1-PART II - CONDITIONS OF THE CONTRACT.pdf

PDF 465 KB Posted

Attached to
Stockton Town- Soldier Canyon Water Line
Solicitation number
RA26-98
Issued by
Tooele County, Utah

About this file

This is a General Conditions and Supplementary Conditions document for a procurement contract between Stockton Town and a seller for the Soldier Canyon Water Line Project in Utah. The contract establishes the terms and conditions governing the furnishing of goods and special services required for the project. Bidding documents are submitted online through the Utah Public Procurement Place at https://utah.bonfirehub.com or in person at Stockton Town Hall, 18 North Johnson Street, Stockton, Utah 84071, with a submission deadline of Thursday, March 5, 2026 at 4:00 p.m. local time. All questions regarding the procurement bidding documents must be submitted online at the Bonfire Hub or emailed to eneil@bowencollins.com no later than March 2, 2026 at 5:00 p.m. The seller is responsible for delivering goods free on board (FOB) to the point of destination in accordance with the procurement contract times specified in the procurement agreement. The contract requires the seller to submit preliminary schedules, including a progress schedule and schedule of submittals, within 15 days after the effective date, and a preliminary conference will be held within 20 days after the contract times commence to establish working understanding among the parties.

The seller must furnish performance and payment bonds, each in an amount equal to or greater than the procurement contract price, in the forms specified (EJCDC P-610 and EJCDC P-615, 2019 editions), and maintain comprehensive liability and other insurance including workers' compensation, commercial general liability, automobile liability, and professional liability coverage as outlined in the supplementary conditions. The seller is responsible for all shipping, packaging, transportation, and delivery costs. The contract includes a one-year correction period following acceptance of goods and special services, with an additional one-year extension if corrections are made. Payment is made on a progress basis as stipulated in the procurement agreement, subject to engineer review and approval, with final payment contingent upon correction of all non-conformities and satisfactory completion of all special services. Seller's total liability to the buyer is limited to the procurement contract price, except for claims involving third-party indemnification, bodily injury or death, destruction of tangible property of others, intentional wrongful conduct, or rights conferred by bonds. Disputes not resolved through direct negotiation proceed to mediation under American Arbitration Association Construction Industry Mediation Rules, followed by binding arbitration under Construction Industry Arbitration Rules if mediation fails. The buyer is exempt from payment of sales and compensating use taxes under Utah state law on materials and equipment to be incorporated into the project facilities.

View the file

Other files

File Type Posted
2-PART IV - DRAWINGS.pdf PDF
3-PART III - TECHNICAL SPECIFICATIONS.pdf PDF
4-PART I - BIDDING DOCUMENTS (1).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BC&A

STOCKTON GENERAL CONDITIONS

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 1

SECTION 00 70 00

GENERAL CONDITIONS

Copyright © 2019 (EJCDC® P-700) National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TABLE OF CONTENTS

Page

ARTICLE 1 – DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

1.02 Terminology

ARTICLE 2 – PRELIMINARY MATTERS

2.01 Delivery of Bonds and Evidence of Insurance

2.02 Copies of Documents

2.03 Electronic Transmittals

2.04 Preliminary Schedules

2.05 Preliminary Conference

2.06 Safety

ARTICLE 3 – PROCUREMENT CONTRACT DOCUMENTS

3.01 Intent

3.02 Reference Standards

3.03 Reporting and Resolving Discrepancies

3.04 Requirements of the Procurement Drawings and Procurement Specifications

3.05 Reuse of Documents

ARTICLE 4 – COMMENCEMENT AND SCHEDULE

4.01 Commencement of Procurement Contract Times

4.02 Continuing Performance

4.03 Adjustments to Progress Schedule

4.04 Delays

ARTICLE 5 – BONDS AND INSURANCE

5.01 Performance, Payment, and Other Bonds

5.02 Insurance

5.03 Surety or Insurance Companies

ARTICLE 6 – LICENSES AND FEES

6.01 Intellectual Property and License Fees

6.02 Seller’s Infringement

6.03 Buyer’s Infringement

ARTICLE 7 – SELLER’S RESPONSIBILITIES

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 2

7.01 Performance of Obligations

7.02 Labor, Materials and Equipment

7.03 Laws and Regulations

7.04 “Or Equals”

