This is a project manual and standard specifications document prepared by Horrocks Engineers for the Utah Department of Transportation (UDOT) to support construction of maintenance site improvements at a UDOT facility located at 1325 East Highway 90 in Brigham City, Utah. The project encompasses demolition of an existing evaporative pond, wash rack, sander storage rack, and asphalt pavement, followed by construction of new site features including asphalt paving, wash rack, material storage bin, sander storage rack, brine-mixing vault, and brine tank pad. The scope includes earthwork with pond excavation and site re-grading; utility work consisting of stormwater inlets, catch basins, storm drain piping, water supply piping, yard hydrants, sanitary sewer piping and structures; and various hardscape improvements such as curbs, gutters, and waterways. The project manual was issued July 21, 2021, and includes detailed specifications for divisions covering general requirements, site work, concrete, and structural steel. Construction is scheduled for March 2026 with a substantial completion deadline of June 15, 2026. A mandatory virtual pre-bid meeting is scheduled for March 31, 2026, at 2:00 pm, and bids must be submitted electronically through the UP3 system.

The contract will be awarded to the lowest responsive and responsible bidder, with UDOT reserving the right to evaluate contractor responsibility based on past performance on MS4 projects, requiring completion without excessive delays or warranty issues. The awarded contractor must provide performance and payment bonds upon contract execution. The specifications establish detailed measurement and payment procedures for various line items including mobilization, surveying, demolition, earthwork, erosion control, water distribution, sanitary sewer, storm drainage, base course, and asphalt paving, with payment made based on completion percentages and actual quantities. Funding sources and contract pricing details are not specified in this technical specifications document, though general contractual provisions address modifications, substitutions, quality control testing by an Owner-selected Construction Testing Laboratory at no cost to the contractor, and extensive closeout and warranty requirements. The contract incorporates American Public Works Association (APWA) specifications and DFCM General Conditions, with the most stringent requirements applying where conflicts occur.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Horrocks Engineers Page 1 of 1

UDOT 00001

UDOT Maintenance Site Improvements SECTION 00001 Brigham City Site

For Construction March 2026

SECTION 00001 – PROJECT TITLE PAGE

PROJECT MANUAL

Including specifications for

Construction of:

UDOT Maintenance Site Improvements

Brigham City Site

Prepared by:

2162 West Grove Parkway, #400 Pleasant Grove, Utah 84062

Phone: 801.763.5100

Project Number #UT-1880-1908-15

Date of Issue:

July 21, 2021

END OF SECTION 00001

Horrocks Engineers Page 1 of 2

UDOT 00010

UDOT Maintenance Site Improvements SECTION 00010 For Construction Brigham City Site July 2021

SECTION 00010 – TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00001 PROJECT TITLE PAGE

00010 TABLE OF CONTENTS

00200 INSTRUCTIONS TO BIDDERS

00400 BID SCHEDULE

SPECIFICATIONS GROUP

General Requirements Subgroup

DIVISION 01 – GENERAL REQUIREMENTS

01110 SUMMARY OF WORK

01150 SUPPLEMENTARY GENERAL CONDITIONS

01200 MEASUREMENT AND PAYMENT

01250 MODIFICATION PROCEDURES

01310 PROJECT COORDINATION

01330 SUBMITTALS

01400 QUALITY CONTROL SERVICES

01500 TEMPORARY FACILITIES

01600 MATERIALS AND EQUIPMENT

01631 PRODUCT SUBSTITUTIONS

01700 PROJECT CLOSEOUT

01740 WARRANTIES

Technical Specifications Subgroup

DIVISION 02 – SITE WORK

02230 SITE DEMOLITION AND CLEARING

02300 EARTHWORK

02370 EROSION CONTROL

02510 WATER DISTRIBUTION

02535 02536

SANITARY SEWAGE

MANHOLES

02540 02630

OIL / WATER SEPARATORS

STORM DRAINAGE

02721 UNTREATED BASE COURSE

02742 HOT MIX ASPHALT

Horrocks Engineers Page 2 of 2

UDOT 00010

UDOT Maintenance Site Improvements SECTION 00010 For Construction Brigham City Site July 2021

DIVISION 03 – CONCRETE

03110 CONCRETE FORMWORK

03200 CONCRETE REINFORCEMENT

03300 CONCRETE WORK

03304 PORTLAND CEMENT CONCRETE

03350 CONCRETE FINISHING

03390 CONCRETE CURING

DIVISION 05 – METALS

05210 STRUCTURAL STEEL

05530 GRATING, COVER PLATES, AND HANDRAILS

END OF SECTION 00010

Horrocks Engineers Page 1 of 4

UDOT 00200

UDOT Maintenance Site Improvements SECTION 00200 For Construction Brigham City Site July 2021

SECTION 00200 – INSTRUCTIONS TO BIDDERS

PART 1 - GENERAL

1.1 PROJECT GENERAL INFORMATION

A. Project Location: The maintenance facility is located at 1325 East Highway 90, Brigham City, Utah 84032.

B. Project Owner: Utah Department of Transportation, Region 1.

C. Project Summary: Demolition of evaporative pond, wash rack, sander storage rack, and asphalt pavement. Construction of new asphalt paving, wash rack, material storage bin, sander storage rack, brine-mixing vault, brine tank pad. Earthwork including pond excavation, site re-grading, placement of base material, subgrade prep, etc. Utility work including new stormwater inlets, catch basins, and storm drain pipe; water supply piping and yard hydrants; above-grade wash rack piping; sanitary sewer piping, manholes, and structures. All other work as defined in the contract documents and the Sciquest bid solicitation.

