3. Specifications.pdf
PDF 1022 KB Posted
- Attached to
- Bass Lake Recreation Sites Storm Damage Project
- Solicitation number
- 12970223Q0091
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains technical specifications for a federal construction contract to repair damage at several recreation sites on the Bass Lake Ranger District. The project involves repairing parking lots, campground roads and trails, restoring drainage, and installing signage and other site amenities. Work includes clearing, earthwork, aggregate base and asphalt paving, culvert installation, car stops, and bulletin boards. The specifications define requirements for materials, construction methods, testing, and quality control. The contract will be awarded before July 31, 2023 and the contractor must complete all work by that date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1 SF30.pdf | ||
| Bass Lake Recreation Sites Storm Damage Project RFI Log.xlsx | XLSX spreadsheet | |
| 7. Fire Plan.doc | DOC document | |
| 6. Spec_839_RestoreDrainageFunctions.pdf | ||
| 1. Schedule of Items.xls | XLS spreadsheet | |
| 4. Drawings.pdf | ||
| 8. CA20230018 08-11-2023.txt | TXT text file | |
| 5. Spec_814_AsphaltPavementPatching.pdf | ||
| 2. Statment of Work.rtf | RTF text file | |
| 12970223Q0091.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications D-i BassLakeRecSites_StormDamage_Specifications_071023_FINA L.docx
BASS LAKE RECREATION SITES STORM DAMAGE PROJECT
TECHNICAL SPECIFICATIONS
1010 SUMMARY OF WORK
REGULATORY REQUIREMENTS
SHOP DRAWINGS AND SUBMITTALS
SCHEDULES AND REPORTS
QUALITY CONTROL AND QUANTITY MEASUREMENT
MOBILIZATION
1507 TEMPORARY FACILITIES AND UTILITIES
MATERIAL SOURCES
PRODUCT HANDLING
CONTRACT CLOSEOUT AND CLEANUP
CLEARING AND DEMOLITION
EARTHWORK
HARDENED AGGREGATE SURFACE AND AGGREGATE BASE
ROCK RIPRAP
ASPHALT CONCRETE PAVEMENT
CORRUGATED METAL PIPE CULVERT – INLET/OUTLET PROTECTION
CAR STOPS
BULLETIN BOARDS
PAINT
Specifications D-1 BassLakeRecSites_StormDamage_Specifications_071023_FINA
1010 SUMMARY OF WORK
SCOPE
The requirements of these Technical Specifications cover the Bass Lake Recreation Sites Storm Damage Project.
This project consists of having the contractor furnishing all labor, equipment, materials, and incidentals necessary to:
• Repair the parking lot at the Willow Creek Trailhead – clearing and demolition of the broken asphalt section and removal of stumps, downed trees, and debris, placement and compaction of fill material, grading and pavement of the new asphalt section, installing car stops, and installing riprap at inlet/outlet of an existing culvert;
• Repair the parking lot at the Recreation Point Group Picnic Site – clearing and demolition of the broken asphalt section and removal of stumps, downed trees, and debris, grading and pavement of the new asphalt section, and installing car stop;
• Restore drainage function at the Forks Campground – cleaning out two existing culverts and installing riprap at inlet/outlet;
• Repair the road section and restore drainage flow at the Spring Cove Campground – clearing and demolition of the broken asphalt section and removal of stumps, downed trees, and debris, placement and compaction of fill material, grading and pavement of the new asphalt section, and cleaning out an existing culvert and installing riprap at inlet/outlet;
• Repair the road and trail sections and restore drainage flow at Dry Gulch
Campground – clearing and demolition of the broken asphalt sections of the parking lot and trail and removal of stumps, downed trees, and debris, placement and compaction of fill material, grading and pavement of the new asphalt sections at parking lot and trails, installing bulletin board, and cleaning out an existing culvert and installing riprap at inlet/outlet;
• and implement all other aspects shown on the project plans.
STORAGE AREAS
The project is within a high use recreation area. The Contractor will be required to restore these areas to their original conditions as outlined in Section 01700. Material storage and maintenance of equipment will be confined to the marshalling areas. Mar-shalling areas will be identified by the Forest Service. When not in use, equipment shall be stored in a marshalling area.
Specifications D-2 BassLakeRecSites_StormDamage_Specifications_071023_FINA
TRAFFIC
1. Traffic Control: The Contractor shall keep the project area open and passable for all administrative and emergency traffic at all times.
Any warning devices and/or barricades used on the project shall be maintained in the construction area at all times, and shall be in compliance with the Manual on Uniform Traffic Control Devices.
2. Traffic Safety: Safety precautions shall be in accordance with the latest edition of the State of California Construction Safety Regulations.
3. Hauling Restrictions: The Contractor shall comply with all legal load re-strictions in the hauling of materials on public roads within and outside of the limits of the project. Federal, State or local permits will not relieve the Con-tractor of liability for damage which may result from the moving of equipment.
4. Equipment Cleaning: All off-road equipment shall be free of noxious weeds, free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Contractor shall certify in writing that all off-road equipment is free of noxious weeds prior to commencing operations on the project site. Contractor shall employ whatever cleaning methods necessary to ensure that all off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seeds and other such debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required. Contractor shall at least, 5 working days prior to moving each piece of equipment onto the project site, identify the location of the equip-ment’s’ most recent operation.
