AMENDMENT 0002 ATTACHMENT PAGE.pdf

PDF 107 KB Posted

Attached to
USCG Station Indian River HAZMAT Building Overhaul and Removal of Hazardous Material
Solicitation number
30293RFQ260000008
Issued by

About this file

This is a Questions and Answers document (Amendment 0002) issued to clarify requirements for a federal contract opportunity involving environmental remediation work at a Coast Guard Station.

The amendment addresses six inquiries from potential contractors regarding soil contamination assessment and removal procedures. Key points include: soil sampling and laboratory data questions are answered in Amendment 0001, and the revised Statement of Work removes the requirement to remove contaminated soil. Questions concerning the horizontal and vertical limits of contamination, cleanup standards for determining excavation cessation, and soil classification for disposal are all cross-referenced to Amendment 0001 for answers. The Coast Guard Station is identified as the EPA generator for removed soil. Additionally, any unanticipated additional work beyond the contract scope will be handled as growth work to be negotiated between the contractor and Government rather than processed as a formal change order.

View the file

Other files

File Type Posted
Amendment 0002 SF30.pdf PDF
REV. 1 Hasmat Building Overhaul Complete Overhaul SOW.pdf PDF
Amendment 0001 SF30.pdf PDF
AMENDMENT 0001 ATTACHMENT PAGE.pdf PDF
Davis Bacon Act WD.pdf PDF
RFQ 30293RFQ260000008.pdf PDF
SF25A.pdf PDF
SF1442.pdf PDF
Davis Bacon Act WD Poster.pdf PDF
Hasmat Building Overhaul Complete Overhaul SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 0002 ATTACHMENT PAGE

1. QUESTION: Has the soil been sampled? Can the Government provide the lab data.

ANSWER: This question has been answered in Amendment 0001. Additionally, the revised Statement of Work (SOW) provided removes reference to the requirement of removal of any contaminated soil.

2. QUESTION: What are the horizontal and vertical limits of contamination?

ANSWER: Please see the answer to question number one.

3. QUESTION: What cleanup standard determines when excavation stops?

4. QUESTION: How will soil be classified for disposal?

5. QUESTION: Who is the EPA generator for removed soil?

ANSWER: The Coast Guard Station.

6. QUESTION: Will additional contamination be handled as a change order?

ANSWER: Any additional work that could not be reasonably anticipated will be handled as growth work to be negotiated between the contractor and Government.

(End of Amendment 0002)