This document is a Request for Competitive Quotes (RFCQ) for the McMinnville Maintenance Station Camera Upgrade project. The project is being managed by the Oregon Department of Transportation (ODOT) and involves the installation of a new Network Video Recorder (NVR) system and IP video cameras at the McMinnville Maintenance Station. The RFCQ outlines the required camera specifications, installation responsibilities, testing, labeling, and documentation requirements. The successful contractor will be responsible for the full installation of the camera system, with ODOT providing the NVR and installing the CAT 6 cabling. The contract includes a 3-week timeline for substantial completion and 4-week timeline for final completion, with liquidated damages of $100 per day for delays. The contract also includes standard state and federal compliance requirements.

The RFCQ does not specify pricing terms or set-asides. It is a competitive solicitation, and no incumbent contractor is identified. Funding for the project is provided by ODOT. Contractors must meet the specified technical and certification requirements for the camera equipment and installation work.

View the file

Other files

File Type Posted
35651_Exhibit 2 Plans.pdf PDF
35650 Preliminary Bid Tab.xlsx XLSX spreadsheet
35650_Attachment E Camera Layout.pdf PDF
35650_RFCQ_Mac MS Camera.pdf PDF
35650 Questions and Answers.docx DOCX document
35651 Preliminary Bid Tab.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A – Specifications

McMinnville Maintenance Station Camera Upgrade

These specifications identify certain responsibilities of the Project Manager that would otherwise be responsibilities of the Owner’s Authorized Representative, in accordance with General Conditions Section A.1. ODOT, as Owner, hereby delegates those identified responsibilities to the Project Manager. All other responsibilities of Owner remain with the Owner’s Authorized Representative identified in the Public Improvement Agreement Form.

1. PROJECT MANAGER:

Eric Spond ODOT Facilities Service Branch 885 Airport Rd SE, Bldg. X Salem, OR 97301 Phone: 503-302-3705 Email: Eric.SPOND@odot.state.or.us

2. 2021 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION:

Not applicable for this project.

3. SPECIFICATIONS FOR ODOT IP CAMERA SYSTEM

AA. GENERAL

1. SUMMARY

a. Section includes Network Video Recorder (NVR); Video Cameras, Cabling, Labeling, Programming and Testing

b. Products - IP video cameras, with multi-streaming (H.265, H.264 and MJPEG);

c. 2 RU rack-mounted NVR, capable of processing video up to 64 IP video cameras.

Supplied by ODOT/Installed and Programmed by Contractor.

d. Contractor to furnish and install patch panel, patch cables, mounts, and cable management supplies as needed for complete system.

e. Related Requirements; installation, testing, identification and Administration.

f. Contractor must apply and pay for permit as required by local jurisdiction.

2. REFERENCES

a. Abbreviations

(1) AGC - Automatic Gain Control

(2) ARP – Address Resolution Protocol

(3) AWB - Automatic White Balance

(4) BLC – Back light compression

(5) CBR – Constant Bit Rate

(6) CVBS – Color, Video, Blanking, Sync

(7) DHCP - Dynamic Host Configuration Protocol mailto:Eric.SPOND@odot.state.or.us

(8) DNR – Digital Noise Reduction

(9) DNS - Domain Name Server

(10) DDNS – Dynamic Domain Name Server

(11) DSCP – Differentiated Services Code Point

(12) fps - frames per second

(13) FTP - File Transfer Protocol

(14) GOV – Group of Video

(15) GUI – Graphical User Interface

(16) HD – High Definition

(17) HTTP - HyperText Transfer Protocol

(18) ICMP – Internet Control Message Protocol

(19) IGMP - Internet Group Management Protocol

(20) IP - Internet Protocol

(21) JPEG - Joint Photographic Experts Group

(22) MJPEG - Motion JPEG

(23) MP - MegaPixel

(24) MPEG - Moving Pictures Experts Group

(25) NAS – Network Attached Storage

(26) NTP - Network Time Protocol

(27) PIM-SM - Protocol Independent Multicast-Sparse Mode

(28) PoE - Power over Ethernet

(29) PPPoE – Point to Point Protocol over Ethernet

(30) RTP - Real-time Transport Protocol

(31) RTCP – Real-Time Control Protocol

(32) RTSP - Real-Time Streaming Protocol

(33) SDK – Software Development Kit

(34) SMTP - Simple Mail Transfer Protocol

(35) SNMP – Simple Network Management Protocol

(36) SSL – Secure Sockets Layer

(37) TCP - Transmission Control Protocol

(38) UDP - User Datagram Protocol

(39) UPnP – Universal Plug and Play

(40) VBR – Variable Bit Rate

(41) VMS - Video Management System

(42) WDR – Wide Dynamic Range

(43) LDC – Lens Distortion Correction

b. Reference Standards

(1) Network - IEEE

(A) 802.3 Ethernet Standards

(B) 802.1x Port-based Network Access Control

(2) Video

(A) ISO/IEC 23008-2:2013, MPEG-H Part2 (ITU H.265, HEVC)

(B) ISO / IEC 14496–10, MPEG-4 Part 10 ( ITU H.264)

(C) ISO / IEC 10918 – JPEG

(D) ONVIF – Profiles S and G

(3) Emissions

(A) FCC-47 CFR Part 15 Subpart B Class B

(B) CE EN 55022:2010

(4) Immunity - CE

(A) EN 50130-4:2011

(B) EN 61000-3-3:2014

(C) EN 61000-4-2:2009

(D) EN 61000-4-3:2006+A2:2010

(E) EN 61000-4-4:2012

(F) EN 61000-4-5:2014

(G) EN 61000-4-6:2009

(5) Safety

(A) UL listed

(B) CE EN 50581:2012 (hazardous substances)

(6) Ingress Protection and Vandal Resistance

(A) ANSI / IEC60529 – Degrees of Protection Provided by Enclosures : IP67

(B) IEC EN 62262 - Degrees of protection provided by enclosures for electrical equipment against external mechanical impacts : IK10

(C) IEC 60068-2-75 : IK10

c. Definitions

(1) GOV (Group of Video object planes) - A set of video frames for H.264 and H.265 compression, indicating a collection of frames from the initial I-Frame (key frame) to the next I-Frame. GOV consists of 2 kinds of frames: I-Frame and P-Frame.

