This is a Scope of Work document for the City of Wheat Ridge, Colorado's 35th Avenue Multimodal Improvements project, specifically detailing the final design phase requirements for a consultant contract. The project encompasses a 1.5-mile corridor extending the existing 35th Avenue neighborhood bikeway from Sheridan Boulevard to Wadsworth Boulevard in Wheat Ridge, integrating traffic-calming measures, bicycle infrastructure, and pedestrian amenities. The scope includes 13 major task categories: project management and administration; public involvement including stakeholder meetings, City Council presentations, and a public open house; topographic surveying using UAS LiDAR and aerial imagery at 2-inch pixel resolution; utility investigation including coordination with up to 10 utility owners and up to 40 test hole excavations; hydrology and hydraulic engineering with stormwater design; comprehensive engineering and design producing 30%, 60%, 90%, and 100% construction plans; landscape design and streetscape improvements; right-of-way plan development with property acquisition tracking; lighting design; geotechnical investigation and pavement design; traffic analysis and traffic-calming design; right-of-way acquisition services; and construction support services. The consultant will conduct 22 bi-weekly progress meetings and 4 major plan review meetings, prepare monthly invoices and progress reports, and develop opinion of probable construction costs at each design phase utilizing CDOT bid items and recent City of Wheat Ridge project data.
The project design standards follow a hierarchy including AASHTO guidelines, CDOT M&S Standards, City of Wheat Ridge codes, NACTO Urban Street Design Guidelines, and FHWA MUTCD standards. The corridor design will be context-sensitive with 5-foot attached sidewalks and sharrows in higher-activity zones near parks and destinations, while utilizing advisory shoulders in constrained segments. The consultant will develop a comprehensive project manual for advertisement and bid support, facilitate right-of-way acquisition with exhibits and legal descriptions, and perform geotechnical and traffic studies to inform final design recommendations. Community engagement efforts will build upon previous planning initiatives including the 2017 Bicycle and Pedestrian Master Plan, 2020 neighborhood engagement program with over 240 participants, and 2025 City Plan designation of the corridor as a Neighborhood Bike Connector. No specific pricing, funding sources, contract duration, award dates, or bidder conference information is provided in this scope of work document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit A City of Wheat Ridge W 35th Ave TIP Final Design Scope of Work – 6/1/2026
City of Wheat Ridge W 35th Avenue Traffic Improvement Plan Final Design Scope of Work – June 1, 2026
INTRODUCTION
The 35th Avenue neighborhood bikeway in Denver now ends at Sheridan Boulevard, leaving a critical gap in bike infrastructure between Sheridan and Wadsworth Boulevard. This corridor is also a key pedestrian route, providing access to amenities like Panorama Park, Founders Park, the Active Adult Center, and the Wadsworth Urban Center. Unfortunately, many sidewalks along this stretch are inadequate or non‐existent, forcing pedestrians to walk in the street—creating dangerous conflicts with both cyclists and vehicles. The 35th Avenue Multimodal Improvement Project will address these issues and enhance safety and accessibility for all users.
BACKGROUND
The 35th Avenue Multimodal Improvements project will establish a 1.5-mile multimodal corridor connecting Sheridan Boulevard to Wadsworth Boulevard. This segment will extend the existing 35th Avenue neighborhood bikeway in Denver to reach the Wadsworth Urban Center, providing essential pedestrian and bicycle accesses, especially valuable since the east end of the current bikeway lies just blocks from both the Denver Central Business District and the 41st & Fox Transit-Oriented Development.
By bridging this gap, the project will create a vital non‑motorized connection between western and central Denver and Wheat Ridge. It enhances access to pedestrian-focused zones near 35th & Wadsworth and lies within three blocks of the 38th & Sheridan pedestrian district. Along the route, improved multimodal access will benefit key destinations like two parks and Wheat Ridge’s Active Adult Center.
Critically, the improvement links to the shared-use trail under construction along the east side of Wadsworth, which connects to the Clear Creek Trail—part of the broader Peaks-to-Plains Regional Trail System. It also ties into the Pierce Street bike lanes, offering further connectivity north and south to the 32nd Avenue Regional Bikeway, 26th Avenue bike lanes, and onward into Lakewood acppubs.com.
Nearly 24,000 residents within the project area will benefit from increased safety and improved connectivity, linking them to multiple regional multimodal routes. The corridor enhancements also include traffic-calming features aimed at reducing speeds and prioritizing safe, shared use.
