cut to the exisitng floor with existing grounding strips being preserved and reinstalled.

2. These items will remain. No replacement needed.

3. 40k BTUs

4. Repainting should be included, no countertop/millwork needed.

5. 100A Breaker in the scan room is available and all existing loads will be removed.

VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Line 50 and Line 53, Please clarify what type of table you would prefer; standard floating table (no cradle motion included) or tilting table(floating and cradle motion included)?standard floating table
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Room Size, FGI guidelines are not met with current equipment or for the proposed equipment. How will this be addressed?As this Turnkey project is only to replace the existing SPEC-CT with a near in-kind unit and provide only cosmetic upgrades, the FGI Guidelines will not apply
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Are architectural and engineering services required as a part of this room prep proposal? If Yes, is a book specification required or can specifications be incorporated into the drawings?Architectural and engineering services, drawings, and specifications are all required. Specifications must be a specification book based on VA standards.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Can the material specifications (floor covering and base) in the scan room and control room be provided?Floor finish and base materials must be selected based on the TIL and VA standards. Samples must be provided to the VA for selection.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Please confirm that the existing millwork throughout the work area is to remain.New millwork is not required as long as there is available space for any required equipment workstations along with any existing VA system stations.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Where will the UPS be placed? Please provide a floor plan mark up.UPS will not be needed as the current system does not have one - tech specs updated to reflect
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Electrical: 480 volt panel in MP 277/480. Please provide a scale floor plan that shows this panel in relation to panel MP 277/480The VA will provide access to the space along with any available existing drawings to assist with system verification. The contractor's electrical engineer must complete a survey and assessment of the existing electrical infrastructure.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Electrical: What size conduit runs from NHB-A to MP 277/480? How many conductors are in this conduit? What size are each of the conductors? What size circuit breaker is within NHB-A where this feeder is connected?The VA will provide access to the space along with any available existing drawings to assist with system verification. The contractor's electrical engineer must complete a survey and assessment of the existing electrical infrastructure.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Is the fire alarm scope to be included in this project? If yes, please provide contact info for the building fire alarm vendor.The fire alarm system must be assessed by the contractor's engineer. Any deficiencies per VA requirements and NFPA 72 in relation to this renovation must be part of the scope.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Is the connection to the local area network already in place in the work area? If not, please verify that the VA will provide the installation of cabling hardware needed to make this connection.There is already connection to the local network in place
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - HVAC/BMS - Are the mechanical systems servicing the work area connected to an existing BMS system? If so, please provide contct information for the BMS vendor.The full extent of the HVAC/BMS system will need to be verified by the awarded firm. The VA will provide access to the space along with any available existing drawings to assist with system verification. The contractor's mechanical engineer must complete a survey and assessment of the existing HVAC infrastructure.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - HVAC - How much cooling capacity is in place currently serving the work area? Do the existing HVAC systems provide for humidification and de-humidification control to the work area?The full extent of the HVAC system will need to be verified by the awarded firm. The VA will provide access to the space along with any available existing drawings to assist with system verification. The contractor's mechanical engineer must complete a survey and assessment of the existing HVAC infrastructure.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Room shielding - Please provide a sheilding report for the room to call out any upgrades or additions that will be needed to the existing sheilding at the walls, doors, and or view window.Additional room shielding is not anticipated to be required. Any shielding disturbed to facilitate contract scope must be restored at no cost to the government.
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Turnkey Question - Will any ceiling mounted equipment supports need to be included in the proposal? If yes, please identify the type of equipment and in which room.Ceiling mounted equipment supports are only necessary to facilitate the project scope and equipment replacement - none anticipated to be needed
VISN 2: VA Healthcare Network Upstate New York632 NORTHPORT, NY632B51003632B51004Line 22: Please change to 50cm as this is the standard DFOV of CT in the market1. Room size

FGI Guidelines call for three or four feet clearance around imaging equipment.

