Stockton Town- Soldier Canyon Water Line
Solicitation number
RA26-98
Issued by
Tooele County, Utah

About this file

Summary

This document comprises the technical specifications and construction requirements for the Stockton Town Soldier Canyon Water Line project, a state and local contract opportunity issued by Stockton Town, Utah. The project involves the construction of 2,220 linear feet of 8-inch C900 DR-18 water line extending from the existing water treatment facility to the new Soldier Canyon Well No. 2, including all fittings, appurtenances, valves, connections to existing piping, trenching, backfill, and restoration. The work is to be performed under a single lump-sum contract with a contract completion date aligned with the contract documents. Bids will be received online through the Utah Public Procurement Place at https://utah.bonfirehub.com or in person at Stockton Town Hall, 18 North Johnson Street, Stockton, Utah 84071, until Thursday, March 5, 2026, at 4:00 p.m. local time. All questions regarding the bidding documents must be submitted no later than March 2, 2026, at 5:00 p.m. through the Bonfire platform or via email to eneil@bowencollins.com. The specifications encompass detailed requirements for materials, installation procedures, testing protocols, quality control, safety standards, environmental controls, and closeout procedures in accordance with referenced industry standards including AWWA, ASTM, NACE, SSPC, and OSHA regulations.

The project requires strict compliance with scheduling constraints, including work hours limited to 7:00 a.m. to 7:00 p.m., with overtime requiring prior approval from both the Owner and Engineer. The contract incorporates comprehensive requirements for pipe materials (PVC and ductile iron), coating and lining systems, field testing and disinfection, and utility protection. The contractor must maintain a detailed construction schedule with S-curve analysis, establish a quality control plan, provide appropriate safety programs and documentation, and manage all mobilization, site preparation, excavation, backfill, and restoration activities. Payment shall be based on earned value methodology tied to the Schedule of Values and Construction Schedule, with progress payments determined monthly. All materials and work are subject to inspection and testing by the Engineer or Owner-designated representatives, and the contractor bears responsibility for all costs associated with submittals, materials delivery, storage, security, dewatering, environmental compliance, and corrective work, with no additional compensation for these items unless specifically provided as separate bid line items.

View the file

Other files

File Type Posted
2-PART IV - DRAWINGS.pdf PDF
1-PART II - CONDITIONS OF THE CONTRACT.pdf PDF
4-PART I - BIDDING DOCUMENTS (1).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 1

GENERAL REQUIREMENTS

BC&A

STOCKTON SUMMARY OF WORK

SOLDIER CANYON WATER LINE PROJECT PAGE 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. The Work to be performed under this Contract consists of furnishing all plant, tools, equipment, materials, supplies, and manufactured articles and furnishing all labor, transportation, and services, including fuel, power, water, and essential communications, and performing all Work, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The Work shall be complete, and all Work, materials, and services not expressly indicated or called for in the Contract Documents, which may be necessary for the complete, safe, and proper construction of the Work in good faith shall be provided by Contractor as though originally so indicated, at no increase in cost to Owner.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of this Contract comprises the construction of 2,220 linear feet of 8” C900 DR-18 water line from the existing water treatment facility to the new Soldier Canyon Well No. 2.

Installation includes all fittings and appurtenances, valves, connections to existing piping, trenching, backfill and restoration.

B. The Work is located in Soldier Canyon as indicated on the Drawings.

1.3 CONTRACT METHOD

A. The Work hereunder will be constructed under a single lump-sum contract.

1.4 STREAMLINED SPECIFICATIONS

A. These specifications are written in streamlined or declarative style, often using incomplete sentences. This imperative language is directed to Contractor unless specifically noted otherwise.

B. Omissions of such words and phrases as “Contractor shall,” “in conformity therewith,” “shall be,” “as shown on the Drawings,” “a,” “an,” “the,” and “all” are intentional in streamlined sections.

1. Omitted words shall be supplied by inference in the same manner as when a note appears on the Drawings.

2. Omission of such words shall not relieve Contractor from providing the items and work described herein or indicated on the Drawings.

3. Words “shall be” are included by inference where a colon (:) is used within sentences or phrases.

1.5 WORK BY OTHERS

A. Owner reserves the right to perform or award other work concurrent with the Work included in this Contract

SOLDIER CANYON WATER LINE PROJECT PAGE 01 11 00 - 2

1. Work may be conducted at or adjacent to the Site by other contractors during the performance of the Work under this Contract. Conduct operations to cause a minimum of interference with the Work of such other contractors and cooperate fully with such contractors to provide continued safe access to their respective portions of the Site, as required to perform Work under their respective contracts.

B. Interference With Work On Utilities:

1. Cooperate and coordinate fully with all utility forces of Owner or forces of other public or private agencies engaged in the relocation, altering, or otherwise rearranging of any facilities which interfere with the progress of the Work.

2. Schedule the Work to minimize interference with said relocation, altering, or other rearranging of facilities.

1.6 WORK SEQUENCE AND SCHEDULING CONSTRAINTS

A. Schedule and perform the Work in such a manner as to result in the least possible disruption to the public's use of roadways, driveways, and utilities. Utilities shall include but not be limited to water, sewerage, drainage structures, ditches and canals, gas, electric, cable television, and telephone. Refer to Utility Adjustment and other plan and profile sheets for approximate location of utilities. However, there is no guarantee as to accuracy or completeness. Contractor shall incorporate as-built locations on the reproducible record plans, in red ink, showing proper location on each sheet where these utilities are located.