7.05 Taxes

7.06 Submittals

7.07 Indemnification

7.08 Concerning Subcontractors and Suppliers

ARTICLE 8 – SHIPPING AND DELIVERY

8.01 Shipping

8.02 Delivery

8.03 Risk of Loss

ARTICLE 9 – BUYER’S RIGHTS

9.01 Seller’s Warranties and Guarantees

9.02 Inspections and Testing

9.03 Non-Conforming Goods and Special Services

9.04 Correction Period

ARTICLE 10 – ENGINEER’S STATUS

10.01 Engineer’s Role Defined

10.02 Duties and Responsibilities; Authority; Limitations

ARTICLE 11 – CHANGES

11.01 Amending and Supplementing the Procurement Contract

11.02 Change Orders

11.03 Change Directives

11.04 Field Orders

11.05 Buyer-Authorized Changes in the Goods and Special Services

11.06 Buyer’s Contingency Allowance

11.07 Unauthorized Changes in the Goods and Special Services

11.08 Change of Procurement Contract Price

11.09 Change of Procurement Contract Times

11.10 Notification to Surety

ARTICLE 12 – CLAIMS, DISPUTES, AND DISPUTE RESOLUTION

12.01 Claims

12.02 Dispute Resolution Method

ARTICLE 13 – PAYMENT

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 3

13.01 Applications for Progress Payments

13.02 Review of Applications for Progress Payments

13.03 Basis and Amount of Progress Payments

13.04 Suspension of or Reduction in Payment

13.05 Final Payment

13.06 Waiver of Claims

ARTICLE 14 – CANCELLATION, SUSPENSION, AND TERMINATION

14.01 Cancellation

14.02 Suspension of Performance by Buyer

14.03 Suspension of Performance by Seller

14.04 Breach and Termination

ARTICLE 15 – MISCELLANEOUS

15.01 Giving Notice

15.02 Controlling Law

15.03 Computation of Time

15.04 Cumulative Remedies

15.05 Survival of Obligations

15.06 Entire Agreement

15.07 No Waiver

15.08 Headings

15.09 Successors and Assigns

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 4

ARTICLE 1 – DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

A. Whenever used in the Procurement Bidding Requirements or Procurement Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated, which are applicable to the singular or plural thereof. In addition to terms specifically defined, terms with initial capital letters in the Procurement Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms.

1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Procurement Contract Documents.

2. Application for Payment—The document prepared by Seller, in a form acceptable to Buyer, to request progress or final payments, and which is to be accompanied by such supporting documentation as is required by the Procurement Contract Documents.

3. Bid—An offer or proposal of a prospective Seller submitted on the prescribed form setting forth the prices for the Goods and Special Services to be provided.

4. Bidder—An individual or entity that, as a prospective Seller, submits a Bid to Buyer.

5. Buyer—The individual or entity purchasing the Goods and Special Services.

6. Change Directive—A written directive from Buyer to Seller issued on or after the Effective Date of the Procurement Contract, ordering an addition, deletion, or revision in the Goods and Special Services.

7. Change Order—A document which is signed by Seller and Buyer and authorizes an addition, deletion, or revision to the Procurement Contract Documents or an adjustment in the Procurement Contract Price or the Procurement Contract Times, issued on or after the Effective Date of the Procurement Contract. Change Orders may be the result of mutual agreement by Buyer and Seller, or of resolution of a Claim.

8. Claim—A demand or assertion by Buyer or Seller seeking an adjustment of Procurement Contract Price or Procurement Contract Times, or both, or other relief with respect to the terms of the Procurement Contract. A demand for money or services by a third party is not a Claim.

9. Contractor/Assignee—A construction contractor with which Project Owner enters into a construction contract, and to which Project Owner, as initial Buyer, assigns this Procurement Contract.

10. Effective Date of the Procurement Contract—The date indicated in the Procurement Agreement on which the Procurement Contract becomes effective.

11. Electronic Document—Any Project-related correspondence, attachments to correspondence, data, documents, drawings, information, or graphics, including but not limited to Shop Drawings and other Submittals, that are in an electronic or digital format.

12. Electronic Means—Electronic mail (e-mail), upload/download from a secure Project website, or other communications methods that allow: the transmission or communication of Electronic Documents; the documentation of transmissions, SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 5 including sending and receipt; printing of the transmitted Electronic Document by the recipient; the storage and archiving of the Electronic Document by sender and recipient; and the use by recipient of the Electronic Document for purposes permitted by this Procurement Contract. Electronic Means does not include the use of text messaging, or of Facebook, Twitter, Instagram, or similar social media services for transmission of Electronic Documents.

13. Engineer—The individual or entity designated as such in the Procurement Agreement.

14. Field Order—A written order issued by Engineer which requires minor changes in the Goods or Special Services, but which does not involve a change in the Procurement Contract Price or Procurement Contract Times.

15. Goods—The tangible and movable personal property that is described in the Procurement Contract Documents, regardless of whether the property is to be later attached to realty.

16. Goods and Special Services—The full scope of materials, equipment, other items, and services to be furnished by Seller, including Goods, as defined herein, and Special Services, if any, as defined herein. This term refers to both the Goods and the Special Services, or to either the Goods or the Special Services, and to any portion of the Goods or the Special Services, as the context requires.

17. Laws and Regulations; Laws or Regulations—Any and all applicable laws, statutes, rules, regulations, ordinances, codes, and binding decrees, resolutions, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.

18. Milestone—A principal event specified in the Procurement Contract that Seller must attain by the date or within the number of days indicated, including but not limited to the delivery of the Goods and the furnishing of Special Services.

19. Notice of Award—The written notice, by Buyer to a Bidder, of Buyer’s acceptance of the Bid.

20. Point of Destination—The specific address of the location where delivery of the Goods will be made, as stated in the Procurement Agreement.

21. Procurement Agreement—The written instrument, executed by Buyer and Seller, that sets forth the Procurement Contract Price and Procurement Contract Times, identifies the parties and the Engineer, and designates the specific items that are Procurement Contract Documents.

22. Procurement Bidding Documents—The Procurement Bidding Requirements and the proposed Procurement Contract Documents (including all Addenda).