The existing work area does not provide that for either the existing system or for the proposed new equipment.

Please provide direction:

Is the goal to install the new equipment into the existing space and accept the lack of clearance? Or, Can the work area be expended in either direction? Or, Is another space available that will provide conforming space?

2. Design services

a. Are architectural and engineering services required as part of this room prep proposal?

b. If yes, is a book specification required or can specifications be incorporated into the drawings?

3. Finishes Provide material specifications in the scan and control room work areas for the new work:

a. Floor covering and base

4. Millwork Please confirm that the existing millwork throughout the work area is existing to remain.

5. Electrical / UPS system

a. Is it to be included or not: The technical specification item # 3 ‘Additional specifications’ calls for the inclusion of a UPS system that will provide full functionality of the scanner system and the camera system for a minimum of ten minutes in the event of a power outage.

Please verify if the proposal scope should include a UPS system.

b. If yes – that it is to be included : Where will the UPS be placed: The size will vary based on the manufacturer that the equipment vendor will supply, however the UPS assembly will be approximately 7’-0” wide and 6’-9” high.

Provide a floor plan mark up showing where this UPS could be placed so that a survey can be scheduled to determine the scope related to this equipment (structural supports, supplemental cooling, electrical upgrades, etc.).

6. Electrical / 480 volt equipment feeder assembly As observed on the walk through, there is a 480 volt panel in ‘MP 277/480’ which is called out to be fed from panel ‘NHB-A, in transfer room AO-11B’

a. Provide a scale floor plan that shows this panel in relation to panel MP 277/480.

b. What sized conduit runs from NHB-A to MP 277/480?

c. How many conductors are in this conduit?

d. What size are each of the existing conductors?

e. What size circuit breaker is within panel NHB-A where this feeder is connected?

7. Fire Alarm

a. Is fire alarm scope to be included in the project?

b. If yes, provide contact information for the building fire alarm vendor

8. Electrical

a. Is replacement lighting scope to be included in the project?

9. Network connection

a. For remote service, there will need to be connection to the local area network.

Is this connectivity already in place in the work area?

b. If not, please verify that the VA will provide the installation of cabling and hardware as needed to make this connection.

c. OR, if this needs to be included in the extended installation provide a floor plan identifying the point of tie in for the low voltage cabling run.

10. HVAC / BMS

a. Are the mechanical systems servicing the work area connected to an existing BMS system? If so, please provide contact information for the BMS vendor.

11. HVAC – existing systems

a. How much cooling capacity is in place currently, serving the work area?

b. Do the existing HVAC systems provide for humidification and de-humidification control to the work area?

12. Room shielding

a. Provide a shielding report for the room to call out any upgrades or additions that will be needed to the existing shielding at the walls, doors, and or view window.

13. Ceiling supports

a. Will any ceiling mounted equipment supports need to be included in the Proposal?

If yes, please identity the type of system and which room it will be located within. Tech specs updated 1. As this Turnkey project is only to replace the existing SPEC-CT with a near in-kind unit and provide only cosmetic upgrades. The FGI Guidelines will apply where possible within the existing site constraints.

2. Architectural and engineering services, drawings, and specifications are all required. Specifications must be a specification book based on VA standards.

3. Floor finish and base materials must be selected based on the TIL and VA standards. Samples must be provided to the VA for selection.

4. New millwork is not required as long as there is available space for any required equipment workstations along with any existing VA system stations.

5. UPS will not be needed as the current system does not have one - tech specs updated to reflect.

6. The VA will provide access to the space along with any available existing drawings to assist with system verification. The contractor's electrical engineer must complete a survey and assessment of the existing electrical infrastructure.

7. The fire alarm system must be assessed by the contractor's engineer. Any deficiencies per VA requirements and NFPA 72 in relation to this renovation must be part of the scope.

