3 Combined SpecsCBPEWI20260624.pdf
PDF 3 MB Posted
- Solicitation number
- 1240LT26Q0172
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Project Specifications package for the Mark Twain National Forest Council Bluff Primary Electric and Well Improvements project, issued by the USDA Forest Service in Rolla, Missouri, with a completion date of June 2026.
The project encompasses coordination with Ameren utility company to extend primary electric service approximately 12,700 feet to power a new well pump at the Wild Boar Ridge Campground in Iron County, Missouri (coordinates 37.724361°N, -90.940618°W). The work includes directional drilling along Missouri State Highway DD for approximately 9,600 feet, followed by trenching or directional drilling along an old road corridor for approximately 3,100 feet, with pull boxes placed every 500 feet. Tree removal along the corridor is restricted to November 1 through March 31 to protect Indiana bat and Northern long-eared bat hibernation. The contractor must obtain all permits, pay all fees, and provide complete labor, materials, and equipment for primary distribution system installation per Ameren specifications. The Ameren contact is Michael Swain (mswain@ameren.com, 573-438-8023). Additional work includes replacing the existing well pump, drop pipe, pitless adaptor, well cap, and connecting the well to the new electrical system. The contractor's electrician must design transformer sizing for specified future electrical needs including a new well house (200 AMP panel), 2 host campsites, 40 standard campsites with RV pedestals (50/30/20 AMP each), septic system with two 230V pumps, and the existing well pump. Contract duration is 120 calendar days with work preferred after July 4th. Utilities are available at Chapel Hill Beach (3 miles away) and the site will remain open to the public during construction, requiring contractor responsibility for safety signage and public access management.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MARK TWAIN NATIONAL FOREST
GAOA – COUNCIL BLUFF PRIMARY ELECTRIC
AND WELL IMPROVEMENTS
PROJECT SPECIFICATIONS
USDA – FOREST SERVICE
401 FAIRGROUNDS ROAD
ROLLA, MO 65401
06/2026
PAGE LEFT INTENTIONALLY BLANK
TABLE OF CONTENTS
DIVISION 1 – GENERAL REQUIREMENTS
011000 – SUMMARY
012700 – MEASUREMENT AND PAYMENT
012800 – MOBILIZATION
013100 – PROJECT MANAGEMENT AND COORDINATION
013250 – CONSTRUCTION PROGRESS SCHEDULE
013300 – SUBMITTAL PROCEDURES
014000 – QUALITY CONTROL
017700 – CLOSEOUT PROCEDURES
DIVISION 2 – SUPPLEMENTAL SPECIFICATIONS
221114 – WATER DISTRIBUTION
260010 – GENERAL TECHNICAL PROVISIONS
260050 – BASIC METHODS AND MATERIALS
260400 – UNDERGROUND POWER DISTRIBUTION
329200 – SEEDING AND MULCHING
APPENDIX A – WELL PUMP TEST AND RECOVERY DATA SHEET
APPENDIX B – EXISTING CONDITIONS PHOTOS
COUNCIL BLUFF PRIMARY ELECTRIC AND WELL IMPROVEMENTS
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Project Identification: Council Bluff Primary Electric and Well Improvements
1. Project Location: This project is located in Iron County Missouri in the Mark Twain National Forest, Potosi-Fredericktown Ranger District recreation site Council Bluff – Wild Boar Ridge Campground.
2. Wild Boar Ridge Campground:
Lat: 37.724361° Long: -90.940618°
B. Owner: Government or Owners refers to the USDA Forest Service
1. Owner’s Representative: The Federal Contracting Officer (CO) and his/her designated representative(S), as named in writing. Contractive Officer (CO) refers to the person assigned by the USDA Forest Service to administer the contract. Soon after Contract award, the Contracting Officer will designate a Contracting Officer’s Representative
(COR).
C. The Work consists of coordinating with Ameren to extend their existing primary electric line from an overhead power line located near Missouri State Highway DD to the Wild Boar Campground.
This includes coming off an existing electric pole on the east side of the highway and installing buried line along the edge of the cleared highway right-of-way to the existing well within the Council Bluff Recreation Area. The corridor will parallel the east side of Missouri State Highway DD for approximately 9,600 feet and then use an “old road corridor” along the top of Wild Boar Ridge leading to the well for approximately 3,100 feet.
The Contractor shall clear the old road corridor along the top of Wild Boar Ridge leading to the well as necessary to allow construction vehicle access. The existing old road corridor contains downed trees and minor brush. Any tree removal shall occur during the Indiana bat and Northern long-eared bat’s hibernation season (between November 1 and March 31).
A pull box will be placed at approximately every 500-ft along the buried cable. The electric line along Missouri State Highway DD shall be installed utilizing directional drilling methods.
The electric line along the old road corridor can be installed utilizing either directional drilling or trenching.
The Contractor shall coordinate with the Public Utility (PU) provider, Ameren, to obtain all permits, pay all fees, and provide all labor, materials and equipment to extend the primary distribution system which includes transformers, meter bases, metering, and service connection requirements. This includes all trenching, backfilling, boring, landscaping and other requirements for replacing and extending the primary distribution system necessary to meet project
SUMMARY 011000 - 2
requirements. Primary electric installation shall follow Ameren’s specifications (latest version) which can be found on their website (https://www.ameren.com/property/construction).