B. Access to the site is limited to the hours of 7 am to 7 pm.

1.7 CONTRACTOR USE OF PROJECT SITE

A. Use of the Project Site shall be limited to construction operations, including on-Site storage of materials, on-Site fabrication facilities, and field offices.

1.8 OWNER USE OF THE PROJECT SITE

A. Owner may utilize portion of the site. Cooperate and coordinate with Owner to facilitate Owner's operations and projects and to minimize interference with Contractor's operations at the same time. In any event, Owner shall be allowed safe access to the Project Site during the period of construction.

1.9 PARTIAL UTILIZATION OF THE WORK BY OWNER

A. None.

1.10 CONTRACTOR’S WORKING HOURS

A. Perform work within Owner’s regular working hours from 7 am to 7 pm. If Contractor desires to work overtime or work on a Saturday, Sunday, or any legal holiday, obtain prior approval from Owner and Engineer.

B. If overtime work is approved by Owner and Engineer, pay to Owner, overtime fees as follows:

1. $ ##.00 an hour for Inspector

2. $ ##.00 a day for truck

SOLDIER CANYON WATER LINE PROJECT PAGE 01 11 00 - 3

3. Fees shall be paid on the Thursday prior to Saturday, Sunday or legal holiday requested. Minimum 4-hours/Maximum 10-hours.

1.11 STORAGE

A. Storage conditions shall be acceptable to Owner for all materials and equipment not incorporated into the Work but included in Applications for Payment. Such storage arrangements and conditions shall be presented in writing for Owner’s review and approval and shall afford adequate and satisfactory security and protection. Off-site storage facilities shall be accessible to Engineer. The stored materials shall be insured for full value.

Certificates of liability insurance coverage must be submitted to Engineer with the request for payment by Contractor. All arrangements and costs for storage facilities shall be paid by Contractor, unless specifically designated in the Contract Documents to be furnished by Owner.

1.12 NOTICES TO OWNERS OF ADJACENT PROPERTIES AND UTILITIES

A. Notify Owners of adjacent property and utilities when prosecution of the Work may affect them.

B. When it is necessary to temporarily deny access by owners or tenants to their property, or when any utility service connection must be interrupted, Give notices sufficiently in advance to enable the affected person(s) to provide for their needs. Notices shall conform to any applicable local ordinance and, whether delivered orally or in writing, shall include appropriate information concerning the interruption and instructions on how to limit any resulting inconvenience.

C. Utilities and other concerned agencies shall be contacted at least seven days prior to cutting or closing streets or other traffic areas or excavating near underground utilities or pole lines.

D. Review with the various utility companies the construction methods, safety procedures, and Work to be done in the vicinity of utilities. When temporary relocation of utilities is necessary, provide sufficient advance notice to the utility involved.

1.13 LINES AND GRADES

A. Perform all Work to the lines, grades, and elevations shown on the Drawings.

B. Basic horizontal and vertical control points will be established or designated as provided in General Conditions paragraphs. Use these points as datum for the Work. Perform any additional survey, layout, or measurement work needed for proper construction of the Work as a part of the Work at no additional cost to Owner.

C. Employ experienced instrument personnel, competent assistants, and such instruments, tools, stakes, and other materials required to complete the survey, layout, and measurement work. In addition, furnish, without additional charge, competent personnel and such tools, stakes, and other materials as Engineer may require in establishing or designating control points or in checking survey, layout, and measurement of Work performed.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 11 00 - 4

D. Keep Engineer informed, a reasonable time in advance, of the times and places at which Work is to be done, so that horizontal and vertical control points may be established, and any checking deemed necessary by Engineer may be done with minimum delay to the Project.

E. Remove and reconstruct Work, which is improperly located.

1.14 PROJECT MEETINGS

A. Preconstruction Conference

1. Prior to the commencement of Work at the Site, a preconstruction conference will be held at a mutually agreed time and place which shall be attended by Contractor's Project Manager, its Superintendent, its Safety Representative, and its Subcontractors as Contractor deems appropriate. Other attendees will be:

a. Engineer

b. Representatives of Owner

c. Governmental representatives as appropriate

d. Others as requested by Contractor, Owner, or Engineer

e. Engineer’s Representative

2. Bring to the conference, any submittals so indicated in Section 01 33 20 - Contractor Submittals.

3. The purpose of the conference is to designate responsible personnel, discuss contract requirements and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The complete agenda will be furnished by Engineer prior to the meeting date. However, be prepared to discuss all the items listed below.

a. Contractor's assignments for safety and first aid, including Designated

Competent person(s) and Contractor's safety Representative.

b. Status of Contractor's insurance and bonds.

c. Contractor's tentative schedules.

d. Transmittal, review, and distribution of Contractor's submittals.

e. Processing applications for payment.

f. Maintaining record documents.

g. Critical Work sequencing.

h. Field decisions and Change Orders.

i. Use of project site, office and storage areas, security, housekeeping, and

Owner's needs.

j. Major equipment deliveries and priorities.

k. Permits required for construction.

l. Utilities required for construction.

m. Contract Owner and channels of communication.

n. Coordination with others.

4. Engineer will preside at the preconstruction conference and will arrange for keeping and distributing the minutes to all persons in attendance.