This initiative builds upon the current Denver multimodal corridor ending at Sheridan by extending infrastructure to Wadsworth and directly serving the Wadsworth Urban Center in Wheat Ridge. Meanwhile, a shared-use path is already under construction between 35th Avenue and the Clear Creek Trail, integrating the corridor into the regional trail network and facilitating inter-subregional access across Jefferson County and Denver.
PAST PLANNING EFFORTS Comment by Ashley Holland: Added the section below.
Improvements to W 35th Avenue between Sheridan Boulevard and Wadsworth Boulevard have been identified as a community priority through multiple planning and engagement efforts over the past several years. In 2017, the city’s Bicycle and Pedestrian Master Plan designated this segment of W 35th Avenue as a Neighborhood Bikeway and recommended improvements including pavement markings, signage, traffic calming measures, crossing enhancements, and wayfinding elements to improve multimodal safety and connectivity.
In 2020, residents reaffirmed the need for corridor improvements through the city’s neighborhood engagement program, Let’s Talk East Wheat Ridge. Community input gathered through that process led to the launch of the W 35th Avenue Street Improvements project in 2022, which focused on identifying neighborhood priorities and desired corridor enhancements. More than 240 area residents participated in the engagement process. Key themes that emerged from community feedback included:
· Concerns about vehicle speeds and traffic safety along the corridor
· Prioritizing safer conditions for pedestrians, bicyclists, and individuals using mobility aids
· A strong desire for continuous and connected sidewalk infrastructure Most recently, the 2025 City Plan identified W 35th Avenue between Sheridan Boulevard and Teller Street as a Neighborhood Bike Connector. This designation calls for implementation of the best feasible bicycle facility to improve east-west connectivity. Improvements may include bike lanes, traffic calming measures, shared lane markings, signage, and related multimodal safety enhancements.
Together, these planning efforts and community engagement initiatives have established a strong foundation for the current final design process.
SCOPE OF WORK Comment by Lauren Mikulak: Did the TIP or funding agreement specific sidewalk widths? Comment by Logan Huffaker: @Lauren Mikulak I haven’t seen anything specifying sidewalk widths. Should we go with our typical section with 5ft attached or 6ft detached? Comment by Lauren Mikulak: It would be 5 foot attached I think if we’re also trying to fit in bike facilities The City seeks the Consultant’s expert guidance in shaping a varied and context-sensitive corridor along 35th Avenue, extending the neighborhood bikeway from Sheridan Boulevard to Wadsworth Boulevard. This project must integrate three key elements—traffic calming, bicycle infrastructure, and pedestrian amenities—adapted to local conditions and community input.
· Corridor Tailoring: Recognizing diverse conditions and feedback from residents along the route, the design will be customized. In zones with higher activity—such as parks, major walking destinations, and higher-traffic areas, the focus will be on installing 5 foot wide attached sidewalks and sharrows (shared-lane markings).
· Strategic Flexibility: In less-traveled or more constrained segments, where right-of-way or property access is sensitive, the use of advisory shoulders will be considered. This approach preserves access to adjacent properties while promoting multimodal use and minimizing potential impacts.
0.0 PROJECT MANAGEMENT & ADMINISTRATION
0.1 Administer the contract per City of Wheat Ridge requirements
0.2 Prepare monthly invoices and progress reports.
0.3 Schedule & conduct a project kick-off meeting with project staff and bi-weekly progress meetings with project staff and prepare meeting minutes and/or summaries (assume 22 meetings).
0.4 Schedule & conduct plan deliverable review meetings with project staff after major submittals (assume 4 meetings).
1.0 PUBLIC INVOLVEMENT
1.1 Plan, coordinate, and hold small group stakeholder meetings with properties most impacted (assume 4 separate meetings).
1.2 Develop materials to support City staff presentations to City Council (assume 2 presentations).
1.3 Plan, coordinate, and hold one public open house meeting and online engagement opportunity. Develop informational flyers & invites. City will develop mailing list and send mailings. Provide public engagement results to staff for use on the City website.
2.0 TOPOGRAPHIC SURVEY
2.1 Perform UAS LiDAR survey of the entire corridor at 2-inch pixel resolution; includes Calibration, QC, and CAD Processing. Delivered as 40 Scale Detailed Planimetric Mapping within right-of-way in Civil 3D.
2.2 Perform Aerial Imagery Collection of the entire corridor with 2-inch pixel resolution; includes Calibration, QC, and CAD Processing of 3D surfaces and contours. Delivered as 40 Scale contours and surfaces in Civil 3D
2.3 Perform traditional detailed topographic survey of critical areas (sidewalk ramps, tie-in curb/gutter, pavement tie-in points, etc. Includes QC and CAD Processing of line features in Civil 3D). Survey Control shall be City of Wheat Ridge Datum, Central Zone, NAD 83 US Feet.