D. See SECTION 01110 – SUMMARY OF WORK and the Contract Documents for additional description of work.

E. Construction Documents: Prepared by Horrocks Engineers dated July 21, 2021.

1.3 BID SUMISSION

A. All bids shall be submitted electronically through the UP3. When submitting a bid electronically through Sciquest, bidders shall allow sufficient time to complete the online forms and upload documents. The solicitation will end at the closing

Horrocks Engineers Page 2 of 4

UDOT Maintenance Site Improvements SECTION 00200 For Construction Brigham City Site July 2021 time listed in the RFP. If you are in the middle of uploading your bid at the closing time, the system will stop the process and your bid will not be received by the system.

B. Electronic bids may require uploading of electronic attachments. UP3

1.4 will accept a wide variety of documents types as attachments. However, the submission of documents containing embedded documents (zip files), mov, wmp, and mp3 files are prohibited. All documents should be attached as separate files.

BID LIMITATIONS

A. MODIFICATIONS AND ALTERNATIVE BIDS: Unauthorized conditions, limitations, or provisions attached to a Bid may render it non-responsive and may cause its rejection.

The completed Bid forms shall be without interlineations, alterations, or erasures.

Alternative Bids will not be considered unless called for. Oral, telegraphic, or facsimile Bids or modifications will not be considered.

B. DISCREPANCIES IN BIDS: In the event there is more than one bid item in a bid schedule, the Bidder shall furnish a price for all bid items in the schedule; failure to do so may render the Bid non-responsive and subject to rejection. In the event there are unit price bid items in a bid schedule and the "amount" indicated for a unit price bid item does not equal the product of the unit price and quantity, the unit price shall govern and the "amount" will be corrected accordingly, and the Bidder shall be bound by said correction. In the event there is more than one bid item in a bid schedule and the total indicated for the schedule does not agree with the sum of the prices bid on the individual items, the prices bid on the individual items shall govern and the total for the schedule will be corrected accordingly, and the Bidder shall be bound by said correction. In the event that there is a conflict between the written and the numerical amount, the written amount shall supersede the numerical amount.

1.5 BIDDER'S EXAMINATION OF CONTRACT DOCUMENTS AND SITE

A. It is the responsibility of each Bidder before submitting a Bid, to:

1. Examine the Contract Documents thoroughly.

2. Visit the site to become familiar with local conditions that may affect cost, progress, performance, or furnishing of the WORK.

3. Consider federal, state and local laws and regulations that may affect cost, progress, performance or furnishing of the WORK.

4. Study and carefully correlate the Bidder's observations with the Contract

Documents.

5. Notify the ENGINEER of all conflicts, errors, or discrepancies in the Contract

Documents.

B. Information and data reflected in the Contract Documents with respect to underground facilities at/or contiguous to the site are based upon information and data furnished to the OWNER and the ENGINEER by the owners of such underground facilities or others.

The OWNER has no responsibility for the accuracy or completeness thereof including any damages whatsoever that may be incurred by the Bidder through its reliance

Horrocks Engineers Page 3 of 4

UDOT Maintenance Site Improvements SECTION 00200 For Construction Brigham City Site July 2021 thereon, unless it is expressly provided otherwise in the Supplementary General Conditions.

C. Before submitting a Bid, the Bidder shall conduct such examination, investigations, studies and tests as are necessary to satisfy itself as to: the nature and location of the physical conditions, (surface, subsurface and underground facilities), the general and local conditions particularly those bearing upon transportation, disposal, handling and storage of materials, availability of labor, availability of utilities, local weather conditions, the character of equipment and facilities required preliminary to and during the prosecution of the WORK; any and all other conditions that may in any way affect the cost, progress, performance or furnishing of materials in accordance with the Contract Documents. All such examination, investigation, studies, tests and the like shall be at the Bidder's expense.

D. The submission of a Bid hereunder shall be considered prima facie evidence that the Bidder has made such examination as is set forth in the above paragraph and is knowledgeable as to the location and site conditions surrounding the WORK and the conditions to be encountered in performing the WORK and as to the requirements, conditions and terms of the Contract Documents.

E. The OWNER has no responsibility for: (1) any oral representations made by any of its officers, employees or agents during or prior to the execution of the Agreement; (2) information contained in any reports, subsurface studies, or other information which may be made available for the Bidder's information and which are not included as Contract Documents; or (3) any understanding or representations by the OWNER or by others which are not expressly stated in the Contract Documents, unless such responsibility is expressly assumed by the OWNER or its representatives in the Contract Documents. Such information shall be deemed to be for the information of the Bidder and the Bidder shall have the obligation of evaluating any such information as to its accuracy and effect. The OWNER will not be liable or responsible for any such information or any conclusions that may be drawn therefrom by the Bidder.

F. The lands upon which the WORK is to be performed, right-of-ways and easements for access thereto, together with other lands designated for use by the Bidder in performing the WORK, are identified in the Contract Documents. All additional lands and access thereto that are required for temporary construction facilities or storage of materials and equipment are to be provided by the Bidder. Easements for permanent structures or permanent changes in existing structures are to be obtained and paid for by the OWNER unless otherwise provided in the Contract Documents.

G. The submission of a Bid shall constitute an incontrovertible representation by the Bidder that the Bidder has complied with every requirement of this section, and that without exception the Bid is premised upon performing and furnishing the work required by the Contract Documents in compliance with such techniques, sequences, or procedures of construction as may be indicated in or required by the Contract Documents; and that such techniques, sequences or procedures described in the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing the WORK.

