This is an Amendment 0003 Attachment Page containing clarifications to the USCG Station Portsmouth & Sector Virginia Logistics Building Bathroom Renovations solicitation (31040Q260000223). The amendment addresses two key points: (1) proposals must be accepted within 45 days, and (2) a site visit is recommended rather than required, though it remains recommended per the Statement of Work. This represents a modification from the original solicitation language, which stated that a site visit was required to conduct field verifications of the bathroom renovation sites and construction needs.
The underlying solicitation requires contractors to provide all labor, equipment, and materials for bathroom renovations at two USCG facilities totaling 890 square feet across four bathrooms, including tile and grout restoration, and a complete renovation of the men's bathroom shower area at USCG Sector Virginia Logistics Building that involves dividing an existing single shower into two separate stalls and constructing a dedicated changing area. Respondents must submit SF-1442 forms and proposals to Keasha.M.Colvin@uscg.mil. This is a new requirement with no incumbent contractor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF-30 Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| SF1442 Amendment 0002.pdf | ||
| Amendment 0001 SF30.pdf | ||
| REV. 1 TERMS AND CONDITIONS - CLAUSES AND PROVISIONS.docx | DOCX document | |
| Sector Logistics Bathroom.pdf | ||
| Station Bathrooms.pdf | ||
| TERMS and CONDITIONS-CLAUSES and PROVISIONS.doc | DOC document | |
| Statement of Work (SOW) Repair Bathrooms at STA Portsmouth and SEC Logistics at Base Portsmouth.docx | DOCX document | |
| SF1442.pdf | ||
| Davis Bacon VA20260161.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 0003 ATTACHMENT PAGE
1. QUESTION: How many days for proposal acceptance?
ANSWER: 45 days
2. QUESTION: Is a site visit required?
ANSWER: No, but it is recommended per the SOW.