23. Procurement Bidding Requirements—The advertisement or invitation to bid, Instructions to Bidders, Bid security of acceptable form, if any, and Bid Form with any supplements.

24. Procurement Contract—The entire and integrated written agreement between Buyer and Seller concerning the Goods and Special Services.

25. Procurement Contract Documents—Those items so designated in the Procurement Agreement, and which together comprise the Procurement Contract. Shop Drawings and other Seller submittals are not Procurement Contract Documents, even if accepted, reviewed, or approved by Engineer or Buyer.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 6

26. Procurement Contract Price—The money that Buyer has agreed to pay Seller for furnishing the Goods and Special Services in accordance with the Procurement Contract Documents.

27. Procurement Contract Times—The times stated in the Procurement Agreement by which the Goods must be delivered, Special Services must be furnished, and other Milestones must be attained.

28. Procurement Drawings—That part of the Procurement Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Goods and Special Services to be furnished by Seller. Shop Drawings and other Seller submittals are not Procurement Drawings as so defined.

29. Procurement Specifications—That part of the Procurement Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the furnishing of the Goods and Special Services, and certain administrative requirements and procedural matters applicable thereto.

30. Project—The total undertaking to be accomplished for Project Owner by engineers, contractors, and others, including planning, study, design, construction, testing, commissioning, and start-up, and of which the Goods and Special Services are a part.

31. Project Owner—The entity that has retained (or will retain) engineers, contractors, and others for the planning, study, design, construction, testing, commissioning, and start-up of facilities and improvements. As of the Effective Date of the Procurement Contract, the Project Owner is the Buyer.

32. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Goods and Special Services and which establish the standards by which such portion of the Goods and Special Services will be judged.

33. Schedule of Submittals—A schedule, prepared and maintained by Seller, of required Submittals and the time requirements for Engineer’s review of the Submittals.

34. Seller—The individual or entity furnishing the Goods and Special Services.

35. Shop Drawings—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Seller and submitted by Seller to illustrate some portion of the Goods and Special Services.

Shop Drawings, whether approved or not, are not Procurement Drawings and are not Procurement Contract Documents.

36. Special Services—Services to be performed by Seller (or its agents or subcontractors) in association with the Goods to be furnished by Seller, as required by the Procurement Contract Documents.

37. Submittal—A written or graphic document, prepared by or for Seller, which the Procurement Contract Documents require Seller to submit to Engineer, or that is indicated as a Submittal in the Schedule of Submittals accepted by Engineer.

Submittals may include Shop Drawings and Samples; schedules; product data;

sustainable design information; information on special procedures; testing plans;

results of tests and evaluations, source quality-control testing and inspections, and field or site quality-control testing and inspections; warranties and certifications;

suppliers’ instructions and reports; records of delivery of spare parts and tools;

operations and maintenance data; record documents; and other such documents

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 7

required by the Procurement Contract Documents. Submittals, whether or not approved or accepted by Engineer, are not Procurement Contract Documents.

Change proposals, Change Orders, Claims, notices, Applications for Payment, and requests for interpretation or clarification are not Submittals.

38. Successful Bidder—The Bidder whose Bid the Buyer accepts, and to which Buyer makes an award of the Procurement Contract.

39. Supplementary Conditions—The part of the Procurement Contract that amends or supplements these General Conditions.

40. Unit Price Goods and Special Services—Goods and Special Services to be paid for on the basis of unit prices (if any).

1.02 Terminology

A. The words and terms discussed in Paragraphs 1.02.B and 1.02.C are not defined, but have the indicated meanings when used in the Bidding Requirements or Procurement Contract Documents.

B. Intent of Certain Terms or Adjectives

1. The Procurement Contract Documents include the terms “as allowed,” “as approved,” “as ordered,” “as directed” or terms of like effect or import to authorize an exercise of professional judgment by Engineer. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Engineer as to the Goods and Special Services. It is intended that such exercise of professional judgment, action, or determination will be commercially reasonable and will be solely to evaluate, in general, the Goods and Special Services for compliance with the requirements of and information in the Procurement Contract Documents and conformance with the design concept of the completed Project as a functioning whole, as shown or indicated in the Procurement Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective will not be effective to assign to Engineer any duty or authority to supervise or direct the furnishing of Goods or Special Services or any duty or authority to undertake responsibility contrary to any other provision of the Procurement Contract Documents.

2. The word “non-conforming” when modifying the words “Goods and Special Services,” “Goods,” or “Special Services,” refers to Goods and Special Services that are unsatisfactory, faulty, or deficient in that they:

a. do not conform to or comply with the requirements of the Procurement Contract Documents;

b. do not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Procurement Contract Documents; or

c. in the case of Special Services, have not been completed.

3. The word “receipt” when referring to the Goods, means the physical taking and possession by the Buyer under the conditions specified in Paragraph 9.02.B.2.

4. The word “day” means a calendar day of 24 hours measured from midnight to the next midnight.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 8

5. The word "furnish," when used in connection with the Goods and Special Services means to supply and deliver said Goods to the Point of Destination (or some other specified location) and to perform said Special Services fully, all in accordance with the Procurement Contract Documents.

