STA Noyo River Renovations Questions and Answers.pdf
PDF 135 KB Posted
- Attached to
- Bathroom Renovations at USCG Station Noyo River Federal contract opportunity
- Solicitation number
- 30464PR260000002
About this file
This document is a Questions and Answers file for the STA Noyo River Renovations contract opportunity. It addresses ten clarifications submitted by prospective contractors regarding the scope of bathroom renovation work.
Key clarifications include: replacement shower enclosures shall be fiberglass (not tile) for men's and ladies bathrooms; ceiling panels require no work; urinal mounting shall remain wall-mounted despite initial work list references to floor-mounted units; bathrooms must be renovated in stages with no temporary facilities required; new countertops and faucets are required for sinks in male and female berthing as well as the Command bathroom vanity sink, with specifications to be provided; and newly installed fixtures must properly drain, with drainage system repairs required based on condition assessment. The contractor must commence work within fifteen calendar days of receiving the award and complete all work ready for use within sixty calendar days after receipt of the notice to proceed, which will be issued once all submittals are approved.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Construction Solicitation Noyo River Bathroom Renovations.pdf | ||
| USCG Station Noyo River - Lead ACM Survey Report.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STA Noyo River Renovations Questions and Answers
1. For the men’s and ladies bathrooms, should the replacement shower enclosure be fiberglass or tile? For tile choices, should it be 2x2 inch squares on floor and 4x4 inch on the walls?
Answer: Fiberglass
2. Does any work need to be done on the ceiling panels?
Answer: No
3. When is work required to start?
Answer: The contractor shall be required to commence work under this contract within fifteen calendar days after the date the contractor receives the award and complete the entire work ready for use not later than 60 calendar days after receipt of the notice to proceed. The notice to proceed shall be issued once all submittals are approved.
4. The urinals are wall mounted currently. The list of work says floor mounted. Do you want them changed from wall to floor mount?
Answer: The current mounting configuration is not an issue. The urinal mounting shall remain wall mounted.
5. Will it be allowable to renovate all bathrooms at the same time and will temporary facilities be required when bathrooms are oƯline?
Answer: They will need to be renovated in stages. Temporary facilities are not required.
6. Will new countertops be required for sinks in male and female berthing?
Answer: Yes
7. Will new faucets be required and will specifications be provided for new sinks in male and female berthing?
8. Sink in Command bathroom is a vanity cabinet with an integral sink countertop. Will a new faucet be required and will specifications be provided for this sink?
9. Existing urinals are wall hung not floor mounted. Will new urinals be wall hung and will they utilize existing carriers?
Answer: The current mounting configuration is not an issue. The urinal mounting shall remain wall mounted.
10. Please clarify what drainage system is to be upgraded in women’s berthing?
Answer: The contractor shall ensure newly installed fixtures (sinks, showers, toilets) properly drain. Repairs to the drainage system may be required based on its condition.