5. Traffic Speed: This project is located within a heavily used recreation area in which the roads are winding with limited site distances. The speed limit within the Campground is 5 mph. These speed limits shall be strictly adhered to by the Contractor under this contract.
CLOSURES
The project area will be CLOSED to public use, including camping during the approved Contract Time. This will not prevent recreational uses by persons, such as hiking, walk-ing, fishing, swimming, etc. which may occur during the duration of the contract time.
It is the contractors’ responsibility to ensure the safety of the public on the jobsite at all times.
MAINTAINING UTILITY SERVICE
1. Electrical: Contractor shall notify the Forest Service 24 hours in advance of any utility service interruption.
2. Water: Contractor shall notify the Forest Service 24 hours in advance of any utility service interruption.
3. Identifying the location of all existing underground utilities shall be the re-sponsibility of the Contractor. Any damage to existing utilities that occur shall be the responsibility of the Contractor.
Specifications D-3 BassLakeRecSites_StormDamage_Specifications_071023_FINA
ENCROACHMENT PERMIT
Any additional permits which may be required from utility companies shall be the re-sponsibility of the Contractor (refer to FAR 52.236-7).
PROTECTION OF LAKES AND STREAMS
All lakes and streams in the Project Area shall be protected by the Contractor in ac-cordance with requirements of the California Department of Fish and Game and the California Water Quality Control Board. All water encountered during the construction of this Project shall be discharged in conformance to these requirements (refer to
AGAR 452.236-74).
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
END OF SECTION 1010
Specifications D-4 BassLakeRecSites_StormDamage_Specifications_071023_FINA
REGULATORY REQUIREMENTS
GENERAL
SCOPE
This Section describes the Regulatory Requirements and the Codes and Standards that apply to the work in this contract.
REGULATORY REQUIREMENTS
A. All laws, ordinances, codes, and regulations shall apply and be implemented into this contract.
B. The following codes and standards shall apply to the work in this contract.
Where no date is specified, the applicable edition shall be the one in effect on the date of solicitation.
1. American Society for Testing Materials (ASTM).
2. American Water Works Association Standards.
3. Forest Service Handbook 6709.11 Health and Safety Code Hand-book.
4. International Association of Plumbing and Mechanical Officials.
5. International Code Council (ICC).
6. Manual on Uniform Traffic Control Devices.
7. Manufacturer’s Instructions.
8. National Electrical Code (NEC).
9. National Sanitation Foundation.
10. State of California Construction Safety Orders.
11. Underwriters Laboratory.
12. California Building Code, (CBC), latest edition.
13. California Building Code Standards.
14. Uniform Plumbing Code (UPC).
15. Uniform Fire Code (UFC).
16. Uniform Fire Code Standards.
17. Underwriters’ Laboratories (UL).
18. Uniform Federal Accessibility Standards (ADAAG).
CODES AND STANDARDS
Standards and practices set forth by the references mentioned elsewhere in these specifica-tions shall be adhered to unless otherwise noted.
Specifications D-5 BassLakeRecSites_StormDamage_Specifications_071023_FINA
DUTIES OF THE CONTRACTOR
A. Responsibilities. It is the duty of the Contractor to perform all work in ac-cordance with the approved plans, specifications and regulations required for completion, during the term of this contract.
B. Performance of the work: The Contractor shall study carefully the approved plans and specifications and shall plan his schedule of operations well ahead of time. If at any time it is discovered the work is being done which is not in accordance with the approved plans and specifications, the Contractor shall correct the work immediately.
All inconsistencies or items which appear to be in error in the Specifications shall be promptly called to the attention of the Forest Service. Local condi-tions which may affect the construction operations shall likewise be brought to the attention of the Forest Service at once. In no case, however, shall the instruction of the Forest Service be construed to cause work to be done which is not in conformity with the approved plans, specifications and change orders.
The Contractor shall not carry on work except with the knowledge of the Forest Service.
Where so indicated or in lieu of drawing or specification requirements, materials shall be used and installed in the best quality manner and method recommended by the man-ufacturer. Such recommendation shall be submitted in writing by the Contractor. Sub-stitution of materials shall be considered a Contract Change and will be subject for approval by the Forest Service prior to use or fabrication.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
PRODUCTS
PRODUCTS AND MATERIALS
All products and materials incorporated into this contract shall meet the standards and requirements of the codes and standards as referenced in Part 1 – General of this Sec-tion, and elsewhere herein unless otherwise SHOWN ON THE DRAWINGS, the more stringent requirements shall take precedence within the codes and standards that govern this Contract.
All materials, unless specified otherwise, shall be handled, stored, installed, and main-tained in accordance with the manufacturer’s instructions and recommendations.
Specifications D-6 BassLakeRecSites_StormDamage_Specifications_071023_FINA
EXECUTION
WORK REQUIREMENTS
All work in the contract shall meet the standards and requirements of the codes and standards referenced in Part 1 - General of this Section and elsewhere herein, unless otherwise SHOWN ON THE DRAWINGS or in the specifications. When more strin-gent requirements are called out in these specifications or shown on the drawings, the more stringent requirements shall take precedence over the codes and standards. All work shall be performed in a workman-like manner according to the best practices of the trade and the best standards of the industry.