3.0 UTILITY INVESTIGATION
3.1 Review existing utility reports, records, maps, and plans from study phase.
3.2 Perform and mark on-site designating & locating of existing UG utilities (QLC). Survey marked locations (QLB) and process into topographic survey CAD files.
3.3 Develop preliminary utility plan sheets & potential locations for QLA Test Holes.
3.4 Perform preliminary utility coordination with up to 10 impacted utility owners. Develop preliminary utility conflict plans for up to 5 separate utility owners.
3.5 Verify Test Hole locations, perform up to 40 test hole excavations with survey and field reports,
3.6 Finalize Utility Plans with QLA information.
3.7 Perform final utility coordination with up to 10 impacted utility owners. Develop relocation plans for up to three utility facilities. Develop and assist the City with executing up to 3 utility agreements.
4.0 HYDROLOGY AND HYDRAULIC ENGINEERING
Evaluate current stormwater infrastructure and design improvements for performance and flood mitigation. No floodplain impacts anticipated; floodplain permitting excluded.
4.1 Task management and coordination (internal hydraulic discipline management and stakeholder meetings).
4.2 H&H Modeling, Design, and Reporting
4.3 Update existing conditions H&H based on comments or new survey data.
a. Complete H&H drainage design including minor and major storm criteria:
i. Determine locations, sizes, and alignment based on conceptual hydraulic design. Identify locations by highway station or coordinates, as appropriate.
ii. Determine the allowable headwater and roadway spread.
iii. Assess the degree of sediment and debris problems to be encountered
iv. Update per roadway comment and review changes after 30%, 60%, and 90% review periods.
4.4 Preliminary (30%) Plans
i. 30% plans will consist of general layout of the system with preliminary plan and profile sheets for the proposed drainage system. This will be used to highlight potential conflicts with ROW and Utilities.
4.5 60% Plans
i. Refinements to the 30% plans will be implemented based on 30% city review comments and conflict resolution between ROW and Utilities. Major redesign of the roadway and general layout of the system are not anticipated past the 60% design stage.
4.6 90% Plans, Details, and Specifications
i. 60% city review comments will be addressed, and plans will be refined to the 90% level, minor changes to pipe elevations and alignment are included.
ii. Necessary details and specifications will be provided at this stage.
4.7 100% Plans, Details, and Specifications
i. 90% city review comments will be addressed, and plans will be refined to the 100% level. Only very minor changes to pipe alignment or elevations are anticipated at this level. Plans will be reviewed for standardization across disciplines.
ii. Final refinements to the details and specifications will be provided at this stage.
5.0 ENGINEERING & DESIGN
5.1 Develop alignment and profile for roadways, curbs, and ramps.
5.2 Perform comprehensive 3D modeling and cross sections of the project template to develop plan sheets.
Design Criteria to be followed (in order of precedence and hierarchy):
· AASHTO; A Policy on Geometric Design of Highways & Streets
· AASHTO Roadside Design Guide
· FHWA Manual of Uniform Traffic Control Devises (MUTCD)
· CDOT M&S Standards
· City of Wheat Ridge Zoning and Development Code
· NACTO Urban Street Design Guidelines
· AASHTO Guide for the Development of Bicycle Facilities
PLAN DEVELOPMENT AND PRODUCTION
Develop 30% construction plans for roadway, bicycle facilities, sidewalks, and drainage facilities to include:
Title sheet Survey Control Diagram Geometric Control Typical Section Removals Roadway Plan & Profiles Preliminary Intersection Details Preliminary ADA Ramp Details Preliminary Drainage Plan & Profiles Preliminary Drainage Details Develop 60% construction plans for roadway, bicycle facilities, sidewalks, and drainage facilities to include 30% Plan elements plus:
Standard Plans List General Notes SAQ & Quantity Tabulations Intersection Details ADA Ramp Details indicating compliance with the latest version of CDOT “Curb Ramp” standards M-608-1 Comment by Lauren Mikulak: Is this meant to be a black bullet as part of 60% plans instead of 6.3?
Preliminary Driveway Details Drainage Plan & Profiles Drainage Details Preliminary Lighting Plans & Details Preliminary Signing & Striping Plans, Details, and Quantities Preliminary Construction Stormwater/Erosion Control Sheets (SWMP or ECS) Utility Plans Preliminary Construction Phasing/MOT Plans Develop 90% construction plans to include 60% Plan elements plus:
Driveway Details Lighting Plans & Details Signing & Striping Plans, Details, and Quantities Construction Stormwater/Erosion Control Sheets (SWMP or ECS) Utility Plans Construction Phasing/MOT Plans Miscellaneous Details Cross Sections Finalize 100% PS&E construction plans.