(2) Dynamic GOV – Dynamic assignment of GOV length based on the complexity of the scene to efficiently manage bitrate of the video stream and reduce the storage required.

(3) Multi-exposure wide dynamic range - Operation which automatically adjusts shutter speed to provide a wide range between dark and light areas visible at the same time, preventing backlighting issues. Long exposure is used for dark areas and a short exposure is used in light areas.

(4) Dynamic fps – Dynamic assignment of fps (frames per seconds) based on the movement of object(s) in the scene to efficiently manage bitrate of the video stream and reduce the storage required.

(5) Smart Codec – Smart Codec that controls quantization parameter and dynamic fps in H.265 and H.264 to efficiently manage bitrate of the video stream and reduce the storage required.

BB. Network Video Recorder (Video Storage Server)

1. ODOT will provide and install the Network Video Recorder.

CC. CAMERAS

1. GENERAL SPECIFICATIONS

a. Ensure that the camera:

(1) Is a dome or positional type as specified in the pre-bid or pre-construction site walk.

(2) Is compatible with encoder integral to IP camera.

(3) Has Electronic Image Stabilization

(4) Has Compass Direction

(5) ONVIF Compatible

(6) NTCIP Complaint

(7) Built-in Analytics

(8) Compatible with Supplied NVR

(9) 1 year Manufacturer Warranty

(10) 1 year Installation Warranty on all workmanship

(11) Minimum 60 PPF Image (or as noted per Camera List/Drawing)

2. SUBMITTALS

a. Product Data

(1) Manufacturer’s printed or electronic data sheets

(2) Manufacturer’s installation and operation manuals

(3) Warranty documentation

3. QUALIFICATIONS

a. Manufacturer shall have a minimum of five years’ experience in producing IP video equipment.

4. DELIVERY, STORAGE AND HANDLING

a. Deliver the camera in the manufacturer’s original, unopened, undamaged container with identification labels intact.

b. Store the camera in a temperature environment specified in section 2.04 Detailed

Specification, protected from mechanical and environmental conditions as designated by the manufacturer.

5. WARRANTY, LICENSING AND SUPPORT

a. Manufacturer shall provide at least a limited 1 year warranty for the product to be free of defects in material and workmanship.

b. Manufacturer shall provide embedded camera video analytics free of license charges.

DD. PRODUCTS

1. EQUIPMENT

a. Manufacturer: Design based on Hanwha Techwin (Samsung)

b. Models listed on drawings under Attachment E

(1) Camera Type 1: PNM-9030V

(2) Camera Type 2: PNF-9010R

(3) Camera Type 3: XNV-9082R

(4) Camera Type 4: XND-9082RV

c. Alternates: Equal product approved by the Owners Authorized Representative per the Request for Competitive Quotes documents. (compatible with NVR and PIKO software system, onvif is not compliant)

d. All proposed equipment must meet the National Defense Authorization Act.

Equipment listed below that does not meet the National Defense Authorization Act has been reviewed and approved by the ODOT Project Manager.

2. CAMERA TYPE 1: PNM-9030V

3. CAMERA TYPE 2: PNF-9010R

4. CAMERA TYPE 3: XNV-9082R

5. CAMERA TYPE 4: XND-9082RV

Rev 1/4/2019

EE. EXECUTION

1. INSTALLERS

a. Contractor personnel shall comply with all applicable state and local licensing and permitting requirements.

2. PREPARATION

a. The network design and configuration shall be verified for compatibility and performance with the camera(s).

b. Network configuration shall be tested and qualified by the Contractor prior to camera installation.

c. All firmware found in products shall be the latest and most up-to-date provided by the manufacturer, or of a version as specified by the provider of the Video Management Application (VMA) or Network Video Recorder (NVR).

3. INSTALLATION

a. Contractor is responsible for full installation of each camera and each monitor.

b. ODOT will connect the patch panel to the NVR.

c. The Contractor shall carefully follow instructions in documentation provided by the manufacturer to insure all steps have been taken to provide a reliable, easy-to-operate system.

d. All equipment shall be tested and configured in accordance with instructions provided by the manufacturer prior to installation.

e. Before permanent installation of the system, the Contractor shall test the system in conditions simulating the final installed environment.

f. ODOT will install CAT 6 cable for each camera.

g. Cables should be labeled at each end with camera ID, location.

h. Coordinate camera ID nomenclature with ODOT PM

i. Furnish Site Graphic with camera location and ID for easy user interface.

j. Provide identification labels for all wiring devices, including switches and Patch Panels.

Labels shall be pressure sensitive adhesive machine typewritten 1/8" black letters indicating switch, port and camera ID. Label the Switch and patch panel “Video Surveillance System”

k. Label the ports

l. Strap cables as necessary to organize and reduce clutter.

m. Install video surveillance signs per Attachment E.

4. STORAGE

a. The hardware shall be stored in an environment where temperature and humidity are in the range specified by the Manufacturer.

5. WARRANTY

a. Contractor shall provide a 1 year Installation warranty on all workmanship.