END OF SECTION 1060
Specifications D-7 BassLakeRecSites_StormDamage_Specifications_071023_FINA
SHOP DRAWINGS AND SUBMITTALS
SCOPE
A. Perform all work necessary and required for the construction of the project as indi-cated. Such work includes but is not limited to the following:
1. Shop Drawings
2. Samples
3. Catalog Data
4. Operation and Maintenance Manuals
5. Certificates and Warranties
SUBMITTALS
Submittals shall include all pertinent data required to understand the quality of compo-nents, dimensional relationships, integration with other materials, assembly techniques, structural aspects, color, finish, texture, and other such characteristics as may be nec-essary to fully describe the item and its intended use.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
EXECUTION
SUBMITTALS
Submittals and shop drawings shall be submitted in a timely fashion to allow ten (10) working days for review by the Forest Service. No work shall begin until shops draw-ings and submittals are approved. TWO (2) copies of all submittals shall be submitted to the Forest Service. Contractor has the option to submit electronically.
SHOP DRAWINGS
A. Original Submittal: TWO (2) legible copies of all shop drawings shall be submitted for approval as required under 1300.2.1 above prior to fabrica-tion, installation or order placement to allow for checking and coordination.
If approved, the submittal summary and only ONE (1) copy of the shop drawings will be returned to the contractor.
B. Resubmittal: When a resubmittal is required, the submittal summary and only ONE (1) copy of the shop drawings indicating so will be returned to the Contractor. After revision of the original, TWO (2) copies shall be re-submitted for approval. Contractor has the option to submit electronically.
C. Approval: Once approved, the submittal summary and only ONE (1) copy of the shop drawings will be returned to the contractor. Variation from the approved documents shall be likewise submitted and approved before being
Specifications D-8 BassLakeRecSites_StormDamage_Specifications_071023_FINA carried out. Approval of satisfactory submittals and substitutions will be made within 10 working days of receipt.
SAMPLES
A. Original Submittal: Two samples of each item for which samples are re-quired, unless otherwise specified, shall be furnished for approval. Ap-proval shall be obtained prior to delivery of the material to the project site.
These samples shall be representative of the actual material proposed for use in the project and of sufficient size to demonstrate design, color, texture and finish as they will appear in the completed installation.
B. Resubmittals: All rejected samples will be returned upon request and any or all resubmittals required shall consist of two new samples.
C. Approval: Upon approval, one sample so noted will be returned and the re-mainder will be retained by the Forest Service until completion of the work.
When requested, all approved samples will be returned for installation providing identity is maintained in an approved manner until final ac-ceptance of the project.
CATALOG DATA
A. Submittals: TWO legible copies of catalog data are required for the original submittal and each resubmittal. Catalog data shall be submitted along with shop drawings. Contractor has the option to submit electronically. Only ONE (1) copy of the shop drawings will be returned to the contractor.
B. Data: Each submittal shall have all pertinent data contained therein that is applicable to the item submitted for approval.
IDENTIFICATION
A. Catalog Data: Each separate catalog brochure or page submitted shall have the identification shown. Catalog of brochures submitted containing multi-ple items for approval need have only cover identification. In such cases the identification shall include page and catalog item numbers.
B. In the event one or more of the multiple items are not approved in any sub-mittal, the additional copies required will not be requested until all items are approved.
TIMING
A. The Contractor shall provide submittals far enough in advance of the sched-uled dates of installation to provide time for reviews, securing necessary approvals, for possible revisions and resubmittals and for placing orders and securing delivery.
B. No portion of the work requiring an approved submittal shall be started nor shall any material be fabricated or installed prior to the approval of such item.
Specifications D-9 BassLakeRecSites_StormDamage_Specifications_071023_FINA
END OF SECTION 1300
Specifications D-10 BassLakeRecSites_StormDamage_Specifications_071023_FINA
SCHEDULES AND REPORTS
SCOPE
This Section includes the requirements for the submittal of the Contractor’s proposed work schedule for the project.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
EXECUTION
WORK SCHEDULE
Within fifteen (15) working days of the issuance of the Notice to Proceed, the Contrac-tor shall submit to the Forest Service for approval a proposed work schedule for the project. It shall be the contractor’s responsibility to follow this schedule as closely as possible. Under no circumstance shall the contractor’s completion of construction of the project go any later than July 31st, 2023. This construction end date shall not be extended under any circumstance, whether delays are caused by the contractor, Forest Service, weather, or any other manmade or natural occurrence.
Such schedule shall be in the form of a critical path network or other approved format and shall include the timing for each major phase of the work. The Contractor shall update such approved schedule as necessary when significant changes occur during the progress of the work.
Include in the critical path schedule time for submissions and approval of substitutions as well as tests and inspections.
END OF SECTION 1315
Specifications D-11 BassLakeRecSites_StormDamage_Specifications_071023_FINA
QUALITY CONTROL AND QUANTITY MEASUREMENT
DESCRIPTION
This work shall consist of providing certification that the quality and quantity of con-struction conforms to the drawings, specifications, and requirements of the contract.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
EXECUTION
CONSTRUCTION REQUIREMENTS
Offsite Produced Materials
The Contractor shall furnish certificates executed by the manufacturer, supplier, or ven-dor, stipulating that all offsite produced materials incorporated into the work meet the applicable requirements shown on the drawings or stated in these specifications. Each certificate shall apply to a single commodity or invoice. Incidental purchases needed to remedy minor shortages of material shall be certified by the Contractor.