Ameren Contact Information:
Michael Swain mswain@ameren.com 573-438-8023
The work also includes replacing the existing water supply well’s pump, drop pipe, pitless adaptor, well cap, and other related appurtenances; connecting the existing well into the new electric system; and other work indicated in the Contract Documents.
D. The Contractor’s electrician shall provide plans for transformer sizing based on the following future needs:
Proposed future electrical needs include:
1. New well house building with a 200 AMP panel
2. 2 host campsites with 50/30/20 AMP RV pedestals
3. 40 campsites with 50/30/20 AMP RV pedestals
4. Septic system with 2 – 230V sewage pumps
5. Existing well with submersible pump
E. Work is preferred to occur after Independence Day (July 4th) weekend.
1.2 CONTRACTOR’S USE OF SITE AND PREMISES
A. The government will conduct a preconstruction survey with the Contractor to review and document the existing project conditions prior to construction.
B. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of the Project site beyond areas in which Work is indicated.
1. The Contractor is responsible for the security of the Contractor’s equipment and materials.
2. Schedule deliveries to minimize on-site storage of materials and equipment.
3. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or salvaged as Government property, shall become the property of the Contractor and shall be promptly removed from the site.
4. Utilities are available near the site for construction purposes. The Chapel Hill Beach area has electric, water, and sewer utilities. This is located approximately 3 miles from the Wild Boar Ridge Campground. The water service at Chapel Hill Beach is closed in September and reopened in April.
5. The site will be open to the public for use during construction. Care will be exercised to adhere to the schedule and to secure the Government facility after hours. The Contractor will be responsible for signing, limiting access, and safety of public and/or government employees in the area.
6. Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner’s employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
mailto:mswain@ameren.com
SUMMARY 011000 - 3
C. Staging and storage areas:
1. Areas for staging operations and storage of materials shall be approved by the COR. The Contractor must request in writing for approval from the COR to stage trailers on site.
1.3 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in all project areas to normal business working hours of 8 a.m.
to 5 p.m., Monday through Friday, unless otherwise indicated or approved by the COR.
1. No work is permitted without written authorization from the CO on Government Holidays or weekends.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner’s written permission before proceeding with utility interruptions.
D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner’s written permission before proceeding with disruptive operations.
E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Project site is not permitted. Use of any type of marijuana on federal property is illegal.
F. Site Cleanup: Before leaving the Site each day the Contractor shall secure equipment, tools, and materials; pickup and dispose of paper and other debris/construction waste. The Site shall be left in a safe and secure manner with the public protected from construction hazards.
G. Before leaving the Site on Fridays a more complete policing, pickup and securing of the Site shall be performed. The Site shall be left in a neat and orderly manner as determined by the COR with the public protected from construction related hazards.
1.4 INSPECTION OF THE WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of the work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, SUMMARY 011000 - 4 or for proceeding to successfully perform the work without additional expenses to the government.
1.5 SAFETY
A. Contractor shall comply with all State and Federal safety regulations during the performance of the work.
1.6 FIELD VERIFICATION
A. Contractor shall field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.7 DISPOSAL OF MATERIAL
A. Contractor shall remove and legally dispose of all debris offsite.
1.8 SPECIFICATION AND DRAWING CONVENTIONS
A. Division 1 – General Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.
B. Division 2 – Supplemental Specifications: Requirements in Division 02 apply to the Work of all Sections in the Specifications.
1.9 CONTRACT TIME
A. 120 Calendar Days
1.10 NOTICE TO PROCEED
A. Performance of the contract shall begin within ten (10) calendar days after receipt of the Notice to Proceed. The Notice to Proceed will be issued by the Contracting Officer (CO) at the pre-work conference.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011000
MEASUREMENT AND PAYMENT 012700 - 1
SECTION 012700 – MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes:
1. Measurement and payment criteria applicable to the work performed.
2. Administrative and procedural requirements necessary to prepare and process Applications for Payment.
3. Defect assessment and non-payment for rejected work.
4. General description of work included under each pay item.
B. Related Requirements:
1. Schedule of Items Form (SOI): The Contractor is required to complete the SOI Form, provided by the Government, as part of their Proposal or Bid.
2. Invoice Processing Platform (IPP) System: All invoices are to be submitted via the electronic IPP System. The Contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in communications from USDA and Treasury. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Ensure your company has registered at https://www.ipp.gov/vendors/enrollmentvendors.htm to establish your account. Offeror must have an established account prior to commencement of work.
3. Certified Payrolls: Certified payrolls for construction work must be submitted to the CO/COR for review at regular intervals as work progresses. At least one week prior to Contractor requesting payment via IPP, all certified payrolls related to the subject pay request work must have been received by the CO/COR. Incomplete or inaccurate payroll submittal will result in rejection of the IPP invoice. Contractor and all subcontractors, through the contractor, shall furnish all certified payrolls covering payments to laborers and mechanics for on-site work. Payroll hourly rates and fringe benefits must be in accordance with the established Wage Determination for the project.