6. CAMERA SETUP

a. Contractor shall focus each camera at the direction of the Owners Authorized

Representatives.

b. All camera Username and Password shall be set as follows:

(1) Username: Admin

(2) Password: ODOT.dmvcam

TESTING, IDENTIFICATION, AND ADMINISTRATION

PART 1 – DESCRIPTION, QUALITY ASSURANCE, AND SUBMITTAL

1.1 DESCRIPTION

A. All testing and identification is to be completed.

B. Documentation is to cover all parts of the cabling system, equipment, and locations.

1.2 QUALITY ASSURANCE

A. All labels are to match from cable to outlet to As-Built.

B. All labels are to be made by means of a permanent printable label.

C. See Section 17010 for additional requirements.

D. Code Requirements:

1. BISCI TDMM, Latest edition

2. TINEIA-606 Administration Standard for Commercial Telecommunications Infrastructure

3. TINEIA 5688.2-1 (all addendums)

4. TSB-72

5. ANIS/TINEIA-568-A (all addendums)

1.3 SUBMITTALS

A. Submit product data for all equipment to be used for testing and labeling.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Any manufacturer of tester that meet the current Category 6 test parameters.

B. Fiber optic testers

1. Power Meter

PART 3 - TESTING AND ADMINISTRATION

3.1 TESTING

A. Testing will be completed per Industry Standard for cable type to be tested. TIA/EIA- 568-8.1

(category 5e) and TIA/EIA-568-8.2-1 (category 6) ISO/IEC 11801:2002 2nd Edition (classes D, E and F)

B. Tie Cable Testing

1. Wire-map

2. Length

3. Cable faults

C. Fiber Testing

1. Power Meter One way

2. Test at 850 & 1300

3. Must meet acceptance values as stated by ANSI/TIA/EIA-568-B.1

D. All Testing

1. All systems to be 100% tested

3.2 DOCUMENTATION

A. Tests that do not generate a report.

1. Give 1 week written notice, to the Owner Representative (Eric Spond, Eric.SPOND@odot.oregon.gov) of test day and confirm the test schedule Owner Representative and ODOT staff may witness the tests.

3.3 ADMINISTRATION

A. Plans

1. Indicate for all systems.

a. Equipment list for all locations

b. Camera number and type

2. Furnish Camera As-built plans on PDF format.

B. Labeling Labeling will be done by means of a mechanical device i.e. printer, P-Touch, or other printing device. Hand written labels are not acceptable.

mailto:Eric.SPOND@odot.

Attachment B – Sample Agreement Form

OFFEROR INSTRUCTIONS: Do not submit this document with your quote. If you are the successful offeror, ODOT will fill in the blanks within this form and request your signature, which will represent your agreement to enter into a contract. PLEASE NOTE: There are some terms in this document that you will be agreeing to should you be awarded a contract; for instance, completion dates and liquidated damages. Please make sure you have read and understand this document before you submit a quote.

STATE OF OREGON SERVICES AGREEMENT FORM

for the project

Contract Number

Resulting from Request for Competitive Quotes (“RFCQ”) No. S-73000-00006718/35650

Note: The Contract described in this agreement form is not a Public Improvement contract as defined in Oregon’s procurement code. However, ODOT has chosen to use the State of Oregon General Conditions for Public Improvement Contracts (“General Conditions”) as the governing terms and conditions for this contract. When the terms “Public Improvement Agreement” or “Public Improvement Agreement Form” are used in the General Conditions, for this contract those terms mean “Services Agreement” or “Services Agreement Form.”

This Agreement (the “Agreement”), made by and between the State of Oregon, acting by and through the Department of Transportation, hereinafter called OWNER, and_____________________________________ hereinafter called CONTRACTOR, (collectively the “Parties”) shall become effective on the date this Agreement has been signed by all the Parties and all required State of Oregon governmental approvals have been obtained, whichever is later. Unless otherwise defined in the in this Agreement or its attachments, the capitalized terms used herein are defined in Section A.1 of the State of Oregon General Conditions for Public Improvement Contracts.

WITNESSETH:

1. Contract Price, Contract Documents and Work.

CONTRACTOR, in consideration of the sum of $_____________________ (the “Contract Price”), to be paid to CONTRACTOR by OWNER in the manner and at the time hereinafter provided, and subject to the terms and conditions provided in the Contract Documents, all of which are incorporated herein by reference, hereby agrees to perform all Work described and reasonably inferred from the Contract Documents. CONTRACTOR understands and agrees that various Attachments to the RFCQ and other Contract Documents were not physically attached but were and are incorporated by reference and have the same force and effect as if fully set forth therein.

CONTRACTOR shall perform the Work for the Contract Price pursuant to the RFCQ identified above (including all Addenda thereto, if any), CONTRACTOR’S response to the RFCQ, and the following attachments to the RFCQ, which were posted in ORBuys as part of the RFCQ advertisement and are incorporated into the Contract by this reference:

Attachment A Specifications Attachment B Reserved Attachment C Terms and Conditions Attachment D Contract Closeout Compliance Checklist Attachment E Camera Layout (separate file)

The Contract Price includes: Competitive Quote Items #1

Insert Bid results here prior to Contract Execution

2. Representatives.

Unless otherwise specified in the Contract Documents, OWNER designates the person listed below as its Authorized Representative in the administration of the Contract. The Owner’s Authorized Representative shall be the initial point of contact for matters related to performance, payment, authorization, and to carry out the responsibilities of OWNER. CONTRACTOR has named _______________________________________ its authorized representative to act on its behalf.

Owner’s Authorized Representative:

Name: Eric Spond Position: Construction Project Manager Address: 885 Airport Rd SE, Bldg. X City state Zip: Salem, OR 97301 Phone: 503-302-3705 Email: eric.spond@odot.oregon.gov

3. Project Location:

1502 OR-99W

McMinnville, OR 97128

4. Contract Dates (See the General Conditions for definitions of Substantial and Final Completion):

Start Date: Immediately after issuance of notice to proceed.

Substantial Completion: 3 weeks from notice to proceed.

Final Completion: 4 weeks from notice to proceed.

mailto:eric.spond@odot.oregon.gov

5. Liquidated Damages.

Failure to achieve Substantial Completion by the time specified above for Substantial Completion will result in damage to OWNER. Since actual damage will be difficult to determine, it is agreed that CONTRACTOR shall pay to OWNER, not as a penalty but as liquidated damages, $100.00 per calendar day for each day elapsed in excess of the Substantial Completion date specified in Section 3 of this Agreement until Substantial Completion is achieved.