C. Procurement Contract Price or Procurement Contract Times: References to a change in “Procurement Contract Price or Procurement Contract Times” or “Procurement Contract Times or Procurement Contract Price” or similar, indicate that such change applies to

(1) Procurement Contract Price, (2) Procurement Contract Times, or (3) both Procurement Contract Price and Procurement Contract Times, as warranted, even if the term “or both” is not expressed.

D. Unless stated otherwise in the Procurement Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Procurement Contract Documents in accordance with such recognized meaning.

ARTICLE 2 – PRELIMINARY MATTERS

2.01 Delivery of Bonds and Evidence of Insurance

A. When Seller delivers the executed counterparts of the Procurement Agreement to Buyer, the Seller also shall deliver to Buyer the performance bond and payment bond (if the Procurement Contract requires Seller to furnish such bonds).

B. Evidence of Seller’s Insurance: When Seller delivers the signed counterparts of the Procurement Agreement to Buyer, the Seller also shall deliver to Buyer, with copies to each additional insured (as identified in the Procurement Contract), the certificates, endorsements, and other evidence of insurance required to be provided by Seller in accordance with Article 5. Evidence of insurance to be obtained at a later date, such as insurance relating to transit or storage of the Goods, will be provided to Buyer at the time of such insurance is obtained.

C. Evidence of Buyer’s Insurance: After receipt of the signed counterparts of the Procurement Agreement and all required bonds and insurance documentation, Buyer shall promptly deliver to Seller, with copies to each additional insured (as identified in the Procurement Contract), certificates and other evidence of insurance (if any) required to be provided by Buyer.

2.02 Copies of Documents

A. Buyer shall furnish to Seller four printed copies of the Procurement Contract (including one fully executed counterpart of the Procurement Agreement), and one copy in electronic portable document format (PDF). Additional printed copies will be furnished upon request at the cost of reproduction.

2.03 Electronic Transmittals

A. Except as otherwise stated elsewhere in the Procurement Contract, the Buyer, Seller, and Engineer may send, and shall accept, Electronic Documents transmitted by Electronic Means.

B. If the Procurement Contract does not establish protocols for Electronic Means, then Buyer, Seller, and Engineer shall jointly develop such protocols.

C. Subject to any governing protocols for Electronic Means, when transmitting Electronic Documents by Electronic Means, the transmitting party makes no representations as to long-term compatibility, usability, or readability of the Electronic Documents resulting

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 9

from the recipient’s use of software application packages, operating systems, or computer hardware differing from those used in the drafting or transmittal of the Electronic Documents.

2.04 Preliminary Schedules

A. Within 15 days after the Effective Date of the Procurement Contract, Seller shall submit to Buyer and Engineer for timely review:

1. a progress schedule of activities, consistent with the Procurement Contract Times, including at a minimum, Shop Drawing and Sample submittals, tests, and deliveries as required by the Procurement Contract Documents.

a. The progress schedule will be acceptable to Buyer and Engineer if it provides an orderly progression of the Submittals, tests, and deliveries to completion within the specified Milestones of the Procurement Contract Times.

b. Such acceptance will not impose on Buyer or Engineer responsibility for the progress schedule, for sequencing, scheduling, or progress of Seller’s performance of its obligations under the Procurement Contract, nor interfere with or relieve Seller from Seller’s full responsibility therefor.

c. Such acceptance will not be deemed as an acknowledgment of the reasonableness and attainability of the schedule.

2. a preliminary schedule of Submittals.

B. No progress payment will be made to Seller until an acceptable progress schedule and acceptable schedule of Submittals are submitted to Buyer and Engineer (and other conditions applicable to progress payments are met).

2.05 Preliminary Conference

A. Within 20 days after the Procurement Contract Times start to run, a conference attended by Seller, Buyer, Engineer and others as appropriate will be held to establish a working understanding among the parties as to the Goods and Special Services and to discuss the schedules referred to in Paragraph 2.04.A, procedures for handling Shop Drawings and other Submittals, processing Applications for Payment, and maintaining required records.

2.06 Safety

A. Buyer and Seller shall comply with all applicable Laws and Regulations relating to the safety of persons or property, and to the protection of persons or property from damage, injury, or loss.

B. When Seller's personnel, or the personnel of any subcontractor to Seller, are present at the Point of Destination or any work area or site controlled by Buyer, the Seller shall be responsible for the compliance by such personnel with any applicable requirements of Buyer's safety programs that are made known to Seller.

C. If Buyer or its representatives visit the Seller’s manufacturing or storage facilities, for testing, inspection, or other purposes, Seller shall inform Buyer in advance of any safety preparations, standards, or programs with which Buyer and its representatives must comply.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 10

ARTICLE 3 – PROCUREMENT CONTRACT DOCUMENTS

3.01 Intent

A. The Procurement Contract Documents are complementary; what is called for by one is as binding as if called for by all.

B. Any labor, documentation, services, materials, or equipment that may reasonably be inferred from the Procurement Contract Documents or from prevailing custom or trade usage as being required to produce or furnish the indicated Goods and Special Services will be provided, whether or not specifically called for, at no additional cost to Buyer.

C. Unless otherwise stated in the Procurement Contract Documents, if there is a discrepancy between the electronic or digital versions of the Procurement Contract Documents (including any printed copies derived from such electronic or digital versions) and the printed record version, the printed record version will govern.