Horrocks Engineers Page 4 of 4

UDOT Maintenance Site Improvements SECTION 00200 For Construction Brigham City Site July 2021

1.6 QUANTITIES OF WORK:

A. The quantities of WORK or material stated in the Bid Schedule are supplied only to give an indication of the general scope of the WORK; the OWNER does not expressly or by implication agree that the actual amount of WORK or material will correspond therewith.

The OWNER reserves the right after award of the contract to increase or decrease the quantities of any unit price item of the WORK by an amount up to and including twenty five percent (25%) of the quantity of any bid item, or to omit portions of such WORK as may be deemed necessary or expedient by the ENGINEER or OWNER, without a change in the unit price. Such right to revise and omit shall include the right to delete any bid item in its entirety, or to add additional bid items in quantities up to and including an aggregate total amount not to exceed twenty five percent (25%) of the total Contract Price.

B. Neither the Bidder nor the ultimate CONTRACTOR on the Project shall at any time after the submittal of a Bid make or have any claim for damages or anticipated profits or loss of profit or otherwise because of any difference between the quantities of WORK actually done and material furnished and those stated in said unit price items of the Bid.

PART 2 - NOT USED

PART 3 - NOT USED

END OF SECTION 00200

Horrocks Engineers Page 1 of 3

UDOT 00400

UDOT Maintenance Site Improvements SECTION 00400 For Construction Brigham City Site July 2021

SECTION 00400 – BID SCHEDULE

PART 1 - GENERAL

1.1 BIDDER

A. Name and Address

B. Telephone Number

C. Facsimile Number

D. Tax Identification Number

E. Bidder holds license number issued by the

Utah State Department of Commerce, Occupational and Professional Licensing

Division, on the day of , 20 .

Bidder is licensed to practice as a contractor.

License renewal date is the day of , 20 .

1.2 CONSTRUCTION CONTRACT

A. Name of Project: UDOT MAINTENANCE SITE REHAB: BRIGHAM CITY

B. Project Number Pin: TBD

1.3 SCHEDULES TO BE ADDED TO THE AGREEMENT

A. This Bid Schedule contains the schedules of prices, which will be incorporated into the Agreement by reference.

1.4 BASIS OF AWARD

A. Award of the contract, if it be awarded, shall be made to the lowest qualified, responsible and responsive bidder subject to UDOT's contract policy, and whose Bid complies with all of the requirements prescribed. The lowest overall cost to the project will be based on the Total Bid Amount.

Horrocks Engineers Page 2 of 3

UDOT Maintenance Site Improvements SECTION 00400 For Construction Brigham City Site July 2021

1.5 SCHEDULE OF PRICES

A. Base Bid Schedule

CSI

Code

DESCRIPTION Qty (Unit)

$/Unit Amount

01500 MOBILIZATION & ENVIRONMENTAL CONTROLS (LS)

01540 CONSTRUCTION SURVEYING AND STAKING (LS)

02220 SITE DEMOLITION & CLEARING (LS)

02310 EARTHWORK – ONSITE

REUSE AND STOCKPILE

1971 (cy)

02315 EARTHWORK – SUBGRADE

PREP

8900 (sy)

02370 EROSION CONTROL (LS)

02510-01 WATER DISTRIBUTION (LS): BELOW GRADE

02510-02 WATER DISTRIBUTION (LS): ABOVE GRADE

02630 SANITARY SEWER (LS)

02630 STORM DRAINAGE (LS)

02721 UNTREATED BASE COURSE 1455 (cy)

02742 HOT MIX ASPHALT 6222 (sy)

03300-01 CAST-IN-PLACE CONCRETE:

MAT, SLABS, & FOOTINGS 138 (cy) $ $

03300-02 CAST-IN-PLACE CONCRETE:

WALLS & PILASTERS 80 (cy) $ $

05120 STRUCTURAL & MISCELLANEOUS STEEL (LS)

TOTAL BID AMOUNT

in words.

Horrocks Engineers Page 3 of 3

UDOT Maintenance Site Improvements SECTION 00400 For Construction Brigham City Site July 2021

B. Bid Alternate #1

CSI

Code DESCRIPTION Qty

(Unit) $/Unit Amount

13000 TWO ADD’L SANDER STORAGE RACK BAYS $

END OF SECTION 00400

UDOT 01110

UDOT Maintenance Site Improvements SECTION 01110 For Construction Brigham City Site July 2021

SECTION 01110 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.2 PROJECT DESCRIPTION

A. The project is located at an existing UDOT maintenance complex located in Brigham City, UT. The following description is a rough outline of the work to be accomplished and not a definitive scope of work:

1. Demolition and haul-off of existing site elements including evaporative pond, wash rack & foundations, truck wash slab, sander storage rack & foundations, and associated asphalt pavement.

2. Construction of new site features and improvements including asphalt paving, wash rack, truck wash slab & decant area, material storage bin, sander storage rack, brine-mixing vault, brine tank pad, and various hardscape improvements such curb & gutter, waterways, etc.

3. Earthwork including excavation of a new stormwater pond, site re-grading with acceptable on-site borrow materials, supply and placement of untreated base course materials, subgrade preparation & compaction, etc.

4. Utility work including new stormwater inlets, catch basins, and storm drain piping;

buried cold water supply piping and freezeless yard hydrants to truck wash and brine-making areas; above-grade cold supply piping, valves, nozzels, etc. on the new wash rack structure; new sanitary sewer structures & piping to route truck wash water and shop drain water to existing sanitary sewer lift sump at the front of the property.

