312319 Dewatering.pdf

PDF 13 KB Posted

Attached to
Y1LZ--693-222 | Parking Structure Solicitation Amendment 2 Federal contract opportunity
Solicitation number
36C24420R0075
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

This document includes specifications for a dewatering system and instructions for its installation and operation on a parking garage construction project. The contractor will be responsible for providing all necessary equipment, labor, and services to lower and control groundwater levels through excavation and construction to allow work to be performed in dry conditions. This includes operating a dewatering system continuously until backfilling is complete to maintain water levels at least one foot below excavation surfaces. The system must be designed to prevent issues from groundwater pressure, seepage, or erosion. The contractor must control surface water runoff, properly dispose of water removed from excavations according to permitting requirements, and have standby equipment available in case of system issues. Instructions are provided for installing and operating the dewatering system along with corrective actions if requirements are not met and removal upon project completion.

View the file

Other files for this federal contract opportunity

Other files attached to Y1LZ--693-222 | Parking Structure Solicitation Amendment 2, newest first.
File Type Posted
095113 Acoustical Panel Ceilings.pdf PDF
019100 Gen Commis.docx DOCX document
015816 Temp Int Signage.docx DOCX document
014535 Special Inspections.docx DOCX document
013323 Shop dwgs Product Data.docx DOCX document
042000 Unit Masonry Assemblies.pdf PDF
S02 Pricing Sheet.pdf PDF
36C24420R0075_6.docx DOCX document
EXHIBIT D -SampleTransmittalLetter Past Performance Evaluation Questionnaire.docx DOCX document
36C24420R0075_5.docx DOCX document
S04 Site Visit Sign-in.pdf PDF
P03 JA Yale Lock.pdf PDF
321723 Pavement Markings.pdf PDF
321216 Asphalt Paving.pdf PDF
320523 Cement and Concrete for Exterior Improvements.pdf PDF
280513.pdf PDF
265100.pdf PDF
260526.pdf PDF
238200.pdf PDF
233700.pdf PDF
233400.pdf PDF
233100.pdf PDF
230511.pdf PDF
221436.pdf PDF
210511.pdf PDF
099123 Painting.pdf PDF
024100.docx DOCX document
022113.docx DOCX document
017700 Contract Closeout_Single Prime.pdf PDF
017419.doc DOC document
017700a Contract Closeout Master Punch List_Single Prime.pdf PDF
013526.docx DOCX document
012900 Applications for Payment_Single Prime.pdf PDF
S02 ParkStructure Electrical Dwg.pdf PDF
Pstruct Dwg 21-25.pdf PDF
Pstruct Dwg 5-10.pdf PDF
Pstruct Dwg 1-2.pdf PDF
Arch Dwg 6-10.pdf PDF
S02 Dwg T1-S2.pdf PDF
EXHIBIT E - Past Performance Questionnaire.docx DOCX document
EXHIBIT B - Subcontractor Information and Consent Form.docx DOCX document
36C24420R0075_3.docx DOCX document
329000 Planting.pdf PDF
283100.pdf PDF
280528-33.pdf PDF
262416.pdf PDF
262200.pdf PDF
260573.pdf PDF
238216.pdf PDF
230593.pdf PDF
Show all 50

Y1LZ--693-222 | Parking Structure Solicitation Amendment 2 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Parking Garage Project Number 693-222

Department of Veterans Affairs

Wilkes-Barre, Pennsylvania

312319 - 1

SECTION 31 23 19

DEWATERING

PART 1 - GENERAL

1.1 DESCRIPTION:

This section specifies performance of dewatering required to lower and control ground water table levels and hydrostatic pressures to permit excavation, backfill, and construction to be performed in the dry. Control of surface water shall be considered as part of the work under this specification.

1.2 SUMMARY:

A. The work to be completed by the Contractor includes, but is not necessarily limited to the following:

1. Implementation of the Erosion and Sedimentation Control Plan.

2. Dewater excavations, including seepage and precipitation.

B. The Contractor shall be responsible for providing all materials, equipment, labor, and services necessary for care of water and erosion control. Excavation work shall not begin before the

Erosion and Sedimentation Control Plan is in place.

1.3 REQUIREMENT:

A. Dewatering system shall be of sufficient size and capacity necessary to lower and maintain ground water table to an elevation at least 300 mm (1 foot) below lowest foundation subgrade or bottom of pipe trench and to allow material to be excavated and concrete placed, in a reasonably dry condition. Materials to be removed shall be sufficiently dry to permit excavation to grades shown and to stabilize excavation slopes where sheeting is not required. Operate dewatering system continuously until backfill work has been completed.

B. Reduce hydrostatic head below any excavation to the extent that water level in the construction area is a minimum of 300 mm (1 foot) below prevailing excavation surface.

C. Prevent loss of fines, seepage, boils, quick conditions or softening of foundation strata.

D. Maintain stability of sides and bottom of excavation.

E. Construction operations are performed in the dry.

F. Control of surface and subsurface water is part of dewatering requirements. Maintain adequate control so that:

1. The stability of excavated and constructed slopes are not adversely affected by saturated soil, including water entering prepared subbase and subgrades where underlying materials are not free draining or are subject to swelling or freeze-thaw action.

