This document is a Notice of Intent to Award from the Oregon Department of Transportation (ODOT) for a Mini-Request for Proposals (Mini-RFP) for the I-84 (Westbound) Union Pacific Railroad Bridge (Hood River) project in Hood River County. ODOT has selected David Evans and Associates as the top-ranked firm for negotiations of a Work Order Contract to provide personal services such as bridge quality control checking, bridge load rating, bridge design CAD drafting, superstructure and substructure design, and construction support services. The anticipated contract term is 3 years, and the construction budget is not expected to exceed $500,000.
The selected firm will be required to submit a detailed Breakdown of Costs and an updated Consultant Quality Plan prior to contract award. Payment will be made based on a combination of compensation methods, including cost plus fixed-fee, fixed price, and time and materials. The project is funded by a mix of Federal Highway Administration (FHWA) and state sources, and there is no information provided regarding incumbent vendors or current contractors. The contract opportunity is not set aside for any specific type of organization.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20242032_G1_Notice of Award.pdf | ||
| 35919_Mini RFP Att A Cover Sheet.doc | DOC document | |
| 35919_Final_ Mini_v2.docx | DOCX document | |
| 35919_Final_Attachment B_SOW.docx | DOCX document | |
| 35919_Addendum #1_Final.docx | DOCX document | |
| 35919_QA 1_Final.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OREGON DEPARTMENT OF TRANSPORTATION
Notice of Intent to Award
DATE: 08/14/2024
TO: 35919 Proposers SUBJECT: Mini-RFP (S-73000-00009348) (PCMS # 35919) for: I-84 (Westbound) Union Pacific Railroad Bridge (Hood River) David Evans and Associates is the top ranked firm selected.
for negotiations of a Work Order Contract (WOC) to provide Personal Services as specified in the above referenced Mini-Solicitation. The scores and rankings of all Proposers are shown in the score matrix accompanying this notice. The award submittal requirements stated in the Mini-Solicitation are summarized on Attachment 1 of this notice.
Stephen Burgess will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work (SOW), schedule of performance and costs under the WOC. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC-NBR as applicable) and submitted to ODOT’s PM. A BOC must demonstrate subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal set forth in the Mini-Solicitation. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:
| Activity |
| Responsible Party |
| Business Days |
| Negotiations |
| Establish work session to discuss the SOW with Consultant |
| ODOT PM |
| Within 5-10 days of this notice (days depend on size and complexity of the project) |
| Respond to work session with comments/edits to SOW |
| Consultant |
| Within 5 days of work session |
| Respond to SOW comments/edits |
| ODOT PM / OPO |
| Within 3 days of receipt of Consultant comments/edits |
| Submission of BOC |
| Consultant |
| Within 5-10 days of final ODOT scope (days depend on size and complexity of the project) |
Respond to BOC, negotiate, and
Submit for legal sufficiency
ODOT PM / OPO
OPO
Within 5-10 days of Consultant submission of the BOC (days depend on the size and complexity of the project)
| Legal Sufficiency |
| OPO, ODOT PM, and DOJ |
| Within 15 (Mini-Solicitation) & 20 (Formal) days of submission by ODOT PM |
| Signature routing and execution |
| OPO, Consultant, and ODOT Expenditure Authority (if required) |
| Within 6-8 days from initial routing |
| Issue Notice to Proceed (NTP) |
| ODOT PM |
| 1 day after execution |
Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice. If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon. If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).
Note that no work is authorized until the WOC is executed and Consultant has received a written NTP from the ODOT PM.
ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.
Sincerely, David Brudnok ODOT Procurement Office | Contract Coordinator | OPBC ODOT Procurement Office, MS#2-2 355 Capitol ST NE, Salem OR 97302-1166 Phone: 503-871-7881|david.brudnok@odot.state.or.us
OPO Purpose: “OPO provides Procurement solutions with integrity by fostering collaborative experiences that advance the transportation system.”
OPO Vision: “We are a trusted partner dedicated to consistently optimizing procurement expertise and resources with a proactive, results-oriented approach.”
Attachment 1 – Award Submittal Requirements Please email to me, the Contract Coordinator, the following items if marked as “REQUIRED” in the Mini-Solicitation (see detailed requirements and due date for each item in Section 2.1 of the Mini-Solicitation).
· Billing Rate Information (if applicable)
· Breakdown of Costs
· Certificates of Insurance
Direct Deposit via Automated Clearing House (ACH). For Consultants that receive ongoing monthly payments from Agency on one or more contracts or work orders, Agency prefers making Consultant payments via ACH direct deposit. While not required, if Consultant has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, Consultant must complete a Vendor ACH Authorization form and submit to Agency per the instructions on the form. To expedite Consultant’s payments to its subcontractors, if applicable, Consultant should make reasonable efforts to offer ACH direct deposit payments.
image1.png
File details come from the government source that posted it. Updated .