B. Progress Meetings

1. Engineer will schedule and hold regular on-Site progress meetings at least weekly and at other times as deemed necessary by Engineer or as required by progress of the Work. Contractor, Engineer, and all Subcontractors active on the Site must attend each meeting. Contractor may at its discretion request attendance by representatives of its Suppliers, manufacturers, and other Subcontractors.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 11 00 - 5

2. Engineer will preside at the meetings and will arrange for keeping and distributing the minutes. The purpose of the meetings will be to review the progress of the Work, discuss safety, maintain coordination of efforts, discuss commercial issues, discuss changes in scheduling, and resolve other problems, which may develop. During each meeting, all parties are required to present any issues, which may impact its Work, with a view toward resolving these issues expeditiously.

1.15 AVAILABLE SUPPLEMENTAL REPORTS

A. None

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

SOLDIER CANYON WATER LINE PROJECT PAGE 01 11 00 - 6

THIS PAGE INTENTIONALLY BLANK

STOCKTON MEASUREMENT AND PAYMENT

SOLDIER CANYON WATER LINE PROJECT PAGE 01 20 00 - 1

SECTION 01 20 00

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 MEASUREMENT AND PAYMENT

A. Allowance Bid Items

1. Except for the Allowance Bid Item for Builder's Risk, none of the amounts of the

Allowance Bid items contained in the Bid form may be increased without a Change Order to increase.

B. Lump Sum Bid Items

1. All Work Required by the Contract Documents

a. The sum allowed for Bid Item No. 1 as set forth in the Bid Form includes all Work for and in connection with construction of the Contract in its entirety, including but not limited to all costs associated with dust control mitigation measures, permit fees and other related costs to ensure compliance with the Board of Health Air Pollution Control Regulations.

b. Payment for Work under this Bid item will be based on the breakdown of costs for each scheduled activity in the Construction Schedule and the percentage of completion for each activity in accordance with the Contract Documents.

c. Preparing the Construction Progress Schedule shall be a separate activity on the Construction Schedule and shall also be a separate activity on the Schedule of Values. Payment for the Construction Progress Schedule is not in addition to, but is incidental to the other lump-sum items included in the Work.

d. Payment for preparing the CPM Construction Schedule in accordance with Section 01 32 21 - CPM Construction Schedule is made under Bid Item No. 1.

The bid item amount shall be equal to or less than two percent (2%) of the Bid Item. Preparing the CPM Construction Schedule shall also be a separate activity on the CPM Construction Schedule and be a separate item in the Schedule of Valves.

1) Contractor may submit application for the full amount of this Bid Item if the CPM Schedule is accepted by Engineer within 45 days after issuance of Notice to Proceed.

2) Because the CPM Construction Schedule has less value to Owner and Contractor as time passes, an amount of $ 0 per day will be deducted from the Contract Price for each day after 45 days following Notice to Proceed that the CPM Construction Schedule has not been accepted by Engineer.

3) Deductions for overdue schedule submittal will cease to accumulate when the earliest of either of the following items occurs.

a) Engineer accepts the CPM Construction Schedule.

b) The number of accumulated deductions equals two percent

(2%) of the applicable Bid Item.

c) The Work is accepted as Substantially Complete.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 20 00 - 2

4) Both Owner and Contractor agree that deductions for delayed submittal of an acceptable CPM Construction Schedule are not penalties but reflect the diminishing value of the delayed submittal.

e. Payment for mobilization, as defined in Section 01 71 00 – Mobilization, as part of the lump sum price named in the Bid Schedule shall equal six percent (6.0%) of the total lump sum price bid for the Work. The payment for mobilization is not in addition to, but is part of the lump sum price for the Work. Include a separate activity for mobilization in the Construction Schedule and in the Schedule of Values. This activity shall include all principal items and all submittals specified in Section 01 71 00 – Mobilization, as applicable. The remaining lump sum, except as otherwise required by this Agreement, shall be appropriately distributed among the remaining work activities that make up the total lump sum price. Payment for mobilization will be approved in accordance with the status of completion of each mobilization component as defined in the approved mobilization plan required in Section 01 71 00; except that no payment for mobilization will be approved until Items 1, 2, 8, 9, 10, and 11 of paragraph 3.1.A of Section 01 71 00 are complete. No more than one-half of the payment for mobilization will be paid until all submittals required by paragraph 3.2 of Section 01 71 00 have been approved by Engineer.

f. Payment for each update of the CPM Construction Schedule accepted by Engineer within the timeframes and as defined in Section 01 32 21– CPM Construction Schedule, as part of the lump sum price named in the Bid Schedule under Bid Item No. 1 shall be equal to $ 1,000. The payments for CPM Construction Schedule updates are not in addition to, but are part of the lump sum price of the Work and represents the direct and indirect value to Contractor and Owner from having an updated schedule. However, the payments for the CPM Schedule updates are separate from the payment for the CPM Construction Schedule described in paragraph 1.10.C of this Section.

Separate monthly submittals for CPM Construction Schedule Updates, each valued at $ 1,000, shall be included in the CPM Construction Schedule and in the Schedule of Values. The remaining lump sum price, except as otherwise required by this Contract, shall be appropriately distributed among the remaining work activities that make up the total lump sum price. Beginning with the first payment following the first update, Contractor may request the payment if Engineer has accepted the update. When a monthly update is not accepted by the time of submission of the succeeding Application for Payment, the [$5,000] for that monthly update will not be earned by Contractor and an amount equal to $ 1,000 shall be deducted from the Contract Price. Failure to update the CPM Construction Schedule properly within this period means no value was received and therefore no payment is due for that update. Any deducts from the Contract Price for not submitting an acceptable CPM Construction Schedule update shall not be considered a penalty but reflects the loss of value to Owner.

g. Payment for each approved Operations & Maintenance (O & M) Manual, as defined in Section 01 33 20 – Contractor Submittals, as part of the total lump sum price named in the Bid Schedule shall equal 10% of the value of the piece of equipment or group of like-kind pieces of equipment that it represents. The payment for each O & M Manual is not in addition to but is part of the lump sum price for the Work. A separate activity for each O & M Manual shall be

SOLDIER CANYON WATER LINE PROJECT PAGE 01 20 00 - 3

included in the Construction Schedule and in the Schedule of Values. The remaining lump sum price, except as otherwise required by this Contract, shall be appropriately distributed among the remaining work activities that make up the total lump sum price.