Sampling, Testing and Inspection The Contractor shall provide and maintain appropriate measuring and testing devices, equipment, and supplies to accomplish the required measurement, testing and inspec-tion in a timely manner. Tests, measurements, and certifications shall be made as re-quired by the drawings and specifications. The Contractor shall take samples and per-form inspections and tests necessary to achieve the quality of construction required by the contract. Sampling and testing frequency for specific items shall be as shown on the drawings or in these specifications, or as noted below:
1. Cast-In-Place Concrete: Contractor shall test for compressive strength, air content, and slump, and as required to meet specifications of Section 0.3300.
2. Excavation and Embankment (including trenching operations): Contractor shall test for moisture density, and in place density and compaction, and as required to meet the specifications of Section 0.2200.
3. Asphalt Concrete: Contractor shall test for aggregate gradation, compaction, thick-ness and temperature, and as required to meet the specifications of Section 0.2513.
4. Aggregate Base: Contractor shall test for field density, and as required to meet the specifications of Sections 0.2340 and 0.2513.
Records
1. Record Drawings: The Contractor shall maintain TWO (2) sets of the contract drawings depicting as-built conditions resulting from Forest Service-authorized
Specifications D-12 BassLakeRecSites_StormDamage_Specifications_071023_FINA changes. The drawings shall be maintained in a current condition. GREEN pencil shall be used to indicate deletions; RED to show addition and changes. TWO (2) complete sets of “as-Built” drawings, fully marked-up, shall be submitted to the Forest Service within one week after acceptance of the Work, or retention payment may be withheld.
END OF SECTION 1442
Specifications D-13 BassLakeRecSites_StormDamage_Specifications_071023_FINA
MOBILIZATION
DESCRIPTION
This work shall consist of obtaining all bonds, insurance and permits, preparatory work and operations necessary for the movement of personnel, equipment, supplies, and in-cidentals to the project site, and for all other work and operations that must be per-formed or that cause costs to be incurred prior to beginning work on the various items on the project site including temporary facilities and utilities.
MEASUREMENT AND PAYMENT
Measurement and/or payment will be made for the work described in this Section, as shown on the schedule of items under the titles:
• MOBILIZATION
END OF SECTION 1505
Specifications D-14 BassLakeRecSites_StormDamage_Specifications_071023_FINA
1507 TEMPORARY FACILITIES AND UTILITIES
1507.1 GENERAL
1507.1.1 SCOPE
A. The work of this Section includes providing all temporary facilities and con-trols needed for the project. The Contractor shall furnish all equipment, la-bor, materials and incidentals necessary to hook-up, install and maintain the facilities. Such facilities include but are not limited to:
1. Sanitary facilities.
2. Directional signs, safety signs and barricades.
3. Temporary utilities such as power, water, electricity, and telephone service.
1507.1.2 QUALITY ASSURANCE
1. OSHA Compliance: Comply with Occupational Health and Safety Require-ments for Construction (29 CFR 1926).
2. Hazardous Materials Compliance: For hazardous materials regulated by OSHA see 29 CFR Part 1910, Subpart Z.
1507.2 PRODUCTS
1507.2.1 WATERING EQUIPMENT
Watering equipment, including piping, shall be watertight. Tanks shall be of known capacity. Equipment used for dust control and finishing operations of subgrade and surfaces shall provide uniform and controlled application of water from the driver’s position at all times.
1507.2.2 MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
1507.3 EXECUTION
1507.3.1 SANITARY FACILITIES
A. The Contractor shall provide temporary sanitary facilities for all workers and maintain the facilities in a clean and sanitary state. Contractor furnished facilities shall be available for Forest Service personnel use.
B. At no time shall the Contractor use any of the existing sanitary facilities within, or adjacent to the project site.
1507.3.2 REMOVAL
The Contractor shall remove temporary facilities and controls as progress of the work will permit or as directed by the Forest Service.
Specifications D-15 BassLakeRecSites_StormDamage_Specifications_071023_FINA
1507.3.3 FENCES
Temporary fences will be permitted for securing materials, equipment, vehicles, tools, for protection of work, and protection for the public.
1507.3.4 OPERATIONS AND STORAGE AREAS
Operations and storage areas shall be restricted to the project site, AS SHOWN ON THE DRAWINGS or as directed by the Forest Service.
1507.3.5 COSTS
A. All fees and costs for the hook-up, installation, use, maintenance and re-moval of temporary facilities and controls shall be paid by the Contractor and no separate payment will be allowed therefore.
END OF SECTION 1507
Specifications D-16 BassLakeRecSites_StormDamage_Specifications_071023_FINA
MATERIAL SOURCES
BORROW SOURCE
No borrow sites have been identified for the project. In the event the contractor pro-poses to use a borrow site, the contractor shall provide the Forest Service with the fol-lowing submittals:
• Location of borrow site
• Material to be obtained
• Location and purpose for use of borrow material
• Material samples and/or test results of borrow material in accordance with the sections of these specifications for intended use
• Authorization from the land owner
• Valid permit documentation for grading operation to remove such material
• Any other items, tests and/or studies required for the Forest Service to make an educated decision on use of the material
No borrow material can be used on the project until the material has been reviewed and APPROVED by the Forest Service.
