This is an asbestos abatement specification document prepared by Michael Kelly (Utah DAQ Card ASB-0844) for the Piute County School District regarding demolition and removal services at Oscarson Elementary School located at 160 West Sevier Avenue, Marysvale, Utah. The specification outlines the removal and disposal of asbestos-containing materials (ACM) in three distinct phases. Phase 1 involves abatement of thermal systems insulation from the tunnel system, consisting of approximately 190 mudded fittings with 3%-85% chrysotile content and approximately 30 square feet of friable debris, scheduled to begin May 25, 2026, with an estimated 15-day completion timeline. Phase 2 and Phase 3 encompass removal of floor tile and mastic from classroom closets (4), custodial closet (approximately 45 square feet), and floor tile mastic from the cafeteria under carpet (approximately 1,350 square feet), both containing 3%-5% chrysotile, with a start date of May 21, 2027, and a precise completion date of May 31, 2027, preceding demolition activities on June 1, 2027. All contractors must be AHERA certified with the Utah Division of Air Quality, capable of performing work under negative air pressure in accordance with OSHA, EPA, and State of Utah DAQ regulations, and must comply with Utah Division of Air Quality Rules R307-801.
Bidders are required to submit comprehensive proposals including full cost breakdowns for labor, materials, insurance, and disposal permits, along with verification of Utah DAQ Company licensing. Contractors must agree to hold bid pricing until June 1, 2027, as specified in the contract documents. All asbestos-containing materials must be disposed of in accordance with Utah Division of Air Quality regulations. The invitation to bid was issued on March 16, 2026, and encompasses two separate scopes of work for both Oscarson Elementary School and Circleville Elementary School, though detailed specifications for Circleville are referenced as a separate attached document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OSCARSON ELEMENTARY SCHOOL
160 WEST SEVIER AVENUE
MARYSVALE, UTAH 84750
ASBESTOS ABATEMENT FOR DEMOLITION
REMOVAL AND DISPOSAL SPECIFICATION
Dated: March 3, 2026
Prepared for:
Piute County School District
500 North Main Street Junction, Utah 84740
Prepared by:
Michael Kelly (Utah DAQ Card ASB-0844, Inspector, Management Planner, Project Designer)
Health & Safety Services
P.O. Box 4741 Salt Lake City, Utah 84110
(Utah DAQ Company Card ASBC-133)
Piute County School District Demolition Specification Oscarson Elementary School
Part 1 - General Information
1.1 Scope of Work – Oscarson Elementary School Asbestos Abatement for Demolition Removal and Disposal Specification.
1.1.1 Owner’s schedule is as follows:
Thermal Systems Insulation (Tunnels)
Start Date: May 25, 2026 Completion Date: It is estimated that abatement can be completed within 15 days
Remaining Asbestos Containing Materials; Wallboard Systems, Floor Tile, Floor Tile Mastic
Start Date: May 21, 2027 Completion Date: May 31, 2027 This is a precise completion date. Demolition will start
June 1, 2027
1.1.2 This specification covers the abatement of asbestos from building structures and components. It is the intent of the Contract Documents to show the work necessary to complete the project.
1.1.3 All dimensions, quantities or areas provided in the Scope of Work are approximate and are only included to assist Contractor in determining the amount of asbestos-containing material (ACM) designated for removal. Contractor is responsible for accurately determining the amount of ACM included in the Scope of Work.
ASBESTOS CONTAINING MATERIALS TO BE ABATED
1. Thermal System Insulation - Mudded Fittings
A) Abatement contractor shall abate asbestos-containing thermal systems insulation materials from the tunnel system. There is approximately 190 each fittings and minimal debris on concrete floor approximately 30 sq. ft. that contains 3% - 85% chrysotile. There are very few complete fittings, most material is incomplete abatement remaining on pipes and asbestos debris on cloth/fiberglass wrap. This material is included in Table 1. This material is friable and shall be disposed of as asbestos-containing material. The start date for removal of this material will be May 25, 2026 and it is estimated that abatement can be completed within 15 days.
2. Floor Tile and Mastic
B) Abatement contractor shall remove floor tile and underlying mastic from the classroom closets
(4) and custodial closet. There is approximately 45 sq. ft. of flooring that contains 3% chrysotile and 5% chrysotile in the underlying mastic. This material is included in Table 1. This material is non-friable and shall be disposed of as an asbestos-containing material. The start date for removal of this material will be May 21, 2027 with a completion date of May 31, 2027 this is a precise completion date. Demolition will start June 1, 2027.
3. Floor Tile Mastic
C) Abatement contractor shall remove floor tile mastic from the cafeteria; this material is under carpet. There is approximately 1,350 sq. ft. of floor tile mastic that contains 5% chrysotile. This material is included in Table 1. This material is non-friable and shall be disposed of as an asbestos-containing material. The start date for removal of this material will be May 21, 2027 with a completion date of May 31, 2027 this is a precise completion date. Demolition will start June 1, 2027.
4. Disposal
D) Abatement contractor shall dispose of thermal systems insulation, floor tile and associated mastic, and floor tile mastic as asbestos-containing materials per Utah Division of Air Quality R307-801- 15 contained in the Utah Division of Air Quality Rules R307-801, dated 8/1/2000.
Table 1
Asbestos-Containing Materials to be Abated in Oscarson Elementary School
Material ACM Location Amount Thermal Systems Insulation
3%-85% Chrysotile
Tunnel system ~190 each ~30 sq. ft. of debris on concrete floor
Floor Tile & Mastic
Floor Tile = 3% Chrysotile Mastic = 5% Chrysotile
Classroom closets (4) and custodial closet
~45 sq. ft.
