This request for proposal (RFP) from the Smithsonian Institution seeks an architect-engineer multidiscipline contract to provide planning and design services for the Public Space Renewal Program Phase IV at the National Museum of American History in Washington, DC. Key disciplines required include architecture, mechanical and electrical engineering, landscape architecture, civil engineering, graphic design, and geotechnical engineering. Responses are due no later than 3:00 pm Eastern time on April 8, 2022. The RFP specifies a minimum 40% small business subcontracting requirement. An attachment provides responses to 14 questions from prospective offerors regarding the solicitation requirements and response format.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
33330222RF0010020
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
OCON
Washington DC 20013-7012
MRC 1200
P.O. BOX 37012
SMITHSONIAN INSTITUTION
03/18/20220001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. The Solicitation Number cited above, for NMAH Public Space Renewal Program (PSRP) Phase
IV at the National Museum of American History, located in Washington, DC is hereby amended as follows:
A.1. The Due Date for Receipt of Submittals remains April 8, 2022, at 3:00 PM EST.
A.2. Attached hereto and made part of this Amendment One are the SI Responses to Bidders
Questions Number 1 to 14.
END OF AMENDMENT ONE
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of Contracting Officer)(Signature of person authorized to sign)
Willard B. Powell
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
9B. DATED (SEE ITEM 11)
03/18/2022
Smithsonian Institution
Office of Planning Design & Construction
PROJECT:NMAH Public Space Renewal Program (PSRP) Phase IV
LAST UPDATED: 3/18/2022
Request for Information SI Response
Are you able to provide the contractor and contract numbers for Phase 1 to Phase III? Any information you can provide will be helpful.
We will not provide contractor and contractor numbers for previous projects, they are not relevant to the current contract
I had question about the 100-page limit, what parts are included in that limit? Also, the SF300 Part 1 & 2 has ½” margins, would we still need to follow the 1” rule, or is the ½” acceptable?
SF330 Parts I and II should be utilized without reformatting.
All attached, additional pages should be formatted with 1" margins.
Please confirm if any portion of the SF-330 Part I or Part II’s are excluded from the 100-page count limitation. Will the table of contents, dividers, and cover letter also be included in the page limit?
Covers, tabs, cover letter, table of contents and signed amendment forms are excluded. We anticipate a high volume of responses.
The solicitation notes that it is primarily an interior renovation, but landscape architecture, civil engineering and geotechnical engineering are noted as required disciplines. Can you provide clarification of the exterior scope?
The PSRP IV exterior scope may include limited site and drainage improvements and limited redevelopment of the landscaping of the Victory Garden to protect the East facade.
On page 7, part 5 Submission Requirements, C: “On the SF330, Part I, Block F, provide the title and contract award dates for all projects listed in that section.” Can you please clarify the intent? Is this just to request that section F projects list title and contract award dates on their respective sheets?
F. Example Projects Which Best Illustrate Proposed Team's
Qualification for this Contract shall be complete and provide all information required by the form. Ensure that POC's information is up to date and phone numbers are accurate.
RFP (p.8) states “E. Please submit one (1) hard copy of the SF 330 submission along with electronic submission in electronic pdf format.
The SF 330 shall have a page limit of 100 pages.”
• Question: Would you exclude admin content (cover letter, cover page, back page, TOC, acronym list, etc.) from the 100 page limit?
See #3
As there is a minimum 40% SB requirement there will be multiple Part
IIs; the more diverse your proposed team the more Part IIs that will be required. Can these be excluded from the page count so that team diversity isn’t compromised?
No
Within the last 7 years we have several pages of recognitions, accolades, and awards. Can these be provided as an attachment and outside of the page count?
No
Graphic Design is included as a key discipline, requiring a key lead, under section D “Services” of the RFP. What scope is anticipated for the
Graphic Design team for this pursuit?
Signage and Wayfinding & large graphics for temporary construction
Civil is included as a key discipline, under section D “Services” of the RFP.
Civil covers a wide range of specialties. Are there a specific civil specialty that are of interest?
The bearing capacity and stability of the soils will need to be confirmed as there have been sinkholes reported in this portion of the site.
There are below-grade utilities that will need to located and coordinated
RFP (p.5) states “Firms responding are encouraged to submit a list of recognitions, accolades and awards obtained in the last seven years.”
However, the time limit for the past performance on contracts is not specified in Sec. 3.C.
•Question: What is the time limit for past performance on contracts
(CPARS, CCASS, etc.)?
7 years
RFP (p.8) states “E. Please submit one (1) hard copy of the SF 330 submission along with electronic submission in electronic pdf format. To make it easier to find the information we would like to use dividers.
Would the dividers be excluded from the page count?
See #3
A typical SF330 resume is 2 pages. You are requesting 22 key discipline leads and narratives emphasizing their contributions and therefore anticipate that we will use 2 pages. This would be 44 pages of the 100 page count which seems inconsistent with the importance given to the evaluation criteria. Would you consider excluding the resumes (Section
E) from the page count?
No
My firm is working on the National Museum of American History, Public
Space Renewal Program (PSRP) Phase IV RFQ and we were wondering if you could clarify the scope of work for graphic design?
See #9