5. All other work as defined in the contract documents and the Sciquest bid solicitation.

1.3 PROJECT DATES

A. Commencement: The work on this Project shall commence within ten (10) days of receipt of the Notice to Proceed.

B. Substantial Completion: The Substantial Completion Deadline for the project will be communicated to bidders during the bid period either in the Sciquest Solicitation narrative or through other portal-based methods. The project shall be substantially complete as defined in Section 01700 PROJECT CLOSEOUT by the Substantial Completion Deadline.

1.4 LIQUIDATED DAMAGES

UDOT 01110

UDOT Maintenance Site Improvements SECTION 01110 For Construction Brigham City Site July 2021

A. Substantial Completion. In the event that Contractor fails to substantially complete all of the work required herein by the Substantial Completion Deadline described above, then for each partial or complete day during which the work remains uncompleted thereafter, the Contractor agrees to pay UDOT $500 per day for 15 calendar days and $1,000 per day thereafter, which the parties believe, due to the difficulty of actually assessing the damages UDOT will suffer in the event of such a delay, is a fair estimate of the loss UDOT will suffer. The parties agree that the daily liquidated damages provided for herein is reasonable and fair, and is not a penalty. TIME IS OF THE

ESSENCE IN THIS AGREEMENT.

B. Final Acceptance. In the event that the Contractor fails to obtain Final Acceptance as defined in Section 01700 PROJECT CLOSEOUT within 30 days after the Substantial Completion Deadline, the contractor agrees to pay UDOT $500 per day, which the parties believe is a fair estimate of the loss UDOT will suffer. The parties agree that the daily liquidated damages provided for herein is reasonable and fair, and is not a penalty. TIME IS OF THE ESSENCE IN THIS AGREEMENT.

1.5 INCLEMENT WEATHER

A. Work stoppage due to inclement weather conditions and other factors must be approved in writing by the Project Manager. Inclement weather shall not otherwise constitute cause for delay. Unless otherwise agreed by UDOT by Change Order, no damages shall become due to Contractor for UDOT-caused delay.

B. A Change Order for delay will generally be accepted for delay so excessive and unreasonable that it is beyond the scope of the Contract or delay attributed to direct, active or willful interference by UDOT. The Change Order must be based upon actual damages sustained by the Contractor which are directly attributed to the delay.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 01110

UDOT 01150

UDOT Maintenance Site Improvements SECTION 01150 For Construction Brigham City Site July 2021

SECTION 01150 – SUPPLEMENTAL GENERAL CONDITIONS

PART 1 - GENERAL

1.1 CONTRACTOR USE OF PREMISES

A. General: During the construction period, the Contractor and subcontractors shall have use of the premises for construction operations. The use of the premises is limited only by the End User's right to perform construction operations with its own forces or to employ separate contractors on portions of the project.

1. Confine operations to areas within Contract limits indicated. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.

2. Keep driveways and entrances serving the premises clear and available to the Owner and the Owner's employees at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.

1.2 END USER CONSTRUCTED WORK

A. Coordinate with the Owner and Project Manager/General Contractor where construction in this contract interfaces with work performed by the End User.

B. Repair any damage to End User constructed items which occurs during the course of construction as a result of construction activity. Replace damaged items when repair is not possible to restore to the original undamaged condition or when required by Owner.

1.3 INSURANCE

A. WORKERS COMPENSATION

1. The contractor will be required to furnish proof that all employees involved in this project are covered by Workmen's Compensation. The State will not be liable for injuries incurred during this project.

B. CERTIFICATE OF INSURANCE

1. Before contract award, successful bidder must provide a certificate of insurance certifying that the contractor will provide and maintain a policy of insurance in which the Department of Transportation is named as an additional insured.

Coverage shall be in the following amounts:

a. $250,000 for bodily injury

b. $500,000 for each accident occurrence

c. $100,000 for property damage

2. If the contractor cannot obtain this insurance, the contractor shall provide a policy with a minimum coverage of $1,000,000 in the aggregate.

UDOT Maintenance Site Improvements SECTION 01150 For Construction Brigham City Site July 2021

3. The certificate must also state that no cancellation or decrease in coverage shall be made without giving the State at least 30 days prior written notice.

1.4 GENERAL CONDITIONS

A. American Public Works Association (APWA) current specifications apply to this this project. The DFCM General Conditions shall apply to this project. This document may be viewed at https://dfcm.utah.gov/wp-content/uploads/DFCM-General-Conditions.pdf.

Where conflicts occur between APWA and DFCM the most stringent will apply as determined by UDOT or their representative.

1.5 DESIGN REQUIREMENTS

A. American Public Works Association (APWA) current specifications apply to this this project. The DFCM Design Requirements shall apply to this project. This document may be viewed at https://dfcm.utah.gov/wp-content/uploads/1.17.19-design_requirements.pdf. Where conflicts occur between APWA and DFCM the most stringent will apply as determined by UDOT or their representative.

1.6 SAFETY

A. Contractor shall comply with the current edition of the Utah Department of Transportation Safety and Health Manual. Copies may be downloaded from the web site https://www.udot.utah.gov/main/uconowner.gf?n=22185504109947669. Owner intends to inspect the job site monthly for compliance with the standard. Failure to comply with the requirements of the cited manual may result in the Owner issuing a cease and desist order until such time as the noted violations are corrected. Contractor will be held responsible for all costs resulting from safety violations.

