3-Attachment B Scope of Work.docx

DOCX document 510 KB Posted

Attached to
NC27-103 Bear Flat Aspen Lop, Prune, and Pile Project
Solicitation number
NC27-103
Issued by
Grand County, Utah

About this file

This is a Scope of Work attachment for an Invitation for Bid (IFB) issued by the State of Utah Division of Purchasing, with implementation managed by the Utah Division of Forestry, Fire and State Lands (UFFSL), the Utah Division of Wildlife Resources (UDWR), and the Cedar City Ranger District of the Dixie National Forest. The project involves lop, prune, and pile work on 45.5 acres of Forest Service land in Iron County, Utah, southwest of Brian Head. The primary task is hand thinning and removal of all live and dead conifers 8 inches diameter breast height (DBH) and smaller from aspen communities, with pruning of lower branches from remaining conifer trees over 8 inches DBH up to 6 feet, and construction of compacted piles approximately 8 feet by 8 feet by 8 feet. The contractor must furnish all labor, equipment, supervision, and materials, including a minimum 12-person crew. The contract must be completed between September 15, 2026, and April 1, 2027, with work prohibited when snow is on the ground. No mandatory site visit is required prior to bidding, though bidders are strongly recommended to inspect the site. A pre-work conference must be held at the project site before work commences, and the contractor must provide at least 7 full days' notice of arrival. The contract will be awarded to the lowest responsive and responsible bidder who meets all requirements.

Bidding is conducted on a per-acre price basis, with the extended price calculated by multiplying the per-acre bid by 45.5 acres. The total price must include all labor, equipment, materials, mobilization, and operating costs, with no fuel surcharges or slope adjustments permitted. Participation in this IFB is limited to pre-qualified contractors only; bids from non-prequalified contractors will not be considered. Payment will be made as one lump-sum final payment following final inspection of completed work and consistent with the State's standard terms and conditions, though partial payment requests may be approved at the State's discretion. The contractor is solely responsible for equipment protection and environmental compliance, including high-pressure equipment washing before entering Forest Service lands and removal of all refuse. Work hours are limited to one-half hour before sunrise to one-half hour after sunset unless extended by mutual agreement with suitable exterior lighting. The State reserves the right to stop work at any time due to frozen soil or winter conditions, with discretion to either pay and cancel remaining work or issue a resumption order. Minor change orders (up to 10% acreage modification) do not require price adjustment, while major change orders may authorize increased unit prices or equipment mobilization cost reimbursement, subject to a liability cap calculated as the per-acre bid price multiplied by 10% of untreated remaining acreage.

View the file

Other files

File Type Posted
1-Contract Performance Evaluation FOR REFERENCE USE ONLY.pdf PDF
2-Vendor Prerequisites - IFB Agency.pdf PDF
7-NC27-103 Bid Table Unofficial.xlsx XLSX spreadsheet
5-BearFlatFuelsVicinity map.pdf PDF
Bear Flat - Stan Gurley.kmz KMZ file
8-NC27-103 Bid Table Official.xlsx XLSX spreadsheet
6-Att.-A-PO-Terms-and-Conditions (5).docx DOCX document
9-Award Memo.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B Scope of Work

NC27-103

PROJECT: Bear Flat Aspen lop, prune, and pile project LOCATION: Project is located in Iron County southwest of Brian Head, Utah.

Introduction: Utah Division of Forestry, Fire and State Land (UFFSL), the Utah Division of Wildlife Resources (UDWR), and the Cedar City Ranger District, Dixie National Forest are requesting Services in this contract to provide up to 45.5 acres of lop and scatter, lop and stage, and lop, prune, and pile type work.

· Line Item 1

· Lop, prune, and pile– Forest Service aspen/mixed conifer: 45.5 acres

Total acres awarded will be dependent on availability of funds.

See the attached map for project layout and treatment units. Thinning shall be accomplished throughout each of the identified treatment units. This task order includes the Contractor to furnish labor, equipment, supervision, transportation, operating supplies and incidentals.