Develop Preliminary Construction Specifications at 60% and final Specifications at 90% and 100%. It is assumed CDOT Construction Specifications will primarily be utilized.
Develop opinion of probable construction cost estimate at 30%, 60%, 90%, and 100%. CDOT bid items will be utilized in the plans and CDOT bid history will be utilized to develop the opinion of probably cost, with adjustments based on recent City of Wheat Ridge construction projects.
Develop Project Manual for Advertisement and Contract Provide Bid & Award Support for selection and award of construction contract.
7.0 LANDSCAPE DESIGN
7.1 Develop preliminary corridor streetscape design & cost estimate (per SF) for 30% plans.
7.2 Facilitate discussion and selection of surface water quality elements (i.e. bioswales) where feasible for 60% plans.
7.3 Develop detailed streetscape design and planting & irrigation quantities for 60% plans.
7.4 Develop detailed planting & irrigation plans, quantities, and specifications for 90% and 100% plans.
ROW PLAN DEVELOPMENT
Develop parcel tracking spreadsheet and calculate estimated property impact polygons (acquisition and TCE’s) for use on 30% plans and in tracking spreadsheet (with opinion of acquisition costs).
Develop Preliminary ROW Plans with detailed acquisition and easement shapes (no exhibits or legal descriptions).
Develop Final ROW Plans with detailed acquisition and easement shapes. Develop exhibits and legal descriptions for fee acquisitions.
Perform 1-on-1 coordination with affected landowners.
Field stake acquisition and easement impacts at the request of landowners. Limited to one staking per parcel; parcels will be combined and staked in groups to minimize cost.
9.0 LIGHTING DESIGN
In general, this scope is to perform necessary lighting design for roadway projects. Gather available data and review existing lighting conditions, equipment and delivery systems.
9.1 Coordinate with City staff to determine needs/desires for future corridor lighting.
9.2 Develop a photometric plan for review and discussion with City Staff.
9.3 Develop plans at 60%, 90% and Construction Documents. Plans will include the following information:
· Lighting Layouts
· Conduit and other electrical delivery infrastructure needs
· Lighting details
· Electrical connection design/details
· Opinion of probably cost of equipment for each submittal
10.0 GEOTECHNICAL INVESTIGATION
In general, this scope is to perform necessary geotechnical investigations for roadway projects. See the RMG detailed Scope of Work for exact tasks to be performed.
10.1 In consultation with the project team, develop preliminary investigation map of boreholes and soils samples, depths, and required tests.
10.2 Perform field investigation, including appropriate and approved traffic control and laboratory testing.
10.3 Perform pavement design & recommendations.
10.4 Develop draft and final geotechnical report with findings and recommendations.
11.0 TRAFFIC ANALYSIS & TRAFFIC CALMING DESIGN
11.1 Conduct existing conditions traffic analysis including speed data review, traffic volume review, crash history review, and multimodal conflict evaluation.
11.2 Evaluate and recommend traffic calming measures including curb extensions, mini traffic circles, raised crossings, speed cushions, median treatments, advisory bike lanes, and intersection visibility improvements.
11.3 Prepare signing and striping concepts consistent with MUTCD, NACTO, and City standards.
11.4 Evaluate on-street parking impacts and operational considerations along the corridor.
12.0 ROW ACQUISITION SERVICES
In general, this scope is to perform necessary Right-Of-Way notice, negotiation, closing, and acquisition services meeting the requirements of the Uniform Act. See the WSLS detailed Scope of Work for exact tasks to be performed.
12.1 Perform initial property owner engagement at 60% design level.
12.2 Draft & send notice of intent letters to impacted property owners.
12.3 Perform property valuations.
12.4 Draft & send offer letters to impacted property owners.
12.5 Perform negotiations.
12.6 Draft & send final offer letters to impacted property owners.
12.7 Perform closings.
13.0 CONSTRUCTION SUPPORT SERVICES
13.1 Provide engineering support during construction including responses to RFIs, review of submittals and shop drawings, and preparation of design clarifications.
13.2 Attend preconstruction meetings and periodic construction progress meetings
13.3 Review contractor requests for information and substitution requests.
13.4 Prepare plan revisions or supplemental sketches as required due to field conditions.
13.5 Conduct substantial completion punch list walkthrough and final acceptance review.