2. Erosion is controlled.

3. Flooding of excavations or damage to structures does not occur.

4. Surface water drains away from excavations.

Wilkes-Barre, Pennsylvania

31 23 19 - 2

5. Excavations are protected from becoming wet from surface water, or insure excavations are dry before additional work is undertaken.

G. Permitting Requirements: The contractor shall comply with and obtain the required State and

County permits where the work is performed.

1.4 RELATED WORK:

A. Materials testing and inspection during construction: Division 01, GENERAL REQUIREMENTS.

B. Safety Requirements: Division 01, GENERAL REQUIREMENTS.

C. Submittal requirements as specified in Division 01, GENERAL REQUIREMENTS.

D. Protection of existing utilities, fire protection services, existing equipment, roads, and pavements:

Division 01, GENERAL REQUIREMENTS.

E. Subsurface Investigation: Section 31 20 00, EARTHWORK..

F. Excavation, backfilling, site grade and utilities: Section 31 20 00, EARTHWORK.

1.5 SUBMITTALS:

A. Submit in accordance with Division 01, GENERAL REQUIREMENTS and as follows:

B. Drawings and Design Data:

1. Submit drawings and data showing the method to be employed in dewatering excavated areas 30 days before commencement of excavation.

2. Material shall include: location, depth and size of wellpoints, headers, sumps, ditches, size and location of discharge lines, capacities of pumps and standby units, and detailed description of dewatering methods to be employed to convey the water from site to adequate disposal.

3. Include a written report outlining control procedures to be adopted if dewatering problem arises.

4. Capacities of pumps, prime movers, and standby equipment.

5. Design calculations proving adequacy of system and selected equipment. The dewatering system shall be designed using accepted and professional methods of design and engineering consistent with the best modern practice. The dewatering system shall include the deep wells, wellpoints, and other equipment, appurtenances, and related earthwork necessary to perform the function.

6. Detailed description of dewatering procedure and maintenance method.

7. Materials submitted shall be in a format acceptable for inclusion in required permit applications to any and all regulatory agencies for which permits for discharge water from the dewatering system are required due to the discharge reaching regulated bodies of water.

C. Inspection Reports.

D. All required permits.

31 23 19 - 3

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 INSTALLATION:

A. Install a dewatering system to lower and control ground surface water in order to permit excavation, construction of structure, and placement of backfill materials to be performed under dry conditions. Make the dewatering system adequate to pre-drain the water-bearing strata above and below the bottom of structure foundations, utilities and other excavations.

B. In addition, reduce hydrostatic pressure head in water-bearing strata below structure foundations, utility lines, and other excavations, to extent that water levels in construction area are a minimum of 300 mm (1 foot) below prevailing excavation surface at all times.

3.2 OPERATION:

A. Prior to any excavation below the ground water table, place system into operation to lower water table as required and operate it continuously 24 hours a day, 7 days a week until utilities and structures have been satisfactorily constructed, which includes the placement of backfill materials and dewatering is no longer required.

B. Place an adequate weight of backfill material to prevent buoyancy prior to discontinuing operation of the system.

3.3 WATER DISPOSAL:

A. Dispose of water removed from the excavations in such a manner as:

1. Will not endanger portions of work under construction or completed.

2. Will cause no inconvenience to Government or to others working near site.

3. Will comply with the stipulations of required permits for disposal of water.

4. Will Control Runoff: The Contractor shall be responsible for control of runoff in all work areas including but not limited to: excavations, access roads, parking areas, laydown, and staging areas. The Contractor shall provide, operate, and maintain all ditches, basins, sumps, culverts, site grading, and pumping facilities to divert, collect, and remove all water from the work areas. All water shall be removed from the immediate work areas and shall be disposed of in accordance with applicable permits.

B. Excavation Dewatering:

1. The Contractor shall be responsible for providing all facilities required to divert, collect, control, and remove water from all construction work areas and excavations.

2. Drainage features shall have sufficient capacity to avoid flooding of work areas.

3. Drainage features shall be so arranged and altered as required to avoid degradation of the final excavated surface(s).

31 23 19 - 4

4. The Contractor shall utilize all necessary erosion and sediment control measures as described herein to avoid construction related degradation of the natural water quality.

C. Dewatering equipment shall be provided to remove and dispose of all surface and ground water entering excavations, trenches, or other parts of the work during construction. Each excavation shall be kept dry during subgrade preparation and continually thereafter until the structure to be built, or the pipe to be installed therein, is completed to the extent that no damage from hydrostatic pressure, flotation, or other cause will result.

3.4 STANDBY EQUIPMENT:

Provide complete standby equipment, installed and available for immediate operation, as may be required to adequately maintain de-watering on a continuous basis and in the event that all or any part of the system may become inadequate or fail.

3.5 CORRECTIVE ACTION:

If dewatering requirements are not satisfied due to inadequacy or failure of the dewatering system (loosening of the foundation strata, or instability of slopes, or damage to foundations or structures), perform work necessary for reinstatement of foundation soil and damaged structure or damages to work in place resulting from such inadequacy or failure by Contractor, at no additional cost to Government.

3.6 DAMAGES:

Immediately repair damages to adjacent facilities caused by dewatering operations.

3.7 REMOVAL:

Insure compliance with all conditions of regulating permits and provide such information to the

COR. Obtain written approval from COR before discontinuing operation of dewatering system.

----- 312319 E N D -----