3-b. Dwight ES Macro Schedule Master 2026 0107.pdf
PDF 113 KB Posted
- Solicitation number
- 2026-49
- Issued by
- Fairfield County, Connecticut
About this file
This file is a project schedule for the Town of Fairfield, Connecticut, on behalf of Fairfield Public Schools, documenting the timeline for construction management services associated with the design and construction of a new Dwight Elementary School with Early Childhood Center located at 1600 Redding Road, Fairfield, Connecticut. The schedule outlines a comprehensive project timeline spanning from 2025 through 2030, including multiple phases: PMO selection, architect/designer selection through an RFQ/P process with Board of Selectmen approval, design phases (Schematic Design, Design Development, and Construction Documents) each with estimate and review periods, code review and OGA plan completion review, local permitting processes, general contractor pre-qualification and construction manager selection via request for proposals, bidding and GMP award processes, and construction activities including new building construction, demolition and abatement, substantial completion, move activities, FF&E design and procurement, and project closeout. The design phase is allocated 17 months with Schematic Design lasting 3 months, Design Development 4 months, and Construction Documents 3.5 months. Construction is scheduled for 16.5 months with a separate 5-month demolition and abatement phase. A pre-proposal virtual site visit is scheduled for March 13, 2026, with qualifications due March 26, 2026, shortlist announcement on April 7, 2026, RFP issuance on April 8, 2026, proposals due April 20, 2026, interviews on April 21, 2026, and CMR selection immediately following interviews.
The schedule reflects a comprehensive capital project managed by Colliers Project Leaders as of January 7, 2026, with sequential phases designed to ensure coordinated planning and execution. The document does not contain specific pricing information, funding sources, or financial terms within the schedule itself, as it functions primarily as a master timeline document for project phasing and milestone tracking. The project encompasses full design development, permitting approval processes including conservation and planning reviews, FF&E/IT design and installation phases, and occupancy activities, indicating a complex, multi-year construction and implementation effort.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SCHEDULE
Town of Fairfield
Dwight Elementary School with ECC Schedule per CPL Experience
TIMELINE DESCRIPTIONS 2025 2026 2027 2028 2029 2030
Date: January 7, 2026 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
PMO Selection
Architect / Designer Selection
RFQ/P Process and Selection
BOS Approval
Design Phase
Schematic Design Phase
Schematic Design Estimate & Review
Design Development Phase
Design Development Estimate & Review
Construction Document Phase
Construction Document Estimate & Review
Code Review (30 days)
OGA Plan Completion Review
Approval to Bid by OGA
Local Permitting
Permit Approvals (Conservation/Planning)
GC Pre-Qualification / CM Selection
Request for Proposals
Shortlist and Interview Firms
Selection/Award
Bidding / GMP
Bid Period
Scope Reviews / GMP Award
BOS Approval
Construction
New Building Construction
Demolition / Abatement/Site Restoration
Substantial Completion
Move Activity
FF&E Process
FF&E/IT Design
FF&E/IT OGA Approval
FF&E/IT Procurement
FF&E/IT Installation
Occupancy
Closeout Phase
SD - 3 MONTHS
DESIGN PHASE (17 months)
DD - 4.0 MONTHS
CD - 3.5 MONTHS
BIDDING
CONSTRUCTION (16.5 months)
DEMO (5 months)
FF&E DESIGN
INSTALL
Current Status
Colliers Project Leaders Page 1 of 1 1/7/2026
Dwight ES Macro Schedule Master