6. Integration.

THE CONTRACT DOCUMENTS CONSTITUTE THE ENTIRE AGREEMENT BETWEEN THE PARTIES. NO

WAIVER, CONSENT, MODIFICATION OR CHANGE OF TERMS OF THE CONTRACT SHALL BIND EITHER PARTY UNLESS IN WRITING AND SIGNED BY BOTH PARTIES. SUCH WAIVER, CONSENT, MODIFICATION OR CHANGE, IF MADE, SHALL BE EFFECTIVE ONLY IN THE SPECIFIC INSTANCE AND FOR THE SPECIFIC PURPOSE GIVEN. THERE ARE NO OTHER UNDERSTANDINGS, AGREEMENTS, OR REPRESENTATIONS, ORAL OR WRITTEN, NOT SPECIFIED HEREIN REGARDING THIS CONTRACT. CONTRACTOR, BY THE SIGNATURE BELOW OF ITS AUTHORIZED REPRESENTATIVE, HEREBY ACKNOWLEDGES THAT IT HAS READ THE CONTRACT, UNDERSTANDS IT, AND AGREES TO BE BOUND BY ITS TERMS AND CONDITIONS.

In witness whereof, OWNER executes this Agreement and CONTRACTOR does execute the same as of the day and year indicated below.

CONTRACTOR’S INFORMATION:

CONTRACTOR’S DATA:

NAME & ADDRESS:

CONTACT INFORMATION:

CONTRACTOR’S CCB #: EXPIRATION DATE:

CONTRACTOR’S AUTHORIZED SIGNATURE:

Title Date

OWNER’S AUTHORIZED SIGNATURE:

Title Date

ATTACHMENT C – TERMS AND CONDITIONS

CONFLICT OF INTEREST:

ODOT’s Conflict of Interest Guidelines are available on ODOT’s website (see Guidance, Policy & Resources) and are incorporated into this Contract:

http://www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx See Section C.1.4.

GENERAL CONDITIONS:

This RFCQ and the resulting Contract are governed by the STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS, January 1, 2012 Edition (“General Conditions”) which, although not physically attached, is incorporated herein by reference as an Attachment with the same force and effect as though fully set forth herein:

http://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf

SUPPLEMENTAL GENERAL CONDITIONS:

The following supplements modify the General Conditions this project. Where a portion of the General Conditions is modified or deleted by these Supplemental General Conditions, the unaltered portions of the General Conditions shall remain in effect.

SGC-1 Add the following after A.3.4 under INTERPRETATION OF CONTRACT DOCUMENTS

A.3.5 The characterization of provisions of the Contract as material provisions or the failure to comply with certain provisions as a material breach of the Contract shall in no way be construed to mean that any other provisions of the Contract are not material or that failure to comply with any other provisions is not a material breach of the Contract.

SGC-2 Add the following after Section A.7 GOVERNMENT EMPLOYMENT STATUS:

A.8 TITLE VI NON-DISCRIMINATION PROVISIONS

During the performance of the Contract, Contractor, for itself, its assignees and successors in interest (hereinafter referred to as the “Contractor”) agrees as follows:

a. Compliance with Regulations: Contractor shall comply with the Regulations relative to nondiscrimination in Federally-assisted programs of the Department of Transportation Title 49, Code of Federal Regulations, Part 21, as they may be amended from time to time, (hereinafter referred to as the Regulations), which are herein incorporated by reference and made a part of the Contract.

b. Nondiscrimination: Contractor, with regard to the work performed by it during the Contract, shall not discriminate on the grounds or race, color, sex, or national origin in the selection and retention of subcontractors, including procurements of materials and leases of equipment. Contractor shall not participate either directly or indirectly in the discrimination prohibited by section 21.5 of the Regulations, including employment practices when the Contract covers a program set forth in Appendix B of the Regulations.

http://www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx

c. Solicitations for Subcontracts, Including Procurements of Materials and Equipment: In all solicitations either by competitive bidding or negotiation made by Contractor for work to be performed under a subcontract, including procurements of materials or leases of equipment, each potential subcontractor or supplier shall be notified by Contractor of Contractor’s obligations under the Contract and the Regulations relative to nondiscrimination on the grounds of race, color, sex, or national origin.

d. Information and Reports: Contractor shall provide all information and reports required by the Regulations, or directives issued pursuant thereto, and shall permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by ODOT, FHWA or the Federal Transit Administration (“FTA”) as appropriate, to be pertinent to ascertain compliance with such Regulations, orders and instructions. Where any information required of Contractor is in the exclusive possession of another who fails or refuses to furnish this information, Contractor shall so certify to ODOT, FHWA or FTA as appropriate, and shall set forth what efforts it has made to obtain the information.

e. Sanctions for Noncompliance: In the event of Contractor’s noncompliance with the nondiscrimination provisions of the Contract, ODOT shall impose such Contract sanctions as ODOT, FHWA or FTA may determine to be appropriate, including, but not limited to:

(i) Withholding of payments to Contractor under the Contract until Contractor complies, and/or

(ii) Cancellation, termination or suspension of the Contract, in whole or in part.

f. Incorporation of Provisions: Contractor shall include the provisions of paragraphs (a) through (e) in every subcontract, including procurements of materials and leases of equipment, unless exempt by the Regulations, or directives issued pursuant thereto. Contractor shall take such action with respect to any subcontract or procurement as ODOT of the federal government may direct as a means of enforcing such provisions including sanctions for non-compliance: Provided, however, that, in the event Contractor becomes involved in, or is threatened with, litigation with a subcontractor or supplier as a result of such direction, Contractor may request ODOT, and, in addition, Contractor may request the United States to enter into such litigation to protect the interests of the United States.