SECTION I – CONTRACT REQUIREMENTS

HAND THINNING & LOP/PILE SITE SPECIFICS:

Location and Description: The project area lies north and south of State Route (SR) 143 ) in the vicinity of Forest Service Route (FSR) 30204 (Twisted Forest Road). This project is immediately southwest of Brian Head, UT, borders Brian Head Ski Resort's Wildflowers Lift (Chair 1) and is completely on Forest Service lands in Iron County, UT. Please see the attached map. The project area is comprised of 45.5 acres of land located within the boundaries of the Dixie National Forest. Township 36 South, Range 9 West, Sections 9,10,11,14, and 15. Slopes range from flat to 60%. It is required that boundaries be located by the contractor or sub-contractor via GPS or by using the PDF maps attached and the Avenza maps app on a device that runs the application such as a smart phone or tablet. The work location is shown on the site maps.

Access to the site: Access is possible by a combination of paved highways, county, Forest Service dirt surface roads and overland hiking. Vehicle travel is limited to designated routes; off road/trail vehicle travel is prohibited.

SPECIFIC TASKS:

Work Limits: This is a “Lop, prune, and pile” contract. The silvicultural prescription for the units is a pre-commercial thin, focusing on thinning of all conifers 8 inches DBH and less from aspen communities. The resulting plant communities will be dominated by large conifer and aspen species. All designated trees are required to be thinned.

Only areas shown on the project map will be treated. The project areas are identified with GPS unit and PDF maps. It will be the contractors’ responsibility to provide an electronic device that is capable of loading geo-referenced project area pdf format maps. Government staff will identify unit boundaries for the work executed under the contract in areas of resource protection and sensitive boundaries. In areas without sensitive resource concerns, it will be the contractor’s responsibility to identify unit boundaries with the provided geo-referenced maps. The Contractor shall immediately upon entering the project area, begin work, locate control points, section corners, and take such action to prevent their destruction. Forest improvements such as fences, cattle guards, and pipelines will be located by the contractor and avoided.

Line item 1 - Lop, prune, and pile– Forest Service aspen/mixed conifer – 45 acres

Unit boundary is not flagged.

No slash will be left on State Route 143, Forest Service Route 30204, or other forest system routes, including culvert catch basins, inlets and outlet ditches.

Thinning – Hand thin removal of all live and dead conifers 8-inch Diameter Breast Height (DBH) and smaller. All cut tree boles will be cut into lengths not to exceed 4 feet in length. Trees that are felled will be completely severed from the stump leaving a MAXIMUM stump height no greater than 6 inches measured on the uphill side. ALL branches below the stump cut must be severed. ALL branch wood will be lopped from cut tree boles to achieve better pile construction no project generated thinning slash will be left out of the pile. Do not cut live aspen trees.

Pruning- All lower branches from remaining conifer leave trees over 8-inch Diameter Breast Height (DBH) from the ground level up 6 feet of the tree trunk is to be pruned. Limbs will be pruned flush with the tree bole.

Piling – All branch and bole material generated from felling will be piled. All naturally occurring dead and downed material rotten or sound from 3 inches to 8 inches in diameter will be piled. Dead and downed material under 3 inches in diameter may be left where it is.

Pile Construction – Piles will be approximately 8 feet wide, by 8 feet across, by 8 feet tall dome shaped and TIGHTLY compacted NOT HOLLOW free of dirt and trash. Piles will not be constructed under the drip lines of remaining leave trees over 8-inch Diameter Breast Height (DBH). Piles WILL NOT BE constructed within 50 feet of any stream that has water actively flowing down it.

Additional treatment specifications for all line items:

1. All dead and live conifer trees within speficiations that are partially down must cut to standing lop and scatter standards.

2. Live browse species, or tree species other than identified conifers, shall not be cut or damaged.

3. Only established roads shall be used. No overland travel by vehicle will be allowed.

4. Any trees identified as bearing trees, or any tree blazed or tagged to mark the line of any Government survey, shall not be cut or destroyed under penalty of the law. Trees with reference will be left uncut.

5. Fences, gates, water developments, ponds, tire troughs, metal troughs, head boxes, pipelines and other infrastructure will be avoided and any damages will be repaired by the Contractor.

State and/or Forest Service representatives will inspect all contractor work and confirm compliance with contract provisions. These representatives will notify the State COR when contract work has been completed. The COR and/or PI will do periodic inspections which may include compliance monitoring plots to ensure consistency with contract specifications.

