32701-13840_Trace_Creek_Specifications.pdf

PDF 281 KB Posted

Attached to
WTRBA Trace Creek - UPDATED
Solicitation number
Event 32701-13840
Issued by
Henry County, Tennessee

About this file

This is a project specification document issued by the West Tennessee River Basin Authority and Tennessee Department of Environment and Conservation for the removal of a low-head dam obstruction on Trace Creek in Waverly, Humphreys County, Tennessee. The project involves the removal of a concrete-encased abandoned sewer line that obstructs stream flow, impounding approximately 600 linear feet of water and creating a 6-foot change in stream elevation. The scope of work includes removal of the concrete encasement, restoration of the stream bed and banks at the removal location, restoration and stabilization of approximately 620 linear feet of downstream stream channel, and stabilization of approximately 180 linear feet of upstream streambanks. The estimated quantities include mobilization and demobilization, structure removal, sewer line capping (2 each), haul road construction (735 linear feet), boulder vanes (6 each), longitudinal stone toe protection (838 linear feet), riprap placement (726 tons), various erosion control measures including silt fence, filter sock, and coir fiber blankets, vegetation installation including live stake cuttings and tree plantings totaling over 1,000 plants, and asphalt restoration (350 square yards). Construction must commence upon contract execution and be completed within 30 working days, with one additional day allowable per inclement weather day. Bidders are required to conduct a thorough site visit during normal working hours. A pre-construction conference must be held prior to work commencement, and a preliminary schedule including critical path analysis and schedule of values must be submitted within 10 days of contract execution.

The bid is structured on a unit price basis for estimated quantities, with final payment based on actual quantities determined during construction. This is an American Rescue Plan Act (ARPA) Resource Protection Grant funded project. The specifications reference pending environmental permits and authorizations, including TDEC ARAP NRS 25.186, USACE National Wetland Program permits #53 and #27, and a TDEC Construction General Permit. Contractors must provide as-built drawings showing all changes or corrections, maintain compliance with all permit requirements, and coordinate site access through the Owner or Engineer. Owner and Engineer shall conduct periodic inspections at intervals appropriate to construction stages to ensure conformance with contract documents, though continuous inspections are not required.

View the file

Other files

File Type Posted
Specifications_Version_2.pdf PDF
Attachment_B_Performance_Bond.docx DOCX document
Site_Plans_Version_2.pdf PDF
Attachment_A_Payment_Bond.docx DOCX document
32701-13840_Trace_Creek_Specifications.pdf PDF
WTRBA_Trace_Creek.pdf PDF
32701-13840_Trace_Creek_T_C.pdf PDF
32701-13840_Trace_Creek_T_C.pdf PDF
WTRBA_Trace_Creek.pdf PDF
TRACE_CREEK_LOW_HEAD_DAM.pdf.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SPECIFICATIONS

FOR

TRACE CREEK

LOW HEAD DAM REMOVAL

WAVERY, HUMPHREYS COUNTY,

TENNESSEE

WEST TENNESSEE RIVER BASIN

AUTHORITY

TENNESSEE DEPARTMENT OF

ENVIRONMENT AND CONSERVATION

NOVEMBER 2025

CEC Project No. 343-976

11/25/2025

TRACE CREEK LOW-HEAD DAM REMOVAL SPECIFICATIONS

PART 1 PROJECT DESCRIPTION

1.01 The project is for the removal of a concrete encased abandoned sewer line crossing on Trace Creek in Waverly, Tennessee. The concrete encasement that surrounds the abandoned sewer line pipe extends into the stream substrate, obstructing flow within Trace Creek and functioning as a low head dam. This obstruction is impounding approximately 600 linear feet (LF) of water behind the structure and results in a 6-foot change in stream elevation within this section of stream. The proposed work will consist of removal of the concrete encased sewer line from Trace Creek, restoration of the stream bed and banks at the location of the removed sewer line, restoration/stabilization of approximately 620 LF of stream channel downstream of the removed sewer line, stabilization of streambanks approximately 180 LF upstream of the sewer line crossing. It is an American Rescue Plan Act (ARPA) American Rescue Plan (ARP) Resource Protection Grant funded project.