C. Unit Price Bid Items

1. BID ITEM No. 1 - MOBILIZATION/DEMOBILIZATION

a. No quantity measurement will be made for any of the work required to complete this item; payment will be based upon completion of the work in accordance with the Plans and Specifications.

b. Payment covers cost of mobilization, demobilization, installation of temporary facilities, and bringing all necessary construction equipment to the site. Payment will be made on a percentage basis as follows.

Percent of Original Contract Amount Earned

Percent of Amount Bid for Mobilization to be Paid

5 40 15 20 40 30 50 10

c. Payment Covers: photographing site conditions prior to construction;

obtaining any additional permits not already obtained by the OWNER and administrative items. This pay item shall constitute full compensation for all labor, equipment, tools, supplies and materials required to complete this portion of the Work for this construction project.

d. Payment for mobilization is based on a lump sum basis and shall not exceed six percent (6.0%) of the total base bid price. A separate activity for mobilization items shall be included in the Schedule of Values. This activity shall include all principal items and all submittals as applicable. Payment for mobilization will be approved in accordance with the status of completion of each mobilization component as defined in the approved mobilization plan.

2. BID ITEM Nos. 2 and 3 - 8" C900 DR-18 WATER LINE & 8" DUCTILE IRON CLASS 350

WATER LINE

a. Measured along the pipe with no reduction in length because of valves and fittings.

b. Payment covers the cost of the size and type of pipe indicated, with installation per the plans, reconnection to existing pipes, import bedding and native trench backfill where it meets the specifications per the Contract Documents, compaction of material and testing to the density required in the specifications, core drilling, link-seal, concrete thrustblocks, grout, screens, etc.

c. Payment covers the cost of incidental work such as potholing, valves, fittings, couplings, spools, sleeves, joint lubricants, nuts, bolts and washers; selective clearing and tree removal; removal and disposal of interfering structures and obstructions; concrete rings, cast iron rings, frame and lid as applicable;

grout; jackhammer work; pot hole excavations; trench shoring or trench boxes as applicable; underground plastic line markers; removal and disposal of waste materials; restoration of all utilities damaged as a result of

SOLDIER CANYON WATER LINE PROJECT PAGE 01 20 00 - 4

operations; site dewatering; pipe line cleaning; water main repair or replacement if damaged by CONTRACTOR; compaction density testing;

adjustments to grade of existing valve boxes or traffic lids or manholes; and similar work to complete the installation of the water line.

d. Payment covers the cost of furnishing and placing of import pipe zone, trench backfill, and base course material, hauling and disposal of trench excavation spoils. Import trench backfill material which is required. Native material may be used ONLY if it meets the requirements of the specifications.

e. Payment covers the Disinfection and testing of the lines and all other work associated with commissioning water lines.

3. BID ITEM No. 4 – 8" GATE VALVE

a. Measurement: per each.

b. Payment covers the cost of the installing a new resilient wedge gate valve, 2-piece cast iron screw type valve box, valve cover, gaskets, bolt, nuts, wax taping and poly-ply wrapping all exposed fittings, pressure testing and disinfection of valve; bedding and backfilling, compaction of material per specifications.

4. BID ITEM No. 5 - SURFACE RESTORATION

a. Measured as a lump sum bid item.

b. Payment covers the cost to purchase and install broadcast seeding along the water line alignment and all other areas damaged during construction.

Payment includes the cost to remove and stockpile the existing topsoil and re-installation of the topsoil at the end of the project prior to seed broadcast, broadcast and rake in all seeding prior to a storm to allow the seed to begin germination, etc. Seeding type shall be as required by Tooele County.

1.2 GENERAL PROGRESS PAYMENT REQUIREMENTS

A. A Payment for Work performed shall be in accordance with installed quantities as assessed in comparison to the Schedule of Values and the Construction Schedule. Engineer will verify measurements and quantities. Each activity necessary to manage and complete the Work is identified on the Contract schedules. Each activity will be assigned its respective value, a portion of the Contract Price, as shown on the Schedule of Values (Roll-up), and detailed cost loaded activity schedule.

B. Payment for all lump sum costs and services incurred on this Agreement shall be based on the earned value of Work accomplished during the reporting period. Earned value is determined by the completion percentage of each activity as determined by the Schedule of Values and the Construction Schedule applied to the total value of the activity. No construction activity shall be deemed 100 percent complete until Contractor has completed the physical check out and inspection of the completed Work and has submitted the signed inspection form to Engineer.