After borrow excavation is completed, the excavation site shall be dressed to uniform slopes providing adequate drainage, the bottom smoothed to reduce erosion potential, erosion control devices installed as directed by the Forest Service, and the site mulched in accordance with Section 02801.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be
END OF SECTION 1605
Specifications D-17 BassLakeRecSites_StormDamage_Specifications_071023_FINA
PRODUCT HANDLING
DESCRIPTION
Work included: Contractor shall protect products scheduled for use in the work by means including, but not necessarily limited to those described in this Section.
TESTING LABORATORY RECOMMENDATIONS
A. Except as otherwise approved by the Forest Service, Contractor shall deter-mine and comply with testing Laboratory’s recommendations on product handling, storage and protection.
B. Facility and Equipment: The Contractor shall provide, install, maintain, and operate a complete and adequate facility for the handling, execution, dis-posal, and distribution of all material and equipment required for the proper and timely performance of all work connected with the Contract.
PACKAGING
A. Delivery and Storage: Deliver all manufactured materials in the original packages, containers, or bundles (with the seals unbroken) bearing the name or identification marks of the manufacturer.
Maintain packaged materials with seal unbroken and labels intact until time of use.
Promptly remove damaged material and unsuitable items from the job site, and promptly replace with material meeting the specified, requirements, at no additional cost to the Forest Service.
B. The Forest Service will reject all non-complying materials and products that do not bear identification satisfactory to the Forest Service as to grade, qual-ity, or other pertinent information.
PROTECTION
Contractor shall protect finished surfaces until accepted by the Forest Service.
Store all materials in such manner as necessary to properly protect same from damage.
Materials shall be transported and handled to preserve their quality and fitness for the work. Materials or equipment damaged by handling, weather, dirt, or from any other cause will not be acceptable.
Aggregates shall be stockpiled, loaded, and transported in a manner that will preserve specified gradation and avoid contamination. Stockpiles of aggregate having different gradations shall not be intermingled.
Store material so as to cause no obstructions. Store material off sidewalks, roadways, and underground services. The Contractor shall be responsible for protecting all mate-rial and equipment furnished under the Contract.
Specifications D-18 BassLakeRecSites_StormDamage_Specifications_071023_FINA
REPAIRS AND REPLACEMENTS
A. In event of damage, Contractor shall promptly make replacements and re-pairs as directed by the Forest Service, and at no additional cost to the Forest Service.
B. Additional time required to secure replacements and to make repairs will not be considered by the Forest Service to justify an extension of the Con-tract time.
SUBSTITUTION OF MATERIALS
When a specific manufacturer, trade name or material is specified, or indicated, it is to establish a standard of quality and shall not be construed as limiting competition. If the Contractor desires to use a manufacturer, trade name or material other than that speci-fied, he shall request approval of such substitutions, in writing, to the Forest Service.
Submittals for approval of substitute manufacturer, trade name or materials should con-tain sufficient information, descriptive brochures, drawings, samples or other data as necessary to provide direct comparison to the specified products. Each submittal shall be well marked and identified as to the type and kind of items being submitted for approval. It is the sole responsibility for the Contractor to submit complete descriptive and technical information so that the Forest Service can make proper appraisal. Lack of proper information will be sufficient cause for rejection. References to catalogs that the Forest Service may or may not have, will not be accepted.
Substitutions shall not be offered unless a thorough check is made of all related items and interferences, revised arrangements and other changes that may result. Prepare drawings of revised equipment and piping arrangements caused by substitutions. Such drawings shall be equal in quality to Contract Drawings. The cost of supplying draw-ings shall be included by the Contractor in his estimate of proposed substituted materi-als.
By offering a substitution the contractor shall accept responsibility for its effect on the work of all trades, including any possible delays in the completion time of the Project.
All costs of changes in the work of other trades and drawings, etc., affected by inclusion of Contractor requested substitution shall be paid by the Contractor requesting approval of such substitution.
It shall be the Contractor’s responsibility to insure that substitutes perform in accord-ance with the design intent of the specified product. Certification to that effect shall be required as part of the approval.
Unless specifically submitted and approved in accordance with above, substitutions will not be allowed.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be
Specifications D-19 BassLakeRecSites_StormDamage_Specifications_071023_FINA
END OF SECTION 1640
Specifications D-20 BassLakeRecSites_StormDamage_Specifications_071023_FINA
CONTRACT CLOSEOUT AND CLEANUP
SCOPE
This section includes the requirements covering the disposal of excess material result-ing from construction operations and the cleanup work required in areas affected by the construction, and the protection of existing resources, structures, improvements, and utilities.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
PRODUCTS
CLEANING SUPPLIES
All cleaning materials and equipment used shall be selected and employed with care to avoid scratching, marring, defacing, staining or discoloring the surfaces cleaned.
EXECUTION
EXCESS MATERIALS AND REFUSE
All refuse and unused materials generated by the Contractor’s operations including wood, asphalt, concrete, vegetative materials and the like, shall be removed from the project site and disposed of off National Forest lands in accordance with State and Lo-cal regulations and/or as directed by the Forest Service. The surplus excavated material shall be removed to a proper disposal location off of the site designated by the Forest Service.