PART 2 PROJECT DOCUMENTS

2.01 Trace Creek Low Head Dam Removal Plans dated 11/25/2025.

2.02 TDEC ARAP NRS 25.186 (PENDING)

2.03 USACE NWP #53 Removal of Low Head Dams LRN-2025-00869 (PENDING)

2.04 USACE NWP #27 Aquatic Habitat Restoration LRN-2025-00869 (PENDING)

2.05 TDEC Construction General Permit (PENDING)

PART 3 SITE

3.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

3.02 Examination of Site

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit, the Bidder must not disturb any ongoing operations at the Site.

B. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner or Engineer contact for visiting the Site. Bidder must conduct the required Site visit during normal working hours.

PART 4 AS-BUILT DRAWINGS

4.01 During construction, the contractor shall maintain a set of prints showing any changes or corrections in red. These prints shall be submitted to the engineer at the completion of the work.

PART 5 PRE-CONSTRUCTION MEETING

5.01 Prior to the start of construction, the Contractor shall call a pre-construction conference, including his Project Superintendent and his Foreman, the Engineer, and others as the Engineer may direct. The purpose of this meeting is to review the requirements of the Contract, Permit and Construction Documents to assure complete understanding of the specific responsibilities of each participant and his relationship with the others involved.

PART 6 ENGINEER’S AND OWNER’S STATUS DURING CONSTRUCTION

6.01 Owner and Engineer may make visits to the Site at intervals appropriate to the various stages of construction as Owner deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor’s Work. Based on information obtained during such visits and observations, Owner may determine, in general, if the Work is proceeding in accordance with the Contract Documents. Owner shall not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. Owner’s efforts shall be directed toward providing for Owner a degree of confidence that the completed Work will conform generally to the Contract Documents.

PART 7 SCHEDULE

7.01

7.02

It is expected that the work for this project will commence upon execution of the contract.

The project must be fully completed within 30 working days. The Contractor will be allowed one (1) additional day for each day of inclement weather. Allowable working days are defined as Monday through Friday 7:00 a.m. to 5:00 p.m.; however, Contractor may perform equipment maintenance and startup before and after.

Project Schedule: Within 10 days after the Effective Date of the Contract, Contractor shall submit to Owner for timely review a preliminary schedule including:

A. The Critical Path.

B. The planned start and completion dates for each activity, the duration of each activity, and the sequencing of all activities. If activities have durations of more than one updated period, break the activities into two or more activities distinguished by location or some other feature.

C. Dates related to the procurement of materials, equipment and articles of special manufacture; and dates related to the submission of working drawings, plans and other data specified for review or approval by Owner.

D. Dates related to key Owner inspections.

E. Dates related to specified activities by the Owner and third parties, and times for starting and completing the various stages of Work, including but not limited to all Milestones specified in the Contract.

F. A preliminary Schedule of Submittals.

G. A preliminary Schedule of Values for all of the Work, which includes quantities and prices of items that, when added together, equal the Contract Price, and which subdivides the Work into component parts in sufficient detail to serve as the basis for progress payments during performance of the Work. Such prices shall include an appropriate amount of overhead and profit applicable to each item of Work.

PART 8 BASIS OF BID

8.01 Unit Price and Estimated Quantities

A. Bid shall be based on a unit price basis for each item of Work listed in the unit price section of the Bid Form for the Estimated Quantities.

B. Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item.

C. Estimated quantities are not guaranteed and are solely for the purpose of comparison of

Bids.

D. Final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.

8.02 Bid Form

FOOTNO

TES

ITEM

NO.

DESCRIPTION UNIT QUANTITY

UNIT

COST

TOTAL

MOBILIZATION AND

DEMOBILIZATION

L.S. 1

REMOVAL OF STRUCTURE

(CONCRETE DAM)

L.S. 1

4 003

CUT AND CAP ABANDONED

SANITARY SEWER

EACH 2

6 004 CONSTRUCTION HAUL ROAD L.F. 735

005 BOULDER VANE EACH 6

3 006

LONGITUDINAL STONE TOE

PROTECTION

L.F. 838

9 007 STREAM CONSTRUCTION ENTRANCE EACH 2

8 008 TEMPORARY COFFERDAM L.S. 1

2 009 MINERAL AGGREGATE (SIZE 57) TON 11

010 MACHINED RIPRAP (CLASS C) TON 726

12 011 GRAVEL PATH RESTORATION L.F. 595

TEMPORARY CONSTRUCTION

ENTRANCE/EXIT

EACH 2

11 013 SILT FENCE WITH WIRE BACKING L.F. 200

10 014 FILTER SOCK L.F. 1,200

7 015

GEOTEXTILE TYPE (III) (EROSION

CONTROL) PER S.Y.