1.7 MATERIALS

A. Material furnished to the State of Utah shall be certified as new and must meet all current State and Federal applicable building codes and safety regulations.

B. Bids shall include all materials and equipment necessary for complete finished construction.

1.8 WARRANTY

A. Unless noted otherwise, Contractor shall provide a general written one-year warranty for the replacement of all defective materials, including labor and travel that are used in this project. See individual specification sections for additional warranties. All warranties shall be from date of substantial completion.

1.9 BUILDING CODES

A. The improvements shall be constructed according to all applicable State, Local and National Codes.

https://dfcm.utah.gov/wp-content/uploads/DFCM-General-Conditions.pdf https://dfcm.utah.gov/wp-content/uploads/1.17.19-design_requirements.pdf https://dfcm.utah.gov/wp-content/uploads/1.17.19-design_requirements.pdf https://www.udot.utah.gov/main/uconowner.gf?n=22185504109947669

UDOT Maintenance Site Improvements SECTION 01150 For Construction Brigham City Site July 2021

1.10 AS-BUILT PLAN SUBMITTAL

A. Contractor will be required to submit to the Owner a final set of as-builts and any applicable operations and maintenance manuals. Submittal shall be in pdf format.

1.11 PROJECT COORDINATION

A. Coordination: Coordinate construction activities included under various Sections of these Specifications to assure efficient and orderly installation of each part of the Work.

Coordinate construction operations included under different Sections of the Specifications that are dependent upon each other for proper installation, connection, and operation.

1. Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.

2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Where necessary, prepare memoranda for distribution to each party involved to be submitted to Project Manager/General Contractor, outlining special procedures required for coordination.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Installation and removal of temporary facilities.

2. Delivery and processing of submittals.

3. Project Close-out activities.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials

1.12 SUBMITTALS

A. Coordination Drawings: Prepare and submit coordination Drawings where close and careful coordination is required for installation of products and materials fabricated off-site by separate entities, and where limited space availability necessitates maximum utilization of space for efficient installation of different components.

1. Show the interrelationship of components shown on separate Shop Drawings.

2. Indicate required installation sequences.

3. Comply with requirements contained in Section "Submittals."

4. Refer to Division-15 Section "Basic Mechanical Requirements," and Division-16

Section "Basic Electrical Requirements" for specific coordination Drawing requirements for mechanical and electrical installations.

UDOT Maintenance Site Improvements SECTION 01150 For Construction Brigham City Site July 2021

B. Staff Names: Within 15 days of Notice to Proceed, submit a list of principal staff assignments, including the trade Foreman and other personnel in attendance at the site; identify individuals, their duties and responsibilities; list their addresses and telephone numbers.

PART 2 - NOT USED

PART 3 - EXECUTION

3.1 GENERAL INSTALLATION PROVISIONS

A. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.

B. Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.

C. Inspect materials or equipment immediately upon delivery and again prior to installation.

Reject damaged and defective items.

D. Provide attachment and connection devices and methods necessary for securing Work.

Secure Work true to line and level.

E. Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints in exposed Work to obtain the best visual effect. Refer questionable choices to the Engineer for final decision.

F. Recheck measurements and dimensions, before starting each installation.

END OF SECTION 01150

Horrocks Engineers Page 1 of 7

UDOT 01200

UDOT Maintenance Site Improvements SECTION 01200 For Construction Brigham City Site July 2021

SECTION 01200 – MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements governing Applications for Payment submitted to Project Manager/General Contractor.

1. Coordinate Applications for Payment with the Measurement and Payment Section of this Section along with the Construction Schedule and Submittal Schedule.

1.3 MEASUREMENT AND PAYMENT

1. See measurement and payment procedures in APWA Section 01 29 00.

2. ENGINEER will take all measurements and compute all quantities.

3. CONTRACTOR will verify measurement and quantities.

4. CONTRACTOR will provide all equipment, workers, and survey crews to assist

ENGINEER in making measurements.

5. Units of measurement are listed above in the bid schedule(s).

A. 01500 MOBILIZATION & ENVIRONMENTAL CONTROLS

1. Measured by lump sum (LS).

2. Payment covers cost of mobilization, demobilization, and installation of temporary facilities. Payment will be made on a percentage basis as follows.

Percent of Original Contract Amount Earned

Percent of Amount Bid for Mobilization to be Paid

5 40

15 20

40 30

50 10

B. 01540 CONSTRUCTION SURVEYING AND STAKING

1. Measured by lump sum (LS).

2. Payment includes all costs incidental with project surveying and staking including mobilization.

3. Control and survey support set once by the ENGINEER.

Horrocks Engineers Page 2 of 7

UDOT Maintenance Site Improvements SECTION 01200 For Construction Brigham City Site July 2021

C. 02220 SITE DEMOLITION & CLEARING

1. Measured by lump sum (LS).

2. Payment covers the CONTRACTOR adequately and sufficiently for demolishing and removing the site elements as depicted on the construction plans. These include, but are not limited to existing pipe, organic earth and deleterious soils, structures, and pavements.

3. Payment also includes labor and material to properly cap, abandon, or otherwise terminate existing utilities to remain in place.

4. Payment for export or relocation of native soils required to make grade is covered in 02310-02 EXPORT OF EXISTING SOIL.

D. 02310 EARTHWORK – ONSITE REUSE AND STOCKPILE

1. CONTRACTOR TO CONFIRM AND VERIFY MASS VOLUME QUANTITIES AS

DEPICTED ON ENGINEERS DESIGN DOCUMENTS.