1.2 AUTHORITY
A. The Contracting Officer’s Representative (COR) will take all measurements and compute quantities accordingly.
https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollmentvendors.htm
MEASUREMENT AND PAYMENT 012700 - 2
1.3 MEAUREMENT OF QUANTITIES
A. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the Contract, including all necessary materials, equipment, and labor to complete the job. They will not be measured.
1.4 PAYMENT
A. Pay Request Documentation from Contractor: Contractor must submit the following documentation to the CO/COR for review and approval at least seven (7) days prior to requesting a payment via IPP.
1. All Certified Payroll forms from the general Contractor (including payroll from all subcontractors) for work covered by the pay request.
2. A completed draft Schedule of Items (SOI) Form for work covered by the pay request, indicating the percent complete for each line item in the SOI.
3. Written Quality Control testing results if applicable to items in the payment request.
B. Payment Includes: Full compensation for all required labor, products, tools, equipment, plant, transportation, services, and incidentals; erection, application, or installation of an item of the Work; overhead and profit.
1. “Incidentals” are to be considered as an additional obligation to the other work required for the item(s). Incidental work is not payable directly but is to be considered included in the contract price for the item(s) of work specified.
2. All work not specifically identified as a separate bid item is “Incidental”.
C. The accepted quantities will be paid for at the contract unit price for each item as shown in the Schedule of Items.
D. Payment will not be made for any of the following:
1. Products or construction placed beyond the lines and levels of the required work.
2. Products or construction determined as unacceptable before or after placement.
3. Products wasted or disposed of in a manner that is not acceptable.
4. Products remaining on hand after completion of the Work.
5. Loading, hauling, and disposing of rejected products.
MEASUREMENT AND PAYMENT 012700 - 3
PART 2 - PRODUCTS (NOT USED)
END OF SECTION 012700
MEASUREMENT AND PAYMENT 012700 - 4
MOBILIZATION 012800 - 1
SECTION 012800 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment premiums for bonds and insurance for the project, any required permits to complete the work, and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. Method of Measurement will be by Lump Sum Quantity (LSQ).
B. The maximum Mobilization bid price shall not exceed fifteen percent (15%) of the total base bid contract price or optional bid contract price (not including Mobilization).
C. Progress Payments for Mobilization will be in accordance with the following schedule:
1. The cost of premiums paid for performance and payment bonds are considered incidental to Mobilization and will not be paid for separately. Payment for bond premiums will be in accordance with FAR Clause 52.232-5, Payments under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
PART 2 - PRODUCTS (NOT USED)
END OF SECTION 012800
MOBILIZATION 012800 - 2
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 – PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain administrative procedures for managing and coordinating construction operations.
1.2 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations to provide an efficient and orderly installation of each part of the Work.
1.3 SPILL AND EROSION CONTROL
A. Spill and Erosion Control Plans: At a minimum, the Contractor shall install erosion control devices as indicated on the plans. The Contractor shall install additional erosion control features to prevent sediment from entering wetlands or waters of the United States and to provide for containment of hazardous materials and unplanned spills in accordance with all applicable federal, state, and local laws.
1.4 ADMINISTRATIVE AND SUPERVISORY PERSONNEL
A. In accordance with FAR 52.236-6, at all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent supervisor who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
B. In addition to meeting the requirements of FAR 52.236-6 for an on-site Project Superintendent, the Contractor shall provide other administrative and supervisory personnel as required for the performance of the Work.
1.5 CONFERENCES AND MEETINGS
A. Pre-construction Conference: The Contracting Officer or Contracting Officer’s Representative will schedule a pre-construction conference before starting construction at a time and place agreeable and convenient to both the Contractor and the Government and will review responsibilities and personnel assignments in accordance with FAR 52.236-26.
1.6 SUBMITTALS
A. Staff Names: Within 5 calendar days after Notice to Proceed, submit a list of principal staff assignments including the Superintendent and other primary personnel. Identify individuals by
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
name, duties and responsibilities, and business/cell telephone numbers. Post copies of this list in the temporary field office (if present).
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
B. Construction in Progress: Keep construction in progress, adjoining materials in place, and clean during handling and installation. Apply protective enclosures or coverings for protection from damage or deterioration.
C. Completed Construction: Clean completed construction and provide maintenance to prevent damage, soiling, or other deterioration through the remainder of the construction period. Adjust and lubricate operable components to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging, or otherwise deleterious conditions during the construction period.
END OF SECTION 013100
CONSTRUCTION PROGRESS SCHEDULE 013250 - 1
SECTION 013250 – CONSTRUCTION PROGRESS SCHEDULE
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Preliminary Schedule
1.2 SUBMITTALS
A. Submit a comprehensive, fully developed schedule within 10 days of Notice to Proceed date.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 CONTENT
A. Preparation: Indicate each significant construction activity and the location on the site separately.
Identify first workday of each week.
B. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.
C. Identify each item by specification section number.
D. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each week.