C. Earned value is derived from the current status of Contractor Construction Schedule as determined by the monthly schedule status submittals. Each schedule status submittal is reviewed and approved by Engineer prior to Contractor obtaining approval for the Summary of Earned Values or quantities installed and the Application for Payment.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 20 00 - 5

1.3 APPLICATION FOR PAYMENT

A. Submit application for payment on Owner’s form and be certified by signature of an Authorized Officer of Contractor.

B. The Application for Payment shall contain all necessary references and attachments that substantiate the invoice for progress payment (e.g., certified payrolls, labor reports, progress schedule data, and Summary of Earned Values). It shall substantiate the invoice for progress payment and shall be preceded or accompanied by the schedule and status data as a condition of payment, in accordance with the Construction Schedule and the Schedule of Values.

1.4 REVIEWS/APPLICATION FOR PAYMENT

A. Review meetings between Contractor and Engineer will be held weekly and within 7 Days prior to the payment application date designated by Engineer. Three Days prior to the last review meeting of the month, submit an updated schedule and a signed application for payment showing a Summary of Earned Values for the reporting and payment period so that Engineer can compare earned values to available status data. Make any adjustments to the Master Record Documents, updated schedule, and payment applications required by Engineer. Upon completion of the adjustments, Engineer will sign the payment request and forward it to Owner. Engineer will determine payment amounts if agreement with Contractor is not reached.

1.5 PAYMENT FOR SUPPLIES AND MATERIALS

A. Payment based on the actual cost of supplies, materials and equipment on hand shall be made by Owner with or without a paid invoice. "Actual cost" of materials shall be the invoice amount, whether paid or not, and shall not include any costs associated with installation, testing, etc. Contractor shall be entitled to payment of the actual cost of supplies, materials, and equipment only if it (1) presents an invoice to Owner with the application for payment and (2) states in the application for payment that the materials have been delivered and stored in the time and manner specified in the contract between Contractor and his Supplier or Subcontractor. If Contractor fails to comply with those conditions, Owner may withhold payment in accordance with the provisions. Owner expressly reserves the right to withhold retention until Contractor presents to Owner a paid invoice, or some other proof of payment satisfactory to Owner, for Owner’s use in verifying the accuracy of the actual cost of the supplies, materials or equipment. If the amount paid does not match the actual cost, Owner will adjust the amount of retention accordingly. Payment for supplies, materials or equipment on hand does not alter the responsibility of Contractor for all supplies, materials and equipment until Final Acceptance of the Work.

PART 2 - PRODUCTS (NOT USED)

STOCKTON PRODUCTS, MATERIALS, EQUIPMENT, AND SUBSTITUTIONS

SOLDIER CANYON WATER LINE PROJECT PAGE 01 25 10 - 1

SECTION 01 25 10

PRODUCTS, MATERIALS, EQUIPMENT, AND SUBSTITUTIONS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for delivery and storage of products and materials specified for use in the Project. It also includes requirements for handling requests for equals and substitutions made after award of the Contract.

B.

1.2 DEFINITIONS

A. Definitions in this Article are not intended to negate the meaning of other terms used in the Contract Documents, including "specialties," "systems," "structure," "finishes," "accessories," "furnishings," “special construction," and similar terms, which are self-explanatory and have recognized meanings in the construction industry.

B. The word "Products," as used herein, is defined to include purchased items for incorporation into the Work, regardless of whether specifically purchased for the Project or taken from stock of previously purchased products.

C. The word "Materials," is defined as products which must be substantially cut, shaped, worked, mixed, finished, refined, or otherwise fabricated, processed, installed, or applied to form units of work.

D. The word "Equipment" is defined as products with operational parts, regardless of whether motorized or manually operated, and particularly including products with service connections (wiring, piping, and other like items).

E. Neither "Products" nor "Materials" nor "Equipment" includes machinery and equipment used for preparation, fabrication, conveying and erection of the Work.

1.3 QUALITY ASSURANCE

A. Source Limitations: To the greatest extent possible for each unit of work, provide products, materials, and equipment of a singular generic kind from a single source.

B. Compatibility of Options: Where more than one choice is available as options for selection of a product, material, or equipment, select an option, which is compatible with other products, materials, or equipment. Compatibility is a basic general requirement of product, material, and equipment selections.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Delivery and Acceptance

SOLDIER CANYON WATER LINE PROJECT PAGE 01 25 10 - 2

1. Deliver and store products, materials, and equipment in accordance with manufacturer's written recommendations and by methods and means which will prevent damage, deterioration, and loss including theft.

2. Manage delivery schedules to minimize long-term storage of products at Site and overcrowding of construction spaces. Ensure coordination to minimize holding or storage times for flammable, hazardous, easily damaged, or sensitive materials to deterioration, theft, and other sources of loss.

B. Transportation and Handling

1. Transport products by methods to avoid damage. Deliver in undamaged condition in manufacturer's unopened containers and packaging.

2. Furnish equipment and personnel to handle products, materials, and equipment, including those provided by Owner, by methods to prevent soiling and damage.

3. Provide additional protection during handling to prevent marring and otherwise damaging products, packaging, and surrounding surfaces.

C. Storage and Protection

1. Products shall be stored in accordance with manufacturer's written instructions and with seals and labels intact and legible. Sensitive products shall be stored in weather-tight climate-controlled enclosures and temperature and humidity ranges shall be maintained within tolerances required by manufacturer's recommendations.

2. For exterior storage of fabricated products, products shall be placed on sloped supports above ground. Products subject to deterioration shall be covered with impervious sheet covering and ventilation shall be provided to avoid condensation.

3. Loose granular materials shall be stored on solid flat surfaces in a well-drained area and shall be prevented from mixing with foreign matter.

4. Storage shall be arranged to provide access for inspection. Periodically inspect to assure products are undamaged and are maintained under required conditions.