SGC-3 Make the following revisions to Section B.5 COMPLIANCE WITH GOVERNMENT LAWS AND

REGULATIONS:

• Add the following to the end of Section B.5.1:

All rights and remedies available to Owner under applicable federal, state and local laws are also incorporated by reference herein and are cumulative with all rights and remedies under the Contract.

• Delete Section B.5.2(a) and replace with the following:

(a) Pursuant to ORS 279A.110, Contractor shall not discriminate against a disadvantaged business enterprise, a minority-owned business, a woman-owned business, a business that a service-disabled veteran owns or an emerging small business, in the awarding of subcontracts.

• Add the following Section B.5.2(c):

(c) Compliance with ORS 279C.520 also includes (i) As required by ORS 279C.520, the Contractor must comply with ORS 652.220 and shall not unlawfully discriminate against any of Contractor’s employees in the payment of wages or other compensation for work of comparable character on the basis of an employee’s membership in a protected class.

“Protected class” means a group of persons distinguished by race, color, religion, sex, sexual orientation, national origin, marital status, veteran status, disability, or age. The Contractor’s compliance with this section constitutes a material element of this Contract and a failure to comply constitutes a breach that entitles Agency to terminate this Contract for cause,.

(ii) The Contractor shall not prohibit any of its employees from discussing the employee’s rate of wage, salary, benefits and other compensation with another employee or another person, and shall not retaliate against an employee who discusses the employee’s rate of wage, salary, benefits or other compensation with another employee or another person.

• Add the following Section B.5.2(d):

(d) Respecting certification as a disadvantaged business enterprise, minority-owned business, woman-owned business, business that a service-disabled veteran owns or an emerging small business under ORS 200.055, as and when applicable, the Contactor shall maintain the certifications, and require in its subcontracts that subcontractors maintain the certifications required by ORS 279A.107.

SGC-4 Delete Section B.15 GOVERNING LAW in its entirety and replace with the following:

B.15 GOVERNING LAW. This Contract shall be governed by and construed and enforced in accordance with the laws of the State of Oregon without regard to principles of conflicts of laws.

SGC-5 Add the following after Section D.3 CLAIMS REVIEW PROCESS

D.4 FALSE CLAIMS (OREGON FALSE CLAIMS ACT)

D.4.1 Contractor understands and acknowledges it is subject to the Oregon False Claims Act (ORS

180.750 to 180.785) and to any liabilities or penalties associated with the making of a false claim under that Act. By its execution of the Contract, Contractor certifies the truthfulness, completeness, and accuracy of any statement or claim it has made, it makes, it may make, or cause to be made that pertains to the Contract or the Project for which the services are being performed, including but not limited to Contractor’s statement of proposal and any invoices, reports, or other deliverables.

D.4.2. Contractor shall immediately disclose (in writing) to Agency whenever, in connection with the award, performance or closeout of the Contract, or any subcontract thereunder, Contractor has credible evidence that a principal, employee, agent, or subcontractor of Contractor has committed—

(i) A violation of the Oregon False Claims Act; or

(ii) A violation of State or Federal criminal or civil law involving fraud, conflict of interest, bribery, gratuity or similar misconduct.

http://www.leg.state.or.us/ors/180.html http://www.leg.state.or.us/ors/180.html

D.4.3. Contractor must include subsections D.4.1 and D.4.2 of this section in each subcontract Contractor may award in connection with the performance of the Contract. In doing so, Contractor may not modify the terms of those subsections, except to identify the subcontractors or sub grantee that will be subject to those provisions.

SGC-6 Section E.5 RETAINAGE is deleted in its entirety and replaced with the following:

E.5 RETAINAGE

E.5.1 Retainage, if withheld, shall be withheld and released in accordance with ORS 279C.550 to 279C.580:

E.5.1.1 Owner reserves the right in its sole discretion to not withhold retainage from progress payments or to begin withholding retainage at any time. If Owner withholds retainage from progress payments the amount to be retained will not exceed five percent of the payment. As Work progresses, Owner may reduce the amount of the retainage and may eliminate retainage on any remaining monthly Contract payments after 50 percent of the Work under the Contract is completed if, in the Owner's opinion, such Work is progressing satisfactorily. Elimination or reduction of retainage shall be allowed only upon written application by the Contractor, which application shall include written approval of Contractor's surety; except that when the Work is 97-1/2 percent completed the Owner may, at its discretion and without application by the Contractor, reduce the retained amount to 100 percent of the value of the Work remaining to be done. Upon receipt of written application by the Contractor, Owner shall respond in writing within a reasonable time.

E.5.1.2 If retainage is withheld, unless the Contractor requests and the Owner accepts a form of retainage described in options (a) or (b) below, the Owner (except as otherwise provided below for a contract of $500,000 or less) will deposit the retainage in an interest-bearing escrow account as required by ORS 279C.570(2). The Contractor shall execute such documentation and instructions respecting the interest-bearing escrow account as the Owner may require to protect its interests, including but not limited to a provision that no funds may be paid from the account to anyone without the Owner’s advance written authorization. In accordance with the provisions of ORS 279C.560 and any applicable administrative rules, unless the Owner finds in writing that accepting bonds, securities or other instruments described in option (a) below or a security bond described in option (b) below poses an extraordinary risk that is not typically associated with the bond, security or instrument, the Owner will approve the Contractor’s written request:

(a) to be paid amounts which would otherwise have been retained from progress payments where Contractor has deposited acceptable bonds, securities or other instruments of equal value with Owner or in a custodial account or other mutually-agreed account satisfactory to Owner, with an approved bank or trust company to be held in lieu of the cash retainage for the benefit of Owner. Interest or earnings on the bonds, securities or other instruments shall accrue to the Contractor. The Contractor shall execute and provide such documentation and instructions respecting the bonds, securities and other instruments as the Owner may require to protect its interests. To be permissible the bonds, securities and other instruments must be of a character approved by the Director of the Oregon Department of Administrative Services, including but not limited to:

(i) Bills, certificates, notes or bonds of the United States.

