Tampa Bed Tower Project Management & Activation Services Phase Two Federal contract opportunity
Solicitation number
36A77620Q0079
Issued by
Department of Veterans Affairs Office of Information Service Center

About this file

This pre-solicitation notice and federal contract opportunity document outlines requirements for initial outfitting, transition, and activation services for a new bed tower addition to the James A. Haley Veterans Hospital in Tampa, Florida. The services include project management, furniture, fixtures and equipment planning support and acquisition, concept of operations and transition planning, warehouse and management services, and activation and transition assistance. The estimated period of performance is 24 months to ensure the new bed tower is fully operational by the planned day one clinical services date of January 5, 2022. This is a 100% set-aside for verified service-disabled veteran-owned small businesses. The anticipated solicitation posting date on FBO.gov is February 1, 2020, with a closing date of February 24, 2020.

36A77620Q0079 ATTACHMENT K - JAHVH NBT Construction Schedule 11182019.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Tampa Bed Tower Project Management & Activation Services Phase Two, newest first.
File Type Posted
36A77620Q0079-0002002.pdf PDF
36A77620Q0079-0002001.pdf PDF
36A77620Q0079-0002000.docx DOCX document
36A77620Q0079-0001000.docx DOCX document
36A77620Q0079-0001001.xlsx XLSX spreadsheet
36A77620Q0079-003.pdf PDF
36A77620Q0079-002.pdf PDF
36A77620Q0079-006.pdf PDF
36A77620Q0079-007.pdf PDF
36A77620Q0079-009.pdf PDF
36A77620Q0079-008.pdf PDF
36A77620Q0079-014.pdf PDF
36A77620Q0079-013.pdf PDF
36A77620Q0079-019.xlsx XLSX spreadsheet
36A77620Q0079-017.pdf PDF
36A77620Q0079-010.pdf PDF
36A77620Q0079-016.pdf PDF
36A77620Q0079-015.pdf PDF
36A77620Q0079-004.xlsx XLSX spreadsheet
36A77620Q0079-011.pdf PDF
36A77620Q0079-001.docx DOCX document
36A77620Q0079-005.pdf PDF
36A77620Q0079-018.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original Duration

Remaining Duration

Start Finish Physical % Complete

Total Float

TotalTotal 970 543 22-Feb-18 A 05-Jan-22 0

Design MIlestonesDesign MIlestones 419 0 05-Mar-18 A 01-Nov-19 84

MILE1100 Start Pre-Def Dsgn Workshop 0 0 05-Mar-18 A 100%

MILE1110 Finish Pre-Def Dsgn Workshop 0 0 09-Mar-18 A 100%

MILE1220 65% FT F/MEP/S (Foundations, MEP, Structural) & 35% CD’s 0 0 13-Jul-18 A 100%

MILE1050 35% dsgn Complete 0 0 28-Sep-18 A 100%

MILE1120 IFC Set Issued Phase 0 0 0 09-Oct-18 A 100%

MILE1170 RTC Set Issued (Civil/Utilites) 0 0 09-Oct-18 A 100%

MILE1310 RTC FT F/MEP/S & 65% CD’s [10/27/18] 0 0 09-Oct-18 A 100%

MILE1060 65% dsgn Complete 0 0 27-Mar-19 A 100%

MILE1320 100% dsgn developed and released [1/28/19] 0 0 19-Jun-19 A 100%

MILE1340 100% RTC developed and released [3/25/19] 0 0 19-Aug-19 A 100%

MILE1070 100% dsgn submit for USACE Approval [3/6/19] 0 0 24-Oct-19 A 100%

MILE1330 100% RTC USACE Approval [5/10/19] 0 0 01-Nov-19 0% 44

Construction MilestonesConstruction Milestones 970 543 22-Feb-18 A 05-Jan-22 0

MILE1030 NTP Acknowledged 0 0 22-Feb-18 A 100%

MILE1095 NTP to Contract Completion Date (CCD) 1339 778 22-Feb-18 A 17-Dec-21 0% 19

MILE1090 NTP to Beneficial Occupancy Date (BOD) 1160 595 22-Feb-18 A 17-Jun-21 0% -20