E. Contractor to revise schedule if Work is more than one week behind schedule.
END OF SECTION 013250
CONSTRUCTION PROGRESS SCHEDULE 013250 - 2
SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 – SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section and FAR 52.236-21 include requirements for Shop Drawings, as defined by FAR 52.236-21 and Designs. Shop drawings and Designs may include drawings, specifications, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance, and test data furnished by the Contractor to explain in detail specific portions of the work required by the Contract.
B. This section includes requirements for Samples. Samples may include mailed samples, field samples or mock-ups of full-size physical examples erected on-site or elsewhere.
C. This section includes requirements for Product Data. Product Data includes manufacturer's standard catalogs, manuals, pamphlets and other printed materials, and includes but is not limited to the following: product specifications and installation instructions, color charts and catalog cuts, rough-in diagrams and templates, wiring diagrams, performance curves, operational range diagrams, mill reports, test reports, shop drawings and code approvals.
D. This section includes other quality assurance submittals such as certifications of compliance or conformance, manufacturer's instructions and field reports, and mix designs.
1.2 GENERAL SUBMITTAL REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities and with the schedule.
1. Allow 15 calendar days each for submittal review, corrections following the initial review and re-submittal review before activities scheduled after the submittal approval.
2. Incomplete submittals will be returned to the Contractor with no further review. Delays due to incomplete or rejected submittals will not be excused and no compensation in the form of monetary or time will be provided to the Contractor.
3. When the Contractor desires to submit for approval a product for an “approved equal”, the Contractor MUST provide documentation of the original specified product and the Contractor proposed product in a side-by-side comparison, such as a table, which clearly demonstrates the Contractor proposed product meets or exceeds the originally specified product. If this product comparison is not done the first time it is submitted, the proposed product will be rejected, and the Contractor will be required to provide the specified product. The Government is not obligated to review a re-submittal for a rejected product.
SUBMITTAL PROCEDURES 013300 - 2
4. Submittal Transmittal: Transmit each submittal from the Contractor to the Government by use of one transmittal form per submittal. Transmittal format to be approved by COR and shall include the following information on the transmittal form.
a. Project name and Forest Service contract number.
b. Date.
c. Name, address and telephone number of firm or entity that prepared the submittal.
d. Names of subcontractor, manufacturer, supplier, etc. as applicable.
e. Category and description of submittal.
f. Section of Specifications or Drawing sheet number the Submittal is representing.
g. Certification by Contractor stating that submittal complies with the Contract, or statement of deviations from the requirements of the Contract.
h. Signature of transmitter.
i. Space to record Contractor's review and approval markings, and for Government response.
B. Submit electronic copies of each submittal to the COR for review unless otherwise stated.
1.3 SHOP DRAWINGS AND DESIGNS
A. Submit originally prepared information, drawn accurately to scale.
B. Submittals: Submit three blue-line or black-line prints of each drawing submittal. One print will be marked with action taken and returned. Distribution: When submittal is approved, the Contractor shall prepare and submit three final copies.
C. Shop drawings shall be done in AutoCAD format. Upon final approval the drawings shall be sent on a thumb drive or via email to the COR.
D. Specifications shall be done in Microsoft Word format and a copy sent on a thumb drive or via email to the COR.
1.4 PRODUCT DATA
A. Collect Product Data into a single submittal for each system or element of construction. Mark each copy to show specific product choices and options applicable to the project. Product Data shall include the following information, where applicable:
1. Manufacturer's printed recommendations.
2. Compliance with recognized trade association standards.
SUBMITTAL PROCEDURES 013300 - 3
3. Compliance with recognized testing standards.
4. Applicability of testing agency labels and seals.
5. Notation of dimensions verified for fit by field measurements.
6. Notation of coordination requirements.
B. Preliminary Submittal: Prior to submittal of complete Product Data, submit a preliminary single copy of that part of Product Data when selection of options is required, such as for color charts.
Preliminary submittal will be returned, with selection noted, for the Contractor's use in subsequent submittals.
C. Submittals: Unless otherwise indicated, submit 3 copies of each Product Data submittal. Two copies will be retained, and the remaining copy will be marked with action taken and returned.
The COR may allow electronic copies to be transmitted in lieu of hard copies.
D. Material and Product substitution shall be in accordance with FAR 52.211-6 and Section 013300-
1.2. A.3.
1.5 SAMPLES
A. Submit full-size, fully fabricated samples, cured and finished in the manner specified. Samples shall be physically identical to the material or product proposed for use.
B. Preliminary Submittal: Where color, pattern, texture or similar characteristics are to be selected from a manufacturer's range of standard choices, submit a preliminary single set sample of available choices when required by the CO.
1.6 OTHER QUALITY ASSURANCE SUBMITTALS
A. Submit other quality assurance submittals in compliance with requirements in the individual specification sections.
1.7 REVIEW ACTION ON SUBMITTALS
A. Except for submittals for the record or for information or for another purpose where no action and return is required, the Government will review submittals and mark returned copies to indicate action taken within a maximum time period of 15 calendar days.
B. Submittals that do not contain an appropriate marking of approval by the Government shall not be used for construction.