2. Measured by Cubic Yards (CY) of material cut and filled during mass volume activities.

3. Payment covers the confirmation of volumes of material removed and relocated on site by record keeping of truck logs or pre and post-earth-moving activities.

Payment also covers grading and compaction on and around stockpile areas to facilitate drainage around and stability of stockpiled material.

4. This item assumes that subgrade materials under existing pavements will need to be excavated to install new base course. If existing subgrade materials are deemed adequate to support new pavement by UDOT, then Contractor shall provide a credit for unexcavated material.

5. Control and inspection/support by the OWNER.

E. 02315 EARTHWORK – SUBGRADE PREP

1. Measured by Square Yards (SY) of plan area within limits of disturbance where existing subgrade materials are cut, graded, scarified & recompacted, etc. prior to installation of new improvements including but not limited to swales, ditches, pavements, aggregate surfacing, building structures, pads, aprons, riprap, etc.

2. Payment covers labor and equipment to prepare the subgrade area as shown or described in the contract drawings, details, and specifications.

3. This item includes subgrade prep, finish grading, and compaction only.

Excavation, mass grading, and stockpile of relocated native material is covered in 02310 EARTHWORK – ONSITE REUSE AND STOCKPILE. Placement and compaction of base course material is covered in 02721 UNTREATED BASE

COURSE.

4. Control and inspection/support by the OWNER.

F. 02370 EROSION CONTROL

1. Measured by lump sum (LS).

2. Payment covers the CONTRACTOR in providing and maintaining a storm water pollution prevention plan as required by the local jurisdiction. Payment also covers all erosion control best management practices (BMPs) required by the jurisdiction, Horrocks Engineers Page 3 of 7

UDOT Maintenance Site Improvements SECTION 01200 For Construction Brigham City Site July 2021 including all BMPs shown on the erosion control plan in the contract drawings including but not limited to silt fencing, stabilized roadway entrances, concrete wash-out areas, inlet protection, temporary sediment traps, etc.

G. 02510-01 WATER DISTRIBUTION – BELOW GRADE

1. Measured by lump sum (LS) of pipe installation and inspection.

2. Consists of all necessary labor, materials, and equipment required to install all below grade waterlines, fittings, risers, valves, vaults, etc. Also includes all required excavation, trenching, subgrade preparation, bedding, backfill, compaction, testing, etc.

H. 02510-02 WATER DISTRIBUTION – ABOVE GRADE

1. Measured by lump sum (LS) of pipe installation and inspection attached to the washrack as shown in the design package.

2. Consists of all necessary labor, materials, and equipment required to install all above-grade galvanized piping attached to the washrack. Includes coordination with structural engineer for all pipe supports, hangers, connections, and any other requirement as depicted in design package.

I. 02530 SANITARY SEWER

1. Measured by lump sum (LS).

2. Payment covers all material and labor to install sanitary sewer piping and structures shown on plan. Payment includes excavation and bedding material in the pipe zone.

3. Payment covers the cost of incidental work such as, fittings, couplings, joint lubricants; selective clearing and tree removal; removal and disposal of interfering structures and obstructions; concrete rings, frame and lid as applicable; grout;

jackhammer work; trench shoring or trench boxes as applicable; underground line markers; cleaning of invert covers; removal and disposal of waste materials;

restoration of all utilities damaged as a result of operations; site dewatering; pipe line cleaning; main repair or replacement if damaged by CONTRACTOR; and similar work to complete the installation of the pipe. Also includes all costs incidental to connections with existing and proposed structures.

4. Sewer line must be inspected prior to acceptance by the OWNER.

5. Payment includes all necessary labor, materials, and equipment required to construct and install a complete drainage structure including but not limited to the following: Excavation, subgrade preparation, foundation gravel, backfill, concrete, reinforcing steel, and any other items required in drawings or per manufacturer’s recommendations.

J. 02630 STORM DRAINAGE

1. Measured by lump sum (LS).

2. Payment covers all material and labor to install storm drain piping and structures shown on plan. Payment includes excavation and bedding material in the pipe zone.

Horrocks Engineers Page 4 of 7

UDOT Maintenance Site Improvements SECTION 01200 For Construction Brigham City Site July 2021

3. Payment covers the cost of incidental work such as fittings, couplings, joint lubricants, concrete rings, frame and lid as applicable; grout; jackhammer work;

trench shoring or trench boxes as applicable; underground line markers; cleaning of invert covers, and similar work to complete the installation of the pipe. Payment also includes all costs incidental to connections with existing and proposed structures.

4. Payment includes all material and labor to install gravel and riprap pads, aprons, channel beds, etc. shown on the drawings that are associated with storm runoff collection, routing, filtering, or discharge.

5. Aggregate surfacing and exposed untreated base course material are excluded from this item and are covered in their respective sections.

K. 02721 UNTREATED BASE COURSE

1. Measured by Cubic Yards (CY) of untreated base course under paved or aggregate-surfaced areas. Quantities shall be determined by record keeping of delivery logs or invoices. Final billed quantities shall not exceed those based on layout and thicknesses dimensioned on the drawings.

2. Payment includes all labor, materials, and equipment to deliver, place, and compact untreated base course layers as shown or described in the contract drawings, details, and specifications.

3. Contractor shall provide a credit for any excess base material either left on site or hauled off after finish grading is completed prior to asphalt, aggregate, or concrete surface placement.