8. Lighting to be existing to remain. Clean and relamp existing fixtures.

9. There is already connection to the local network in place

10. The full extent of the HVAC/BMS system will need to be verified by the awarded firm. The VA will provide access to the space along with any available existing drawings to assist with system verification. The contractor's mechanical engineer must complete a survey and assessment of the existing HVAC infrastructure.

11. The full extent of the HVAC system will need to be verified by the awarded firm. The VA will provide access to the space along with any available existing drawings to assist with system verification. The contractor's mechanical engineer must complete a survey and assessment of the existing HVAC infrastructure.

12. Additional room shielding is not anticipated to be required. Any shielding disturbed to facilitate contract scope must be restored at no cost to the government.

13. Ceiling mounted equipment supports are only necessary to facilitate the project scope and equipment replacement - none anticipated to be needed

VISN 20: VA Northwest Network531 BOISE, ID531B53001531B530001)Would you please provide us with CAD drawings?CAD files are attached. The main Cath Lab room is 144, control room is 143 and the electrica or other equipmentl is in 144A. For the MRI, the main room is 128/129, control room is 127 and half of 130 is used for electrical or other equipment.
VISN 20: VA Northwest Network531 BOISE, ID531B53001531B53000Based on the Tech Spec document, it appears the request for the detector types and size are backwards than what is clinically relevant. Was it intended to have the wall detector listed as the 17”x17” fixed detector and the table detector listed as the 14”x17” wireless detector?Not relevant to the technical specifications for this procurement. The requirements only mention a digitial detector. The requirements do not define the detector sizes.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530001) Replace flooring or just patch and repair.
2) New casework/countertops or existing to remain.The scope of the turnkey should include anything required for installation of the equipment including general patching requirement for floors, ceiling, and walls.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B53000Information is needed to identify what is required to change existing 100A breaker to 150A breaker; however, access to the panel is located in the hazardous asbestos environment to which vendors have no access. In lieu of access, can a photo of the access panel be provided showing manufacturer, model number, AJC.Refer to photos attached. Rad room 1 panel corresponds with 219B (663B53000). Rad room 2 panel corresponds with 219A (663B53001).
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530002. Unit physical specifications

o. Maximum system weight [lbs] - 900 Please confirm this value or specify which components this refers to (just the table or ceiling suspension or wall stand or generator?).

If for all components in total, please adjust to 2000 lbs.900 lbs is just the table weight. Structural analysis should be included if the weight distribution of the existing ceiling equipment is higher than currently installed Fujifilm FDR D-EVO. Structural support should be included if structural analysis shows that it is needed.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530003. Additional Specifications:

o. Linear tomography

→ Please remove requirement for XR RAD.Vertical and horizontal stitiching is a requirement.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530001.a. Respectfully request change to adjust Wall Bucky from Maximum Weight of 9 lbs to 9.9lbs to allow for Bone Suppression capabilitiesApproved. Anything over the existing system weight is going to require vendor to provide stamped structural drawings showing that the floor can take the weight of the equipment. If structural support is determined to be needed then a modification to the existing work can be discussed.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530003.k. Respectfiully request removal to change the ability to select the table top, upright bucky or table bucky at the Tube Head to increase competition or through the use of wireless remote control.The ability to change between tabletop, upright bucky, or table bucky from tube head is a requirement.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530003.q. Respectfully request removal of Linear Tomography or add Digital Tomosynthesis as an OptionVertical and horizontal stitiching is a requirement.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530001)Would you please provide us with CAD drawings?Please refer to rooms 219B and 219C in the attached drawings.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53002663B530003.q Linear Tomography. Please move this to Added Value for expanded competition.Vertical and horizontal stitiching is a requirement.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530011) Replace flooring or just patch and repair.
2) New casework/countertops or existing to remain.The scope of the turnkey should include anything required for installation of the equipment including general patching requirement for floors, ceiling, and walls.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530012. Unit physical specifications

o. Maximum system weight [lbs] - 900 Please confirm this value or specify which components this refers to (just the table or ceiling suspension or wall stand or generator?).