(ii) Other obligations of the United States or agencies of the United States.

(iii) Obligations of a corporation wholly owned by the federal government.

(iv) Indebtedness of the Federal National Mortgage Association.

(v) General obligation bonds of the State of Oregon or a political subdivision of the State of Oregon.

(vi) Irrevocable letters of credit issued by an insured institution, as defined in ORS 706.008; or

(b) that the Contractor be allowed, with the approval of the Owner, to deposit a surety bond for the benefit of Owner, in a form acceptable to Owner, in lieu of all or a portion of funds retained, or to be retained. Such bond and any proceeds therefrom shall be made subject to all claims and liens in the manner and priority as set forth for retainage under ORS 279C.550 to ORS 279C.625.

Where the Owner has accepted the Contractor's election of option (a) or (b) above, or an interest-bearing account under ORS 279C.560(5) for a contract of $500,000 or less, Owner may recover from Contractor any additional costs incurred through such election by reducing Contractor's final payment.

Where the Owner has agreed to Contractor's request to deposit a surety bond under option (b), Contractor shall accept like bonds from Subcontractors and suppliers on the project from which Contractor has required retainage.

For a contract over $500,000, if the Contractor requests that the Owner deposit the retainage in an interest-bearing account under ORS 279C.560(5), the Owner will use an interest-bearing escrow account as stated above. For a contract of $500,000 or less, if the Contractor requests that the Agency deposit the retainage in an interest-bearing account under ORS 279C.560(5), the Owner will use an interest-bearing account (in a bank, savings bank, trust company or savings association) as provided under ORS 279C.560(5).

E.5.1.3 The retainage held by Owner shall be included in and paid to the Contractor as part of the final payment of the Contract Price. The Owner shall pay to Contractor interest at the rate of one and one-half percent per month on the final payment due Contractor, interest to commence thirty (30) Days after the Work under the Contract has been completed and accepted and to run until the date Contractor shall notify Owner in writing when the Contractor considers the Work complete and Owner shall, within fifteen (15) Days after receiving the written notice, either accept the Work or notify the Contractor of Work yet to be performed on the Contract. If Owner does not within the time allowed notify the Contractor of Work yet to be performed to fulfill contractual obligations, the interest provided by this subsection shall commence to run thirty (30) Days after the end of the 15-Day period.

E.5.1.4 In accordance with the provisions of ORS 279C.560, if the Owner accepts bonds, securities or other instruments deposited as provided in paragraph (a) of subsection E.5.1.2, the Owner shall reduce the moneys held as retainage in an amount equal to the value of the bonds, securities and other instruments and pay the amount of the reduction to the Contractor in accordance with ORS 279C.570.

E.5.1.5 Contractor agrees that if Contractor elects to reserve retainage from any progress payment due to any Subcontractor or supplier, such retainage shall not exceed five percent of the payment, and such retainage withheld from Subcontractors and suppliers shall be subject to and the Contractor shall comply with all applicable legal requirements.

E.5.1.6 The Contractor shall comply with all applicable legal requirements for withholding and releasing retainage and for prompt payments, including but not limited to those in ORS Chapters 279C and 701, and 49 CFR 26.29.

E.5.2 As provided in subsections C.2.2 and C.2.3, additional withholding in the amount of 25% of amounts earned shall be withheld and released in accordance with ORS 279C.845(7) when the Contractor fails to file certified statements as required by section C.2.1.

SGC-7 Add the following at the end of SECTION E PAYMENTS:

E.7 REPORT OF SUBCONTRACTORS PAID: Following each payment to Contractor, including final payment and any progress payments, Contractor shall submit to the Owner ODOT Form 734-2882, Paid Summary Report. Contractor shall complete and submit the form as specified in the form instructions, which are available online, along with the form at: http://www.oregon.gov/ODOT/Forms/2ODOT/2882.pdf

SGC-8 Amend the first sentence of Section G.2.1 as follows (deletions shown in strikethrough):

G.2.1 When the Contract Price is $100,000 or more (or $50,000 or more in the case of Contracts for highways, bridges and other transportation projects) the Contractor shall furnish and maintain in effect at all times during the Contract Period a performance bond in a sum equal to the Contract Price, and a separate payment bond also in a sum equal to the Contract Price.

SGC-9 Delete Section G.3 INSURANCE in its entirety and replace with the following:

G.3 INSURANCE

G.3.1 Contractor: The Contractor shall obtain the insurance specified below prior to the execution of the Contract. The Contractor shall maintain the insurance in full force at the Contractor’s expense throughout the duration of the Contract and all warranty periods that apply.

G.3.1.2 Subcontracting: If the Contractor specifies prior to the execution of the Contract that a

Subcontractor will satisfy an insurance requirement, that is permitted to be satisfied by a Subcontractor, the Contractor shall obtain Owner approval of Subcontractor and Subcontractor’s insurance coverage(s), at least 35 Calendar Days prior to commencement of subcontracted work.

After the Contractor receives Owner approval of the Subcontractor, the Contractor may contractually obligate the Subcontractor to obtain and maintain, at the Subcontractor's expense or at the Contractor's expense, the insurance permitted.

G.3.1.3 The Contractor shall require that all Subcontractors carry insurance coverage that the Contractor deems appropriate based on the risks of the subcontracted work. The Contractor shall obtain proof of the required insurance coverages, as applicable, from any Subcontractor providing services related to the Contract.

G.3.1.4 Neither the insurance provided by Subcontractor(s) nor any agreements Contractor or

Subcontractor(s) may enter into shall place any limitation on the liability or indemnification obligations of the Contractor under applicable law or the Contract.