S.Y. 50

PERMANENT SEEDING MIX

W/MULCH

AC 3

TEMPORARY SEEDING MIX

W/MULCH

AC 3

700 GRAM COIR FIBER EROSION

BLANKET

S.Y. 1244

019 SEDIMENT FILTER BAG (15' X 15') EACH 2

020 RESTORE ASPHALT S.Y. 350

5 021 BRUSH LAYERING L.F. 1,800

LIVE STAKE CUTTINGS: SALIX

NIGRA (18-24 INCH LENGTH)

EACH 314

LIVE STAKE CUTTINGS: CORNUS

AMOMUM (18-24 INCH LENGTH)

EACH 314

LIVE STAKE CUTTINGS: SAMBUCUS

CANADENSIS (18-24 INCH LENGTH)

EACH 314

LIVE STAKE CUTTINGS: ALNUS

SERRULATA (18-24 INCH LENGTH)

EACH 314

ACER RUBRUM (RED MAPLE 2-5 FT

C.G.)

EACH 41

LIRIODENDRON TULIPIFERA (TULIP

POPLAR 2-5 FT C.G.)

EACH 41

PLATANUS OCCIDENTALIS

(SYCAMORE 2-5 FT C.G.)

EACH 41

QUERCUS ALBA (WHITE OAK 2-5 FT

C.G.)

EACH 41

QUERCUS PALUSTRIS (PIN OAK 2-5

FT C.G.)

EACH 42

031 TREE PROTECTION FENCING L.F. 942

032 ORANGE CONSTRUCTION FENCE L.F. 305

Total Base Bid

FOOTNOTES:

1. ALL QUANTITIES ARE TO BE USED AS DIRECTED BY THE ENGINEER.

2. INCLUDES 11 TONS FOR 1 SEDIMENT FILTER BAG.

3. INCLUDES ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY TO CONSTRUCT

LONGITUDINAL STONE TOE AS SHOWN IN DETAIL 1, SHEET EC800. L.F. BRUSH LAYERING

SHALL BE PAID AS A SEPARATE ITEM. SHALL BE MEASURED AS TOTAL L.F. OF LONGITUDINAL

STONE TOE.

4. INCLUDES ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY TO CUT AND CAP THE

ABANDONED SEWER LINE.

5. INCLUDES ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY FOR BRUSH LAYERING AS

SHOWN IN DETAIL 1, SHEET EC800. PAYMENT SHALL BE PER LINEAR FOOT FOR EACH ROW

OF BRUSH LAYERING CONSTRUCTED. DENSITY OF LIVE BRUSH LAYERING SHALL BE ONE

BUNDLE PER 3 LINEAR FEET. ONE BUNDLE IS A MINIMUM OF 25 BRANCHES. THE FOLLOWING

4 SPECIES ARE TO BE USED: SALIX NIGRA, CORNUS AMOMUM, SAMBUCUS CANADENSIS,

ALNUS SERRULATA.

6. INCLUDES ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY TO CONSTRUCT AND

MAINTAIN THROUGH THE DURATION OF THE PROJECT. HAUL ROAD TO EXTEND FROM HOLLY

LN TO THE PROJECT WORK AREA. INCLUDES ONE LAYER OF GEOTEXTILE TYPE III, 2 INCH

STONE, MIN. 6 INCH THICK, AND MIN. 12 FT IN WIDTH.

7. INCLUDES 50 SY FOR 1 SEDIMENT FILTER BAG .

8. INCLUDES 250 LINEAR FEET PER SETUP TO BE REPOSITIONED INTO MULTIPLE SETUPS AS

NEEDED TO ALLOW WORK IN THE DRY.

9. INCLUDES ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY TO CONSTRUCT STREAM

CONSTRUCTION ENTRANCE AS SHOWN IN DETAIL 3, SHEET EC906. LOCATION OF STREAM

CONSTRUCTION ENTRANCES SHALL BE DETERMINED IN THE FIELD.

10. TO BE USED AS DIRECTED ALONG THE TOP OF STREAM BANK.

11. INCLUDES 200 LF FOR 1 SEDIMENT FILTER BAG.

12. INCLUDES RESTORING AND STABILIZING EXISTING PATH WITHIN LIMITS OF DISTURBANCE

TO EXISTING GRADE AND PLACING A 4 IN LAYER OF #57 STONE ON IT.

File details come from the government source that posted it. Updated .