5. Storage shall be arranged in a manner to provide access for maintenance of stored items and for inspection.

D. Maintenance of Storage

1. Periodically inspect stored products on a scheduled basis. Maintain a log of inspections and make the log available on request.

2. Comply with manufacturer's product storage requirements and recommendations.

3. Maintain manufacturer-required environmental conditions continually.

4. Ensure that surfaces of products exposed to the elements are not adversely affected and that weathering of finishes does not occur.

5. For mechanical and electrical equipment, provide a copy of the manufacturer's service instructions with each item and the exterior of the package shall contain notice that instructions are included.

6. Service products on a regularly scheduled basis. Maintain a log of services and submit as a record document prior to acceptance by Owner in accordance with the Contract Documents.

1.5 PROPOSED SUBSTITUTIONS AND "OR EQUAL" ITEMS

A. Substitution and “or equal” determination shall be submitted and evaluated per the General Conditions included in the Contract Documents.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 25 10 - 3

B. When proposing a substitution, transmit all documents to Engineer in electronic format (single PDF), via web-based construction management software as specified in Section 01 32 00 – Electronic Project Management System.

C. Unless otherwise provided by law or authorized in writing by Engineer, submit the "Substitution Request Form(s)" within 35 days after award of the Contract.

D. Whenever products, materials, or equipment are indicated in the Contract Documents by using the name of a proprietary item or the name of a particular supplier, the naming of the manufacturer is intended to establish the type, function, and quality required. The Contract Price is understood to be based upon furnishing the item specified.

E. If a named item is not available or a supplier is no longer doing business, the following shall apply:

1. When a named supplier is no longer doing business under the name indicated, furnish the specified product from the legal successors to the named supplier.

2. When a named product is no longer available from the named supplier due to acquisition or sale of the given product line, but the product is available from another supplier, provide the named product. In such cases, submit a substitution request form and include certification from the supplier that the product being supplied is materially and functionally identical to the product named in the Contract Documents.

3. When the named product is no longer available from the named supplier or any other supplier, notify Owner in writing and Owner will direct Engineer to identify suitable substitute products. Provide one of the suitable substitute products.

F. The procedure for review by the Engineer will include the following:

1. Wherever a proposed substitution has not been submitted within said 35-day period, or wherever the submission of a proposed substitution material or equipment has been judged to be unacceptable by Engineer, provide the product, material, or equipment indicated in the Contract Documents.

2. Certify that the proposed substitution will adequately perform the functions and achieve the results called for by the general design and be similar and of equal substance to that indicated and be suited to the same use as that indicated.

3. Engineer will evaluate each proposed substitution within a reasonable period.

4. As applicable, do not make shop drawing submittals for a substitution without

Engineer's prior written acceptance of the request for substitution. Do not order, install, or utilize any substitution item prior to written acceptance of the request for substitution.

5. Engineer will record the time required by Engineer in evaluating substitutions and in making changes by Contractor in the Contract Documents occasioned thereby.

G. Application for substitution must contain the following statements and information, which will be considered by Engineer in evaluating the proposed substitution:

1. Submit “Substitution Request Form,” at end of this Section, fully executed.

2. The evaluation and acceptance of the proposed substitution shall not prejudice the achievement of substantial completion on time.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 25 10 - 4

3. Whether or not acceptance of the substitution for use in the Work will require a change in any of the Contract Documents to adapt the design to the proposed substitution.

4. Whether or not incorporation or use of the substitution in connection with the Work is subject to payment of any license fee or royalty.

5. All variations of the proposed substitution from the items originally specified shall be identified.

6. Available maintenance, repair, and replacement service shall be indicated. The manufacturer shall have a local service agency (within 50 miles of the site) which maintains properly trained personnel and adequate spare parts and is able to respond and complete repairs within 24 hours.

7. Itemized estimate of all costs that will result directly or indirectly from acceptance of such substitution, including cost of redesign and claims of other contractors affected by the resulting change.

H. Without any increase in cost to Owner, be responsible for, and pay all costs in connection with proposed substitutions and costs of inspections and testing of equipment or materials submitted for review prior to purchase thereof for incorporation in the Work, whether or not Engineer accepts the proposed product, equipment, or material. Reimburse Owner for the charges of Engineer and other authorized representatives for evaluating each proposed substitution.

PART 2 - PRODUCTS (NOT USED)

CE1006 PAGE 1

REV 10/00

SUBSTITUTION REQUEST FORM

To: Project:

Date:

Owner:

Specified Item:

Section Page Paragraph Description

The undersigned requests consideration of the following:

Proposed Substitution:

Attached data includes product description, specifications, drawings, photographs, performance and test data adequate for evaluation of the request. Applicable portions of the data are clearly identified.

The undersigned states that the following paragraphs, unless modified on attachments, are correct:

1. The proposed substitution does not affect dimensions shown on Drawings and will not require a change in any of the Contract Documents.

2. The undersigned will pay for changes to the design, including engineering design, detailing, and construction costs caused by the request substitution which is estimated to be $ .

3. The proposed substitution will have no adverse effect on other contractors, the construction schedule (specifically the date of substantial completion), or specified warranty requirements.

4. Maintenance and service parts will be locally available for the proposed substitution.

5. The incorporation or use of the substitute in connection with the work is not subject to payment of any license fee or royalty.

The undersigned further states that the function, appearance, and quality of the proposed substitution are equivalent or superior to the specified item.

