3-TB2643-BB - Attach E - Bidding and Construction Timeline.pdf
PDF 44 KB Posted
- Solicitation number
- TB2643-BB
- Issued by
- Salt Lake County, Salt Lake City, Utah
About this file
This document is a bidding and construction timeline for the Bryant Middle School Exterior Basketball Courts project issued by the Salt Lake City School District (SLCSD) in Utah. The project involves installing exterior basketball courts in the northwest corner of the play field at Bryant Middle School, located at 40 S 800 E, Salt Lake City, Utah 84102. A mandatory pre-bid site visit is scheduled for January 28, 2026 at 12:00 P.M. at the job site, with attendance required for bid eligibility. The timeline indicates that final construction drawings will be available in January 2026, with a bid posting on January 23. Questions must be submitted in writing by February 2 at 1:00 P.M., and a final addendum will be posted by February 4 at 9:00 A.M. Bids are due on February 9 at 10:00 A.M., followed by board review on February 17 and board approval on June 1. The contractor's available start date is June 3, with project completion required by August 18, prior to the first day of school.
Contractors must submit a bid security equal to at least 5% of the total bid amount prior to the bid deadline, with the selected contractor required to obtain a 100% Performance/Payment bond. Contractors must hold a B100 or S330 active contractor's license or equivalent, with a copy of the current license and any licensure limit statements required to be submitted with the bid. Liquidated damages of $500.00 per calendar day apply for completion past the project deadline. All questions and answers must be submitted and communicated exclusively through the Bonfire/U3P system or via authorized addenda issued by SLCSD.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Auxiliary Services 995 West Beardsley Place
Salt Lake City, UT 84119
Excellence and Equity: every student, every classroom, every day slcschools.org
Bryant Middle School Exterior Basketball Courts 2026
Bidding and construction timeline
Jan 2026 Final construction drawings from MHTN
Jan 23 Post bid
Jan 28 Pre-bid at 12:00. Meet at Bryant Middle School back parking lot on the north side of the school
Feb 2 Question due date at 1:00 PM
Feb 4 Post final addendum by 9:00 AM
Feb 9 Bid due date at 10:00 AM
Feb 10 Board letter
Feb 17 Board approval
June 1 Available start date for contractor
Aug 3 Ready for final inspection
Aug 11 Project final completion
Aug 18 First Day of School
File details come from the government source that posted it. Updated .