If for all components in total, please adjust to 2000 lbs.900 lbs is just the table weight. Structural analysis should be included if the weight distribution of the existing ceiling equipment is higher than currently installed Fujifilm FDR D-EVO. Structural support should be included if structural analysis shows that it is needed.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530013. Additional Specifications:

o. Linear tomography

→ Please remove requirement for XR RAD.Vertical and horizontal stitiching is a requirement.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530011.a. Respectfully request change to adjust Wall Bucky from Maximum Weight of 9 lbs to 9.9lbs to allow for Bone Suppression capabilitiesApproved. Anything over the existing system weight is going to require vendor to provide stamped structural drawings showing that the floor can take the weight of the equipment. If structural support is determined to be needed then a modification to the existing work can be discussed.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530013.k. Respectfiully request removal to change the ability to select the table top, upright bucky or table bucky at the Tube Head to increase competition or through the use of wireless remote control.The ability to change between tabletop, upright bucky, or table bucky from tube head is a requirement.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530013.q. Respectfully request removal of Linear Tomography or allow for Digital Tomosynthesis as an alternative.Vertical and horizontal stitiching is a requirement.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530011)Would you please provide us with CAD drawings?Please refer to rooms 219A and 219C in the attached drawings.
VISN 20: VA Northwest Network663 PUGET SOUND, WA663B53003663B530013.q Linear Tomography. Please move this to Added Value for expanded competition.Vertical and horizontal stitiching is a requirement.
VISN 22: VA Desert Pacific Healthcare Network664 SAN DIEGO, CA664B54001664B54003For trade-in please clarify,

1. Last Tube exchange date

2. Is current tube in working condition

3. Current software level "1. Last Tube exchange date - Tube has not been exchanged.

2. Is current tube in working condition - Yes

3. Current software level - Software: syngo CT VC50>Symbia T-2008>VB22A" VISN 22: VA Desert Pacific Healthcare Network 664 SAN DIEGO, CA 664B54001 664B54003 Section 1.a: line 22 32 slice -This is a lockout spec only one vendor can accommodate this spec, reduce from 32 to 16 slice for fair competition.

•Section 4: Workstation Specifications: Is virtualized server acceptable for workstation requirement?

Section 6: Line 22 Software Requirements: What nuclear cardiology configuration software does the customer prefer? Cedars? 4DM? Emery?Turnkey Questions:
1..The space that is being proposed for the SPECT/CT, is not an adequate size to fit any vendors' product that we know of. We have a SPECT only system that would fit. Would the facility be willing to do a SPECT only, or is there another space that would be an adequate size for the SPECT/CT? 1.What is the path for the HEPA filter exhaust duct from the construction area to the exterior of the building?
2.Provide HVAC as-builts for the AC unit(s) serving the PET CT suite.
3.Provide structural slab detail for the Procedure room, as well as confirm if it is slab on grade or an occupied space below?
4.Should vendors include Vibration Testing as part of the scope of work/extended install or will the customer do that separately? If additional work from vibration testing is required, will a Modification be allowed?

Flooring:

1.Existing flooring replaced?
2.Exam and Control room or just Exam room? If so, do you want?
3.Heat welded seamless sheet vinyl or LVT?
4.4” or 6” rubber base or flash cove

Ceilings

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power

1. If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?

HVAC

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?
3.Full UPS a requirement and where do you have space to site a full UPS? Equipment room, closet, same or different floor as imaging equipment?1. at least 32 slice is required Section 4. No Section 6: Cedars Sinai is required"Turnkey Questions:

1. There is no other location in the hospital for the new quipment to be installed. A SPECT/CT is required.

1.Contractor to field verify for exact condition at time of construction for routing. Submit work plan for VA Hygienist to review and approval.

2. VA will provide available as-builts/record drawings to awarded vendor.

3.VA will provide available as-builts/record drawings to awarded vendor.