G.3.1.5 Insurance Provisions: The Contractor and Subcontractor(s), if any, shall obtain insurance from insurance companies or entities that are authorized to transact the business of insurance and issue coverage in the State and that are acceptable to Owner. Insurance coverage shall be primary and noncontributory with any other insurance and self-insurance, with the exception of http://www.oregon.gov/ODOT/Forms/2ODOT/2882.pdf

Workers’ Compensation/Employer’s Liability. The Contractor, or appropriate Subcontractor, but not Owner, shall pay for all deductibles, self-insurance retentions and self-insurance, if any.

G.3.2 Workers' Compensation and Employer’s Liability:

G.3.2.1 All employers, including the Contractor and Subcontractor(s), if any, that employ subject workers, as defined in ORS 656.027, shall comply with ORS 656.017 and shall provide Workers’ Compensation Insurance coverage, unless such employers meet the requirement for an exemption under ORS 656.126(2). The coverage shall include Employer’s Liability Insurance with coverage limits of not less than $500,000 for each accident. Contractors who perform the Work without the assistance or labor of any employee need not obtain such coverage if the Contractor certifies so in writing. Contractor shall ensure that each of its Subcontractors complies with these requirements. The Contractor shall require proof of such Workers’ Compensation by receiving and keeping on file a certificate of insurance from each Subcontractor or anyone else directly employed by either the Contractor or its Subcontractors.

G.3.2.2 All employers, including the Contractor and Subcontractor(s), if any, exempt under

ORS 656.126(2) and subject to any other state’s Workers’ Compensation law, shall provide Workers’ Compensation Insurance coverage as required by applicable Workers’ Compensation laws. The coverage shall also include Employer’s Liability Insurance with limits not less than $500,000 each accident.

G.3.3 Liability Insurance:

G.3.3.1 Commercial General Liability: The Contractor shall obtain, at Contractor's expense, and keep in effect during the term of this Contract, Commercial General Liability Insurance written on an occurrence basis and covering bodily injury and property damage. This insurance shall include personal and advertising injury liability, products and completed operations, and contractual liability coverage. When Work to be performed includes operations or activity within 50 feet of any railroad property, bridge, trestle, track, roadbed, tunnel, underpass or crossing, the Contractor shall provide the Contractual Liability – Railroads CG 24 17 endorsement, or equivalent, on the Commercial General Liability policy. Combined single limit per occurrence shall not be less than the dollar amount specified in the Contract. . The annual aggregate limit shall not be less than the dollar amount specified in the Contract.

Per Occurrence Annual Aggregate Commercial General Liability

$1,000,000 $2,000,000

G.3.3.2 Commercial Automobile Liability: The Contractor shall obtain, at Contractor's expense, and keep in effect during the term of this Contract, Automobile Liability Insurance covering owned, non-owned, and hired vehicles for bodily injury and property damage. This coverage may be written in combination with the Commercial General Liability Insurance with separate limits for Commercial Automobile Liability and Commercial General Liability. Combined single limit per occurrence shall not be less than the dollar amount specified in the Contract..

Combined Single Limit Per Occurrence

Commercial Automobile Liability

$1,000,000

G.3.3.3 Extended Reporting: If any of the required liability insurance is permitted to be and is on a

"claims made" basis, the Contractor or Subcontractor who provided the insurance coverage, shall obtain an extended reporting period on the claims made policy or maintain the claims made policy for a duration of at least 24 months from the date the applicable work has been completed and accepted by Owner or the date of Final Completion. This extended reporting requirement shall be satisfied with documentation of one of the following:

o Extended Reporting Endorsement;

o Tail Coverage; or o Maintaining the applicable continuous claims made policy with liability coverage.

G.3.3.4 Excess/Umbrella Liability: A combination of primary and Excess/Umbrella Insurance may be used to meet the required limits of insurance. Excess/Umbrella coverage must be at least as broad as that provided by the underlying primary insurance policies. In addition, the limits of the underlying primary insurance must be sufficient to prevent any gap between such minimum limits and the attachment point of the coverage provided by the Excess/Umbrella Liability policy.

G.3.3.5 Additional Insured: The liability insurance coverages, except Professional Liability and Workers’

Compensation/Employer’s Liability, if included, shall include an Additional Insured Endorsement specifying the “State of Oregon, the Oregon Transportation Commission and the Department of Transportation, and their respective officers, members, agents, and employees” as Additional Insureds, but only with respect to the Contractor's activities to be performed under this Contract. Coverage shall be primary and non-contributory with any other insurance and self-insurance. The liability coverages that are permitted by Owner to be obtained by an appropriate Subcontractor shall include all of the foregoing as Additional Insureds and shall also include the Contractor and its officers and employees as Additional Insureds.

G.3.3.6 Additional Insured – Commercial General Liability: Additional Insured Endorsements on the

Commercial General Liability shall be written on ISO Form CG 20 10 07 04, or equivalent, with respect to liability arising out of ongoing operations and ISO Form CG 20 37 07 04, or equivalent, with respect to liability arising out of completed operations. Additional Insured Endorsements shall be submitted with the Certificate(s) of Insurance and must be acceptable to Owner.

G.3.3.7 Notice of Cancellation or Change: The Contractor shall provide at least 30 Calendar Days written notice to Owner before cancellation of, material change to, potential exhaustion of aggregate limits, or non-renewal of the required insurance coverages. If a Subcontractor is providing insurance to meet the contract requirements, the Contractor shall provide at least 30 Calendar Days written notice to Owner before cancellation of, material change to, potential exhaustion of aggregate limits, or non-renewal of the required insurance coverage(s). Any failure to comply with the reporting provisions of this insurance shall not affect the coverage(s) provided to the State, Owner, County, City, or other applicable political jurisdiction or to Owner's governing body, board, or Commission and its members, and Owner's officers, agents, and employees.