CLEANUP DURING CONSTRUCTION
Cleanup shall be performed by the Contractor as required to prevent accidents to per-sonnel and protect all work in-place. Construction cleanup shall consist of the removal of all dirt, trash, scrap, debris, and excess materials from any floor space or walking surface that may cause the tripping or sliding of workers, ladders, or equipment.
PROTECTION OF EXISTING RESOURCES, STRUCTURES,
IMPROVEMENTS, AND UTILITIES
(a) The Contractor shall preserve and protect all existing vegetation and landform on or adjacent to the work sites, which are not to be removed and which do not unrea-sonably interfere with the work required under this contract.
(b) The Contractor shall protect from damage all existing structures, improvements, and utilities (1) at or near the work site and (2) on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Specifications D-21 BassLakeRecSites_StormDamage_Specifications_071023_FINA
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work.
(c) If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contrac-tor.
FINAL CLEANUP
Immediately prior to the Contractor’s request for final inspection of the Project, final cleanup shall be performed.
QUALITY OF CLEANUP
In addition to the normal “broom clean” requirements, the exposed surfaces of the fol-lowing materials shall be cleaned as listed below:
A. Glass: Remove excess putty and paint and all glass shall be washed clean.
B. Painted Surfaces: Remove marks, stains, fingerprints and dirt. All cleaned and new surfaces shall appear to be the same.
C. Roof: Remove all dust, dirt and debris.
D. Hardware: Clean.
E. Quarry Tile: Mop and clean, remove stain marks and heel marks as neces-sary.
F. Site: Remove all trash, debris and surplus excavated material of off National
Forest lands. No items shall be left or discarded elsewhere on the site. The surplus excavated material shall be removed to a proper disposal location off of the site designated by the Forest Service.
G. General: Remove paper labels from glass fixtures and equipment only after respective items have been inspected, verified and approved to assure that each complies with requirements of the Specifications and Drawings. La-bels and plates that are permanently attached to equipment shall not be re-moved. Remove paint and clean all permanent labels so that they are legible.
H. Lighting fixtures diffusers wiped clean.
SALVAGEABLE ITEMS
A. All salvageable items shall remain the property of the SNF, and shall be removed by the contractor and stored on designated Government land as directed by the Forest Service.
B. Items not salvageable shall be disposed of by the contractor in accordance with Local, State and Federal regulations.
END OF SECTION 01700
Specifications D-22 BassLakeRecSites_StormDamage_Specifications_071023_FINA
CLEARING AND DEMOLITION
SCOPE
This work shall consist of all site clearing and demolition required to complete the Project as shown on the plans, indicated in these specifications or as directed by the Forest Service. The work includes, but is not limited to; clearing and demolition of the broken asphalt sections and asphalt pulverizing and removal and disposal of any re-quired vegetation including merchantable timber, stumps, downed trees, and debris, and any other campground facilities. Inorganic material is the responsibility of the Con-tractor and shall be removed from Forest Service lands, in accordance with State and local regulations.
The Contractor and Forest Service shall identify in the field the locations of the existing items to be removed and disposed.
SALVAGE
Salvageable items, including, but not limited to picnic tables, fire rings, and barrier posts, shall be identified by the Forest Service and removed by the contractor and de-livered to designated Government land as directed by the Forest Service.
MEASUREMENT AND PAYMENT
Measurement and/or payment will be made as shown on the schedule of items under the titles:
• CLEARING AND DEMOLITION (includes clearing and demolition of the broken asphalt sections and removal of stumps, downed trees, and debris)
EXECUTION
VEGETATION CLEARING AND TREE REMOVAL
A. While every effort has been made to pre-determine and identify the trees that need to be removed, once site work commences, construction related activities may identify additional trees that need to be removed. These trees will require complete stump removal and will have a unique color/symbol-ogy identifier painted on them. The stumps shall be removed to a depth of 4 feet or to a depth required to remove all roots 1-1/2" diameter or larger.
Stump removal includes backfilling the hole back to existing grade.
B. While every effort has been made to pre-determine and identify the stumps that need to be removed, once site work commences, construction related activities may identify additional stumps that need to be removed. The stumps shall be removed to a depth of 4 feet or to a depth required to remove all roots 1-1/2" diameter or larger. Stump removal includes backfilling the hole back to existing grade.
Specifications D-23 BassLakeRecSites_StormDamage_Specifications_071023_FINA
C. In case that trees or stumps are required to be removed, all trees, stumps, and slash shall be removed off the project site and disposed of off National Forest lands in accordance with State and Local regulations and/or as di-rected by the Forest Service.
D. Remove all grass, weeds and natural vegetation, including trees less than 10” diameter, in designated areas to a minimum depth of 4”. Branches on remaining trees and shrubs shall be trimmed to give a clear height of 14 feet above roadbed. Tree limbs shall be trimmed as near flush with the trunk as practicable.
E. Soil Litter: Accumulations of vegetative materials lying on top of the min-eral soil (i.e. pine needles and duff) shall be removed.
