DIVISION 2

SECTION 02378

SITE CONSTRUCTION

RIPRAP

PART 1 – GENERAL

1.01

WORK INCLUDED

Work covered under this section consists of the placement of the riprap as shown on the drawings.

1.02

SUBMITTALS

The CONTRACTOR shall provide submittals for filter fabric and riprap. Submittals are to be in accordance with Section 01300.

PART 2 – PRODUCTS

2.01

FILTER FABRIC

Filter fabric shall be utilized as shown in the drawings to prevent washing of fines into the riprap voids on the upstream face of embankments. The geotextile filter fabric shall be a needle-punched, non-woven meeting the following specifications:

TABLE 1

Non-woven Geotextile Filter Fabric Minimum Average Roll Values

Property
Test Method
MARV*
Units
Mass Per Unit Area
ASTM D5261
8
oz./yd2
Tensile Strength
ASTM D4632
180 min.
lbs

Grab test

Puncture Strength
ASTM D4833
90 min.
lbs
Elongation at Failure
ASTM D4632
≥50
%
Ultraviolet light
ASTM D4355
70 min.
%
(% residual tensile strength)
150-hr exposure
Permittivity
ASTM D4491
1.0 min.
sec-1
Flow Rate
ASTM D4491
140 min.
gal/min/ft2
Apparent Opening Size
ASTM D4751
#70 max.
U.S. Sieve Size

*MARV = Minimum average roll values

2.02

RIPRAP

Riprap material shall be hard, durable, angular in shape, resistant to weathering, and to water action, free from overburden spoil and organic material. The following gradation is to be used:

Table 2

Riprap Specifications

Gradation
Rock Diameter
Dmax
12 inches
D50
8 inches
Dmin
3 inches

*Based on rock specific gravity = 2.65

PART 3 – EXECUTION

3.01

PLACING RIPRAP

Prior to placing riprap, filter fabric shall be installed as shown on the drawings and to the manufacturer’s requirements. Rock riprap shall then be placed on the filter fabric in such a way to ensure it is not punctured during placement. Rock riprap shall also be placed to ensure that larger rock fragments are uniformly distributed and that the material when placed is stable. The rock riprap shall be placed to the depth and area as shown on the drawings and placing shall be done to the extent necessary to assure placement in compliance with the above.

Prior to the placement of fabric, the ground surface shall be graded smooth. No rocks, lumps of dirt, or other material, which may damage the fabric, shall remain. Fabric shall be laid smooth without folds or wrinkles. Adjacent rolls of fabric shall be overlapped a minimum of 12-inches.

END SECTION 02378