Submitted by Contractor: Reviewed by Engineer:

Firm: ☐ Accepted as Submitted ☐ Accepted as Noted

By: ☐ Not Accepted ☐ Received too Late

Signature: By:

Telephone: Title:

Attachments: Date:

Comments: Comments:

STOCKTON REQUESTS FOR INTERPRETATION (RFI)

SOLDIER CANYON WATER LINE PROJECT PAGE 01 26 13 - 1

SECTION 01 26 13

REQUESTS FOR INTERPRETATION (RFI)

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes procedures for submitting Requests for Interpretation (RFI) and limitations on use of RFI to obtain interpretation and clarification.

1.2 RELATED SECTIONS

A. Section 01 25 10 – Products, Materials, Equipment, and Substitutions.

B. Section 01 32 00 – Electronic Project Management System.

C. Section 01 33 20 – Submittal Procedures.

1.3 DEFINITIONS

A. Request for Interpretation: A document submitted to Engineer by Contractor, requesting clarification of a portion of the Contract Documents, hereinafter referred to as an RFI.

1.4 CONTRACTOR’S REQUESTS FOR INTERPRETATION (RFI)

A. Contractor's Requests for Interpretation (RFI): Should Contractor be unable to determine from the Contract Documents, the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of Work is described differently at more than one place in the Contract Documents;

request that Engineer make an interpretation of the requirements of the Contract Documents to resolve such matters. Comply with procedures specified herein to make Requests for Interpretation (RFI).

B. Submission of RFI: Prepare RFI and submit electronically utilizing the Electronic Project Management System. Refer to Section 01 33 20 – Submittal Procedures.

1. Fill in transmittal form completely, and if supplemental drawings or other information is prepared by hand, it shall be fully legible and attached with the transmittal form.

2. The Project Management System will automatically assign each RFI a discrete, consecutive number. Include this number in the title of the RFI. For instance, Revision #1 to RFI 029 should be noted in the title as “original title name, Rev 1”.

3. Each page of the RFI and each attachment to the RFI shall bear Owner’s project name, project number, date, RFI number and a descriptive title. Merge all into a single PDF document for attachment in the system.

4. Clearly and concisely set forth the issue for which clarification or interpretation is sought and why a response is needed. In the RFI, indicate presumed interpretation or understanding of the requirement along with reasons for such understanding.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 26 13 - 2

Include proposed solutions that may be set forth to complete the Work with associated cost and schedule impact, if any.

5. Engineer will review all RFI to determine whether they are RFI within the meaning of the term. If Engineer determines that the transmittal is not an RFI, it will be returned, unreviewed as to content, for resubmittal in the proper manner.

6. Frivolous RFI or simply passing on the RFI without first vetting the RFI will be subject to reimbursement from Contractor to Owner for fees charged by Engineer and other design professionals engaged by Owner.

B. Submission of RFI: Prepare RFI and submit electronically utilizing the RFI form found at the end of this Section.

1. Fill in form completely, and if supplemental drawings or other information is prepared by hand, it shall be fully legible and attached with the RFI form in a single PDF document.

2. Assign each RFI a discrete, consecutive number. For revisions, attach a sequential decimal number to the original RFI number. For instance, Revision #1 to RFI 029 should be noted as RFI 029.1.

3. Each page of the RFI and each attachment to the RFI shall bear Owner’s project name, project number, date, RFI number and a descriptive title.

4. Clearly and concisely set forth the issue for which clarification or interpretation is sought and why a response is needed. In the RFI, indicate presumed interpretation or understanding of the requirement along with reasons for such understanding.

Include proposed solutions that may be set forth to complete the Work with associated cost and schedule impact, if any.

5. Engineer will review all RFI to determine whether they are RFI within the meaning of the term. If Engineer determines that the transmittal is not an RFI, it will be returned, unreviewed as to content, for resubmittal in the proper manner.

6. Frivolous RFI or simply passing on the RFI without first vetting the RFI will be subject to reimbursement from Contractor to Owner for fees charged by Engineer and other design professionals engaged by Owner.

C. Subcontractor-Initiated and Supplier-Initiated RFI: RFI from subcontractors and material suppliers shall be submitted through, be reviewed by, and be attached to an RFI prepared, signed, and submitted by Contractor. RFI submitted directly by subcontractors or material suppliers will be returned unanswered to Contractor.

1. Review all subcontractor- and supplier-initiated RFI and take actions to resolve issues of coordination, sequencing, and layout of the Work. Coordination of the work, sequence, and layout are not the responsibility of Owner or Engineer.

2. RFI submitted to request clarification of issues related to means, methods, techniques, and sequences of construction or for establishing trade jurisdictions and scopes of subcontracts will be returned without interpretation. Such issues are solely Contractor's responsibility.

D. Requested Interpretation: Carefully study the Contract Documents to ensure that information sufficient for interpretation of requirements of the Contract Documents is not included therein. RFI that request interpretation of requirements clearly indicated in the Contract Documents will be returned without interpretation.

1. In all cases in which RFI are issued to request clarification of issues related to means, methods, techniques and sequences of construction; for example, pipe and duct

SOLDIER CANYON WATER LINE PROJECT PAGE 01 26 13 - 3

routing, clearances, specific locations of Work shown diagrammatically, apparent interferences and similar items, furnish all information required for Engineer or Owner to analyze and/or understand the circumstances causing the RFI and prepare a clarification or direction as to how to proceed.

2. If information included with this type of RFI is insufficient, the RFI will be returned unanswered.

E. Unacceptable Uses for RFI: RFI shall not be used to request the following:

1. Approval of submittals (use procedure specified in Section 01 33 20 - Submittal

Procedures).

