3515R08 - Appendix K - Work Order Requirements.pdf

PDF 22 KB Posted

Attached to
Instrumentation and Monitoring of PA Bridges
Solicitation number
3515R08
Issued by
Allegheny County, Brodheadsville CDP, Pennsylvania

About this file

This document is the APPENDIX K - WORK ORDER REQUIREMENTS for a contract between the Pennsylvania Department of Transportation (PennDOT) and a selected Offeror.

The document outlines the requirements for work orders issued under the contract, including the scope limits, initiation process, format, execution, and modification procedures. It specifies that work orders must be deliverable-based with lump sum payments upon completion and acceptance by PennDOT. Work orders will be consecutively numbered and may be done concurrently. The Contractor must provide project timelines, and labor costs not identified as lump sum deliverables must be itemized by key personnel and hourly rate. No work can begin before a fully executed purchase order is issued as the notice to proceed, and any work done outside the purchase order validity period is subject to non-payment.

The document also covers requirements for work order modifications, substitution or addition of personnel, and consequences for failure to complete work orders. It references the IT Contract Terms and Conditions in Appendix B for further details on changes and termination.

View the file

Other files

File Type Posted
3515R08 - Appendix N - Enterprise Information Technology Standards.pdf PDF
3515r08 - Appendix H - Diverse Business Participation for Non-Federally Funded Contracts.pdf PDF
3515R08 - Addendum 5.pdf PDF
Addendum 5 - Appendix T – Questions and Answers 11.16.16.pdf PDF
3515R08 - Appendix F - List of Bridges Unlocked 10.25.16.xlsx XLSX spreadsheet
3515R08 - Appendix D - Domestic Workforce Utilization Certification.pdf PDF
3515R08 - Appendix O - Non Disclosure Authorization.pdf PDF
3515R08 - Appendix R - Live Load Testing - General Protocol.pdf PDF
3515R08 - RFP Bridge Instrumentation - FINAL.pdf PDF
3515R08 - Addendum 3.pdf PDF
3515R08 - Appendix G - Service Level Agreement.pdf PDF
3515R08 - Appendix F - List of Bridges to be Instrumented and Monitored 11.16.16.xlsx XLSX spreadsheet
3515R08 - Addendum 4.pdf PDF
3515R08 - Appendix C - Cost Submittal.xlsx XLSX spreadsheet
3515R08 - Appendix E - Proposal Cover Sheet.pdf PDF
3515R08 - Appendix A - Sample Contract.pdf PDF
Addendum 2 - Appendix S – Questions and Answers 10.25.16.pdf PDF
3515R08 - Appendix I - District Community Relations Coordinators Unlocked 10.25.16.xlsx XLSX spreadsheet
3515R08 - Appendix Q - Instrumentation Plan - General Protocols.pdf PDF
3515R08 - Appendix L - Sample Work Order Authorization Page.pdf PDF
3515R08 - Appendix P - Long Term Bridge Performance Protocols.pdf PDF
3515R08 - Appendix B - IT Contract Terms and Conditions.pdf PDF
3515R08 - Addendum 2.pdf PDF
3515R08 - Appendix J - Confirmation of Services (Form OS-501).pdf PDF
3515R08 - Addendum 1.pdf PDF
3515R08 - Appendix M - Trade Secret - Confidentiality Proprietary Information Notice Form.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX K

WORK ORDER REQUIREMENTS

APPENDIX K Page 1 of 4

WORK ORDER REQUIREMENTS

I. Work Order Limits:

1. The work defined within a Work Order must be within the scope of the Contract and not already be identified under one or more of the Tasks as noted in the RFP, Part IV, Work Statement, IV-4, Tasks.

II. Work Order Initiation:

1. PennDOT will initiate a Work Order by defining an observed need that can be addressed under the scope of work.

2. PennDOT will then discuss the required scope of work with the Contractor. The Contractor will provide a draft, unexecuted copy, of the Work Order to PennDOT.

3. All Work Orders will be negotiated.

4. Once the Work Order is established and accepted by PennDOT, the Work Order will be executed.

III. Work Order Format:

1. A Work Order shall contain an “authorization page.”

2. The work to be completed through a Work Order shall be deliverable-based and will establish payment benchmarks.

3. Work Orders shall clearly define the deliverable and a lump sum payment will be made upon completion and acceptance by PennDOT of the defined deliverable. Benchmarks will be identified during negotiation when a single Work Order provides for more than one

(1) clearly defined benchmark. Each identified benchmark within a Work Order will be considered a separate deliverable with a lump sum payment made upon completion and acceptance by PennDOT of the identified benchmark.