D. The Procurement Contract supersedes prior negotiations, representations, and agreements, whether written or oral.

E. Engineer will issue clarifications and interpretations of the Procurement Contract Documents, as provided in Paragraph 3.04.

F. Any provision or part of the Procurement Contract Documents held to be void or unenforceable under any Law or Regulation will be deemed stricken, and all remaining provisions will continue to be valid and binding upon Buyer and Seller.

3.02 Reference Standards

A. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws and Regulations, whether such reference be specific or by implication, means the standard, specification, manual, code, or Laws and Regulations in effect at the time of opening of Bids (or on the Effective Date of the Procurement Agreement if there were no Bids), except as may be otherwise specifically stated in the Procurement Contract Documents.

B. No provision of any such standard specification, manual, reference standard, or code, and no instruction of a supplier, will be effective to change the duties or responsibilities of Buyer, Seller, or Engineer from those set forth in the part of the Procurement Contract Documents prepared by or for Engineer. No such provision or instruction will be effective to assign to Buyer or Engineer any duty or authority to supervise or direct the performance of Seller’s obligations, or any duty or authority to undertake responsibility inconsistent with the provisions of the part of the Procurement Contract Documents prepared by or for Engineer.

3.03 Reporting and Resolving Discrepancies

A. Reporting Discrepancies

1. Seller’s Review of Procurement Contract Documents: If, before or during the performance of Seller’s obligations, Seller discovers any conflict, error, ambiguity, or discrepancy within the Procurement Contract Documents, or between the Procurement Contract Documents and (a) any applicable Law or Regulation,

(b) actual field conditions, (c) any standard specification, manual, reference standard, or code, or (d) any instruction of any supplier to Seller, then Seller shall promptly report it to Engineer (or if the Procurement Contract is assigned, then directly to Contractor/Assignee) in writing. Seller shall not proceed with the Goods

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 11

and Special Services affected thereby until the conflict, error, ambiguity, or discrepancy is resolved, by a clarification or interpretation by Engineer (or if the Procurement Contract is assigned, then by Contractor/Assignee) or by an amendment or supplement to the Procurement Contract Documents issued pursuant to Article 11.

2. Seller shall not be liable to Buyer or Engineer for failure to report any conflict, error, ambiguity, or discrepancy in the Procurement Contract Documents unless Seller had actual knowledge thereof.

B. Resolving Discrepancies: Except as may be otherwise specifically stated in the Procurement Contract Documents, the provisions of the Procurement Contract Documents will take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Procurement Contract Documents and:

1. the provisions of any standard, specification, manual, code, or instruction (whether or not specifically incorporated by reference in the Procurement Contract Documents); or

2. the provisions of any Laws or Regulations applicable to the furnishing of the Goods and Special Services (unless such an interpretation of the provisions of the Procurement Contract Documents would result in violation of such Law or Regulation).

3.04 Requirements of the Procurement Drawings and Procurement Specifications

A. During the performance of Seller’s obligations and until final payment, Seller and Buyer shall submit to the Engineer all matters in question concerning the requirements of the Procurement Drawings and Procurement Specifications (sometimes referred to as requests for information or interpretation—RFIs) or relating to the acceptability of the Goods and Special Services, as soon as possible after such matters arise. Engineer will be the initial interpreter of the requirements of the Procurement Drawings and Procurement Specifications, and judge of the acceptability of the Goods and Special Services thereunder.

1. After assignment (if any) Seller shall submit such matters directly to Contractor/Assignee for response or administration, and the Procurement Contract provisions in Paragraphs 3.04.B and C will not apply.

B. Engineer will issue with reasonable promptness a written clarification, interpretation, or decision on the issue submitted, and if necessary, initiate an amendment or supplement to the Procurement Drawings or Procurement Specifications. Engineer’s written clarification, interpretation, or decision will be consistent with the overall intent of the Procurement Contract Documents and will be final and binding on Seller and Buyer. If either Buyer or Seller believes that a written clarification or interpretation justifies an adjustment in the Procurement Contract Price or Procurement Contract Times, either may make a Claim for such adjustment as provided in Article 12.

C. If a submitted matter in question concerns terms and conditions of the Procurement Contract Documents that do not involve (1) the performance or acceptability of the Goods and Services, (2) the design (as set forth in the Procurement Drawings, Procurement Specifications, or otherwise), or (3) other engineering or technical matters, then Engineer will promptly give written notice to Buyer and Seller that Engineer is unable to provide a decision or interpretation.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 12

3.05 Reuse of Documents

A. Seller and its subcontractors and suppliers shall not:

1. have or acquire any title to or ownership rights in any of the Procurement Drawings, Procurement Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer or its consultants, including electronic media editions, or reuse any such Procurement Drawings, Procurement Specifications, other documents, or copies thereof, on extensions of the Project or any other project, without written consent of Buyer and Engineer and specific written verification or adaptation by Engineer; or

2. have or acquire any title or ownership rights in any other Procurement Contract Documents, reuse any such Procurement Contract Documents for any purpose without Buyer’s express written consent, or violate any copyrights pertaining to such Procurement Contract Documents.

B. The prohibitions of this Paragraph 3.05 will survive final payment, or termination of the Procurement Contract. Nothing herein precludes Seller from retaining copies of the Procurement Contract Documents for record purposes.