2. Approval of substitutions (refer to Section 01 25 10 – Products, Materials, Equipment and Substitutions).

3. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Contract General Conditions).

4. Different methods of performing Work than those indicated in the Contract Drawings and Specifications (comply with provisions of the Contract General Conditions).

F. Disputed Requirements: If Engineer’s response to an RFI is believed to cause a change to the requirements of the Contract Documents, immediately give written notice to Engineer stating why this is believed to be true. Failure to give such written notice immediately shall waive any right to seek additional time or compensation under the Contract.

PART 2 - PRODUCTS

SOLDIER CANYON WATER LINE PROJECT PAGE 01 26 13 - 4

PA 311 PAGE 1

REV 10/00

REQUEST FOR INTERPRETATION

RFI No:

Project No:

Project: Date:

Owner:

Engineer: Construction Mgr:

Contractor: Contractor PM:

Subject:

Drawing No: Specification Sect:

Contractor’s Request for Interpretation (RFI)

Contractor’s Signature: Date:

Engineer’s Response

Engineer’s Signature: Date:

STOCKTON SCHEDULE OF VALUES

SOLDIER CANYON WATER LINE PROJECT PAGE 01 29 73 - 1

SECTION 01 29 73

SCHEDULE OF VALUES

PART 1 - GENERAL

1.1 GENERAL

A. This Section defines the process whereby the Schedule of Values shall be developed and incorporated into the Construction Progress Schedule as specified in Section 01 32 16 – Construction Progress Schedule. Monthly progress payment amounts shall be determined from the weekly progress updates of the scheduled activities. The schedule of values shall, as a minimum, list the value of every activity on the schedule, and shall include such additional breakdowns as required herein. The values in the Schedule of Values do not establish a commitment by either Contractor or Owner when negotiating changes to the Contract Documents.

1.2 DETAILED SCHEDULE OF VALUES

A. Prepare and submit a detailed Schedule of Values to Engineer as part of the Construction Progress Schedule submittal. Because the ultimate requirement is to develop a detailed Schedule of Values sufficient to determine appropriate monthly progress payment amounts, sufficient detailed breakdown shall be provided to meet this requirement. The Schedule of Values shall have a one-to-one relationship to the work activities of the Construction Progress Schedule even though additional detailed breakdowns for the Schedule of Values may be required. Engineer will be the sole judge of acceptable breakdowns, details, and descriptions of the values established. If, in the opinion of Engineer, a greater number of Schedule of Values items than proposed is necessary, add the additional items so identified.

B. The minimum details of a breakdown of the major Work components are indicated below.

Provide greater detail when directed by Engineer.

1. Mobilization: Six percent of Contract Price..

2. Construction Progress Schedule shall be broken down by initial submittal and monthly updates.

3. Break down Civil site Work into roadways, individual drainage systems, individual flood control structures, site concrete, soil cement, paving, excavation cut and fill, clearing and grubbing and any other items determined to be necessary for the establishment of pay and activity items.

4. Break down concrete structures into excavation, subgrade preparation, and appurtenant pre-foundation Work, concrete foundation construction, slabs on grade, walls, columns, suspended slabs, etc. (provide sufficient breakdown to accommodate necessary schedule detail.

5. Break down mechanical Work within each structure to identify individual piping systems, equipment installation by equipment name and number, and equipment testing and checkout.

6. Break down electrical and Instrumentation Work within each structure to identify individual systems, equipment installation by equipment name and number, and equipment testing and checkout.

a. Break down fiber optic conduit Work into conduit installation and pullboxes.

SOLDIER CANYON WATER LINE PROJECT PAGE 01 29 73 - 2

b. Break down cathodic protection Work by ribbon anode and appurtenances, test station types, rectifiers, and insulating flanges.

7. Break down protective coating Work by system. Where specific coating Work may be critical to performing the Work to meet milestone and schedule dates, such Work shall be included as individual pay and activity items.

8. Break down utility relocation Work into individual pipelines running from and to termination points. Each pipeline shall be an individual pay item unless otherwise allowed by the Engineer.

9. Break down pipeline Work into individual items including pipe, specials, and other pipe materials, excavation, pipe installation, joint welding (including testing), joint protection, CLSM, pipe zone, backfill, surface restoration, and hydrostatic testing;

pipeline crossings; pipeline interconnections; and any other items determined necessary for the establishment and pay and schedule activities.

10. Break down in-field pipeline lining by stations between access manholes.

11. Provide breakdown for disinfection, testing, and commissioning of pipelines and reservoirs.

12. Operations and Maintenance (O & M) Manuals shall be broken down into one O & M

Manual per piece of equipment or one O & M Manual per group of like-kind pieces of equipment for establishment of pay and schedule activity items.

13. Break down all other Work not specifically included in the above items as necessary for establishment of pay and schedule activity items.

C. After submittal of the Schedule of Values, as part of the Construction Progress Schedule submittal, meet with Engineer and jointly review the schedules. Review the value allocations and extent of detail to determine any necessary adjustments to the values and to determine if sufficient detail has been proposed. Make adjustments deemed necessary to the value allocation or level of detail and submit a revised detailed Schedule of Values within 5 work days from receipt of comments from Engineer.

1.3 CHANGES TO SCHEDULE OF VALUES

A. Assign values, approved by Engineer, for changes to the Construction Schedule which add activities not included in the original Construction Schedule but are included in the original Work…