The UFFSL project manager or designee will do periodic inspections which may include compliance monitoring plots to ensure consistency with contract specifications.

Records and Notification: The Contractor shall maintain adequate records to allow the State, NRCS, and/or Forest Service representatives to monitor contract progress and for the Contractor to be accountable for work quality. Contractor records shall include: (1) work dates, (2) number of acres completed, (3) location of acres completed (4) supervisor/inspector name, (5) work quality percentage and (6) supervisor signature and date. Written notice of completed acreage shall be submitted to the Project Manager on a biweekly basis.

CONTRACTOR FURNISHED EQUIPMENT:

The Contractor shall furnish all labor, equipment, supervision, transportation, operating supplies and incidentals to perform all work as set forth in the specifications.

Equipment Requirements:

The Contractor shall furnish Equipment on a fully-operational basis, with competent, fully-qualified operators, and shall meet the following specifications:

1. Must provide a minimum of a 12-man crew.

2. Operate chainsaw, hand saw or shears capable of cutting pinion/juniper tree species on steep slopes, cutting as low to the ground level as possible.

3. Equipment shall be free of fluid leaks and be in good operating condition.

4. Equipment shall be washed by a high-pressure system before entering Forest Service lands at an off-Forest location.

5. All soil and plant parts shall be removed to prevent the spread of noxious weeds in and out of the project area. Equipment will need inspected by a project inspector prior to entering Forest Service lands.

GOVERNMENT FURNISHED PROPERTY:

No Government property shall be furnished on this project.

EQUIPMENT AND WORKMANSHIP:

All equipment and/or materials incorporated into the work covered by this contract shall be of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. All work under this contract shall be performed in a skillful and workmanlike manner. The State may require, in writing, that the contractor remove from the work any employee deemed by the State to be incompetent, careless, or otherwise objectionable.

Surface Disturbance: All public or private access roads damaged by the Contractor shall be restored at the Contractors expense to the same condition they were in at the commencement of work. Vehicles must not be operated or driven off identified roads or trails. All-terrain vehicles may be used within project areas as long as vehicle use is restricted to existing roads and motorized trails. All created visible trails and/or ruts will be reclaimed at the expense of the contractor.

Environmental Considerations:

1. Equipment shall be washed by a high-pressure system before entering Forest Service at an off-Forest location.

2. All soil and plant parts will be removed to prevent the spread of noxious weeds in and out of the project area. Equipment will need inspected by a project inspector prior to entering the Forest Service lands.

3. Project sites shall be cleaned up of all refuse from work camps and refuse be removed by the Contractor. The Contractor shall be responsible for disposal of materials in a manner consistent with State, Federal and local laws and for all expenses incurred with disposal. Public or private access roads damaged by the Contractor shall be restored at the Contractors expense to the same condition they were in at the commencement of work.

4. Use of 2-wheel and 4-wheel vehicles is only permitted on designated routes. Off road/trail vehicle travel is prohibited.

5. Hazardous Materials:

A. Use of Hazardous Materials and/or petroleum products requires that all appropriate State and Federal Regulations be complied with including, but not limited to, Materials Safety Data Sheets (MSDS) on hand and use of necessary Personal Protective Clothing (PPE).

B. On-site disposal of Hazardous Materials or Waste including hydrocarbons is not authorized. On-site disposal will subject the contractor to at least the cost of reclamation and the appropriate disposal of contaminated soil.

C. Incidental (de minimus) leaks from fittings, gaskets or ruptured hoses will not subject the contractor to remedial requirements. They will be considered to be normal and unavoidable losses. Continual leaks will be noted on inspection reports and correction through maintenance required.

D. Maintenance and repair operations that require the draining of engines or hydraulic systems may be conducted on site only if the fluids are captured, containerized, and removed from public lands for proper disposal.

ACCESS:

Access into and through the project site shall remain at all times. The Contractor shall maintain roadways free of vehicles, tools and debris.

SECURITY OF EQUIPMENT AND PROPERTY:

The Contractor may leave equipment at the work site; however, the Contractor shall be solely responsible for protection of equipment and is solely responsible if the equipment is lost, stolen or damaged.