ARTICLE 4 – COMMENCEMENT AND SCHEDULE

4.01 Commencement of Procurement Contract Times

A. The Procurement Contract Times will commence to run on the Effective Date of the Procurement Contract.

4.02 Continuing Performance

A. Seller shall adhere to the progress schedule established in accordance with Paragraph 2.04.A., as duly adjusted, and the Goods will be delivered and the Special Services furnished within the Procurement Contract Times.

B. Seller shall carry on furnishing of the Goods and Special Services and adhere to the progress schedule during all disputes or disagreements with Buyer. No furnishing of Goods and Special Services will be delayed or postponed pending resolution of any disputes or disagreements, except as expressly permitted herein, or as Buyer and Seller may otherwise agree in writing.

4.03 Adjustments to Progress Schedule

A. The progress schedule established in accordance with Paragraph 2.04 may be adjusted from time to time as provided below.

1. Seller shall submit to Buyer for acceptance (to the extent indicated in Paragraph 2.04) proposed adjustments in the progress schedule that will not result in changing the Procurement Contract Times. Such adjustments will comply with any applicable provisions of the Procurement Specifications.

2. Proposed adjustments in the progress schedule that will change the Procurement Contract Times must be submitted in accordance with the requirements of Article 11. Adjustments in Procurement Contract Times may only be made by a Change Order.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 13

4.04 Delays

A. If Buyer, Engineer, or anyone for whom Buyer is responsible, delays, disrupts, or interferes with Seller’s performance or progress, then Seller shall be entitled to an equitable adjustment in Procurement Contract Price or Procurement Contract Times.

B. Seller shall not be entitled to an adjustment in Procurement Contract Price or Procurement Contract Times for delay, disruption, or interference caused by or within the control of Seller or anyone for whom Seller is responsible.

C. If Seller’s performance or progress is delayed, disrupted, or interfered with by unanticipated causes not the fault of and beyond the control of Buyer, Seller, and those for which they are responsible, then Seller shall be entitled to an equitable adjustment in Procurement Contract Times. Such an adjustment will be Seller’s sole and exclusive remedy for the delays, disruption, and interference described in this paragraph. Causes of delay, disruption, or interference that may give rise to an adjustment in Procurement Contract Times under this paragraph include but are not limited to the following:

1. severe and unavoidable natural catastrophes such as fires, floods, epidemics, and earthquakes;

2. abnormal weather conditions;

3. inspection delays by governmental authorities, and custom delays;

4. international shipping delays;

5. acts or failures to act of third-party entities; and

6. acts of war or terrorism.

D. Adjustments of Procurement Contract Times or Procurement Contract Price—General Provisions: Seller’s entitlement to an adjustment of Procurement Contract Times or Procurement Contract Price is limited as follows:

1. Seller’s entitlement to an adjustment of the Procurement Contract Times is conditioned on the delay, disruption, or interference adversely affecting an activity on the critical path to completion of Seller’s obligations, as of the time of the delay, disruption, or interference.

2. Seller shall not be entitled to an adjustment in Procurement Contract Price for any delay, disruption, or interference if such delay is concurrent with a delay, disruption, or interference caused by or within the control of Seller. Such a concurrent delay by Seller does not preclude an adjustment of Procurement Contract Times to which Seller is otherwise entitled.

3. Adjustments of Procurement Contract Times or Procurement Contract Price are subject to the provisions of Articles 11 and 12.

E. Each Seller request seeking a delay-related increase in Procurement Contract Times or Procurement Contract Price must be supplemented by supporting data that sets forth in detail the following: (1) the circumstances that form the basis for the requested adjustment; (2) the date upon which each cause of delay, disruption, or interference began to affect Seller’s progress; (3) the date upon which each cause of delay, disruption, or interference ceased to affect Seller’s progress; (4) the number of days’ increase in Procurement Contract Times claimed as a consequence of each such cause of delay, disruption, or interference; and (5) the impact on Procurement Contract Price. Seller shall also furnish such additional supporting documentation as Buyer or Engineer may

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 14

require including, where appropriate, a revised progress schedule indicating all the activities affected by the delay, disruption, or interference, and an explanation of the effect of the delay, disruption, or interference on the critical path to completion.

ARTICLE 5 – BONDS AND INSURANCE

5.01 Performance, Payment, and Other Bonds

A. Seller shall furnish a performance bond and a payment bond, each in an amount at least equal to the Procurement Contract Price, as security for the faithful performance and payment of Seller’s obligations under the Procurement Contract. These bonds must remain in effect until one year after the date when final payment becomes due or until completion of the correction period specified in Paragraph 9.04, whichever is later, except as provided otherwise by Laws or Regulations, the terms of a prescribed bond form, the Supplementary Conditions, or other provisions of the Procurement Contract.

B. Seller shall also furnish such other bonds (if any) as are required by the Supplementary Conditions or other provisions of the Procurement Contract.

C. All bonds must be in the form included in the Bidding Documents or otherwise specified by Buyer prior to execution of the Procurement Contract, except as provided otherwise by Laws or Regulations, and must be issued and signed by a surety named in “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Department Circular 570 (as amended and supplemented) by the Bureau of the Fiscal Service, U.S. Department of the Treasury. A bond signed by an agent or attorney-in-fact must be accompanied by a certified copy of that individual’s authority to bind the surety. The evidence of authority must show that it is effective on the date the agent or attorney-in-fact signed the accompanying bond.