SUBMITTAL PROCEDURES 013300 - 4
PART 2 - PRODUCTS (NOT USED)
END OF SECTION 013300
QUALITY CONTROL 014000 - 1
SECTION 014000 – QUALITY CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. This section, FAR 52.246-1 Contractor Inspection Requirements and FAR 52.246-12 Inspection of Construction, include requirements for Contractor quality control services used to verify quality assurance requirements specified elsewhere in the Contract.
B. The Government reserves the right to conduct independent tests.
C. This section includes requirements for quality control services such as piping pressure tests, water sampling, concrete mix and strength testing, and bedding and sand gradation tests (this is not an all-inclusive list of tests that may be required) per State of Missouri Agency Requirements – MO DOT and MO DNR– as they apply to the work being performed.
D. The quality control services include tests and related actions, including reports, performed by the Contractor, independent testing agencies or governing authorities.
1.2 QUALIFICATIONS OF INDEPENDENT TESTING AGENCIES
A. A qualified independent testing Agency shall be an accredited entity engaged to perform tests or inspections, and to report on and, if required, to interpret results of those tests or inspections.
1.3 SUBMITTALS
A. REPORTS: The Contractor shall submit a certified written report, in duplicate (or electronic format), of each test, inspection or other quality control service to the Government.
B. Written reports shall include but not be limited to the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making the test or inspection.
6. Designation of the work and test method.
7. Identifications of product and specification section.
8. Complete test or inspection data.
QUALITY CONTROL 014000 - 2
9. Test results and an interpretation of test results.
10. Ambient conditions at the time of sample taking and testing.
11. Comments or professional opinion on whether tested or inspected Work complies with Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting.
1.4 MEASUREMENT AND PAYMENT
A. Method of Measurement will be by Lump Sump Quantity (LSQ).
B. Payment will be full compensation for work prescribed in this Section. Payment of lump sum pay items will be prorated based on the progress of the work under this Section.
C. Progress Payments and Final Payment for Quality Control will be in accordance with FAR 52.232-5 Payments under Fixed-Price Construction Contracts. The Government shall make progress payments monthly as the work proceeds on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
1.5 RESPONSIBILITIES
A. Contractor Responsibilities: The Contractor shall provide for tests, inspections and other quality control services (such as well water, electrical, etc. tests and inspections) where specified in the Contract or when required by authorities having jurisdiction such as the State of Missouri Agencies—MODOT and MODNR. Costs for these services are included in the Contract price.
The Contractor shall maintain complete inspection records and make them available to the Government.
B. The Contractor shall employ and pay for a qualified independent testing agency (Agency) to perform the quality control services.
C. Associated Services: The Contractor shall cooperate with others performing required tests, inspections and other quality control services, shall provide access to the work, and shall furnish incidental labor and facilities necessary to facilitate inspections and tests.
PART 2 - PRODUCTS (NOT USED)
END OF SECTION 014000
CLOSEOUT PROCEDURES 017700 - 1
SECTION 017700 – CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for Phased Project completion and Final Contract closeout, including, but not limited to, the following: The Government reserves the right to conduct independent tests.
1. Systems Commissioning including Demonstration and Training.
2. Record Documents including Record Drawings and Product Data.
3. Substantial and Final completion procedures.
4. Final cleaning.
1.2 DEFINITIONS
A. Substantial Completion - The point at which the project, or a major phase of the project, is complete such that it can be safely and effectively used by the public without further delays, disruption, or other impediments.
B. Final Completion – The point at which the project is 100% complete, accepted by the Government and ready for final payment.
1.3 RECORD DOCUMENT SUBMITTALS
A. Record Drawings (a.k.a. as-built drawings):
1. Maintain a clean, undamaged set of blue or black line prints of Contract Drawings and
Shop Drawings. Mark the set to show the actual installation where the installation varies from the Work as originally shown. Mark all drawings that are affected by the variation(s) fully and accurately. Where Shop Drawings are used, record a cross-reference at the corresponding location on the Contract Drawings. Give particular attention to concealed and buried elements that would be difficult to measure and record at a later date.
B. Record Product Data: Maintain one copy of each Product Data submittal. Note related Change Orders and markup of Record Drawings and Specifications.
1. Mark these documents to show significant variations in actual Work performed in comparison with information submitted. Include variations in products delivered to the site and from the manufacturer’s installation instructions and recommendations.
2. Give particular attention to concealed products and portions of the Work that cannot otherwise be readily determined later by direct observation.
CLOSEOUT PROCEDURES 017700 - 2
1.4 FINAL ACCEPTANCE PROCEDURES
A. Submittals Prior to Final Completion Inspection and Final Acceptance: Submit the following a minimum of 10 days before scheduling a final inspection for determining Final Completion and Acceptance:
1. Submit a final Schedule of Items (SOI) form to reflect the final payment values in accordance with Section 012700 "Measurement and Payment."
2. Submit all remaining Certified Payrolls for the project not previously submitted.
3. Submit completed, signed Contract Release form.
4. Submit a signed copy of the Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Government CO/COR. Certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
5. Submit all remaining specific warranties, workmanship bonds, maintenance agreements, final certifications and similar documents not previously submitted.