MILE1080 Mobilize For Construction 0 0 18-Jun-18 A 100%

A1170 Turner Mobilize On-site 0 0 18-Jun-18 A 100%

MILE1200 Phase 0 Start 0 0 16-Jul-18 A 100%

MILE1210 Phase 1 Start 0 0 14-Sep-18 A 100%

MILE1140 Start of Piles 0 0 18-Jan-19 A 100%

MILE1350 Start of Foundations 0 0 14-Mar-19 A 100%

EDD2210 Open Emergency Drive @ ED Drive 0 0 15-Mar-19 A 100%

MILE1160 Turnover of New ED Drive 0 0 15-Mar-19 A 100%

MILE.CRNE Tower Crane 0 0 15-Apr-19 A 100%

MILE.STL Start of Steel 0 0 09-Jul-19 A 100%

MILE.DRYW10 Start Layout & Framing [Top Track] 0 0 04-Nov-19 0% 30

MILE.DRYW20 Start Spray-on Fireproofing 0 0 18-Nov-19 0% 37

MILE.TOP TOP OUT Steel 0 0 21-Nov-19 0% 70

MILE.PRE-C Start Precast 0 0 03-Dec-19 0% 3

MILE.GLASS Start Glass 0 0 22-Jan-20 0% 22

MILE.RFG Start Roofing 0 0 07-Feb-20 0% 99

MILE.RFG10 Start Elevators (temp power available) 0 0 28-Feb-20 0% 13

MILE.DRY Building Enclosed 0 0 03-Apr-20 0% 6

MILE.PWR Permanent Power - All Gear 0 0 03-Apr-20 0% 6

MILE.COLD Cold Air Available 0 0 01-May-20 0% 3

MILE.DRYW Start Finishes [drywall] 0 0 01-May-20 0% 109

MILE.ENC Envelope Complete [Roof Detailing, Curtain Wall & Caulking Complete] 0 0 16-Jul-20 0% 0

MILE1360 Construction Complete (inc. Area Punch minus Cx) 0 0 08-Apr-21 0% 36

MILE1130 Beneficial Occupancy Date [BOD 1193 cal days [5/30/21] [constrained date] 0 0 17-Jun-21* 0% -13

MILE1300 Contract Completion Date - Closeout / Rem Govt Trlrs 0 0 05-Jan-22 0% 0

Owner MilestonesOwner Milestones 620 543 28-Jun-19 A 05-Jan-22 0

MILE1460 Bldg 54 Generator -Start Demo Bay #8 0 0 28-Jun-19 A 100%

MILE1470 Bldg 1 Corridor (North Connector) - Level 1 Lobby Area 0 0 05-Sep-19 A 100%

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

01-Nov-19, Design MIlestones

65% FT F/MEP/S (Foundations, MEP, Structural) & 35% CD’s, IFC Set Issued Phase 0, 09-Oct-18 A

RTC Set Issued (Civil/Utilites), RTC FT F/MEP/S & 65% CD’s [10/27/18], 65% dsgn Complete, 100% dsgn developed and released [1/28/19], 100% RTC developed and released [3/25/19], 100% dsgn submit for USACE Approval [3/6/19], 100% RTC USACE Approval [5/10/19], NTP to Beneficial Occupancy Date (BOD)

Start of Piles, 18-Jan-19 A

Start of Foundations, 14-Mar-19 A

Open Emergency Drive @ ED Drive, Turnover of New ED Drive, Tower Crane, 15-Apr-19 A

Start of Steel, 09-Jul-19 A

Start Layout & Framing [Top Track], 04-Nov-19

Start Spray-on Fireproofing, 18-Nov-19

TOP OUT Steel, Start Precast, 03-Dec-19

Start Glass, 22-Jan-20

Start Roofing, 07-Feb-20

Start Elevators (temp power available), 28-Feb-20

Building Enclosed, Permanent Power - All Gear, Cold Air Available, 01-May-20

Start Finishes [drywall], 01-May-20

Envelope Complete [Roof Detailing, Curtain Wall & Caulking Complete], Construction Complete (inc. Area Punch minus Cx), Beneficial Occupancy Date [BOD 1193 cal days [5/30/21] [constrained date], Bldg 54 Generator -Start Demo Bay #8, 28-Jun-19 A

Bldg 1 Corridor (North Connector) - Level 1 Lobby Area, 05-Sep-19 A

JAHVH NBT Construction Schedule_WORKING Steel SOG Precast Milestones 15-Nov-19 10:47

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone summary

Page 1 of 2 TASK filter: Milestone.