D. Seller shall obtain the required bonds from surety companies that are duly licensed or authorized, in the state or jurisdiction in which the Project is located, to issue bonds in the required amounts.

E. If the surety on a bond furnished by Seller is declared bankrupt or becomes insolvent, or the surety ceases to meet the requirements above, then Seller shall promptly notify Buyer and Engineer and shall, within 20 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the bond and surety requirements of this Procurement Contract.

F. If Seller has failed to obtain a required bond, Buyer may exercise Buyer’s termination rights under Article 14.

G. Upon request to Buyer from any subcontractor, supplier, or other person or entity claiming to have furnished labor, services, materials, or equipment used in the performance of Seller’s obligations, Buyer shall provide a copy of the payment bond to such person or entity.

H. Upon request to Seller from any subcontractor, supplier, or other person or entity claiming to have furnished labor, services, materials, or equipment used in the performance of Seller’s obligations, Seller shall provide a copy of the payment bond to such person or entity.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 15

5.02 Insurance

A. Seller shall provide insurance of the types and coverages and in the amounts stipulated in the Supplementary Conditions.

B. Failure of Buyer to demand certificates of insurance or other evidence of Seller's full compliance with these insurance requirements or failure of Buyer to identify a deficiency in compliance from the evidence provided will not be construed as a waiver of Seller’s obligation to maintain such insurance.

C. Upon assignment of this Procurement Contract, Seller shall name the Contractor/Assignee as an additional insured and comply with the written request of Contractor/Assignee to provide evidence of insurance.

D. Buyer does not represent that insurance coverage and limits established in this Procurement Contract necessarily will be adequate to protect Seller.

E. The insurance and insurance limits required herein will not be deemed as a limitation on Seller’s liability under the indemnities and other rights granted to Buyer in the Procurement Contract.

5.03 Surety or Insurance Companies

A. All bonds and insurance required by the Procurement Contract Documents to be purchased and maintained by Buyer or Seller shall be obtained from surety or insurance companies that are duly licensed or authorized in the jurisdiction in which the Project is located to issue bonds or insurance policies for the limits and coverages so required.

Such surety and insurance companies must also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions.

ARTICLE 6 – LICENSES AND FEES

6.01 Intellectual Property and License Fees

A. Except to the extent stated elsewhere in the Procurement Contract Documents, Seller is not transferring any patent rights, copyrights, or other intellectual property rights for the Goods delivered.

B. To the extent Seller is manufacturing to Buyer’s design, Buyer retains all patent rights, copyrights, and other intellectual property rights in such design.

C. If an invention, design, process, product, or device is specified in the Procurement Contract Documents for incorporation in the Goods or for the performance of Special Services, and if, to the actual knowledge of Buyer or Engineer, its use is subject to patent rights, copyrights, or other intellectual property rights calling for the payment of a license fee or royalty to others, then the existence of such rights and payment obligations will be disclosed to Seller in the Procurement Contract Documents.

D. Seller shall pay all license fees and royalties and assume all costs incident to the use or the furnishing of the Goods, unless specified otherwise by the Procurement Contract Documents.

6.02 Seller’s Infringement

A. Subject to Paragraph 6.01, to the fullest extent permitted by Laws and Regulations, Seller shall indemnify and hold harmless Buyer, Engineer, and their officers, directors, members, partners, employees, agents, consultants, contractors, and subcontractors, from and against all claims, costs, losses, damages, and judgments (including but not

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 16

limited to all reasonable fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement or alleged infringement of any patent, copyright, or other intellectual property right by any of the Goods as delivered or Special Services as performed.

B. Buyer will promptly notify Seller in writing of any claim, suit, or threat of suit by a third party for any infringement or alleged infringement of any patent, copyright, or other intellectual property right with respect to the Goods as delivered or Special Services as performed.

C. Seller shall promptly defend or settle the claim or suit. Seller shall have control over such claim or suit, bear all expenses, and satisfy any adverse judgment.

1. If Seller fails to defend such suit or claim after written notice by Buyer, Seller will be bound, in any subsequent suit or claim against Seller by Buyer, by any factual determination in the prior suit or claim.

2. If Buyer fails to provide Seller the opportunity to defend such suit or claim, Buyer shall be barred from any remedy against Seller for such suit or claim.

D. If a determination is made that Seller has infringed upon the intellectual property rights of another, Seller may, at Seller’s own expense, obtain the necessary licenses for Buyer’s benefit, or replace the Goods and provide related design and construction, consistent with the requirements of the Procurement Contract Documents, to avoid the infringement.

6.03 Buyer’s Infringement

A. Subject to Paragraph 6.01, and to the fullest extent permitted by Laws and Regulations, Buyer shall be responsible to Seller for any infringement or alleged infringement of any patent, copyright, or other intellectual property right caused by Seller’s compliance with the Procurement Drawings or Procurement Specifications, and will reimburse Seller for any license fee or royalties paid by Seller to others if such payment resulted from any invention, design, process, product, or device specified to be furnished or performed in the Procurement Drawings or Procurement Specifications, but not identified as being subject to payment of such license fee or royalty.