6. Submit all remaining record documents and similar final record information not previously submitted.
7. Deliver tools, spare parts, extra stock and similar items not previously delivered.
8. Complete final clean-up requirements including touch-up painting of marred surfaces, adjustments, lubrication, etc.
B. Final Inspection Procedure: The Government will inspect the Work upon receipt of notice from the Contractor that the Work, including punch list items from earlier inspections, has been completed.
1. Upon completion of inspection, the CO will notify the Contractor of Final Acceptance and Final Payment or will advise the Contractor of Work that it is incomplete or of obligations that have not been fulfilled and are required for Final Acceptance.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 FINAL CLEANING
A. Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage or septic systems.
1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project:
CLOSEOUT PROCEDURES 017700 - 3
a. Clean Project site of rubbish, waste material, litter, and other foreign substances.
b. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.
c. Remove labels that are not permanent.
d. Leave Project clean and ready for occupancy.
B. Construction Waste Disposal: Comply with waste-disposal requirements in all applicable specification sections and contract clauses. Remove waste materials from the site and dispose of it lawfully.
END OF SECTION 017700
CLOSEOUT PROCEDURES 017700 - 4
WATER DISTRIBUTION 221114 - 1
SECTION 221114 – WATER SERVICE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes water-distribution piping and specialties for water services including, but not limited to, water lines, well pumps, and disinfection.
1.2 DEFINITIONS
A. Water Service: Exterior domestic-water piping.
B. The following are industry abbreviations for piping materials:
1. PVC: Poly Vinyl Chloride pipe
2. GS or GIP: Galvanized steel or Galvanized Iron Pipe – used interchangeably.
C. Pump Testing includes well pump testing, pump test reporting, and chlorination.
D. Missouri Department of Natural Resources Division of Environmental Quality “Standards for Noncommunity Public Water Supplies, 1982” is the same as “Standards”.
1.3 SUBMITTALS
A. Product Data: For all piping specialties to include, but not limited to, all valves, transition fittings, GIP pipe and fittings and any other item used in the construction of the water distribution system.
B. Pump Test data written results
C. Pump operation and maintenance manual and pump curve
D. Water Sample written results clearly stating MCL for each contaminant, corresponding test result with units and clearly stating if the contaminant exceeds the MCL.
E. Proof of Laboratory’s current EPA certification for PFAS analysis
F. Licenses:
1. Provide a copy of current Missouri Well Driller License.
2. Provide a copy of current Missouri Electrician License.
1.4 QUALITY ASSURANCE
A. Regulatory Requirements:
WATER DISTRIBUTION 221114 - 2
1. Comply with standards of authorities having jurisdiction for potable-water-service piping, including materials, installation, testing, and disinfection.
2. Piping materials shall bear label, stamp, or other markings of specified testing agency.
3. Comply with NSF 61 for materials for water-service piping and specialties for domestic water.
4. Comply with lead free requirements for all potable water fixtures as per Section 1417 of the Safe Drinking Water Act.
5. AWWA Compliance: Comply with AWWA A100 for water supply wells.
6. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.
PART 2 - PRODUCTS
2.1 WELL PUMP, CAP, PITLESS ADAPTOR, DROP PIPE, CHECK VALVES, TORQUE
ARRESTORS
A. The submersible well pump and controls shall be capable of delivering 15 gallons per minute at 680 feet of total dynamic head. Pump shall be at least a 5HP stainless steel shell and motor, single-phase, 230-volt, with check valve. Pump HP may need to be adjusted after test pumping.
1. Goulds e-GS High Capacity Series 45GS75 or approved equal.
2. The existing well pump is assumed to be a Burke Series SN-34C Hydro-Sub 5 HP 230V.
B. Drop pipe shall be 1.5” diameter, Galvanized steel, Schedule 40, pipe shall be in accordance with ASTM A53 Grade B and have threaded and coupled fittings in accordance with ANSI B16.1.
Pipe shall be NSF 61 approved and rated not less than 200 psig.
C. Provide compatible galvanized reducers as required at connections to pump and pitless adapter.
D. Check valves shall be of the same size as the drop pipe and placed every 200’ with one being just above the pump. Check valve body shall be lead-free bronze or brass, with stainless steel spring material and be NSF-61 approved. Valves must be rated to at least 200 psi water pressure and designed for either horizontal or vertical orientation. Valve body must be rated to handle the weight of the pump and drop pipe assembly, water column and pressure.
E. Torque Arrestors shall be flexible molded rubber adjustable torque arrestors that adjusts to fit 4” to 8” diameter well casings, placed at each check valve location. Each torque arrestor shall include 2 each stainless-steel hose clamps to secure the torque arrestor to the drop pipe. Torque arrestors are to also act as well-centralizers.
F. Well cap shall meet State of Missouri requirements but must be at least a metal sanitary cap that fits over the top of the casing forming a waterproof and vermin seal with threaded hole for electrical PVC conduit. Well cap shall have an integral vent screen. The vent shall terminate in a downturned position, at or above the top of the casing or pitless unit in a minimum 1 ½ inch
WATER DISTRIBUTION 221114 - 3
diameter opening covered with a 24 mesh, corrosion resistant screen. The pipe connecting the casing to the vent shall be of adequate size to provide rapid venting of the casing. There shall be no other openings in the well cap. The well cap shall be lockable, Baker-Monitor well cap part number 6WTCL or approved equal.