4. This item assumes that base material under existing pavements scheduled for demolition will be excavated to install the new base course. If UDOT deems existing base materials adequate to support new pavement, then Contractor shall provide a credit for unplaced base material. In such cases, payment for preparation of the in-situ base course shall be covered in 02315 EARTHWORK –

SUBGRADE PREP.

5. Control and inspection/support by the OWNER.

L. 02742 HOT MIX ASPHALT

1. Measured by square yardage (SY).

2. Payment includes all labor, materials, and equipment to install bituminous asphalt material to the full thickness shown in the drawings and per the project specifications. Payment for material and placement cost of untreated base course is included in Item 02720 UNTREATED BASE COURSE.

3. Payment for soft-spot repair shall be based on the square yardage of the affected areas.

M. 03300-01 CAST-IN-PLACE CONCRETE: MAT, SLABS, & FOOTINGS

1. Measured by cubic yard (CY).

2. Quantities shall be determined based on design dimensions, thicknesses, etc. No additional payment will be made for waste or increased thickness of installed mat slabs.

Horrocks Engineers Page 5 of 7

UDOT Maintenance Site Improvements SECTION 01200 For Construction Brigham City Site July 2021

3. Payment includes all labor, materials, reinforcing, and equipment to construct truck wash slab, wash rack footings, solids settling slab and strip footings, and mag tank pad.

4. Payment also includes all dowels, waterstops, keyways, embeds, or other surface preparation required prior to installation of walls, pilasters, etc.

5. Payment for preparation of native subgrade material is covered in 02315 EARTHWORK – SUBGRADE PREP and placement and compaction of untreated base course is covered in 02721 UNTREATED BASE COURSE.

6. Payment for material and placement cost of untreated base course is included in Item 02720 UNTREATED BASE COURSE.

N. 03300-02 CAST-IN-PLACE CONCRETE: WALLS & PILASTERS

1. Measured by cubic yard (CY).

2. Quantities shall be determined based on design dimensions, thicknesses, etc. No additional payment will be made for waste, etc.

3. Payment includes all labor, materials, reinforcing, and equipment to construct all vertical formed cast-in-place concrete, such as walls, pilasters, junction boxes, etc. Includes vertical concrete for wash rack pilasters and solids settling pony walls. Also includes delivery of materials, formwork, and stripping.

4. Payment includes all above grade appurtenances, embeds, gates, ladders, etc.

5. Payment includes all labor and materials to install anchor rods, anchor rod templates, or other preparation required prior to installation of wash rack structural steel.

O. 05210 STRUCTURAL & MISCELLANEOUS STEEL

1. Measured by each structure (EA) or lumps sum (LS) including structural steel for washrack stairs and catwalk.

2. Payment includes all labor, materials, and equipment to construct washrack stairs and catwalk, including all required detailing, shop drawings, fabrication, delivery, and erection, as depicted on the structural plans in the design package.

P. 13000 ADD ALTERNATE #1

1. TWO ADD’L SANDER STORAGE RACK BAYS

a. Measured by lump sum (LS).

b. Payment includes all labor, materials, and equipment to install two additional sander storage rack bays, including superstructure and foundations as indicated in the contract documents.

1.4 APPLICATIONS FOR PAYMENT:

A. Each Application for Payment shall be consistent with previous applications and payments.

B. Payment Application Times: The date to submit initial application for payment is at the subcontractor’s discretion, and subsequent applications for payment as set forth by the Project Manager/General Contractor but no later than 30 days thereafter.

Horrocks Engineers Page 6 of 7

UDOT Maintenance Site Improvements SECTION 01200 For Construction Brigham City Site July 2021

C. Payment Application Format: Use format consistent with Schedule of Values.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions have been made.

2. Include amounts of Change Orders issued prior to the last day of the construction period covered by the application.

D. Transmittal: Submit 3 executed copies of each Application for Payment to the Project Manager/General Contractor by means ensuring receipt within 24 hours; one copy shall be complete, including waivers of lien and similar attachments, when required.

1. Transmit each copy with a transmittal form listing attachments, and recording appropriate information related to the application in a manner acceptable to the Project Manager/General Contractor.

E. Waivers of Mechanics Lien: With each Application for Payment, submit waivers of mechanics liens from subcontractors or sub- subcontractors and suppliers for the construction period covered by the previous application.

1. Submit partial waivers on each item for the amount requested, prior to deduction for retainage, on each item.

2. When an application shows completion of an item, submit final or full waivers.

3. The Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Waiver Delays: Submit each Application for Payment with the Contractor's waiver of mechanics lien for the period of construction covered by the application.

a. Submit final Application for Payment with or preceded by final waivers from every entity involved with performance of Work covered by the application who could lawfully be entitled to a lien.

5. Waiver Forms: Submit waivers of lien on forms, and executed in a manner acceptable to Owner.

F. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of the first Application for Payment include the following:

1. List of principal suppliers and fabricators.

2. Schedule of Values.

3. Schedule of principal products.

4. Submittal Schedule (preliminary if not final).

5. List of staff assignments.

6. Certificates of insurance and insurance policies as applicable.

G. Final Payment Application: Administrative actions and submittals which must precede or coincide with submittal of the final payment Application for Payment include the following:

1. Completion of Project closeout requirements.

2. Completion of items specified for completion after Substantial Completion.

3. Assurance that unsettled claims will be settled.

Horrocks Engineers Page 7 of 7

UDOT Maintenance Site Improvements SECTION 01200 For Construction Brigham City Site July 2021

4. Assurance that Work not complete and accepted will be completed without undue delay.

5. Transmittal of required Project construction records to Owner.

6. Proof that taxes, fees and similar obligations have been paid.

7. Removal of temporary facilities and services.

8. Removal of surplus materials, rubbish, and similar elements.

PART 2 - PRODUCTS (Not Applicable)

END OF SECTION 01200

UDOT 01250

UDOT Maintenance Site Improvements SECTION 01250 For Construction Brigham City Site July 2021

SECTION 01250 – MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 1 Specification sections, apply to this section.