© Oracle Corporation

Activity ID Activity Name Original Duration

Remaining Duration

Start Finish Physical % Complete

Total Float

SD-0160 Gov't Provided VC Equip Selection Period 44 44 01-Nov-19 09-Jan-20 0% 44

MILE1500 Bldg 1 - Tunnel @ Pool (to be linked to interior work schedule) 0 0 18-Dec-19 0% 322

MILE1530 Toilet and Bath Accessories - Cut Sheets [backing] 0 0 20-Dec-19 0% 199

MILE1540 All other VC Items - Cut Sheets [backing] 0 0 20-Dec-19 0% 199

SDR-1120 Gov't Provided VC equip Internal review and Publication 60 60 10-Jan-20 06-Apr-20 0% 44

MILE1380 Patient Lifts - start rough-in/Rough-in Kits required 0 0 16-Mar-20 0% 93

MILE1420 Bldg 1 ICU Room (North Connector) - Level 2 - Date to be confirmed after 100% CDs 0 0 23-Mar-20 0% 259

MILE1490 CLC - Tunnel @ Corridor (to be linked to interior work schedule) 0 0 23-Mar-20 0% 259

SDF-1150 Gotv't Provided VC equip Fab & Delivery 120 120 07-Apr-20 24-Sep-20 0% 44

MILE1430 Bldg 1 Corridor (South Connector)- Level 2 - Date to be confirmed after 100% CDs 0 0 08-Apr-20 0% 194

MILE1480 Bldg 1 Room (South Connector) - Level 1 - Date to be confirmed after 100% CDs 0 0 08-Apr-20 0% 194

MILE1370 Headwalls - start rough-in/Rough-in Kits required 0 0 05-Jun-20 0% 42

MILE1390 Medical Booms - start rough-in/Rough-in Kits required 0 0 05-Jun-20 0% 35

MILE1510 Install Patient Lifts 0 0 28-Jul-20 0% 180

MILE1450 Install Medical Booms 0 0 29-Jul-20 0% 179

MILE1410 Toilet and Bath Accessories - ROJ (VC Items Delivery) 0 0 21-Aug-20 0% 162

MILE1520 Install Headwalls 0 0 25-Sep-20 0% 128

MILE1400 Canteen (Kitchen/Servery) VCS Equipment - ROJ (VC Items Delivery) 0 0 02-Oct-20 0% 153

MILE1590 All Other VC Items - ROJ (Tray Assemblies, Ice Machines, Wall Brackets etc.) 0 0 02-Oct-20 0% 153

MILE1440 IT Room Fitout - Room available to OIT 0 0 09-Apr-21 0% 36

MILE1550 Infection Control & Safety Inspections 60 60 18-Jun-21 13-Sep-21 0% 75

MILE1580 Day in a Life Simulation 0 0 16-Sep-21 0% 75

MILE1570 Ribbon Cutting Ceremony 0 0 11-Oct-21 0% 58

MILE1560 1st Patient Day [6 months after BOD - 138d] 0 0 05-Jan-22 0% 0

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Gov't Provided VC Equip Selection Period

Bldg 1 - Tunnel @ Pool (to be linked to interior work schedule), 18-Dec-19

Toilet and Bath Accessories - Cut Sheets [backing], 20-Dec-19

All other VC Items - Cut Sheets [backing], 20-Dec-19

Gov't Provided VC equip Internal review and Publication

Patient Lifts - start rough-in/Rough-in Kits required, 16-Mar-20

Bldg 1 ICU Room (North Connector) - Level 2 - Date to be confirmed after 100% CDs, 23-Mar-20

CLC - Tunnel @ Corridor (to be linked to interior work schedule), 23-Mar-20

Gotv't Provided VC equip Fab & Delivery

Bldg 1 Corridor (South Connector)- Level 2 - Date to be confirmed after 100% CDs, 08-Apr-20

Bldg 1 Room (South Connector) - Level 1 - Date to be confirmed after 100% CDs, 08-Apr-20

Headwalls - start rough-in/Rough-in Kits required, 05-Jun-20

Medical Booms - start rough-in/Rough-in Kits required, 05-Jun-20

Install Patient Lifts, 28-Jul-20

Install Medical Booms, 29-Jul-20

Toilet and Bath Accessories - ROJ (VC Items Delivery), 21-Aug-20

Install Headwalls, 25-Sep-20

Canteen (Kitchen/Servery) VCS Equipment - ROJ (VC Items Delivery), 02-Oct-20

All Other VC Items - ROJ (Tray Assemblies, Ice Machines, Wall Brackets etc.), 02-Oct-20

IT Room Fitout - Room available to OIT, 09-Apr-21

Infection Control & Safety Inspections

Day in a Life Simulation, Ribbon Cutting Ceremony, JAHVH NBT Construction Schedule_WORKING Steel SOG Precast Milestones 15-Nov-19 10:47

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone summary

Page 2 of 2 TASK filter: Milestone.