G. Pitless adapter shall be a weld on type or approved equal, State of Missouri approved, with minimum 3.5’ bury depth.
2.2 JOINING MATERIALS
A. Transition Couplings:
1. Underground Piping, NPS 2.5” and Smaller: Manufactured fitting or coupling same size as, with pressure rating at least equal to and ends compatible with, piping to be joined.
B. Pipe thread compound shall be Blue Magic Industrial Grade or approved equal. It shall be NDF 61 approved for potable water, grit free, lead free and non-hardening once applied to the pipe threads.
PART 3 - EXECUTION
3.1 FIELD QUALITY CONTROL
A. Performance Testing: Conduct final pumping tests after new well pump, drop pipe, and appurtenances have been installed. Test pump the existing well as per Missouri Department of Natural Resources requirements and record on FS provided form (modify as needed for time of pumping/recharge).
1. Provide discharge piping to conduct water to locations where disposal will not create a nuisance or endanger adjacent property.
2. Measure elevation to water level in well.
3. Test Pump: Variable capacity test pump with capacity equal to maximum expected yields at pressure equal to drawdown in wells, plus losses in pump columns and discharge pipes.
4. Start and adjust test pumps and equipment to required pumping rates.
5. Record readings of water levels in wells and pumping rates as per the FS provided form
Well Pump Test and Recovery Data Sheet.
6. Record well recovery water levels in well as per the FS provided Well Pump and Recovery
Data Sheet until the static water level has become stable.
7. Remove sand, stones, and other foreign materials that may become deposited in wells after completing final tests.
B. Water Analysis Testing: Make bacteriological, physical, and chemical analyses of water from the well and report the results. Samples of water shall be collected in laboratory provided sample bottles and tested by a State of Missouri certified laboratory for the following constituents:
1. Antimony
2. Arsenic
3. Aluminum
4. Asbestos
5. Barium
WATER DISTRIBUTION 221114 - 4
6. Beryllium
7. Cadmium
8. Chloride
9. Chromium
10. Copper
11. Corrosivity
12. Cyanide
13. Fluoride
14. Foaming agents
15. Iron
16. Lead
17. Manganese
18. Mercury
19. Nitrate
20. Nitrite
21. Odor (Threshold Number)
22. Per- and Polyfluoroalkyl Substances (PFAS)
a. Must submit proof of Lab’s current EPA certification for PFAS analysis
b. Analyze sample using a US EPA approved analytical method (EPA Methods 533 or
537.1)
23. pH
24. Selenium
25. Silver
26. Sulfate
27. Thallium
28. Total Coliform (2 tests, at least 24 hours apart)
29. Total Dissolved Solids
30. Turbidity
31. Water Temperature (at the site)
32. Zinc
3.2 CLEANING
A. Disinfect water supply wells according to AWWA A100 and AWWA C654 before testing well pumps.
3.3 PROTECTION
A. Water quality protection: Prevent well contamination, including undesirable physical and chemical characteristics.
B. Provide casings, seals, sterilizing agents, and other materials to eliminate contamination; shut off contaminated water.
3.4 PIPING APPLICATIONS
A. Do not use flanges, unions, or keyed couplings for underground piping.
WATER DISTRIBUTION 221114 - 5
3.5 JOINT CONSTRUCTION
A. Make pipe joints according to the following:
1. Dissimilar Materials Piping Joints: Use adapters compatible with both piping materials, with OD, and with system working pressure.
2. Galvanized Iron Pipe: Use proper thread compound.
END OF SECTION 221114
WATER DISTRIBUTION 221114 - 6
GENERAL TECHNICAL PROVISIONS 260010 - 1
SECTION 260010 – GENERAL TECHNICAL PROVISIONS
PART 1 - GENERAL
1.1 DESCRIPTION OF THE PROJECT
A. Furnish all labor and materials necessary for the installation, connection, testing, and adjustment of all electrical equipment specified herein, shown, or notes on the drawings, specified or required in other portions of this specification and delivered to the Government as a complete installation in all respects ready for use.
B. Coordinate all sections of Division 26, within the division and with all other divisions. All general technical provisions apply to all sections of Division 26.
1.2 PROJECT SCOPE FOR ELECTRICAL WORK
A. The contractor shall coordinate with the Public Utility (PU) provider, Ameren, to pay all fees and provide all labor, materials and equipment to extend their primary distribution system which includes transformers, meter bases, metering, and service connection requirements. This includes all trenching, backfilling, boring, landscaping and other requirements for replacing and extending the primary distribution system necessary to meet project requirements.
B. It is the Contractor's responsibility to perform all coordination to determine Ameren’s requirements at the time of bidding and include all costs within the contract amount. The Contractor shall provide the COR with copies of all permit applications and other requirements provided by the utility company for review.
C. The Contractor shall provide and install the electrical system as shown on the drawings and indicated in the specifications.