Floor Tile Mastic Mastic = 5% Chrysotile
Cafeteria ; this material is under carpet ~1,350 sq. ft.
<1% ASBESTOS CONTAINING MATERIALS TO BE ABATED
5. Wallboard Systems
E) Abatement contractor shall remove all finished wallboard systems walls in the classrooms, main office area, server room, west offices, custodial closet, and stage entrance. The wallboard systems have been composite point counted and are <1% chrysotile. There is ~10,120 sq. ft. of wallboard to be abated. This material is included in Table 2. The start date for removal of this material will be May 21, 2027 with a completion date of May 31, 2027 this is a precise completion date.
Demolition will start June 1, 2027.
6. Disposal
F) Wallboard systems have been point counted and shown to contain <1% asbestos. These materials shall be contained in clear plastic bags to mitigate dust, and disposed of as construction debris.
Wallboard Systems debris may go to Garfield County Landfill – (435) 676-1101 please contact Garfield County Landfill for payment information and hours of operations.
Table 2 <1% Asbestos Materials to be Abated in
Oscarson Elementary School Material Asbestos Content Location Amount Wallboard Systems
<1% Chrysotile by composite point count
Classrooms, main office area, server room, west offices, custodial closet, and stage entrance
~10,120 sq. ft.
ASBESTOS CONTAINING MATERIALS TO REAMAIN DURING DEMOLITION
7. Caulk - Exterior
G) Exterior caulk around windows and doors will remain in place during demolition. There is approximately 300 ln. ft. of caulk that contains 5% chrysotile. This material is included in Table
3. This material is non-friable and will remain in place during demolition.
Table 3
Asbestos Materials to Remain in Place During Demolition Oscarson Elementary School
Material Asbestos Content Location Amount Caulk Exterior
5% Chrysotile Exterior windows and doors ~300 ln. ft.
GENERAL
1. Utilities
a. Water sources will be made available by General Contractor/Piute County School District.
b. Electricity will be made available by General Contractor/Piute County School District and/or the abatement contractor if necessary.
c. Restroom facilities shall be provided by General Contractor/Piute County School District.
2. Dumpster placement: Dumpster placement will be directed by the General Contractor/Piute County School District.
3. All dimensions, quantities or areas provided in the Scope of Work are approximate, and are only included to assist Contractor in determining the amount of ACM designated for removal.
Contractor is responsible for accurately determining the amount of ACM included in the Scope of Work.
4. All poly sheeting used by the Contractor in the construction of containments or barriers shall be of the fire-retardant type.
5. Contractor shall hold his bid for this project until June 1, 2027.
6. Contractor shall perform the prescribed abatement procedures within approved containments or mini-containments that meet OSHA, EPA, and State of Utah DAQ regulations. All work shall be performed within pre-approved containment configurations, critical barriers, and under negative air pressure.
7. The work specified herein shall be the removal and disposal of asbestos-containing materials by competent persons trained, AHERA certified with the Utah Division of Air Quality, knowledgeable and qualified in the techniques of abatement, handling and disposal of asbestos-containing and asbestos-contaminated materials and the subsequent cleaning of contaminated areas, which comply with all applicable Federal, State and Local regulations and are capable of and willing to perform the work of this Contract.
8. Removal and disposal of the asbestos-containing materials identified shall be performed in a manner which prohibits the release of asbestos fibers into the surrounding environment. This shall be accomplished by constructing negative pressure enclosures and following the removal techniques indicated in the contract specifications provided by Health & Safety Services consultants.
9. The Contractor shall supply all labor, materials, services, insurance, permits and equipment necessary to carry out the work in accordance with all applicable Federal, State and Local regulations and these specifications.
10. Abatement projects involving greater than 260 linear feet of pipe insulation or 160 square feet of sprayed, troweled or otherwise applied material or covering or composing building structures or components, send written notification in accordance with 40 CFR Part 61.146 of Sub Part M, to the appropriate State or Federal air pollution control agency responsible for the enforcement of the National Emission Standard for Asbestos at least ten (10) days prior to the commencement of any on site project activity. If the abatement project is less-than NESHAP size, then the appropriate notification shall be sent to the Utah State Division of Air Quality as per State of Utah regulations.
11. Abatement contractor shall post in the Clean Room area of the worker decontamination enclosure a list containing the names, addresses, and telephone numbers of the Contractor, The Building Owner, the Asbestos Project Officer, the General Superintendent, the Air Sampling Professionals, the testing laboratory and any other personnel who may be required to assist during abatement activities (e.g. Safety Officer, Building Maintenance Supervisor, Energy Conservation Officer).
12. A copy of the inspection report shall be on site at all times for the duration of the abatement.
13. Following the completion of abatement/clean-up operations, the Contractor shall notify the Contract Administrator that work areas are ready for clearance air monitoring. The Contract Administrator shall then arrange for an Air Monitoring Professional to sample the air in the work area for airborne fiber concentrations.
14. Contractor shall conform to the Owner’s projected scheduling requirements. Contractor agrees to a schedule at the Owner’s convenience. Contractors’ bid shall reflect this consideration.
Owner’s schedule is as follows:
Thermal Systems Insulation (Tunnels)
Start Date: May 25, 2026 Completion Date: It is estimated that abatement can be completed within 15 days
Remaining Asbestos Containing Materials; Wallboard Systems, Floor Tile, Floor Tile Mastic
Start Date: May 21, 2027 Completion Date: May 31, 2027 This is a precise completion date. Demolition will start