F. All cut true fir or pine stumps greater than 15" diameter shall be treated with an EPA registered borax fungicide, such as Sporax for the prevention of the spread of annosum root disease. Sporax would be applied by hand in an approved granular form within one hour of stump creation. The fungicide shall not be applied when it is raining. All Forest Service policies and prac-tices and California regulations related to pesticide use would be followed including developing a spill plan for Sporax use.
DEMOLITION
This pay item on the schedule of items shall include any and all demolition listed below, as shown on the plans or directed by the Forest Service. This work shall be completed in accordance with State and local regulations.
AC PAVEMENT
Remove and recycle all pavement surface materials within the construction limits. The recycled AC pavement material may be used as either a base material or recycled and reused in the hot mix bituminous; however, the recycled AC pavement material must meet the criteria set forth in these specifications for each of these uses. Any aggregate material encountered under the existing pavement may remain and be incorporated into the base material before final grading.
UTILITIES
All below-grade utility services not designated to remain shall be disconnected, capped and plugged, and location noted on the AS-BUILT drawings.
All above-grade utilities not designated to remain shall be removed and disconnected, capped and plugged below grade to a depth of 2 feet or to the lateral connection, which-ever is less. The Contractor shall coordinate with the affected utility companies prior to starting work.
TRANSPORTATION
All materials designated to be salvaged shall be carefully removed. The materials shall be delivered to the location as directed by the Forest Service, and neatly stacked. The
Specifications D-24 BassLakeRecSites_StormDamage_Specifications_071023_FINA
Contractor shall coordinate the transportation and delivery of these materials with the Forest Service a minimum of 5 working days prior to the proposed moving date.
DISPOSAL
All demolition materials, not designated for salvage, shall be disposed of off National Forest lands, in accordance with State, local and federal regulations. Burning of re-moved materials will not be permitted on the project site.
END OF SECTION 2100
Specifications D-25 BassLakeRecSites_StormDamage_Specifications_071023_FINA
EARTHWORK
SCOPE
This work consists of all excavation, compaction, grading, trenching, fill, and backfilling for all parking areas, roadways, building pads, outdoor recreation access routes (ORARS) and miscellaneous site items.
PROTECTION
Furnish, install and maintain all supports, shoring and sheet piling required to support the sides of excavation and to protect adjacent work or existing improvements.
VERIFICATION OF CONDITIONS
The Contractor shall carefully examine existing conditions and information, shall become familiar with the nature and location of the work, the conformation of the ground, the nature of subsoil conditions, groundwater conditions, nature and extent of materials or existing im-provements to be encountered and any and all determinable matters that can affect the work, prior to beginning work.
MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work of this Section, all costs associated with the work, materials and full compliance of this section shall be included in other bid items and no separate payment shall be made therefore.
PRODUCTS
SITE BORROW MATERIAL
Imported borrow material shall be non-expansive and predominantly granular soil or soil rock mixture which is free from organic matter and other deleterious materials and rocks over 3 inches in diameter. Any borrow source location proposed to be used by the contractor will be designated by the contractor and reviewed and approved by the Forest Service in accordance with other sections of these Technical Specifications, see Section 1605
BACKFILL MATERIAL - STRUCTURES
A. General. All fill material shall be approved by the Forest Service. Exca-vated materials from the site may be used if approved. Imported fill shall be non-expansive and predominantly granular soil or soil-rock mixture which is free from organic matter and deleterious substances and which does not contain materials over two inches in greatest dimension. Material having a dimension greater than 1-1/2 inches shall not be used in the upper six inches of fill. Liquid limit shall not exceed 20; plasticity index in accordance with ASTM D4318; sieve analysis in accordance with ASTM C136.
B. Material for use behind retaining walls and exterior foundation walls as compacted backfill shall consist of approved sound, hard, durable, well-graded sands and gravels.
Specifications D-26 BassLakeRecSites_StormDamage_Specifications_071023_FINA
C. Material for use as building and foundation subgrade compacted backfill shall consist of approved well-graded, clean sands and gravels.
BACKFILL MATERIAL - TRENCHES
Trench Backfill Materials are designated ON THE DRAWINGS and shall be as fol-lows:
A. Native Backfill Materials: Excavated native material with all organic and 4 inch oversize material removed.
B. Select Native Backfill Material: Excavated native material with all organic and 2 inch oversize material removed.
C. Sand Bedding Material: Shall conform to the Table below:
SIEVE SIZE PERCENT PASSING
3/8 inch -
No. 4 100% No. 8 90 – 100%
No. 30 10 – 30% No. 200 2 – 9%
ROCK BASE FOR SLABS ON GRADE
Aggregate material shall be crushed stone or gravel free of organic matter and other deleterious materials. Material shall be graded as follows:
SIEVE SIZE PERCENT PASSING
1 inch 100%
3/4 inch 90-100% No. 4 0-10%
No.100 0-3%
VAPOR BARRIERS
Where vapor barrier is shown on the plans, it shall be 6 mil polyethylene sheeting.
EXECUTION
GENERAL
Contractor shall verify all actual site conditions, levels and grades prior to beginning work and inform the Forest Service as to any discrepancies that exist, prior to start of work.