D. The electrical drawings are schematic in nature and not intended to show exact routing, or all equipment, devices, connections, and materials that is required. The Contractor is required to provide all additional equipment, materials, and labor necessary to complete the electrical system and make it fully operational in accordance with the Contract and National Electric Code (NFPA
70) latest edition.
E. Transformer, meter/panel locations, and feeder corridors shall be staked in the field and reviewed and approved by the COR prior to the start of any electrical work.
1.3 REFERENCES
A. 013300 – Submittal Procedures
B. 260050 – Basical Materials and Methods
C. 260400 – Underground Power Distribution
GENERAL TECHNICAL PROVISIONS 260010 - 2
1.4 QUALITY ASSURANCE
A. Codes and Standards: All materials shall conform to the applicable current standards (standard rules, regulations and specifications), Institute of Electrical and Electronic Engineers (IEEE), Insulated Power Cable Engineers Association (IPCEA), NFPA-70 National Electric Code (NEC).
All materials shall bear the label of, or be listed by, the Underwriter’s Laboratory, Inc., (U.L.).
Where conflicts exist between any of the above standards, the standard which is the most stringent shall take precedence.
B. Errors and Omissions: Any errors found in the plans or specifications shall be brought to the attention of the COR. Contractor is responsible for execution of all work to meet applicable codes.
Discovery of errors does not relieve contractor from responsibility to perform all work to meet standards and codes.
C. Resolve all conflicts with applicable regulations. Prepare and submit to the CO all additional clarifying details including substitute methods and materials as needed to secure the required approval and resolve conflicts.
D. All work shall be done by electricians licensed by the State of Missouri.
1.5 DRAWINGS
A. For clarity and legibility, the electrical plan is a broad schematic representation of the overall electrical system. The size and location of equipment is approximate. Make use of all the data in the contract documents and verify information against actual field conditions. Install materials and equipment to conform to the available space. Maintain required clearances and satisfy the requirements of the governing codes.
B. Electrical drawings and layout may not necessarily suit the requirements of a particular manufacturer’s equipment. Modify wiring and location, provide additional materials and work as required for proper installation in accordance with NEC or manufacturer's instructions.
C. Submit proposed deviations to COR for approval and note change(s) on record drawings prior to making such modification.
1.6 SUBMITTALS
A. Submit under provisions of Section 013300 – Submittals.
1.7 DELIVERY AND STORAGE
A. Deliver and store materials in original containers, protected from the elements and theft, and accessible for inspection.
B. Store items subject to moisture in a dry, heated place.
C. Protect material against dirt, water, chemical, or mechanical injury.
GENERAL TECHNICAL PROVISIONS 260010 - 3
1.8 EXCAVATION AND BACKFILL
A. Typical underground utility electrical details for the secondary power system are shown on the drawings. For the primary distribution system follow utility provider’s requirements.
1.9 INSPECTION AND TESTS
A. At the pre-final inspection, conduct tests to determine that a complete workable electrical system has been installed conforming to the drawings, applicable codes, and specifications.
PART 2 - PRODUCTS
2.1 GENERAL
A. See Section: 260050 Basic Materials and Methods and 260400 Underground Power Distribution
B. Provide all products show complete with accessories and mounting materials.
2.2 COMMON MANUFACTURER
A. Provide all materials of the same type from one manufacturer for all products used on the project.
Example: Do not supply power panels from multiple manufacturers.
PART 3 - EXECUTION
3.1 GENERAL
A. Follow manufacturer’s directions in delivery, storage, protection and installation of equipment and materials. Obtain submittal approval prior to installation of materials or equipment.
B. Notify COR of any conflicts between manufacturer’s instructions and contract documents.
3.2 WIRING METHODS
A. Underground conduit is 3” Schedule 40 PVC or equivalent HDPE unless noted otherwise.
B. Install equipment and materials, align, level and adjust for satisfactory operation. Install equipment so that all parts are easily accessible for inspection, operation, and maintenance and repair.
C. Structural Openings: Obtain written permission of the COR before cutting or piercing structural members. Install sleeves to accommodate the penetration. All openings in structure made by parts piercing waterproofing shall be sealed and made watertight.
GENERAL TECHNICAL PROVISIONS 260010 - 4
D. Sealing: Seal equipment raceways, boxes, etc., exiting through structures exposed to the weather and make watertight and insect-proof. Protect equipment outlets and conduit openings at all times that work is not in progress; utilize temporary plastic plugs or caps designed for the purpose All penetrations through fire rated walls and floors shall be fire sealed with UL listed fire rated material.
E. Required Clearances: Comply with NEC Part 110-26. No grounded equipment will be allowed in this clearance space.
F. Mounting Heights: Conform to the following mounting height requirements unless otherwise indicated on the drawings by detail or by dimension shown. Mounting heights indicate for pendant mounted devices are to the bottom of the device’ mounting heights indicated for outlets and similar devices are to the center of the box unless otherwise indicated.
DEVICE MOUNTING HEIGHT
Toggle switches and push-button stations 48-inches…
This is the start of the file's text. The full file is on GovTribe.