3-b. Dwight ES Macro Schedule Master 2026 0107.pdf

PDF 113 KB Posted

Attached to
Construction Management Services - Dwight Elementary School with Early Childhood Center
Solicitation number
2026-49
Issued by
Fairfield County, Connecticut

About this file

This file is a project schedule for the Town of Fairfield, Connecticut, on behalf of Fairfield Public Schools, documenting the timeline for construction management services associated with the design and construction of a new Dwight Elementary School with Early Childhood Center located at 1600 Redding Road, Fairfield, Connecticut. The schedule outlines a comprehensive project timeline spanning from 2025 through 2030, including multiple phases: PMO selection, architect/designer selection through an RFQ/P process with Board of Selectmen approval, design phases (Schematic Design, Design Development, and Construction Documents) each with estimate and review periods, code review and OGA plan completion review, local permitting processes, general contractor pre-qualification and construction manager selection via request for proposals, bidding and GMP award processes, and construction activities including new building construction, demolition and abatement, substantial completion, move activities, FF&E design and procurement, and project closeout. The design phase is allocated 17 months with Schematic Design lasting 3 months, Design Development 4 months, and Construction Documents 3.5 months. Construction is scheduled for 16.5 months with a separate 5-month demolition and abatement phase. A pre-proposal virtual site visit is scheduled for March 13, 2026, with qualifications due March 26, 2026, shortlist announcement on April 7, 2026, RFP issuance on April 8, 2026, proposals due April 20, 2026, interviews on April 21, 2026, and CMR selection immediately following interviews.

The schedule reflects a comprehensive capital project managed by Colliers Project Leaders as of January 7, 2026, with sequential phases designed to ensure coordinated planning and execution. The document does not contain specific pricing information, funding sources, or financial terms within the schedule itself, as it functions primarily as a master timeline document for project phasing and milestone tracking. The project encompasses full design development, permitting approval processes including conservation and planning reviews, FF&E/IT design and installation phases, and occupancy activities, indicating a complex, multi-year construction and implementation effort.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SCHEDULE

Town of Fairfield

Dwight Elementary School with ECC Schedule per CPL Experience

TIMELINE DESCRIPTIONS 2025 2026 2027 2028 2029 2030

Date: January 7, 2026 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul

PMO Selection

Architect / Designer Selection

RFQ/P Process and Selection

BOS Approval

Design Phase

Schematic Design Phase

Schematic Design Estimate & Review

Design Development Phase

Design Development Estimate & Review

Construction Document Phase

Construction Document Estimate & Review

Code Review (30 days)

OGA Plan Completion Review

Approval to Bid by OGA

Local Permitting

Permit Approvals (Conservation/Planning)

GC Pre-Qualification / CM Selection

Request for Proposals

Shortlist and Interview Firms

Selection/Award

Bidding / GMP

Bid Period

Scope Reviews / GMP Award

BOS Approval

Construction

New Building Construction

Demolition / Abatement/Site Restoration

Substantial Completion

Move Activity

FF&E Process

FF&E/IT Design

FF&E/IT OGA Approval

FF&E/IT Procurement

FF&E/IT Installation

Occupancy

Closeout Phase

SD - 3 MONTHS

DESIGN PHASE (17 months)

DD - 4.0 MONTHS

CD - 3.5 MONTHS

BIDDING

CONSTRUCTION (16.5 months)

DEMO (5 months)

FF&E DESIGN

INSTALL

Current Status

Colliers Project Leaders Page 1 of 1 1/7/2026

Dwight ES Macro Schedule Master