1.2 SUMMARY

A. This section specifies administrative and procedural requirements for subcontractors for handling and processing Contract modifications to be submitted to Project Manager/General Contractor.

B. Related Sections: The following sections contain requirements that relate to this section:

1. Division 1 Section "Measurement and Payment" for administrative procedures governing applications for payment.

2. Division 1 Section "Product Substitutions" for administrative procedures for handling requests for substitutions made after award of the Contract.

1.3 CHANGE ORDER PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Proposed changes in the Work that will require adjustment to the Contract Sum or Contract Time will be issued by the Project Manager/General Contractor, with a detailed description of the proposed change and supplemental or revised Drawings and Specifications, if necessary.

1. Proposal requests issued by the Project Manager/General Contractor are for information only. Do not consider them an instruction either to stop work in progress, or to execute the proposed change.

2. Unless otherwise indicated in the proposal request, within 15 days of receipt of the proposal request, submit to the Project Manager/General Contractor for review an estimate of cost necessary to execute the proposed change.

a. Include a list of quantities of products to be purchased and unit costs, along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include a statement indicating the effect the proposed change in the Work will have on the Contract Time.

B. Subcontractor-Initiated Change Order Proposal Requests: When latent or other unforeseen conditions require modifications to the Contract, the subcontractor may

UDOT 01250

UDOT Maintenance Site Improvements SECTION 01250 For Construction Brigham City Site July 2021 propose changes by submitting a request for a change to the Project Manager/General Contractor.

1. Include a statement outlining the reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change.

Indicate the effect of the proposed change on the Contract Sum and Contract Time.

2. Include a list of quantities of products to be purchased and unit costs along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

C. Comply with requirements in Section "Product Substitutions" if the proposed change in the Work requires the substitution of one product or system for a product or system specified.

PART 2 - PRODUCTS (Not Applicable)

END OF SECTION 01250

UDOT 01310

UDOT Maintenance Site Improvements SECTION 01310 For Construction Brigham City Site July 2021

SECTION 01310 – PROJECT MEETINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for project meetings including but not limited to:

1. Pre-Construction Conference.

2. Coordination Meetings.

B. Construction schedules are specified in another Division-1 Section.

1.3 PRE-CONSTRUCTION CONFERENCE

A. Attend a pre-construction conference and organizational meeting, scheduled by Owner, at the project site or other convenient location no later than 5 days after execution of the Agreement and prior to commencement of construction activities. Conduct the meeting to review responsibilities and personnel assignments.

B. Attendees: The Owner, Project Manager/General Contractor, Engineer and their consultants, major subcontractors, manufacturers, suppliers and other concerned parties shall each be represented at the conference by persons familiar with and authorized to conclude matters relating to the Work.

C. Proposed Agenda: Parties attending the Pre-Construction Meeting shall be familiar with the project to discuss items of significance that could affect progress including such topics as:

1. Tentative construction schedule.

2. Critical Work sequencing.

3. Designation of responsible personnel.

4. Procedures for processing field decisions and Change Orders.

5. Procedures for processing Applications for Payment.

6. Distribution of Contract Documents.

7. Submittal of Shop Drawings, Product Data and Samples.

8. Preparation of record documents.

9. Use of the premises.

10. Office, Work and storage areas.

11. Equipment deliveries and priorities.

12. Safety procedures.

13. First aid.

UDOT 01310

UDOT Maintenance Site Improvements SECTION 01310 For Construction Brigham City Site July 2021

14. Security.

15. Housekeeping.

16. Working hours.

1.4 SUBCONTRACTOR COORDINATION MEETINGS

A. Participation in project coordination meetings is required. Meeting shall be held at regularly scheduled times convenient for all parties involved. Project coordination meetings are in addition to specific meetings held for other purposes, such as regular progress meetings and special pre-installation meetings.

B. Project Manager/General Contractor will notify applicable subcontractor for representation at coordination meetings.

PART 2 - PRODUCTS (Not Applicable)

END OF SECTION 01310

UDOT 01330

UDOT Maintenance Site Improvements SECTION 01330 For Construction Brigham City Site July 2021

SECTION 01330 – SUBMITTALS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for submittals required for performance of the Work, including;

1. Submittal procedures.

2. Shop Drawings.

3. Product Data.

4. Samples.

B. Administrative Submittals: Refer to other Division-1 Sections and other Contract Documents for requirements for administrative submittals. Such submittals include, but are not limited to:

1. Permits.

2. Applications for payment.

3. Insurance certificates.

C. The Schedule of Values submittal is included in Section "Measurement and Payment."

D. Inspection and test reports are included in Section "Quality Control Services."

1.3 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related elements of the Work so processing will not be delayed by the need to review submittals concurrently for coordination.

a. The Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

3. Processing: Allow sufficient review time so that installation will not be delayed as a result of the time required to process submittals, including time for re-submittals.

UDOT Maintenance Site Improvements SECTION 01330 For Construction Brigham City Site July 2021

a.…