SERC Solar Project- Pre-Proposal Conf Brief.pdf

PDF 3 MB Posted

Attached to
(CANCELED) 33330225RF0010010 Design Build Services for Solar Project at Smithsonian Environmental Research Center (SERC)
Solicitation number
33330225RF0010010
Issued by

About this file

This is a pre-proposal conference presentation for the SERC Solar PV Project at the Smithsonian Environmental Research Center. The project involves designing and constructing a ground-mounted solar photovoltaic system with a base capacity of 3.2 MW DC and an optional capacity of up to 4.0 MW DC, to be located across two parcels near Muddy Creek Rd. and Cumberstone Rd. in Edgewater, MD.

The presentation outlines key project details including: proposal due date of March 13, 2025 at 3:00 PM ET; RFI submission deadline of February 27, 2025; site visit and pre-proposal conference scheduled for February 13, 2025 from 9:15 AM to 1:00 PM. The project aims to make SERC net-zero for energy usage and includes options for operations and maintenance services for up to 5 years. Technical evaluation factors (weighted equally) include the design-build team qualifications, schedule/plan of accomplishment, and concept design submission. The project timeline requires completion within 54 weeks after Notice to Proceed, with key milestones including 50% design at week 8, 100% design at week 12, and construction completion by week 52. The presentation includes detailed site maps, LIDAR imagery, and HelioScope modeling assumptions for the solar array layout across the two parcels totaling 12.84 acres (4.91ac + 7.93ac).

View the file

Other files

File Type Posted
33330225RF0010010 ( Amend 3).pdf PDF
33330225RF0010010 ( Amend 2).pdf PDF
33330225RF0010010 ( Amend1).pdf PDF
Section J Attachments.pdf PDF
Section J Attachments.pdf PDF
33330225RF0010010 Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SERC Solar PV Project Preproposal Conference and Site Visit

February 13, 2025

Proposals are due by March 13, 2025, at 3:00 PM ET

RFIs requested by February 27, 2025, at 3:00 PM ET

AGENDA

SERC Solar PV Project Preproposal Conference

• 9:15 – 10:15: Presentation of Project Overview

• 10:15 – 11:00: Q&A (about the presentation)

• 11:00 – 1:00: Site Visit

• Key Smithsonian Personnel:

• Contracting Officer: Christine Grant

• Contracting Officer’s Technical Representative: Ray Jones

• SERC Site Representative: Jacob Bradd

SERC Solar PV – Project Introduction

• Design-Build Project for a 3.2 to 4.0 MW Solar System at SERC

• Would enable SERC to become Net Zero for Energy Usage

• Project would deliver long-term cost savings for SERC and Smithsonian

• Eliminate electric procurement costs at SERC, saving federal utilities funds

• Aligned with SI / SERC mission

• Reduce Greenhouse Gas emissions by equivalent of over 500 typical homes per year

• Solar Project would support science, research and education at SERC

• Renewable energy is a critical enabler for resilience

Disclaimer: These are the author's opinions and do not alter or influence the terms of the Request for Proposal (RFP).

Solar PV Project – Science, Research & Education Benefits for SI and SERC

• Support the SERC mission for Science, Research and Education

• Study the effects of solar fields on biodiversity, ecosystem function and agriculture

• Conduct vital research and inter-institutional collaborations on land management and agrivoltaics

• Net Zero+ status and green infrastructure of

Edgewater campus will promote SERC as a convening center for SI to build and lead new partnerships and collaborations

• Educate students and the public on renewable energy and integrated climate solutions

Disclaimer: These are the author's opinions and do not alter or influence the terms of the Request for Proposal (RFP).

SERC Solar PV – Project Site

SERC Solar PV – Project Site Location

Parcel #2

Parcel #1

Google Earth (Lat/Long: 38.8588856,-76.5579751)

SERC Solar PV – Project Site

Parcel #2Parcel #1

Solar Field North 4.91ac Solar Field South 7.93ac

Solar PV Project – HelioScope

*Estimated Solar PV Capacity of 3.2 MW DC with option up to 4.0 MW

DC

Parcel #1

Parcel #2 *Assuming trees are cleared from the middle of Parcel 2.

Solar PV Project – HelioScope

Parcel #1

Parcel #2

*Assuming the trees are cleared in the middle of Parcel 2.

HelioScope Models

Parcel #1

Parcel #2

Top-Down View 3D View Trees at the border of the property are shown above

SERC Solar PV – Site LIDAR Imagery

SERC Solar PV – Project Site Street View

Google Street View (Lat/Long: 38.8588856,-76.5579751)

Muddy Creek Road Cumberstone Rd

• There are large trees on the border of the property, with a height of approximately 50 feet or more.

Solar PV Project – Base Bid and Options

BASE BID: Design, permitting, construction and commissioning of all site infrastructure improvements and equipment installation required to install the specified and proposed 3.2 MW DC PV system interconnected to the BGE electrical distribution system. Note: system O&M is not included in the base bid.

OPTION 1: O&M of the 3.2 MW PV System for one year, with a further option for up to four (4) additional years. This is additive to the base bid.

OPTION 2: Design, permitting, construction and commissioning of all site infrastructure improvements and equipment installation required to install the specified and proposed 4.0 MW DC PV system interconnected to the BGE electrical distribution system as specified and proposed. Note: system O&M is not included in this Option. Option 2 is not additive but in lieu of the base bid.

OPTION 3: O&M of the 4.0 MW PV System for one year, with a further option for up to four (4) additional years. This is in lieu of Option 1.

Solar PV Project Milestones

Completion by Number of Weeks After NTP Weeks are Total/Cumulative, not additive

Submission/Phase/Activity

1Site Specific Safety Plan

2Schedule of Estimated Values

3Project Schedule

4Basis of Design Document

850% design

10Design review (by SI)

12100% design

14Design review (by SI)

16Final Design

52Construction Complete

54Testing and Commissioning

Excerpt from RFP/SOW: SI may authorize the contractor to proceed with various aspects of construction or procurement, prior to the final design submission/approval, once those requirements have been sufficiently defined in the design documents to the satisfaction of the Smithsonian.

Solar PV Project – Technical Evaluation Factors (all weighted equally)

1. Design-Build Team A. Design Build Team Overview B. Prime Contractor

a. Past Performance

b. Qualifications/Experience of Key Personnel

c. Project Experience on Similar Projects

C. Design Team

a. Past Performance

b. Qualifications/Experience of Key Personnel

c. Project Experience on Similar Projects

2. Schedule and Plan of Accomplishment

3. Concept Design Submission including the offeror’s proposed site layout, panels, inverters, and other key components, as well as the estimated annual energy generation.

SERC Solar PV – BGE Developers & Contractors Resource Link

Developers & Contractors | BGE - An Exelon Company

KEY BGE Personnel – James Mirabile, Principal Engineer of Green Power Connection Team https://www.bge.com/smart-energy/my-green-power-connection/developers-contractors

SERC Solar PV Project Preproposal Conference

BACK UP SLIDES

February 2025

Solar PV Project – HelioScope Assumptions

Technology Assumptions: Helioscope1 PV Model

AssumptionInputSystem Type

First Solar, FS-6450 (450W)

Module type

Ground mount, fixed tilt racking

20°Module tilt (degrees)

Parcel 1: 160 degree Parcel 2: 180 degree

Azimuth (degrees)

5 wide x 4 tallFrame size

10 ftRow spacing (ft)

1 ftFrame spacing (ft)

6 ftPerimeter setback (ft)

LandscapeOrientation