EXCAVATION AND DISPOSAL
All excavations of every description and of whatever substances encountered shall be performed to the depth indicated on the drawings or staked on the ground. All materials shall be piled in an orderly manner a sufficient distance from the banks of an excavation
Specifications D-27 BassLakeRecSites_StormDamage_Specifications_071023_FINA to avoid overloading and to prevent slides or cave-ins. Any excess excavated material may be utilized in other work areas, provided it is suitable material. Sheeting and shor-ing should be used as is necessary for the protection of the work and for the safety of personnel. Excavations shall be by open cut. Whenever depth of excavation exceeds 5 feet, the surface shall be sloped back at a 1-1/2 to 1 slope or the excavation shall be shored, as per OSHA requirements.
SITE EXCAVATION
The existing surface materials shall be removed in accordance with Section 02100. All suitable excavated material remaining after the demolition is accomplished shall be used in the construction of subgrades, shoulders, slopes, bedding and backfill for trenches and structures and backfill of future landscape areas.
TRENCH EXCAVATION
A. Trenches shall be of the necessary width for properly laying utility lines.
Water line trenches shall be uniformly graded to avoid high points that would necessitate the placing of air valves in the water lines. Trenches shall be of a depth to provide the minimum cover over the utility line shown on the drawings.
B. All roots shall be cut and removed from trenches. Bottoms of trenches shall be accurately graded to an elevation 4 inches below the grade line of the proposed utility line. Care shall be taken not to over excavate. When unsta-ble material that is incapable of properly supporting the utility is encoun-tered in the bottom of the trench, such materials shall be excavated to a depth to allow for construction of a stable bedding. In all cases, where ex-cavation is made below the indicated trench depths, such over excavation shall be backfilled with compacted granular material.
EXCAVATION FOR FORMWORK AND STRUCTURES
A. Excavation for slabs on grade shall be sufficient to allow for rock base, va-por barrier, sand, and slab thickness AS SHOWN ON THE DRAWINGS and as otherwise required.
B. Forest Service will not make payment on excavations beyond indicated lim-its unless such excavations are authorized by the Forest Service in advance of doing the work. Over excavation shall be restored to specified elevations with compacted backfill approved by the Forest Service. Over excavation below footings shall be filled with concrete poured integrally with the foot-ing.
C. Excavated material not suitable for backfill shall be removed and disposed of off National Forest lands or as specified elsewhere herein.
Specifications D-28 BassLakeRecSites_StormDamage_Specifications_071023_FINA
D. All material to be excavated shall be unclassified and shall include earth fills, gravels, boulders, debris and any other materials encountered in exca-vation and grading operations. The Contractor shall remove all materials to the depth and extent indicated on the drawings or specified herein.
E. Unsuitable material not having the required bearing capacity AS SHOWN ON THE DRAWINGS or that has been disturbed or weakened by construc-tion activity shall be completely removed and replaced with compacted backfill material or concrete to the required levels. The unsuitable material removed shall be disposed of as directed by the Forest Service.
F. All roots shall be cut and removed from subbase of campsites and ORARS.
Bottoms of subbase of campsites and ORARS shall be accurately graded.
EXISTING UTILITY LINES
A. The Contractor’s attention is directed to the existence of pipe and other un-derground improvements which may or may not be shown on the drawings.
All reasonable precautions shall be taken to preserve and protect any such improvements. The Contractor shall be responsible for contacting Under-ground Service Alert (U.S.A.) 5 working days before excavating to locate utilities.
B. The Contractor shall be aware of the possible existence of underground util-ities and improvements which may be in place but not shown on the draw-ings. If such are encountered the Contractor shall notify the Forest Service immediately and take precautions to preserve and protect any such improve-ments until further instructions can be issued by the Forest Service.
C. Where existing utilities or improvements interfere with the work, they shall not be removed, relocated or otherwise disturbed unless authorized by the Forest Service.
CONTROL OF WATER
Whenever subsurface water is encountered or surface water can enter an excavation, the Contractor shall furnish, install and maintain, and operate all necessary machinery, appliances, and equipment to keep the excavation free of water until the placing of the bedding material, laying and joining of the utility line, installation of tanks or struc-tures, inspection and approval for backfill, is complete and all danger of flotation and other damages is removed.
SITE BACKFILL AND COMPACTION
Compact all subgrade areas to receive surfacing (asphalt concrete or concrete pads) to not less than 95 percent of AASHTO T-180, method C or D for a minimum depth of 2 feet below subgrade elevation. Areas identified for future landscaping shall be graded and wheel rolled.
Specifications D-29 BassLakeRecSites_StormDamage_Specifications_071023_FINA
A. The density of the material specified for compaction shall be determined during the progress of the work by AASHTO T-191 or T-205 or T-238.
Moisture of the fill material shall be determined by AASHTO T-217 or T- 239 or T-255. Adjustment for coarse particles will be made in accordance with of AASHTO T-224.
In areas where field density test results indicate less than the required degree of compaction, or in areas where previously accepted compaction has been disturbed, the backfill shall be replaced or reconditioned to obtain the re-quired results at no additional cost to the Forest Service.
Reference Section 02340 for compaction requirements for campsites and ORARS.
BACKFILL FOR UTILITY TRENCHES
Trenches shall be backfilled AS SHOWN ON THE PLANS. The Contractor must ob-tain approval from the Forest Service prior to backfilling. Backfilling will not be au-thorized until the trenching, pipe, and pipe joints are inspected and conform in every way to these specifications.
Care shall be taken in the backfilling of sewer and drainage…