CREW SUPERVISION:

1. Contractor shall designate one English literate supervisor (understands and can speak English well enough to effectively communicate with the Project Manager and inspectors), whom will be on-site daily during operation hours. Supervisors shall be identified during the pre-work conference. Any changes in supervisory designations must be submitted in writing to the Project Manager at least 24 hours prior to the change taking effect.

2. Person designated by the Contractor, as supervisor must remain with and effectively directs the crew by (1) making periodic inspections of the crew’s work, (2) advising them as to improper work methods, (3) providing instructions for correcting any improper work methods encountered.

3. Emergency transportation will be provided by the Contractor at all times.

WORK CAMPS:

Work camps may be established only in location authorized in advance by the Project Manager in coordination with the Government. Should such a camp be authorized, the Contractor shall maintain the camp in an orderly and sanitary manner. Upon vacating a camp and prior to final payment, the Contractor shall remove all refuse and other signs of occupancy to the satisfaction of the Project Manager.

WORK HOURS:

Work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. Work hours may extend into darkness only when the contractor’s equipment is suitably outfitted with exterior lighting sufficient to allow safe operation; AND only when mutually agreed upon between the Contractor and the Project Manager. Work may be done on Saturday, Sunday, and legal national holidays as mutually agreed between the Contractor and the Project Manager.

WORK SCHEDULE:

The work schedule shall be submitted at the pre-work conference.

DELAYS:

The Contractor is expected to complete all contract performance in a timely manner, regardless of the Contractor or subcontractor's other workload, including any work being performed under other state contracts. A delay or failure to perform may be considered excusable when the delay or failure arises from causes beyond the control and without the fault or negligence of the Contractor or subcontractor. The State may also exercise excusable delay for a cause beyond their control and without fault or negligence of the State. Examples of these causes are (1) acts of God or of the public enemy, (2) acts of the State in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and (9 unusually severe weather. In each instance, the failure to perform must be beyond the control and without the fault or negligence of the Contractor or subcontractor.

Upon request of the Contractor, the Contracting Officer shall ascertain the facts and extent of the failure. If the Contracting Officer determines that any failure to perform results from one or more of the causes above, the delivery schedule may be revised, subject to the State’s contract termination rights under the contract.

Note: “Unusually severe weather” means weather that is outside the normal weather patterns for a specific area at a specific time of the year. For example, strong wind and snow storms in fall and winter, or strong wind, rain or hail storms in spring and summer are not considered unusually severe. An unusually severe snow, wind or rain storm is one that is worse than even the harshest normal conditions during a season.

PROJECT MEETINGS:

Pre-work Conference:

1. Location: Meetings shall be held at the project site, or as determined by the Forest Service and the State Project Manager.

2. Notification: A pre-work conference will be held prior to the start of work. No work can commence prior to the pre-work conference. The Contractor will be notified in advance of the meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the contract. The contractor needs to provide at least 7 full days’ notice of when they plan to arrive on site.

3. Attendance: The Contractor, subcontractors, and the people responsible for coordination of the work shall be present at the meeting.

4. Presentation: The Contractor shall be prepared to summarize and explain procedures planned for each project and present the work schedule requested in the specifications.

Progress Meetings:

1. Location: Meetings shall be held at the project site, or as determined by the Project Manager.

2. Notification: Meetings may be called by either the Project Manager or the Contractor. The meeting request shall state who should attend and the basis for the meeting. DNR/WRI statewide management staff as well as a representative from the State Attorney General’s office may be requested to attend to assist with dispute resolution between the Contractor and the Project Manager.

FIRE DANGER SEASON:

If the Project Manager allows the Contractor to continue work during the periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the Project Manager.

PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA:

1. The Contractor agrees that should he, or any of his employees, in the performance of this contract discover evidence of possible scientific, pre-historical, historical, or archeological data he will notify the Project Manager immediately giving the location and nature of the findings.

2. Where appropriate by reason of discovery, the Project Manager may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted.

3. The Contractor agrees to insert this paragraph in all subcontracts, which involve the performance of work on the terrain of the site.