G.3.3.8 Certificate(s) of Insurance: As evidence of the insurance coverages required by this Contract, the Contractor shall furnish Certificate(s) of Insurance to Owner prior to execution of the Contract. As evidence of insurance coverages required by the Contract but permitted by Owner to be obtained by an appropriate Subcontractor, the Contractor shall furnish Certificate(s) of Insurance to Owner for approval on such coverages at least 35 Calendar Days prior to commencement of subcontracted work. The Certificate(s) shall:

• List the “State of Oregon, the Oregon Transportation Commission and the Department of

Transportation, and their respective officers, members, agents and employees” as an endorsed Additional Insured;

• Include all required endorsements or copies of the applicable policy language effecting coverage required by the Contract;

• Specify that all liability insurance coverages shall be primary and non-contributory with any other insurance and self-insurance, with exception of Professional Liability and Workers’ Compensation/Employer’s Liability; and

• Include a list of all policies that fall under the Excess/Umbrella Insurance if Excess or Umbrella Insurance is used to meet the minimum insurance requirement.

G.3.3.9 Owner Acceptance: All insurance and insurance providers are subject to Owner acceptance. If requested by Owner, the Contractor shall provide complete copies of insurance policies, endorsements, self-insurance documents and related insurance documents to Owner’s representatives responsible for verification of the insurance coverages required by the Contract.

G.3.3.10 Insurance Requirement Review: The Contractor agrees to periodic review of insurance requirements by Owner under the Contract and to provide updated requirements as mutually agreed upon by the Contractor and Owner.

G.3.4 Builder’s Risk Insurance and Builder’s Risk Installation Floater (RESERVED – NOT REQUIRED FOR THIS

PROJECT)

SGC-10 Add the following at the end of SECTION H.2 SCHEDULE:

H.2.2 The Project Work schedule is essential to the Owner. The Contractor’s failure to provide the schedule, schedule information, progress reports, or schedule updates when required will be cause to suspend the Work, or to withhold Contract payments as necessary to protect the Owner, until the Contractor provides the required information to the Owner’s Authorized Representative.

SGC-11 Add a new subsection to Section J.4.1 as subsection (f) and renumber existing subsection (f) as subsection (g) as follows:

(f) If Contractor has liquidated and delinquent debt owed to the State of Oregon or any department or agency of the State of Oregon;

(g) If Contractor is otherwise in material breach of any part of the Contract.

SGC-12 Delete Section J.4.2 in its entirety and replace it with the following:

J.4.2 At any time that any of the above occurs, Owner may exercise all rights and remedies available to Owner at law or in equity, including, in the event of the conditions set forth in Section J.4.1 (f) regarding Contractor’s liquidated and delinquent debt, by offset or garnishing all monies due for any and all Work performed by the Contractor when appropriate, and otherwise recovering any liquidated and delinquent debt owed to the State of Oregon or any department or agency of the State of Oregon. In addition, Owner may take possession of the premises and of all materials and appliances and finish the Work by whatever method it may deem expedient. In such case, Contractor shall not be entitled to receive further payment until the Work is completed. If Owner’s cost of finishing the Work exceeds the unpaid balance of the Contract Price, Contractor shall pay the difference to the Owner.

SGC-13 Add the following at the beginning of SECTION K CONTRACT CLOSEOUT:

As a condition of final payment, Contractor shall complete and sign the Contract Closeout Checklist form provided by Owner. If accepted by Owner, Contractor’s delivery of the certification as required in K.3 of the Checklist will be deemed to be compliance with the requirements of Section K.3 below and Contractor’s delivery of the information required in K.7 of the Checklist will be deemed to be compliance with the requirements of Section K.7 below.

SGC-14 Delete Section K.4.1 and replace with the following:

K.4.1 Contractor shall provide Owner notice of Substantial Completion. The notice of Substantial Completion shall state the date of Substantial Completion, and shall be submitted to the Owner’s Authorized Representative. The notification may be communicated verbally to the Owner’s Authorized Representative, sent electronically via email, or sent as a hard copy in the mail. Upon receipt of notification of Substantial Completion, the Owner’s Authorized Representative will perform a final project inspection and provide the Contractor with the project Punchlist. Once all Punchlist items have been completed to the satisfaction of the Owner’s Authorized Representative, the Owner’s Authorized Representative will provide Contractor with a Contract Closeout Checklist form. Contractor shall complete and sign the form and submit it to the Owner’s Authorized Representative. The Owner’s Authorized Representative will provide the final signature on the form upon which date Final Completion shall take effect.

Attachment D

CONTRACT CLOSEOUT COMPLIANCE CHECKLIST

Contract Number Contract Name Contractor Owner Authorized Rep.

This checklist is intended to assist Agency and Contractor in complying with the Contract Closeout and Final Payment requirements in the General Conditions for Public Improvement Contracts, Sections K and E.6 : http://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf

Owner will mark “NA” by any requirement that is not applicable to the Contract. Contractor’s and Owner’s Authorized Representatives shall place their initials by each requirement listed below that has not been marked “NA” by Owner, and provide a signature at the end of the Checklist.

ODOT: Keep a copy of the signed form in the Contract Administration file. Email a copy to the ODOT Procurement Office. For ESB contracts, also email a copy to your Office of Civil Rights Field Coordinator.

Requirements Mark NA if not applicable

Date completed

Contractor initials

Owner initials

K.1 Record Documents submitted

K.2 O & M Manuals submitted

K.3 Certification/Release of Claims

By Contractor’s signature below, Contractor certifies and agrees to the following:

All Subcontractors and suppliers have been paid in full or will be paid in full out of the final payment, and in compliance with all prompt payment requirements. All disputes with property owners have been resolved, all obligations on the project have been satisfied, all monetary claims and indebtedness have been paid, and, to the best of the Contractor's knowledge, there are no claims of any kind outstanding against the project.

K.4 Completion notices submitted

Substantial Completion notice Date of substantial completion:

Final Completion notice Date of final completion:

K.5 Training sessions scheduled

K.6 Extra materials provided (List individually):

K.7.…