B. Seller will promptly notify Buyer in writing of any claim, suit, or threat of suit by a third party for intellectual property infringement arising from Seller’s compliance with the Procurement Drawings or Procurement Specifications.

C. Buyer shall defend or settle the claim or suit. Buyer shall have control over such claim or suit, bear all expenses, and satisfy any adverse judgment.

1. If Buyer fails to defend such suit or claim after written notice by Seller, Buyer will be bound, in any subsequent suit or claim against Buyer by Seller, by any factual determination in the prior suit or claim.

2. If Seller fails to provide Buyer the opportunity to defend such suit or claim, Seller shall be barred from any remedy against Buyer for such suit or claim.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 17

ARTICLE 7 – SELLER’S RESPONSIBILITIES

7.01 Performance of Obligations

A. Seller shall be solely responsible for the means, methods, techniques, sequences, and procedures necessary to perform its obligations in accordance with the Procurement Contract Documents.

B. Seller shall supervise, inspect, and direct the furnishing of the Goods and Special Services competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform its obligations in accordance with the Procurement Contract Documents.

C. Seller shall coordinate the provision of Special Services to avoid or limit interference or disruption of other activities at the location where the Special Services are to occur, including but not limited to ongoing facility operations and construction activities.

7.02 Labor, Materials and Equipment

A. Seller shall provide competent, qualified and trained personnel in all aspects of its performance of the Procurement Contract.

B. All Goods, and all equipment and material incorporated into the Goods, must be as specified, and unless specified otherwise in the Procurement Contract Documents, must be:

1. new, and of good quality;

2. protected, assembled, connected, cleaned, and conditioned in accordance with the original manufacturer’s instructions; and

3. shop-assembled to the greatest extent practicable.

7.03 Laws and Regulations

A. Seller shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of its obligations in accordance with the Procurement Contract Documents. Except where otherwise expressly required by such Laws and Regulations, neither Buyer nor Engineer shall be responsible for monitoring Seller’s compliance with any Laws or Regulations.

B. If Seller furnishes Goods and Special Services knowing or having reason to know that such furnishing is contrary to Laws or Regulations, Seller shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such performance. It will not be Seller’s responsibility to make certain that the Procurement Specifications and Procurement Drawings are in accordance with Laws and Regulations, but this provision will not relieve Seller of Seller’s obligations under Paragraph 3.03.

C. Changes in Laws or Regulations not known at the time of opening of Bids (or, on the Effective Date of the Procurement Contract if there were no Bids) that have a direct effect on the cost or time of Seller’s performance will be the subject of an adjustment in Procurement Contract Price or Procurement Contract Times. If Buyer and Seller are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment, a Claim may be made therefor as provided in Article 12.

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 18

7.04 “Or Equals”

A. Whenever an item of material or equipment to be incorporated into the Goods is specified or described in the Procurement Contract Documents by using the names of one or more proprietary items or specific suppliers or manufacturers, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or equal” item is permitted, other items of material or equipment or material or equipment of other suppliers or manufacturers may be submitted to Buyer for Engineer’s review.

1. If in Engineer’s sole discretion, such an item of material or equipment proposed by Seller is functionally equal to that named and sufficiently similar so that no change in related work will be required, it may be considered by Engineer as an “or equal” item.

2. For the purposes of this paragraph, a proposed item of material or equipment may be considered functionally equal to an item so named only if in the exercise of reasonable judgment, Engineer determines that: 1) it is at least equal in quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function imposed by the design concept of the completed Project as a functioning whole; 3) it has an acceptable record of performance and availability of responsive service; and (4) Seller certifies that if approved: a) there will be no increase in any cost, including capital, installation or operating costs, to Buyer; and b) the proposed item will conform substantially to the detailed requirements of the item named in the Procurement Contract Documents.

B. Engineer’s Evaluation: Engineer will be allowed a reasonable time within which to evaluate each proposal or Submittal made pursuant to Paragraph 7.04.A. Engineer will be the sole judge of whether to accept or reject such a proposal or Submittal. No “or equal” will be ordered, manufactured, or utilized until Engineer’s review is complete, which will be evidenced by an approved Shop Drawing. Engineer will advise Buyer and Seller in writing of any negative determination. Notwithstanding Engineer’s approval of an “or-equal” item, Seller shall remain obligated to comply with the requirements of the Procurement Contract Documents.

C. Special Guarantee: Buyer may require Seller to furnish at Seller’s expense a special performance guarantee or other surety with respect to any such proposed “or-equal.”

D. Data: Seller shall provide all data in support of any such proposed “or equal” at Seller’s expense.

7.05 Taxes

A. Seller shall pay all taxes and duties arising out of the sale of the Goods and the performance of Special Services. All taxes and duties are included in the Procurement Contract Price, except as noted in the Supplementary Conditions.

7.06 Submittals

A. Shop Drawing and Sample Requirements

1. Before submitting a Shop Drawing or Sample, Seller shall:

SOLDIER CANYON WATER LINE PROJECT PAGE 00 70 00 - 19

a. review and coordinate the Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Procurement Contract Documents;

b. determine and verify:

1) all field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information with respect to the Submittal; and

2) the suitability of all materials and equipment offered with respect to the indicated application, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of…