PROTECTION OF CULTURAL RESOURCES:

Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1979 (16 U.S.C. 470aa-ll) (36 CFR 296.4 and 36 CFR 261.9(g)), shall be identified on the ground by the Government. The Government may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object which is or may be entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas by either party shall be promptly reported to the other party and operations will be suspended at that location until the significance or potential significance of the site is determined.

Contractor shall protect all known and identified historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture against destruction, obliteration, removal or damage during Contractor's operations. Contractor shall immediately notify the Government if disturbance occurs to any known site and shall immediately halt operations in the vicinity of the site until the Government authorizes the Contractor to proceed. Contractor shall bear costs of evaluation and restoration in accordance with 36 CFR 296.14(c), provided that such payment shall not relieve Contractor from civil or criminal remedies otherwise provided by law.

CONTRACT TIME:

Project Performance Time: Contract must be completed between September 15, 2026, and April 1, 2027. Note this project cannot be completed when there is snow on the ground.

It is the Contractor’s sole responsibility to complete contract performance on time regardless of Contractor’s current workload, including other state contracts. If necessary, the Contractor will be expected to take whatever means are necessary to ensure timely contract performance. At the discretion of the Contractor, this may include sub-contracting with prior written approval from the State, additional equipment/manpower and/or any other necessary action. Any necessary action taken by the contractor to ensure timely completion shall be at no additional expense to the State of Utah beyond the original contract price.

Past Due Notice. If a Contractor fails to complete the Scope of Work during the Project Performance Time, that failure is solely attributable to action or inaction of the Contractor, and the Government determines that a time extension is allowable, the Government and Contractor may negotiate a reduced per-acre completion price to finish the Scope of Work in lieu of cancelling the remainder of the uncompleted acreage. This option in no way restricts the Government’s authority to terminate the Agreement at the end of its term regardless of whether acreage remains uncompleted.

INSPECTION:

Surveillance Plan: The Government will inspect completed acres and provide recommendations to improve work quality while work is in progress. The Contractor is responsible for providing quality control to assure that work complies with the contract specifications.

Final Inspection:

1. Location: Meeting shall be held at the project sites, or as determined by the Project Manager.

2. Notification: The Contractor shall notify the Project Manager at least three (3) working days before completion date so the Government can schedule the final inspection.

3. Deficiencies: The Contractor shall correct deficiencies and project areas will be re-inspected by the Project Manager.

ACCEPTANCE:

Based on inspection results, if the quality level falls below contract specifications, the Project Manager will notify the Contractor in writing within five business days of completing an inspection and instruct the Contractor to improve the quality of work. If the quality of the work is not raised to an acceptable level after written notification, the Project Manager may issue a suspend work order to resolve the problem, during which time contract time will continue to run.

If untreated or unsatisfactorily treated areas are the primary reason for unsatisfactory work, the Contractor shall rework acres designated by the Government until satisfactory work quality is obtained.

PAYMENT:

One lump-sum final payment will be made for the actual number of acres completed following a final inspection of the completed project, and consistent with the payment clause in the State’s standard terms and conditions. However, if a partial payment request is considered, approval of said request shall be at the total discretion of the State. Contractor must get a partial payment request approved prior to submitting an invoice for partial payment. Partial payment invoices received without prior approval will be returned to the contractor as not proper for payment. Partial payment does not constitute final inspection approval.

WINTER STOPPAGE:

At the sole discretion of the State, this contract may be stopped at any time due to frozen soil or other winter conditions. Once the contract work is stopped for winter, the state may pay the contractor and cancel the remaining portion of the contract, or issue a resumption of work order, when spring weather permits. Contractor must proceed diligently with all work as weather permits until a stop-work order is issued.

CHANGE ORDERS:

Minor Change Order. If the State determines that a change in the Scope of Work is necessary, they may modify acreage totals or parcel configuration by up to 10% of the originally proposed Project Area by providing written notice to the Contractor (“Minor Change Order”). Issuance of a Minor Change Order does not excuse the Contractor from their obligation to perform the work under their original per-acre bid price, nor does it excuse the State from paying Contractor for work completed to project specifications. Changes in acreage or parcel configuration will add or exchange work areas with characteristics similar to those in the original Project Area. When possible, a Minor Change Order should be implemented so as to leave a consolidated and contiguous project area having similar access to that originally described in the Scope of Work.