4. The Work Order shall specify each deliverable, a cost for each deliverable, the quantity of each deliverable, the completion date for each deliverable and include annual maintenance payment if applicable.

5. All Work Orders will be negotiated and once established and accepted by PennDOT, a

Work Order will be executed in accordance with Appendix B, IT Contract Terms and Conditions, Paragraph 21. Changes, and reimbursement under the contract will be based on the agreed upon fixed price of each deliverable.

6. A Work Order Authorization Page (see Appendix L) shall be required to be signed by the selected Offeror and PennDOT. Upon acceptance by the selected Offeror and PennDOT, a fully executed Purchase Order will be issued as the Notice to Proceed.

APPENDIX K Page 2 of 4

ALL QUANTITIES ARE ESTIMATED AND ARE NOT GUARANTEED. NO

WORK CAN BE AUTHORIZED BEFORE A FULLY EXECUTED

PURCHASE ORDER IS ISSUED BY PENNDOT AND RECEIVED BY THE

SELECTED OFFEROR.

7. Work Orders shall be consecutively numbered.

8. Work Orders may be done concurrently.

9. Reports and Project Schedule. The Work Order shall also incorporate progress reports, project management aids, meetings and other requirements as specified by PennDOT. The Contractor must provide a project time-line showing major activities and time allotted to these activities. The time frame of the work order must incorporate adequate review times as specified by PennDOT.

10. Labor costs that cannot be identified as a lump sum deliverable shall be itemized by key personnel and hourly rate (which includes all overhead costs, fixed fee, etc.). The hourly rate shall be equal to or lower than those presented in the selected Offeror’s Cost Submittal.

If no hourly rates were provided on the selected Offeror’s Cost Submittal, PennDOT reserves the right to negotiate the hourly rate and number of hours to complete the work outlined in the Work Order. Also subcontractor and miscellaneous items must be itemized and listed. All costs shall be equal to or lower than those presented in the selected Offeror’s Cost Submittal, which has been incorporated and made part of this Contract.

Note: Similar to the policy for reimbursing the cost of preparing proposals in response to a request for proposals, PennDOT will not reimburse the selected Offeror for any costs related to the preparation of Work Orders.

IV. Work Order Execution:

1. Upon agreement of the proposed Work Order between PennDOT and the Contractor’s authorized representative, both parties will sign the Work Order Authorization Form.

2. The fully executed Purchase Order/Notice to Proceed may establish beginning and end dates for both project completion and the Purchase Order “validity period.” The project completion and Purchase Order validity period may be different to ensure the Purchase Order remains valid through project completion but will not go beyond the expiration of the Contract. The Purchase Order must remain valid during the life of the project to ensure that the selected Offeror is eligible to work and receive payment for work through the Purchase Order. Any work done outside the validity period of the Purchase Order is subject to non-payment.

3. No work is authorized to begin before a fully executed Purchase Order is provided to the

Contractor. The fully executed Purchase Order will act as the formal Notice to Proceed.

The fully executed Purchase Order/Notice to Proceed may establish beginning and end

APPENDIX K Page 3 of 4 dates for project completion and the Purchase Order validity period. The project completion and Purchase Order validity period may be different to ensure the Purchase Order remains valid through project completion even if the selected Offeror doesn’t achieve the original project completion date and no time extension has been approved by PennDOT and reflected on the Purchase Order to extend the project completion date. The Purchase Order must remain valid during the life of the project to ensure that the Selected Offeror is eligible to work and receive payment for work through the Purchase Order. Any work done outside the validity period of the Purchase Order is subject to non-payment.

V. Work Order Modifications:

1. Changes in scope of work, cost, and/or time extension requests require a formal change order request and shall follow the requirements for changes in accordance with Appendix B, IT Contract Terms and Conditions, Paragraph 21. Changes. The change order request shall be submitted in the form of a letter from the selected Offeror to PennDOT’s Contract Administrator (typically this is the Issuing Officer identified in Part I-2 of this RFP) for review and approval. No work may begin or take place while the change is under review with PennDOT. If approved, the Notice to Proceed for work related to the change request may be in the form of a new or updated fully executed Purchase Order or a letter issued from PennDOT to the selected Offeror.

VI. Substitution of Addition or Personnel:

1. Changes in personnel shall be reported to the Project Manager before a Work Order will be executed.

VII. Work Order – Failure to Complete and Work Order Termination:

1. Refer to Appendix B, IT Contract Terms and Conditions, of the RFP.