Major Change Order. If the State determines that a change in the Scope of Work is necessary, and that change does not qualify as a Minor Change Order, the State and the Contractor may negotiate a Major Change Order as an amendment to the original contract. Examples of Major Change Orders include: (1) a reduction or cancellation of acreage that is greater than 10% of the original Project Area or (2) a change in the Project Area such that the new project characteristics are not comparable to those described in the original Scope of Work. Major Change Orders may authorize an increase in the unit price of per-acre bid submitted by the Contractor, payment of part or all of equipment mobilization costs incurred by the Contractor, or a combination of both. Any Major Change Order shall be supported by documentation supporting the equitable adjustment in contract terms and is subject to approval by the State of Utah Division of Purchasing.

Change Order Limitations. The sum of all payments made under one or more Change Orders on a single contract may not exceed the liability cap for the contract, calculated by identifying the per-acre bid price, and multiplying that figure by 10% of the acreage within the Project Area that remains untreated. For example, the maximum payment authorized under a Major Change Order would be calculated as follows:

$50 per acre bid price x (10% of 500 acres left untreated) = $2,500 Maximum or $250 per acre bid price x (10% of 1250 acres left untreated) = $31,250 Maximum

Nothing in this Section relieves the Contractor from their obligation to perform as described in Section 1, unless the State determines that a change order is appropriate. Under no circumstances may a Change Order exceed the total approved contract price. In most cases, the actual Change Order amount will be substantially less than the maximum liability cap for the contract. Nothing herein shall be construed as eliminating or modifying a Contractor’s obligation to mitigate damages they may incur due to the circumstances necessitating a Major Change Order, or the State’s right to terminate an Agreement in lieu of issuing a Change Order.

SECTION II – BID REQUIREMENTS/INFORMATION

SITE VISIT

A site visit will NOT be held prior to bidding. It is strongly recommended that each potential bidder inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

SHAPEFILES/MAPS

Maps and/or shapefiles are attached in the Buyer Attachments Section of this solicitation. If bidder needs additional maps/files, please specify the type in the Q&A Section of this solicitation. Maps are provided for informational purposes only.

QUESTIONS:

All other questions related to this solicitation, specifications, or bidding procedures MUST be asked in writing in SciQuest. There are no exceptions to this.

BIDDING:

This contract will be bid on a per-acre price. The per-acre price will be extended based on the quantity of acres to show a total project price. Acreage will be measured using GIS technology on a flat plane. No adjustments will be made for slope. The total price shall include all labor, equipment and materials necessary to complete the job, which includes all mobilization and operating costs. There will be no fuel surcharges or adjustments negotiated.

SCHEDULE OF ITEMS

Work Item
Sub Item/Description
Unit of Measure
Quantity
Price/Acre
Extended Price

Bear Flat Aspen Restoration lop, prune, and pile project

Line Item 1
Acres
45.5
$___________
$___________

Total of all Items

REFERENCES:

Bidding on this project is limited to pre-qualified contractors. Therefore, reference information does not need to be submitted with the bid.

PRE-QUALIFICATION:

Pursuant to the Utah Procurement Code, participation on this solicitation (Invitation for Bid or Request for Quotes) is limited to pre-qualified contractors only. Bids or quotes submitted by a non-prequalified contractor will not be considered.

CONTRACT AWARD:

A contract will be awarded to the lowest responsive/responsible bidder who meets any experience and equipment requirements noted elsewhere in this solicitation.

USE OF SUBCONTRACTORS:

The Project Manager must approve the use of all subcontractors in writing prior to their performance of any work on the project. A subcontractor who submitted a bid on the project, was offered the project as the low bidder, and declined that award, or who defaulted on project after being awarded the contract, is ineligible to be a subcontractor for the successful bidder.

SECTION III – MAPS, DRAWINGS AND OTHER INFORMATION

DOCUMENTS INCORPORATED BY REFERENCE:

Map 1. Bear Flat Aspen lop, prune, and pile project vicinity map.

Directions to project site From Parowan, UT: